Camilty Wind Farm - Partnerships for Renewables

Camilty Wind Farm - Partnerships for Renewables Camilty Wind Farm - Partnerships for Renewables

07.02.2014 Views

Camilty Wind Farm site management. Proposed mitigation measures identified in the ES are summarised in Table 16.9 below, grouped according to the aspect of the development mitigation is designed to address. Full details of mitigation are provided within each individual technical chapter. Table 16.9 Schedule of Mitigation and Enchancement Measures Topic Traffic and Transport Noise Key Mitigation and Enhancement Measures The traffic and trasnsport assessments demonstrate that there is no requirement for any mitigation measures. However, a Traffic Management Plan (‘TMP’) will be drawn up and agreed with the Road Authority as an enhancement measure prior to construction. The TMP will provide the following information: • approved access routes and any necessary restrictions; • temporary signage in the vicinity of the proposed wind farm warning of construction traffic; • temporary signage warning other users of abnormal load turbine movements; • arrangements with Police for escort of abnormal loads; • ground preparation, including protection of services; • arrangements for road maintenance and cleaning; • timing of deliveries – construction hours will be outside of peak traffic hours, subject to agreement with the road authorities; and • wheel cleaning arrangements and regular road sweeping runs. Abnormal loads will be escorted, from the port of entry (currently envisaged being Grangemouth) with timings agreed with the road authorities and police as appropriate. These measures will assist in minimising any environmental effects associated with the construction traffic generated by the proposed wind farm. In order to further reduce traffic effects associated with the construction of the proposed wind farm, construction personnel will be encouraged to car-share where practicable. Construction Phase The following safeguards should operate during the construction to minimise the effects of construction noise: • The various EU Directives and UK Statutory Instruments that limit the noise emissions of a variety of construction plant • The guidance set out in BS 5228: Part 1 (2009) which covers noise control on construction sites • The powers that exist for local authorities under sections 60 and 61 of the CoPA and section 80 of the Environmental Protection Act (1990) to control environmental noise and pollution on construction sites. March 2013 16-33 ES Chapter 16 Copyright Partnerships for Renewables Development Co. Ltd 2013 © Summary of Effects and Mitigation

Camilty Wind Farm Topic Key Mitigation and Enhancement Measures Construction contract documents supplied to contractors will require, through a condition of the planning permission, that the effects of environmental noise are considered during the design and execution of the works. If found to be required a noise control plan that provides a noise management system tailored to the specific needs of the construction works, the site and the surrounding area will be developed. If required, as a minimum, any noise control plan should cover: • Procedures for ensuring compliance with statutory or other identified noise control limits; • Procedures for ensuring that all works are carried out according to the principle of Best Practicable Means, as defined in the CoPA; • General induction training for site operatives and specific training for staff having responsibility for particular aspects of controlling noise from the site; • Liaison with WLC and the existing local community; and • Provision of a contact telephone number and responsible person to whom any complaints or concerns with regard to noise, vibration and other environmental issues should be put as a first port of call. This affords the Contractor the opportunity to address any issues prior to WLC involvement. The following conditions and measures will be imposed on the construction works. • As far as is reasonably practicable, the contractors should bring to site and employ on the works only the most environmentally acceptable and quietly operating plant and equipment compatible with the safe and efficient execution of the works. Equipment should be well maintained and fit for purpose. The noise emitted by any plant item should not exceed the limits quoted in either the relevant EC Directive / UK Statutory Instrument and should be no greater than the relevant values quoted in the current version of BS 5228. All items of plant operating on the site in intermittent use should be shut down in the intervening periods between uses. In particular All pneumatic tools should be fitted with silencers or mufflers. • Deliveries should be programmed to arrive during daytime hours only. Care should be taken when unloading vehicles to minimise noise. Where possible, delivery vehicles should be routed so as to minimise disturbance to local residents. Delivery vehicles should be prohibited from waiting on the highway or within the site with their engines running. • All plant items should be properly maintained and operated according to manufacturers recommendations in such a manner as to avoid causing excessive noise. All plant should be sited so that the noise impact at nearby noise sensitive properties is minimised. Local hoarding, screens or barriers should be erected as necessary to shield particularly noisy activities. • Works should not be undertaken outside of the core daytime hours, unless absolutely necessary. • Relevant NSRs potentially affected by the works should be informed well in advance of such works using a leaflet drop giving full details of the hours during which the works are to be undertaken and also providing an appropriate contact name and number to whom complaints should be addressed. Operational Phase March 2013 16-34 ES Chapter 16 Copyright Partnerships for Renewables Development Co. Ltd 2013 © Summary of Effects and Mitigation

<strong>Camilty</strong> <strong>Wind</strong> <strong>Farm</strong><br />

Topic<br />

Key Mitigation and Enhancement Measures<br />

Construction contract documents supplied to contractors will require, through a condition of the planning permission, that the effects of<br />

environmental noise are considered during the design and execution of the works. If found to be required a noise control plan that<br />

provides a noise management system tailored to the specific needs of the construction works, the site and the surrounding area will be<br />

developed. If required, as a minimum, any noise control plan should cover:<br />

• Procedures <strong>for</strong> ensuring compliance with statutory or other identified noise control limits;<br />

• Procedures <strong>for</strong> ensuring that all works are carried out according to the principle of Best Practicable Means, as defined in the<br />

CoPA;<br />

• General induction training <strong>for</strong> site operatives and specific training <strong>for</strong> staff having responsibility <strong>for</strong> particular aspects of<br />

controlling noise from the site;<br />

• Liaison with WLC and the existing local community; and<br />

• Provision of a contact telephone number and responsible person to whom any complaints or concerns with regard to noise,<br />

vibration and other environmental issues should be put as a first port of call. This af<strong>for</strong>ds the Contractor the opportunity to<br />

address any issues prior to WLC involvement.<br />

The following conditions and measures will be imposed on the construction works.<br />

• As far as is reasonably practicable, the contractors should bring to site and employ on the works only the most environmentally<br />

acceptable and quietly operating plant and equipment compatible with the safe and efficient execution of the works. Equipment<br />

should be well maintained and fit <strong>for</strong> purpose. The noise emitted by any plant item should not exceed the limits quoted in either<br />

the relevant EC Directive / UK Statutory Instrument and should be no greater than the relevant values quoted in the current<br />

version of BS 5228. All items of plant operating on the site in intermittent use should be shut down in the intervening periods<br />

between uses. In particular All pneumatic tools should be fitted with silencers or mufflers.<br />

• Deliveries should be programmed to arrive during daytime hours only. Care should be taken when unloading vehicles to<br />

minimise noise. Where possible, delivery vehicles should be routed so as to minimise disturbance to local residents. Delivery<br />

vehicles should be prohibited from waiting on the highway or within the site with their engines running.<br />

• All plant items should be properly maintained and operated according to manufacturers recommendations in such a manner as<br />

to avoid causing excessive noise. All plant should be sited so that the noise impact at nearby noise sensitive properties is<br />

minimised. Local hoarding, screens or barriers should be erected as necessary to shield particularly noisy activities.<br />

• Works should not be undertaken outside of the core daytime hours, unless absolutely necessary.<br />

• Relevant NSRs potentially affected by the works should be in<strong>for</strong>med well in advance of such works using a leaflet drop giving<br />

full details of the hours during which the works are to be undertaken and also providing an appropriate contact name and<br />

number to whom complaints should be addressed.<br />

Operational Phase<br />

March 2013 16-34 ES Chapter 16<br />

Copyright <strong>Partnerships</strong> <strong>for</strong> <strong>Renewables</strong> Development Co. Ltd 2013 ©<br />

Summary of Effects and Mitigation

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!