Camilty Wind Farm - Partnerships for Renewables
Camilty Wind Farm - Partnerships for Renewables Camilty Wind Farm - Partnerships for Renewables
Camilty Wind Farm • Deliveries should be programmed to arrive during daytime hours only. Care should be taken when unloading vehicles to minimise noise. Where possible, delivery vehicles should be routed so as to minimise disturbance to local residents. Delivery vehicles should be prohibited from waiting on the highway or within the site with their engines running. 8.6.7 All plant items should be properly maintained and operated according to manufacturers recommendations in such a manner as to avoid causing excessive noise. All plant should be sited so that the noise impact at nearby noise sensitive properties is minimised. Local hoarding, screens or barriers should be erected as necessary to shield particularly noisy activities. 8.6.8 Problems concerning noise from construction works can sometimes be avoided by taking a considerate and neighbourly approach to relations with the local residents. Works should not be undertaken outside of the core daytime hours, unless absolutely necessary. 8.6.9 All neighbours potentially affected by the works should be informed well in advance of such works using a leaflet drop giving full details of the hours during which the works are to be undertaken and also providing an appropriate contact name and number to whom complaints should be addressed. 8.6.10 Providing that measures to control construction noise in so far as is reasonably practicable are enforced, then the residual noise impact after mitigation during construction will be negligible. Operational Phase 8.6.11 No mitigation measures are required. Decommissioning Phase 8.6.12 Noise from decommissioning is likely to be similar to that generated during construction. Given the longevity of the development, however, a noise assessment should be undertaken prior to the commencement of decommissioning works and appropriate noise control measures at the time identified and agreed with the relevant authority. 8.7 Assessment of Residual Effects 8.7.1 Potential noise effects during construction, operation and decommissioning of the proposed wind farm have been assessed. 8.7.2 During construction and decommissioning, effects at all nearby receptors are predicted at worst to be slightly adverse. It is considered that adopting the principles of Best Practicable Means will provide sufficient mitigation to render any residual effects negligible and, as such, not significant under the terms of the EIA Regulations. 8.7.3 Noise from operation of the proposed wind farm as an individual entity would comply with the requirements of ESTU-R-97 at all residential locations and, as such, operational wind farm noise is considered not significant under the terms of the EIA Regulations. Cumulative levels are discussed in the following section. March 2013 8-25 ES Chapter 8 Noise Copyright Partnerships for Renewables Development Co. Ltd 2013 ©
Camilty Wind Farm Table 8.11 Summary of Effects Receptor Effect Development Phase Sensitivity/ Importance of Receptor Magnitude of Change Significance Prior to Mitigation Mitigation Enhancement Significance after Mitigation Nature of Effect Residential Noise Sensitive Receptors Temporary Construction High N/A Slight Adopting Best Practicable Means N/A Negligible Temporary Permanent Operation (scheme only) High N/A Negligible N/A N/A Negligible Permanent Temporary Decommissioning High N/A Slight Adopting Best Practicable Means N/A Negligible Temporary March 2013 8-26 ES Chapter 8 Copyright Partnerships for Renewables Development Co. Ltd 2013 © Noise
- Page 104 and 105: Camilty Wind Farm 6.2.8 The report
- Page 106 and 107: Camilty Wind Farm carbon savings fr
- Page 108 and 109: Camilty Wind Farm Table 6.1 Propose
- Page 110 and 111: Camilty Wind Farm 7 Traffic and Tra
- Page 112 and 113: Camilty Wind Farm distraction of wi
- Page 114 and 115: Camilty Wind Farm Table 7.2 Establi
- Page 116 and 117: Camilty Wind Farm 7.3.7 The WLLP al
- Page 118 and 119: Camilty Wind Farm TEMPRO for predic
- Page 120 and 121: Camilty Wind Farm • A length of m
- Page 122 and 123: Camilty Wind Farm construction brea
- Page 124 and 125: Camilty Wind Farm Table 7.8 Constru
- Page 126 and 127: Camilty Wind Farm vehicle speeds, i
- Page 128 and 129: Camilty Wind Farm Table 7.9 Summary
- Page 130 and 131: Camilty Wind Farm 8 Noise 8.1 Intro
- Page 132 and 133: Camilty Wind Farm • The duration
- Page 134 and 135: Camilty Wind Farm 8.3.4 The benefit
- Page 136 and 137: Camilty Wind Farm Baseline Noise Mo
- Page 138 and 139: Camilty Wind Farm Chart 8.1: Parkvi
- Page 140 and 141: Camilty Wind Farm Prevailing Backgr
- Page 142 and 143: Camilty Wind Farm Construction on S
- Page 144 and 145: Camilty Wind Farm 8.5.23 These cons
- Page 146 and 147: Camilty Wind Farm 8.5.28 The follow
- Page 148 and 149: Camilty Wind Farm Chart 8.7: Halfwa
- Page 150 and 151: Camilty Wind Farm Chart 8.11: Over
- Page 152 and 153: Camilty Wind Farm Table 8.10 Differ
- Page 156 and 157: Camilty Wind Farm 8.8 Cumulative Ef
- Page 158 and 159: Camilty Wind Farm Chart 8.16: Colzi
- Page 160 and 161: Camilty Wind Farm Chart 8.20: Harbu
- Page 162 and 163: Camilty Wind Farm Chart 8.24: Whist
- Page 164 and 165: Camilty Wind Farm 8.8.15 Chart 8.26
- Page 166 and 167: Camilty Wind Farm 9 Landscape and V
- Page 168 and 169: Camilty Wind Farm • The Scottish
- Page 170 and 171: Camilty Wind Farm • Select an app
- Page 172 and 173: Camilty Wind Farm 9.2.34 The potent
- Page 174 and 175: Camilty Wind Farm viewpoint locatio
- Page 176 and 177: Camilty Wind Farm landscape’ (par
- Page 178 and 179: Camilty Wind Farm Table 9.5 Recepto
- Page 180 and 181: Camilty Wind Farm Significance of E
- Page 182 and 183: Camilty Wind Farm character. Where
- Page 184 and 185: Camilty Wind Farm 9.3.10 Although t
- Page 186 and 187: Camilty Wind Farm • Harburn House
- Page 188 and 189: Camilty Wind Farm Local plans shoul
- Page 190 and 191: Camilty Wind Farm • Pateshill •
- Page 192 and 193: Camilty Wind Farm settings; however
- Page 194 and 195: Camilty Wind Farm • Urban 9.3.54
- Page 196 and 197: Camilty Wind Farm LCT/LCA Broughton
- Page 198 and 199: Camilty Wind Farm LCT/LCA Landscape
- Page 200 and 201: Camilty Wind Farm Hills lies to the
- Page 202 and 203: Camilty Wind Farm these routes are
<strong>Camilty</strong> <strong>Wind</strong> <strong>Farm</strong><br />
Table 8.11 Summary of Effects<br />
Receptor Effect Development<br />
Phase<br />
Sensitivity/<br />
Importance<br />
of Receptor<br />
Magnitude<br />
of Change<br />
Significance<br />
Prior to<br />
Mitigation<br />
Mitigation<br />
Enhancement Significance<br />
after Mitigation<br />
Nature of<br />
Effect<br />
Residential Noise<br />
Sensitive Receptors<br />
Temporary Construction High N/A Slight Adopting Best<br />
Practicable<br />
Means<br />
N/A Negligible Temporary<br />
Permanent<br />
Operation<br />
(scheme only)<br />
High N/A Negligible N/A N/A Negligible Permanent<br />
Temporary Decommissioning High N/A Slight Adopting Best<br />
Practicable<br />
Means<br />
N/A Negligible Temporary<br />
March 2013 8-26 ES Chapter 8<br />
Copyright <strong>Partnerships</strong> <strong>for</strong> <strong>Renewables</strong> Development Co. Ltd 2013 ©<br />
Noise