Ex-post Data on<br />

Power Generation<br />

Ex-post: After the project implementation, monitoring shall be conducted on<br />

the following items:<br />

• Power generation of the renewable component of the project. If fossil fuel<br />

is used in the project, the power generation metered should be adjusted<br />

to deduct power generation from fossil fuels using the specific fuel<br />

consumption and the quantity of fossil fuel consumed;<br />

• Weighted average emission factor (if the option is chosen instead of<br />

CM calculation): The same data requirements as the average OM of<br />

ACM0002. But the data of the year in which project generation occurs<br />

must be used;<br />

• Data required to recalculate the OM emission factor (if ex-post calculation<br />

is chosen);<br />

• Data required to recalculate the BM emission factor (if ex-post calculation<br />

is chosen); and<br />

• Additional data is required for biomass power projects: The amount of<br />

biomass and fossil (if any) fuel input shall be monitored by fuel type.<br />

Monitoring under a PoA:<br />

• Number of the distributed and scrapped equipment; and<br />

• Additional data is required for biomass power projects following the<br />

general guidance for leakage in small-scale biomass project activities or<br />

the procedures given in AM0042.<br />

5.2.4 AM0029<br />

Project Description<br />

Greenfield Gas<br />

Power Plants<br />

Need for sufficient<br />

Gas Availability<br />

AM0029 is a methodology for greenfield natural-gas-fired grid-connected<br />

power generation projects. After the methodology approval in May 2006,<br />

AM0029 has been repeatedly applied. By September 2007, the number of<br />

AM0029 projects reached 25, most of which were estimated to generate<br />

a large amount of CERs (500 – 3,200 kt CO 2<br />

p.a.). All these projects were<br />

based in China and India.<br />

Applicability Conditions<br />

AM0029 (version 1) is applicable to projects that construct and operate<br />

a new natural-gas-fired grid-connected power generation plant. The<br />

geographic/ physical boundaries of the baseline grid shall be clearly identified<br />

and information pertaining to the grid and estimating baseline emissions<br />

must be publicly available. In addition, natural gas must be sufficiently<br />

available in the region or country.<br />

58