<strong>Camilty</strong> <strong>Wind</strong> <strong>Farm</strong><br />

110% of the fuel tank. Where practicable, refuelling of vehicles and machinery will be<br />

carried out in one or potentially two designated areas, on an impermeable surface,<br />

and well away from any watercourse. Drip trays will also be used during refuelling and<br />

spill kits will be stored in vehicles on site, at designated refuelling areas and where<br />

chemicals are stored. Site staff will be trained in their use.<br />

• Maintenance: where vehicles or plant require maintenance, this will be undertaken in<br />

a designated area within the construction compound where reasonably practicable,<br />

unless vehicles have broken down necessitating maintenance at the point of<br />

breakdown, where special precautions will be taken.<br />

• Welfare Facilities: on-site welfare facilities will be adequately designed and<br />

maintained to ensure that all wastewater and sewage is disposed of appropriately.<br />

This may take the <strong>for</strong>m of an on-site septic tank with soakaway, or offsite disposal<br />

depending on the suitability of the site <strong>for</strong> a soakaway and prior agreement with<br />

SEPA.<br />

• Cement and Concrete: fresh concrete and cement are very alkaline and corrosive,<br />

and can be lethal to aquatic life. The use of wet concrete in and around watercourses<br />

will be avoided or, where essential, carefully controlled by provision of an agreed<br />

construction method statement prior to construction.<br />

• Contingency Plans: will ensure that emergency equipment will be available on-site i.e.<br />

spill kits and absorbent materials, addition pumps, in<strong>for</strong>mation on where and from<br />

whom to seek advice, and who should be in<strong>for</strong>med in the event of a pollution incident.<br />

• Inspections – All mitigation measures put in place, e.g. silt traps and sediment<br />

settlement tanks, will be inspected regularly and will be suitably maintained to ensure<br />

they remain fully operational and effective. Where failures or shortfalls within<br />

mitigation measures are noted, these will be recorded. Suitable action will be<br />

identified and undertaken within a suitable timeframe.<br />

Construction Waste Management<br />

13.6.6 The production of waste will be minimised throughout the works, including wastes from peat<br />

and this has been taken into account in the design process to avoid, where possible, areas of<br />

deeper peat. Where waste is generated, this will be reused and recycled where possible.<br />

13.6.7 A Site Waste Management Plan (SWMP) will be produced to address the management of<br />

waste streams. The SWMP is typically incorporated into the HSEMS and will address the<br />

following issues:<br />

• Waste minimisation;<br />

• Separation of waste at source;<br />

• Appropriate storage and disposal of waste taking account of stability and pollution<br />

prevention;<br />

• Management of peat, superficial deposits and bedrock;<br />

• Re-use of peat where possible on site;<br />

• Management of waste oils; and<br />

• Recommendations <strong>for</strong> inspection and maintenance.<br />

March 2013<br />

13-27<br />

Copyright <strong>Partnerships</strong> <strong>for</strong> <strong>Renewables</strong> Development Co. Ltd 2013 ©<br />

Hydrology, Hydrogeology and Ground Conditions