Camilty Wind Farm - Partnerships for Renewables

Camilty Wind Farm - Partnerships for Renewables Camilty Wind Farm - Partnerships for Renewables

07.02.2014 Views

Camilty Wind Farm Anemometry Mast 4.3.10 An anemometry (met) mast is proposed to be in place for the life of the wind farm. This will have a maximum height of 85 m (the maximum hub height of the selected turbine model). This will be a free standing lattice tower mast feeding information to the wind farm control centre. 4.4 Electrical Connection Off-site Grid Connection 4.4.1 The proposed wind farm will require a connection to the electrical distribution network. The connection is likely to be made at Livingston substation approximately 7 km from the site. It is expected that the connection will be made via one underground cable at 33 kilovolt (kV). The underground cable does not form part of the application for the proposed wind farm is therefore not described in further detail within the ES PfR is in the process of investigating this further and will seek an Offer of Connection from Scottish Power Energy Networks at the appropriate time. 4.4.2 The grid connection for the proposed wind farm may be the subject of a separate application under Section 37 of the Electricity Act 1989 in case of an overhead line connection and is therefore not described in further detail within this ES. Substation Switchroom 4.4.3 Figure 1.2 shows the location of the substation switchroom and Figure 4.6 illustrates the relevant technical parameters. 4.4.4 The single storey substation switchroom building will have a pitched slate (or slate substitute) roof. The building will be finished in a render appropriate to the surrounding area, to be agreed in advance with West Lothian Council. 4.4.5 The substation switchroom will be approximately 16.3 m x 6.3 m x 5.5 m high. The substation switchroom will comprise 2 switchrooms, SCADA room, meter room and store/ welfare facilities. The SCADA system will allow turbine operations to be monitored and controlled from a central location, either on or off site to ensure early reporting and rectification of any faults that may occur. The substation switchroom will have fire and closed-circuit television (CCTV) detection systems. 4.4.6 The substation switchroom will be located in a substation compound (25 m x 12 m) with parking for four vehicles. Any external signage will be agreed with West Lothian Council. There will be no external illumination of the substation switchroom except for a small motion sensitive floodlight above the front entrance. Electrical Transformer and On Site Electrical Connections 4.4.7 Electrical transformers will be located outside the turbine towers bases, linked to the on-site control building by underground cables. The cables will run parallel to access tracks, where practicable. March 2013 4-9 ES Chapter 4 Description of the Proposed Development Copyright Partnerships for Renewables Development Co. Ltd 2013 ©

Camilty Wind Farm 4.5 Civil Engineering Works Wind Turbine Foundations 4.5.1 Foundation construction design will be finalised at the detailed design and engineering stage. However, a typical foundation design is shown in Figure 4.2. The dimensions and engineering design of the foundation will vary according to the turbine model chosen, and the ground conditions. However, although the indicative foundation in Figure 4.2 should not be assumed to be to scale, the diameter (maximum 21 m) and depth (maximum 6 m) shown have been assumed within this ES as a reasonable worst case. Prior to construction, detailed intrusive ground investigations will be undertaken at each turbine location and, depending on the information derived from these investigations, modifications may be made to the foundation designs. 4.5.2 Construction of the turbine foundations will generally require excavation to expose suitable bearing strata. The depth of the excavation will depend on the depth to the suitable bearing strata or pile cap. This will depend on peat/ soil depth on site – as discussed in Appendix 13.2, turbines will not be placed on areas of peat deeper than 3 m. Depending on the terrain, the foundations will typically be constructed at a depth of approximately 3 to 6 m. 4.5.3 The sides will be ‘battered’ back to ensure that they remain stable during construction. 4.5.4 The excavated area will be back-filled with compacted layers of graded material from the original excavation, and capped with soil. Around the turbines, the finished surface will be capped with crushed aggregate to allow for safe personnel access around the base of the turbine. 4.5.5 If appropriate, excavated material will be reused for access track construction, to supplement locally imported rock. 4.5.6 A 5 m radius of hard standing will be laid around the turbine base, above the foundation, to allow for vehicular access to the turbine for maintenance purposes. Crane Pads 4.5.7 A crane pad of approximately 45 m x 25 m will be required adjacent to each turbine base to accommodate the cranes required for construction and to provide a laydown area adjacent to each turbine location. Figure 4.3 illustrates a typical crane hard standing area. All hard standings will be formed with crushed rock over geotextile membranes. 4.5.8 Hard standings will be sufficiently level to ensure the safe operation of the cranes. The turbine foundation will then be completed and backfilled as described above. The final detail of the crane hard standing will depend on the exact specification of the cranes selected by the contractor. A large crawler or wheeled/mobile crane will be required for turbine erection, with one smaller pilot crane assisting with the lift procedure. 4.5.9 Crane hard standing areas will be allowed to naturally re-vegetate during operation of the wind farm, though will not be replanted. Site Access 4.5.10 The existing access routes, in the form of forest tracks and roads, would be upgraded within the site and new routes to each turbine location created where necessary. Typical cross sections across the proposed upgraded internal access tracks are illustrated in Figure 4.4. March 2013 4-10 ES Chapter 4 Description of the Proposed Development Copyright Partnerships for Renewables Development Co. Ltd 2013 ©

<strong>Camilty</strong> <strong>Wind</strong> <strong>Farm</strong><br />

4.5 Civil Engineering Works<br />

<strong>Wind</strong> Turbine Foundations<br />

4.5.1 Foundation construction design will be finalised at the detailed design and engineering stage.<br />

However, a typical foundation design is shown in Figure 4.2. The dimensions and<br />

engineering design of the foundation will vary according to the turbine model chosen, and the<br />

ground conditions. However, although the indicative foundation in Figure 4.2 should not be<br />

assumed to be to scale, the diameter (maximum 21 m) and depth (maximum 6 m) shown<br />

have been assumed within this ES as a reasonable worst case. Prior to construction,<br />

detailed intrusive ground investigations will be undertaken at each turbine location and,<br />

depending on the in<strong>for</strong>mation derived from these investigations, modifications may be made<br />

to the foundation designs.<br />

4.5.2 Construction of the turbine foundations will generally require excavation to expose suitable<br />

bearing strata. The depth of the excavation will depend on the depth to the suitable bearing<br />

strata or pile cap. This will depend on peat/ soil depth on site – as discussed in Appendix<br />

13.2, turbines will not be placed on areas of peat deeper than 3 m. Depending on the terrain,<br />

the foundations will typically be constructed at a depth of approximately 3 to 6 m.<br />

4.5.3 The sides will be ‘battered’ back to ensure that they remain stable during construction.<br />

4.5.4 The excavated area will be back-filled with compacted layers of graded material from the<br />

original excavation, and capped with soil. Around the turbines, the finished surface will be<br />

capped with crushed aggregate to allow <strong>for</strong> safe personnel access around the base of the<br />

turbine.<br />

4.5.5 If appropriate, excavated material will be reused <strong>for</strong> access track construction, to supplement<br />

locally imported rock.<br />

4.5.6 A 5 m radius of hard standing will be laid around the turbine base, above the foundation, to<br />

allow <strong>for</strong> vehicular access to the turbine <strong>for</strong> maintenance purposes.<br />

Crane Pads<br />

4.5.7 A crane pad of approximately 45 m x 25 m will be required adjacent to each turbine base to<br />

accommodate the cranes required <strong>for</strong> construction and to provide a laydown area adjacent to<br />

each turbine location. Figure 4.3 illustrates a typical crane hard standing area. All hard<br />

standings will be <strong>for</strong>med with crushed rock over geotextile membranes.<br />

4.5.8 Hard standings will be sufficiently level to ensure the safe operation of the cranes. The<br />

turbine foundation will then be completed and backfilled as described above. The final detail<br />

of the crane hard standing will depend on the exact specification of the cranes selected by<br />

the contractor. A large crawler or wheeled/mobile crane will be required <strong>for</strong> turbine erection,<br />

with one smaller pilot crane assisting with the lift procedure.<br />

4.5.9 Crane hard standing areas will be allowed to naturally re-vegetate during operation of the<br />

wind farm, though will not be replanted.<br />

Site Access<br />

4.5.10 The existing access routes, in the <strong>for</strong>m of <strong>for</strong>est tracks and roads, would be upgraded within<br />

the site and new routes to each turbine location created where necessary. Typical cross<br />

sections across the proposed upgraded internal access tracks are illustrated in Figure 4.4.<br />

March 2013 4-10 ES Chapter 4<br />

Description of the Proposed Development<br />

Copyright <strong>Partnerships</strong> <strong>for</strong> <strong>Renewables</strong> Development Co. Ltd 2013 ©

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!