Camilty Wind Farm - Partnerships for Renewables

Camilty Wind Farm - Partnerships for Renewables Camilty Wind Farm - Partnerships for Renewables

07.02.2014 Views

Camilty Wind Farm • A length of more than 18.3 metres. 7.5.3 Depending on the width, length or weight of the vehicle different notice periods have to be provided to the Road & Bridge Authorities and the police, this can vary between 2 and 5 days. 7.5.4 Some of the turbine components will qualify as abnormal loads. The vehicles used to transport turbine components would constitute abnormal loads only on the delivery phase of the journey since the extendible trailers are retracted to the size of a standard articulated vehicle (16.5 metres) during the return leg. Each delivery of turbine components therefore consists of one abnormal load movement on the inbound journey to the proposed wind farm and one articulated HGV movement on the return journey. 7.5.5 It is expected that abnormal load vehicles will access the proposed wind farm from Grangemouth via the M9, M8, A801, A706 and the A70, as shown on Figure 7.1 and as described below: • Abnormal loads will access onto the A904 Earl’s Road; • Route south west onto Junction 6 of the M9; • Route south east along the M9 to Junction 1; • Turn westbound onto the M8 to Junction 4; • Turn northbound onto the A801; • Turn westbound onto the A706 to Whitburn and continue south through Forth; • Turn eastbound onto the A721 and A70; • Turn northbound along the A70 at Carnwath; and • Turn left into the site access. 7.5.6 The turbine assumed for this assessment was the Repower 3.4M104, which would involve the transport of the longest potential turbine component (50.8 m blade). A Swept Path Analysis has been undertaken using vehicles suitable of transporting these turbine components and is submitted as part of this application. The vehicles used in the Swept Path Analysis are set out at Appendix 7.2. A report outlining the proposed route and carrying out preliminary analysis of this vehicle is contained in Appendix 7.4. Construction Traffic and Access 7.5.7 Given the layout of the adjacent road network, it is expected that all HGVs and cars associated with the construction phase would route to the proposed wind farm, via the A70 from the north-east and the south-west. This is likely to be an approximate 50% north-east and 50% south-west split. 7.5.8 Given the geometric layout of the B7008, it is not expected that any construction delivery vehicles would utilise this road and all would travel via the A70. Some construction staff cars may travel via the B7008, however, this is expected to be minimal in comparison to the proportion utilising the A70. Therefore, to ensure a robust assessment, all vehicles have been assigned onto the A70 to maximise the number of vehicle movements along this road. 7.5.9 On this basis, all abnormal load vehicles will arrive at the site from the A70 south-west of the site. For simplicity, it is assumed that the return HGV (no longer an abnormal load) would March 2013 7-11 ES Chapter 7 Traffic and Transport Copyright Partnerships for Renewables Development Co. Ltd 2013 ©

Camilty Wind Farm also travel via the A70 south-west of the site. All construction HGVs, construction light delivery vehicles and vans and construction staff have been assigned with 50% along the A70 north-east of the site and 50% along the A70 south-west of the site. 7.5.10 As set out above, a preliminary design access junction has been designed and is shown at Appendix 7.1, which has taken due consideration of the existing road geometries, the adjacent road boundaries and the swept path of the abnormal loads within the extent of surfaced road without any reliance upon verge use. Construction Traffic Trip Generation 7.5.11 The construction of the six turbines is predicted to be over a six month programme and is summarised in Chapter 4: Description of the Proposed Development. 7.5.12 The likely traffic generation resulting from the process can be split into the following elements: • Low loaders containing wind turbine components; • HGVs to deliver and remove necessary equipment and materials to and from the proposed wind farm; and • Cars/vans containing members of the construction workforce. 7.5.13 The estimated traffic generated during the construction phase for each of these elements is attached at Appendix 7.3 and summarised below. Abnormal Load Trip Generation 7.5.14 An abnormal load movement is defined by Transport Scotland as a vehicle in excess of 18.3m in length or 2.9m in width or 44 tonnes in weight. The hubs, nacelles, blades and foundation plates will be placed on articulated vehicles which exceed these dimensions 7.5.15 The vehicles used to transport turbine components would constitute abnormal loads only on the delivery phase of the journey since the extendible trailers are retracted to the size of a standard articulated vehicle (16.5m) during the return leg. Each delivery of turbine components therefore consists of one abnormal load movement on the inbound journey to the proposed wind farm and one HGV movement on the return journey. 7.5.16 Turbine deliveries are predicted to take place during the third, fourth and fifth months of the six month construction process. During that period up to 78 abnormal loads of wind turbine components would be delivered to the proposed wind farm, including blades, tower sections, transformers, nacelles and cranes and components for the six turbines. 7.5.17 Based on the construction programme this equates to a maximum of 26 abnormal load deliveries per month. Heavy Goods Vehicle Trip Generation 7.5.18 It is estimated that 960 construction HGVs will access the proposed wind farm over the six month construction period (1,920 two-way HGV movements). This number of HGV movements is partly due to aggregate being sourced off-site and being transported to the site. It is noted that the abnormal loads contract to a typical HGV size when departing the site. With the inclusion of these, the total number of construction HGVs (non abnormal loads) over the six month construction period equates to 1,998 two-way HGV movements. The March 2013 7-12 ES Chapter 7 Traffic and Transport Copyright Partnerships for Renewables Development Co. Ltd 2013 ©

<strong>Camilty</strong> <strong>Wind</strong> <strong>Farm</strong><br />

also travel via the A70 south-west of the site. All construction HGVs, construction light<br />

delivery vehicles and vans and construction staff have been assigned with 50% along the<br />

A70 north-east of the site and 50% along the A70 south-west of the site.<br />

7.5.10 As set out above, a preliminary design access junction has been designed and is shown at<br />

Appendix 7.1, which has taken due consideration of the existing road geometries, the<br />

adjacent road boundaries and the swept path of the abnormal loads within the extent of<br />

surfaced road without any reliance upon verge use.<br />

Construction Traffic Trip Generation<br />

7.5.11 The construction of the six turbines is predicted to be over a six month programme and is<br />

summarised in Chapter 4: Description of the Proposed Development.<br />

7.5.12 The likely traffic generation resulting from the process can be split into the following<br />

elements:<br />

• Low loaders containing wind turbine components;<br />

• HGVs to deliver and remove necessary equipment and materials to and from the<br />

proposed wind farm; and<br />

• Cars/vans containing members of the construction work<strong>for</strong>ce.<br />

7.5.13 The estimated traffic generated during the construction phase <strong>for</strong> each of these elements is<br />

attached at Appendix 7.3 and summarised below.<br />

Abnormal Load Trip Generation<br />

7.5.14 An abnormal load movement is defined by Transport Scotland as a vehicle in excess of<br />

18.3m in length or 2.9m in width or 44 tonnes in weight. The hubs, nacelles, blades and<br />

foundation plates will be placed on articulated vehicles which exceed these dimensions<br />

7.5.15 The vehicles used to transport turbine components would constitute abnormal loads only on<br />

the delivery phase of the journey since the extendible trailers are retracted to the size of a<br />

standard articulated vehicle (16.5m) during the return leg. Each delivery of turbine<br />

components there<strong>for</strong>e consists of one abnormal load movement on the inbound journey to<br />

the proposed wind farm and one HGV movement on the return journey.<br />

7.5.16 Turbine deliveries are predicted to take place during the third, fourth and fifth months of the<br />

six month construction process. During that period up to 78 abnormal loads of wind turbine<br />

components would be delivered to the proposed wind farm, including blades, tower sections,<br />

trans<strong>for</strong>mers, nacelles and cranes and components <strong>for</strong> the six turbines.<br />

7.5.17 Based on the construction programme this equates to a maximum of 26 abnormal load<br />

deliveries per month.<br />

Heavy Goods Vehicle Trip Generation<br />

7.5.18 It is estimated that 960 construction HGVs will access the proposed wind farm over the six<br />

month construction period (1,920 two-way HGV movements). This number of HGV<br />

movements is partly due to aggregate being sourced off-site and being transported to the<br />

site. It is noted that the abnormal loads contract to a typical HGV size when departing the<br />

site. With the inclusion of these, the total number of construction HGVs (non abnormal loads)<br />

over the six month construction period equates to 1,998 two-way HGV movements. The<br />

March 2013 7-12 ES Chapter 7<br />

Traffic and Transport<br />

Copyright <strong>Partnerships</strong> <strong>for</strong> <strong>Renewables</strong> Development Co. Ltd 2013 ©

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!