02.03.2014 Views

[322/03] Francke - Ingenia

[322/03] Francke - Ingenia

[322/03] Francke - Ingenia

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

INFRASTRUCTURE<br />

Figure 2: The route of the Øresund Bridge<br />

ingenia<br />

The skill with which the contractors<br />

successfully planned and executed the<br />

construction of the tunnel, the bridge<br />

and the major dredging works can<br />

largely be ascribed to the Design-and-<br />

Construct concept which forms a part<br />

of all the major contracts. Optimum use<br />

of prefabrication also played a key role.<br />

As the Design-and-Construct concept<br />

lays down precise functional<br />

requirements for the whole project,<br />

contractors are responsible for the<br />

detailed design as well as for the<br />

construction work.<br />

Rigorous environmental requirements<br />

were in force throughout the<br />

construction period, governing both the<br />

construction of the link and the impact<br />

of the completed link on the<br />

surrounding environment. As the Danish<br />

and Swedish governments had<br />

stipulated that the link must not block<br />

the water flow through Øresund, careful<br />

trimming of the link’s design reduced<br />

the calculated blocking effect from 2.3<br />

per cent of the water flow to 0.5 per<br />

cent prior to final adjustment.<br />

Compensation dredging in and around<br />

the alignment further reduced the<br />

blocking effect.<br />

Dredging and reclamation<br />

The dredging and reclamation contract<br />

included the initial construction works<br />

for the fixed link which began in August<br />

1995. Over four years a total of 7.5<br />

million cubic metres of (mainly) seabed<br />

material was dredged, two thirds in<br />

Danish waters and one third in Swedish<br />

waters. The seabed consists of gravel<br />

and stone, clay till and limestone with<br />

flint layers.<br />

Dredging was carried out by a<br />

number of dredgers, traditional bucket<br />

dredgers as well as a specialised<br />

cutter/suction dredger for the tunnel<br />

trench.<br />

The objective was for the<br />

completed link to have no net effect<br />

on the water flow and on the<br />

movement of salt and dissolved<br />

oxygen through Øresund to the Baltic<br />

Sea. Consequently the size and shape<br />

of the peninsula and the island were<br />

optimised to reduce the blocking of<br />

the water flow through Øresund.<br />

Further reduction to zero blocking was<br />

achieved by compensation dredging.<br />

All dredged seabed material was<br />

reused in the reclaimed areas which<br />

cut sediment spill to a minimum and,<br />

in addition, reduced the need for<br />

dumping sites as well as for import of<br />

sand and gravel.<br />

The dredging works included:<br />

● Work harbours and access channels<br />

at the artificial island and the artificial<br />

peninsula<br />

24

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!