[322/03] Francke - Ingenia

[322/03] Francke - Ingenia [322/03] Francke - Ingenia

ingenia.org.uk
from ingenia.org.uk More from this publisher
02.03.2014 Views

NILS FRANCKE ØRESUNDBRO KONSORTIET INFRASTRUCTURE The Øresund Bridge – linking Scandinavia to the continent The Øresund Bridge, one of the largest infrastructure projects in the history of Europe, is set to change southern Scandinavia forever. A combined tunnel and bridge link carrying the motorway and railway has replaced the existing ferry routes between the Danish capital of Copenhagen and the Swedish regional capital of Malmö. The Øresund Bridge comprises three major civil works projects: a 4 km artificial island, the world’s largest immersed tunnel for both railway and motorway, as well as the 7.8 km bridge with a cable-stayed high bridge as the impressive centrepiece. Almost five years after the civil works began the Øresund Bridge was opened to traffic on 1 July 2000. This 3 billion USD project was completed on schedule as well as on budget. The new and greatly improved infrastructure will further the integration of the area now known as the Øresund Region, a cross-border region with roughly 3.5 million Danish and Swedish inhabitants. Combining the best of Copenhagen and Malmö, the Øresund Region will have a major impact on Northern Europe in terms of education, science, finance and culture. But before full integration can be achieved, a substantial amount of legislation has to be introduced, not least within the labour market and education. ingenia 23

NILS FRANCKE<br />

ØRESUNDBRO KONSORTIET<br />

INFRASTRUCTURE<br />

The Øresund Bridge<br />

– linking<br />

Scandinavia<br />

to the<br />

continent<br />

The Øresund Bridge, one of the<br />

largest infrastructure projects in<br />

the history of Europe, is set to<br />

change southern Scandinavia forever.<br />

A combined tunnel and bridge link<br />

carrying the motorway and railway has<br />

replaced the existing ferry routes<br />

between the Danish capital of<br />

Copenhagen and the Swedish regional<br />

capital of Malmö.<br />

The Øresund Bridge comprises three<br />

major civil works projects: a 4 km<br />

artificial island, the world’s largest<br />

immersed tunnel for both railway and<br />

motorway, as well as the 7.8 km bridge<br />

with a cable-stayed high bridge as the<br />

impressive centrepiece.<br />

Almost five years after the civil works<br />

began the Øresund Bridge was opened<br />

to traffic on 1 July 2000. This 3 billion<br />

USD project was completed on<br />

schedule as well as on budget.<br />

The new and greatly improved<br />

infrastructure will further the integration<br />

of the area now known as the Øresund<br />

Region, a cross-border region with<br />

roughly 3.5 million Danish and Swedish<br />

inhabitants. Combining the best of<br />

Copenhagen and Malmö, the Øresund<br />

Region will have a major impact on<br />

Northern Europe in terms of education,<br />

science, finance and culture. But<br />

before full integration can be achieved,<br />

a substantial amount of legislation has<br />

to be introduced, not least within the<br />

labour market and education.<br />

ingenia<br />

23


INFRASTRUCTURE<br />

Figure 2: The route of the Øresund Bridge<br />

ingenia<br />

The skill with which the contractors<br />

successfully planned and executed the<br />

construction of the tunnel, the bridge<br />

and the major dredging works can<br />

largely be ascribed to the Design-and-<br />

Construct concept which forms a part<br />

of all the major contracts. Optimum use<br />

of prefabrication also played a key role.<br />

As the Design-and-Construct concept<br />

lays down precise functional<br />

requirements for the whole project,<br />

contractors are responsible for the<br />

detailed design as well as for the<br />

construction work.<br />

Rigorous environmental requirements<br />

were in force throughout the<br />

construction period, governing both the<br />

construction of the link and the impact<br />

of the completed link on the<br />

surrounding environment. As the Danish<br />

and Swedish governments had<br />

stipulated that the link must not block<br />

the water flow through Øresund, careful<br />

trimming of the link’s design reduced<br />

the calculated blocking effect from 2.3<br />

per cent of the water flow to 0.5 per<br />

cent prior to final adjustment.<br />

Compensation dredging in and around<br />

the alignment further reduced the<br />

blocking effect.<br />

Dredging and reclamation<br />

The dredging and reclamation contract<br />

included the initial construction works<br />

for the fixed link which began in August<br />

1995. Over four years a total of 7.5<br />

million cubic metres of (mainly) seabed<br />

material was dredged, two thirds in<br />

Danish waters and one third in Swedish<br />

waters. The seabed consists of gravel<br />

and stone, clay till and limestone with<br />

flint layers.<br />

Dredging was carried out by a<br />

number of dredgers, traditional bucket<br />

dredgers as well as a specialised<br />

cutter/suction dredger for the tunnel<br />

trench.<br />

The objective was for the<br />

completed link to have no net effect<br />

on the water flow and on the<br />

movement of salt and dissolved<br />

oxygen through Øresund to the Baltic<br />

Sea. Consequently the size and shape<br />

of the peninsula and the island were<br />

optimised to reduce the blocking of<br />

the water flow through Øresund.<br />

Further reduction to zero blocking was<br />

achieved by compensation dredging.<br />

All dredged seabed material was<br />

reused in the reclaimed areas which<br />

cut sediment spill to a minimum and,<br />

in addition, reduced the need for<br />

dumping sites as well as for import of<br />

sand and gravel.<br />

The dredging works included:<br />

● Work harbours and access channels<br />

at the artificial island and the artificial<br />

peninsula<br />

24


INFRASTRUCTURE<br />

● A trench for the immersed tunnel<br />

● Relocation of the Drogden Channel<br />

● Relocation and deepening of the<br />

Flinte Channel<br />

● Compensation dredging to achieve<br />

zero blocking of the water flow<br />

The reclamation works included:<br />

● The artificial peninsula at Kastrup<br />

● The artificial island which connects<br />

the tunnel and the bridge<br />

The 0.9 km 2 peninsula at Kastrup<br />

serves to bring together the passenger<br />

track from the underground station at<br />

Kastrup Airport with the freight track<br />

running north of the airport. The<br />

motorway along the northern edge of<br />

the peninsula joins the railway at the<br />

entrance to the tunnel portal. The<br />

peninsula also has a track leading to a<br />

railway maintenance area.<br />

The 1.3 km 2 artificial island south of<br />

the natural island of Saltholm forms the<br />

transition between the tunnel and the<br />

bridge. From the tunnel portal on the<br />

western end of the island, the motorway<br />

runs parallel to the railway to the eastern<br />

end, from where the railway runs under<br />

the motorway on to the two level bridge.<br />

The reclamation areas were<br />

constructed as basins surrounded by<br />

coarse pebble bunds lined with a<br />

geotextile membrane. The basins were<br />

then backfilled with clay to prevent the<br />

suspended sediment from escaping.<br />

Reclamation was carried out in stages<br />

as the bunds were completed,<br />

surrounding the individual sections.<br />

During filling at the artificial island, the<br />

traffic corridor for the high-speed<br />

railway was compacted to minimise any<br />

differential settlements which could<br />

interfere with the passage of highspeed<br />

trains. The reclaimed areas were<br />

completed with revetments, comprising<br />

layers of armour stones and filter<br />

stones. The revetments protect the<br />

tunnel against flooding during storms<br />

and high water.<br />

The immersed tunnel<br />

The tunnel extends approximately 4 km<br />

from the Danish coast at Copenhagen<br />

Airport to the artificial island in the<br />

middle of Øresund. The tunnel<br />

comprises five parallel tunnel tubes –<br />

two for the railway, two for the<br />

motorway plus a small tunnel as an<br />

escape gallery. The sheer size of the<br />

tunnel and the shallow waters in this<br />

part of Øresund made an immersed<br />

tunnel the natural choice.<br />

Figure 3: Aerial view of tunnel factory<br />

ingenia<br />

25


INFRASTRUCTURE<br />

ingenia<br />

26<br />

Figure 4: Aerial view of tunnel section being towed to site<br />

The immersed tunnel was<br />

constructed from twenty prefabricated<br />

concrete tunnel elements. The elements<br />

were cast at a purpose-built factory 12<br />

km north of the tunnel site. Each<br />

element was towed to the tunnel site by<br />

four tug boats and lowered into the<br />

tunnel trench with enormous precision,<br />

using GPS satellite navigation.<br />

The fact that casting took place<br />

under cover allowed for efficient and<br />

smooth production, regardless of the<br />

weather. As a positive side effect the<br />

number of work-related accidents was<br />

subsequently reduced.<br />

Each tunnel element is 176 metres<br />

long, 49 metres wide, approximately 9<br />

metres high and weighs around 57,000<br />

tonnes. Each element was cast in eight<br />

sections at the tunnel factory each of<br />

which was cast in one 30 hour cycle.<br />

Each section was cast against the<br />

previous section and the element was<br />

then gradually pushed out of the<br />

casting hall and on to a ramp, in what<br />

was, in effect, a giant lock system.<br />

When all eight sections were cast and<br />

one complete 176 metre element was<br />

ready, a sliding gate was closed behind<br />

the element, and the basin was flooded<br />

until the element floated.<br />

The element could then be pulled<br />

into the deep end of the basin to await<br />

being towed to the tunnel site. After the<br />

water inside the lock had reached sea<br />

level allowing the element to be towed<br />

out, the next two elements would be<br />

cast. Two parallel production lines<br />

allowed for maximum output and<br />

efficiency.<br />

The towing of the elements<br />

demanded great skill and precision. The<br />

57,000 tonne element was almost<br />

completely immersed during towing<br />

and the changing currents in Øresund<br />

had to be calculated in great detail<br />

before the towing-out. This operation<br />

took place in the Drogden Channel in<br />

Western Øresund, which is an<br />

international shipping route used by<br />

some 40,000 ships per year. Early in<br />

the construction phase a radar station<br />

was established to monitor shipping<br />

and guide vessels through the work<br />

areas thus avoiding any major<br />

accidents. During operations only a<br />

handful of collisions and minor incidents<br />

took place involving work vessels and<br />

shipping, causing material damage only.<br />

Not once was a tunnel element<br />

damaged due to a collision. However,<br />

on 4 August 1998, the accident that<br />

everybody was dreading took place: a<br />

tunnel element was flooded while being<br />

positioned in the tunnel trench. Before<br />

tow-out the tunnel tubes in the element<br />

were sealed off with steel bulkheads.<br />

Due to a number of mistakes one<br />

bulkhead was not properly secured and<br />

succumbed to the water pressure. In a<br />

matter of seconds all five tunnel tubes<br />

in the large concrete element filled with<br />

water, and in accordance with<br />

procedures the element was<br />

immediately lowered into the trench,<br />

but several metres out of position. It<br />

took Øresund Tunnel Contractors eight<br />

weeks to inspect, repair and eventually<br />

move the tunnel element into its correct<br />

position.<br />

During this period the lowering gear<br />

and platforms were attached to the<br />

flooded element so the contractor was<br />

unable to save time simply by building<br />

the tunnel from both sides at the same<br />

time. However the tunnel factory<br />

continued to produce the tunnel<br />

elements and once the flooded tunnel<br />

element had been repaired and placed<br />

in the correct position, the tow-out and<br />

construction of the rest of the tunnel<br />

elements was carried out at high<br />

speed. As a result, despite this major<br />

setback, the tunnel was constructed<br />

ahead of schedule.<br />

The Bridge<br />

For the bridge section, which connects<br />

the artificial island with the Swedish<br />

coast at Lernacken, a cable-stay<br />

design was chosen for the high bridge<br />

due to the weight of the combined<br />

railway and motorway link. The entire<br />

bridge is 7.8 km long of which the high<br />

bridge accounts for 1,092 metres. The


INFRASTRUCTURE<br />

Figure 5: Floating crane carrying deck section<br />

The cables of the high bridge are<br />

arranged in a classic harp pattern and<br />

anchored to the superstructure truss at<br />

20 metre intervals. Supported primarily<br />

on two pairs of pillar shafts the bridge is<br />

symmetrical from the centre of the<br />

navigation span. It has intermediate<br />

side span piers to limit the deflections<br />

of the 490 metre main span. Each<br />

pylon consists of twin, cast-in-situ<br />

concrete towers extending to a height<br />

of 204 metres above sea level. Cables<br />

are anchored in the pylons at 12 metre<br />

intervals. The foundations for both the<br />

pylons and the side span piers are<br />

prefabricated concrete caissons,<br />

located in the hard limestone, 14 to 17<br />

metres below sea level.<br />

490 metre long main span of the high<br />

bridge crosses the Flinte navigational<br />

channel, which is used by<br />

approximately 10 per cent of the<br />

vessels passing through Øresund. The<br />

majority of shipping passes through the<br />

Drogden navigational channel along the<br />

Danish coast.<br />

As was the case with the tunnel, a<br />

high level of prefabrication was used in<br />

the construction of the bridge. Apart<br />

from the pylons which were cast in situ,<br />

all other components – caissons, pillar<br />

shafts and bridge girders – were<br />

produced on land and transported to<br />

the bridge by the large floating crane,<br />

the ‘Svanen’. This self-propelled crane,<br />

a unique and highly versatile tool,<br />

positioned the heaviest concrete<br />

caissons and pillar shafts with great<br />

precision. For two years ‘Svanen’ made<br />

regular trips between Sundlink<br />

Contractors’ bridge factory in Malmö<br />

North Harbour and the bridge line,<br />

constructing the two approach bridges<br />

and the high bridge like a giant Lego kit.<br />

The superstructure of the bridge is a<br />

composite steel-concrete structure with<br />

truss girders. The upper deck carries<br />

the motorway and the lower deck<br />

contains the railway. The bridge is the<br />

largest of its kind in the world carrying<br />

both passenger trains, freight trains and<br />

motorway traffic.<br />

Figure 6: View of completed bridge from sea level looking towards tower<br />

ingenia<br />

27


INFRASTRUCTURE<br />

approach bridges were produced by<br />

Dragados in Cadiz in Southern Spain<br />

and subsequently towed to Sweden in<br />

pairs, complete with concrete<br />

motorway deck.<br />

The high bridge is carried by a total<br />

of 80 pairs of cables, ten in each<br />

direction from each pylon leg. Each<br />

cable consists of between 68 and 73<br />

strands. A strand consists of seven 5<br />

mm wires. The wires are galvanised,<br />

waxed and encased in plastic casing.<br />

Each cable has a tensile strength of<br />

2,000 tonnes and the combined length<br />

of all cables is about 25 km. The total<br />

weight is about 2,300 tonnes.<br />

Following the inauguration of the<br />

Øresund Fixed Link on 1 July 2000<br />

approximately 500,000 vehicles<br />

crossed the Øresund Bridge during the<br />

first month. Information about traffic<br />

and toll prices etc. can be seen at<br />

www.oeresundsbron.com. The photo<br />

files of the Øresund Bridge are available<br />

at www.bridgephoto.dk. ■<br />

ingenia<br />

28<br />

Figure 7: Side view of bridge to show cable pattern<br />

With a height of 204 metres above<br />

sea level the pylons of the Øresund<br />

Bridge are the tallest concrete<br />

structures in Sweden. The construction<br />

of the pylons began with the placing of<br />

the pylon caissons which had been<br />

cast in a dry dock in Malmö Harbour<br />

and towed to the bridge line. On top of<br />

the caissons the casting of the pylons<br />

was carried out by means of selfclimbing<br />

formwork. The entire casting<br />

process took seven to ten days for<br />

each 4 metre lift.<br />

About 4,335 m 3 of concrete went<br />

into each pylon leg – 220 m 3 per lift in<br />

the first stage and about 34 m 3 per lift<br />

near the top. The concrete was<br />

provided from a batching plant on a<br />

barge moored next to the pylon<br />

cofferdam. Each pylon leg required 800<br />

tonnes of reinforcement which was<br />

prepared in prefabricated cages, and<br />

then lifted into position. The pentagon<br />

shaped pylon legs are solid for the first<br />

17 metres and hollow above that level.<br />

The reinforcement cages for the<br />

cross beams, which connect the pylon<br />

legs approximately 45 metres above<br />

sea level, were built ashore, then lifted<br />

into position for casting. Steel anchor<br />

boxes were also cast into the pylon<br />

legs, to which the cables are attached.<br />

The eight bridge girders for the high<br />

bridge were produced at Karlskrona<br />

shipyard on the East coast of Sweden<br />

and then towed to Malmö, where the<br />

concrete motorway deck was added.<br />

The forty-nine girders for the two<br />

Main contractors on the<br />

Øresund Bridge<br />

Dredging and Reclamation<br />

Öresund Marine Joint Venture:<br />

● Per Aarselff (DK)<br />

● Ballast Nedam Dredging (NL)<br />

● Great Lakes Dredge and Dock<br />

Co. (USA)<br />

The Tunnel<br />

Øresund Tunnel Contractors:<br />

● NCC International (SE)<br />

● Dumez-GTM International (F)<br />

● John Laing (UK)<br />

● E. Pihl & Søn (DK)<br />

● Boskalis Westminster Dredging<br />

(NL)<br />

The Bridge<br />

Sundlink Contractors:<br />

● Skanska (SE)<br />

● Højgaard & Schultz (DK)<br />

● Monberg & Thorsen (DK)<br />

● Hochtief (D)<br />

The Railway<br />

Banverket Industridivisionen (SE)

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!