<strong>Camilty</strong> <strong>Wind</strong> <strong>Farm</strong><br />

Indicative Construction Programme<br />

4.6.13 Construction of the proposed wind farm is estimated to take approximately 6 months,<br />

including commissioning and site reinstatement. Table 4.4 below provides an indicative<br />

schedule of construction activities. This programme is indicative only and could vary<br />

depending on when construction is started. Subject to achieving consent, it is currently<br />

anticipated that construction would commence not earlier than Quarter 2 of 2016. A more<br />

detailed programme of works will be produced with the appointed construction contractors<br />

and agreed with West Lothian Council in advance of construction.<br />

Table 4.4 Indicative Construction Programme<br />

Site preparation<br />

Main access tracks<br />

Temporary construction compound<br />

Hardstanding installations<br />

Met mast installation<br />

Substation Switchroom<br />

Control and Switchgear<br />

<strong>Wind</strong> turbine foundation installation<br />

Turbine erection<br />

Onsite cabling<br />

Commissioning<br />

Final works<br />

2016<br />

April May June July August Sep<br />

4.6.14 A breakdown of delivery loads to site is provided in Table 4.5.<br />

March 2013 4-15 ES Chapter 4<br />

Description of the Proposed Development<br />

Copyright <strong>Partnerships</strong> <strong>for</strong> <strong>Renewables</strong> Development Co. Ltd 2013 ©

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!