Camilty Wind Farm - Partnerships for Renewables
Camilty Wind Farm - Partnerships for Renewables Camilty Wind Farm - Partnerships for Renewables
Camilty Wind Farm vehicle speeds, it is considered that the effect of driver distraction relating to the movement of abnormal loads would not result in any road safety concerns. It is therefore considered any magnitude of change would be negligible and the significance of effect as a result of the abnormal loads upon receptors along the routes would be negligible. Summary of Construction Effects 7.5.35 The maximum number of vehicle movements generated during the construction of the proposed turbines over a day is estimated at 38 two-way movements per day, 10 of which will be HGVs. 7.5.36 The greatest increase in total traffic is predicted to be on the A70 between the B7008 and Carnwath where an increase of 1.1 % on the 12 hour baseline traffic flows is predicted. In accordance with the IEMA guidance, the traffic generated during the construction phase along the adjacent road network is likely to result in a negligible magnitude of change and the significance of effect would be negligible. 7.5.37 Notwithstanding this conclusion, consideration has also been given to the movement of abnormal loads. This assessment showed that the movement of abnormal loads is generally likely to result in a negligible magnitude of change and the significance of effect would be negligible, with the exception of disruption and driver delay where the magnitude of change would be small to medium and the significance of effect would be slight to moderate. Effects During Operation Phase 7.5.38 During the operational phase of the development, there will be no permanent staff based at the wind farm and only the occasional routine maintenance which is carried out using a 4x4 vehicle will be required on site. It is therefore not considered necessary to assess the environmental effects of the traffic generated by the operational phase of the proposed wind farm. 7.5.39 As above, the evidence base which informed the DCLG publication ‘Planning for Renewable Energy: A Companion Guide to PPS22’, December 2004, has informed the conclusion that drivers would not be distracted by the turbines or the movement of the blades. Effects During Decommissioning Phase 7.5.40 The levels of traffic associated with decommissioning are anticipated to be similar or lower than those required during construction, therefore the construction phase assessment of effects is broadly relevant to that for decommissioning. 7.6 Mitigation and Enhancement Measures 7.6.1 Although the above assessments demonstrate that there is no requirement for any mitigation measures, a Traffic Management Plan (‘TMP’) will be prepared and agreed with the Road Authority as an enhancement measure prior to construction. The TMP will provide the following information: • Approved access routes and any necessary restrictions; • Temporary signage in the vicinity of the proposed wind farm warning of construction traffic; • Temporary signage warning other users of abnormal load turbine movements; March 2013 7-17 ES Chapter 7 Traffic and Transport Copyright Partnerships for Renewables Development Co. Ltd 2013 ©
Camilty Wind Farm • Arrangements with police for escort of abnormal loads; • Ground preparation, including protection of services; • Arrangements for road maintenance and cleaning; • Timing of deliveries – construction hours will be outside of peak traffic hours, subject to agreement with the road authorities; and • Wheel cleaning arrangements and regular road sweeping runs. 7.6.2 Abnormal loads will be escorted, from the port of entry (currently envisaged being Grangemouth) with timings agreed with the road authorities and police as appropriate. 7.6.3 These measures will assist in minimising any environmental effects associated with the construction traffic generated by the proposed wind farm. 7.6.4 In order to further reduce traffic effects associated with the construction of the proposed wind farm, construction personnel will be encouraged to car-share where practicable. 7.6.5 The assessment has considered each construction worker arriving at the proposed wind farm in an individual vehicle. This is considered a robust assessment as construction personnel typically show car occupancy levels of greater than one person per vehicle. 7.7 Assessment of Residual Effects 7.7.1 Although the enhancement measures described above are not required to reduce the level of significance with respect to the effects identified, they are included as measures to manage and control the residual effect resulting from HGV deliveries and abnormal loads. Table 7.9 summarises the effects. March 2013 7-18 ES Chapter 7 Traffic and Transport Copyright Partnerships for Renewables Development Co. Ltd 2013 ©
- Page 76 and 77: Camilty Wind Farm Indicative Constr
- Page 78 and 79: Camilty Wind Farm Construction Work
- Page 80 and 81: Camilty Wind Farm there will be a t
- Page 82 and 83: Camilty Wind Farm to the top surfac
- Page 84 and 85: Camilty Wind Farm Waste Management
- Page 86 and 87: Camilty Wind Farm 5 Planning Policy
- Page 88 and 89: Camilty Wind Farm • To reduce gre
- Page 90 and 91: Camilty Wind Farm Table 5.2 Targets
- Page 92 and 93: Camilty Wind Farm contributes to th
- Page 94 and 95: Camilty Wind Farm Nature Reserves (
- Page 96 and 97: Camilty Wind Farm 5.3.57 Paragraph
- Page 98 and 99: Camilty Wind Farm 5.4.8 The guidanc
- Page 100 and 101: Camilty Wind Farm areas will be req
- Page 102 and 103: Camilty Wind Farm 6 Climate Change
- Page 104 and 105: Camilty Wind Farm 6.2.8 The report
- Page 106 and 107: Camilty Wind Farm carbon savings fr
- Page 108 and 109: Camilty Wind Farm Table 6.1 Propose
- Page 110 and 111: Camilty Wind Farm 7 Traffic and Tra
- Page 112 and 113: Camilty Wind Farm distraction of wi
- Page 114 and 115: Camilty Wind Farm Table 7.2 Establi
- Page 116 and 117: Camilty Wind Farm 7.3.7 The WLLP al
- Page 118 and 119: Camilty Wind Farm TEMPRO for predic
- Page 120 and 121: Camilty Wind Farm • A length of m
- Page 122 and 123: Camilty Wind Farm construction brea
- Page 124 and 125: Camilty Wind Farm Table 7.8 Constru
- Page 128 and 129: Camilty Wind Farm Table 7.9 Summary
- Page 130 and 131: Camilty Wind Farm 8 Noise 8.1 Intro
- Page 132 and 133: Camilty Wind Farm • The duration
- Page 134 and 135: Camilty Wind Farm 8.3.4 The benefit
- Page 136 and 137: Camilty Wind Farm Baseline Noise Mo
- Page 138 and 139: Camilty Wind Farm Chart 8.1: Parkvi
- Page 140 and 141: Camilty Wind Farm Prevailing Backgr
- Page 142 and 143: Camilty Wind Farm Construction on S
- Page 144 and 145: Camilty Wind Farm 8.5.23 These cons
- Page 146 and 147: Camilty Wind Farm 8.5.28 The follow
- Page 148 and 149: Camilty Wind Farm Chart 8.7: Halfwa
- Page 150 and 151: Camilty Wind Farm Chart 8.11: Over
- Page 152 and 153: Camilty Wind Farm Table 8.10 Differ
- Page 154 and 155: Camilty Wind Farm • Deliveries sh
- Page 156 and 157: Camilty Wind Farm 8.8 Cumulative Ef
- Page 158 and 159: Camilty Wind Farm Chart 8.16: Colzi
- Page 160 and 161: Camilty Wind Farm Chart 8.20: Harbu
- Page 162 and 163: Camilty Wind Farm Chart 8.24: Whist
- Page 164 and 165: Camilty Wind Farm 8.8.15 Chart 8.26
- Page 166 and 167: Camilty Wind Farm 9 Landscape and V
- Page 168 and 169: Camilty Wind Farm • The Scottish
- Page 170 and 171: Camilty Wind Farm • Select an app
- Page 172 and 173: Camilty Wind Farm 9.2.34 The potent
- Page 174 and 175: Camilty Wind Farm viewpoint locatio
<strong>Camilty</strong> <strong>Wind</strong> <strong>Farm</strong><br />
• Arrangements with police <strong>for</strong> escort of abnormal loads;<br />
• Ground preparation, including protection of services;<br />
• Arrangements <strong>for</strong> road maintenance and cleaning;<br />
• Timing of deliveries – construction hours will be outside of peak traffic hours, subject<br />
to agreement with the road authorities; and<br />
• Wheel cleaning arrangements and regular road sweeping runs.<br />
7.6.2 Abnormal loads will be escorted, from the port of entry (currently envisaged being<br />
Grangemouth) with timings agreed with the road authorities and police as appropriate.<br />
7.6.3 These measures will assist in minimising any environmental effects associated with the<br />
construction traffic generated by the proposed wind farm.<br />
7.6.4 In order to further reduce traffic effects associated with the construction of the proposed wind<br />
farm, construction personnel will be encouraged to car-share where practicable.<br />
7.6.5 The assessment has considered each construction worker arriving at the proposed wind farm<br />
in an individual vehicle. This is considered a robust assessment as construction personnel<br />
typically show car occupancy levels of greater than one person per vehicle.<br />
7.7 Assessment of Residual Effects<br />
7.7.1 Although the enhancement measures described above are not required to reduce the level of<br />
significance with respect to the effects identified, they are included as measures to manage<br />
and control the residual effect resulting from HGV deliveries and abnormal loads. Table 7.9<br />
summarises the effects.<br />
March 2013 7-18 ES Chapter 7<br />
Traffic and Transport<br />
Copyright <strong>Partnerships</strong> <strong>for</strong> <strong>Renewables</strong> Development Co. Ltd 2013 ©