07.02.2014 Views

Camilty Wind Farm - Partnerships for Renewables

Camilty Wind Farm - Partnerships for Renewables

Camilty Wind Farm - Partnerships for Renewables

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>Camilty</strong> <strong>Wind</strong> <strong>Farm</strong><br />

Topic<br />

Key Mitigation and Enhancement Measures<br />

March 2013 16-43 ES Chapter 16<br />

Copyright <strong>Partnerships</strong> <strong>for</strong> <strong>Renewables</strong> Development Co. Ltd 2013 ©<br />

into adjacent soils.<br />

Where tracks are situated near deep peat, drainage systems will be adapted to ensure that the water table in the adjacent peat is not<br />

affected or only affected over a short distance. For example, drainage ditches along the track will be as shallow as possible but sufficient<br />

to drain rainfall from the track surface and to prevent runoff flooding the track. The track surface will be near the adjacent peat surface<br />

and cross-drains will be installed at or just below the track surface. These measures will ensure that runoff within the upper peat layer<br />

(acrotelm) is not blocked by the track. The track base will be constructed using suitably permeable graded material such that the slow<br />

movement of water in the deeper peat layers is not significantly affected by the track.<br />

Watercourse Crossings<br />

Two new watercourse crossings will be required. Confirmation of the level of any CAR authorisations required <strong>for</strong> the new watwercourse<br />

crossings will be confirmed with SEPA in advance.<br />

The new crossing structures will not <strong>for</strong>m a barrier to river flows (low flows and flood flows) and aquatic fauna, and will be designed and<br />

constructed with respect to relevant guidance and best practice.<br />

Where access tracks cross artificial drainage ditches, simple pipe structures will be installed in accordance with the Forests and Water<br />

guidance document. The pipe invert levels will be installed slightly below upstream and downstream bed levels to ensure that barriers<br />

<strong>for</strong> fish passage and sediment transport are minimised.<br />

Streams, crossings and drainage ditches will be inspected and cleared regularly to prevent blockages and remove the risk of flooding<br />

throughout the construction and operational life of the wind farm.<br />

On-Site Buildings<br />

On-site welfare facilities will be adequately designed and maintained to ensure all wastewater and sewage is disposed of appropriately.<br />

Rainfall on roofs will be collected in a rainwater tank <strong>for</strong> re-use within the building. Any excess rainwater will be discharged to<br />

groundwater or surface water.<br />

Cables<br />

Where cables are required to be buried, the following mitigation shall be put in place:<br />

• Excavations <strong>for</strong> trenches will be of minimal size necessary to undertake works;<br />

• Cable trenches will be dug, cables laid and filled in sections to minimise the areas of active excavation open at any one time;<br />

• Bunds will be placed along the route of the buried cable route to prevent the creation of a preferential pathway <strong>for</strong> groundwater<br />

arising along the path of the cable; and<br />

• All cables will be marked above and below ground to ensure there is no danger to human health or the environment during<br />

maintenance or earth works within the vicinity of the cable routes.<br />

Concrete Pouring<br />

Summary of Effects and Mitigation

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!