INTERNATIONAL CONCLAVE<br />

ON<br />

KEY INPUTS FOR ACCELERATED DEVELOPMENT OF<br />

INDIAN POWER SECTOR<br />

FOR 12 TH PLAN & BEYOND<br />

<strong>Manufacturing</strong> Capabilities <strong>for</strong> <strong>Balance</strong> <strong>of</strong> <strong>Plant</strong><br />

<strong>Equipment</strong> <strong>for</strong> Thermal <strong>Plant</strong>s<br />

BY<br />

D.S. ARORA<br />

CHIEF ENGINEER<br />

CENTRAL ELECTRICITY AUTHORITY<br />

18-19 August 2009


Capacity Addition Targeted <strong>for</strong><br />

11 th Plan (2007-12)<br />

(Capacity in MW)<br />

Sector Thermal Hydro Nuclear Total<br />

Central 24840 8654 3380 36874<br />

State 23301 3482 0 26783<br />

Private 11552 3491 0 15043<br />

All India<br />

Total<br />

59693 15627 3380 78700<br />

1


CAPACITY COMMISSIONED AND UNDER<br />

CONSTRUCTION FOR 11 TH PLAN<br />

(Capacity in MW)<br />

Commissioned<br />

Under<br />

construction<br />

Total<br />

Thermal 12504 49219 61723<br />

(77%)<br />

Hydro 3431 12076 15507<br />

(19%)<br />

Nuclear 220 3160 3380<br />

(4%)<br />

Total 16155<br />

(20%)<br />

64455<br />

(80%)<br />

80610<br />

(100%)<br />

Note- Additional 5482 MW Renewable and 2700 MW Captive Commissioned so far<br />

2


CAPACITY ADDITION<br />

IDENTIFIED FOR 12 TH PLAN<br />

Thermal 76,500<br />

Hydro 20,000<br />

Nuclear 3,400<br />

(Capacity in MW)<br />

Total 99,900<br />

Say 1,00,000<br />

3


TENTATIVE THERMAL CAPACITY ADDITION<br />

DURING 12 TH PLAN<br />

COAL AND LIGNITE BASED THERMAL CAPACITY<br />

CATEGORY<br />

SUPER-<br />

CRITICAL<br />

UNIT SIZE<br />

(MW)<br />

NO. OF<br />

UNITS<br />

NO. OF<br />

PROJECTS<br />

CAPACITY (MW)<br />

800-660 64 27 43,640<br />

SUB-<br />

CRITICAL<br />

500-600 34 18 18,300<br />

MEDIUM SIZE 250-350 46 23 14,148<br />

SMALLER SIZE 125 4 2 500<br />

TOTAL 148 70 76,588<br />

(Say 76500)<br />

4


BALANCE OF PLANTS<br />

(BOPs)<br />

5


SUMMARY OF REQUIREMENT OF BOPs DURING 10 TH ,<br />

11 TH and 12 TH PLAN<br />

Sl<br />

No<br />

Name <strong>of</strong> BOP<br />

No. <strong>of</strong> BOPs<br />

used during<br />

10 th Plan<br />

For 21180<br />

MW<br />

No. <strong>of</strong><br />

BOPs<br />

reqd.<br />

during 11 th<br />

Plan<br />

Tentative<br />

requirement<br />

<strong>of</strong> BOPs in<br />

12 th Plan<br />

1 Coal Handling <strong>Plant</strong> (CHP) 23 68 70<br />

2 Ash Handling <strong>Plant</strong> (AHP) 23 69 70<br />

3 Demineralized (DM) water<br />

<strong>Plant</strong><br />

32 69 70<br />

4 Cooling Tower 41 79 (145) 70 (148)<br />

5 Chimney 36 79 (117) 77 (148)<br />

6 Fuel Oil (FO) System 22 71 70<br />

7 Water Treatment <strong>Plant</strong> 36 76 70<br />

Note: Due to higher unit size, number <strong>of</strong> BOPs may be less but their capacity may be higher<br />

6


Major BOP vendors available in the country<br />

Sl. No Name <strong>of</strong> BOP No. <strong>of</strong> Vendors<br />

1 Coal Handling <strong>Plant</strong>(CHP) 8<br />

2 Ash Handling <strong>Plant</strong> (AHP) 9<br />

3 Demineralized (DM) water <strong>Plant</strong> 5<br />

4 Cooling Tower 5<br />

5 Chimney 4<br />

6 Fuel Oil (FO) System 4<br />

7 Water Treatment <strong>Plant</strong> 5<br />

8 CW System 3<br />

9 Control & Instrumentation (C&I) 4<br />

10 Switchyard/Switchgear (HT/LT) 5<br />

11 Structural steel erection 3<br />

12 Fire protection System 6<br />

Number <strong>of</strong> vendors are based on the in<strong>for</strong>mation available in CEA<br />

7


MAJOR ORDERS PLACED FOR COAL HANDLING<br />

PLANT FOR 11 TH PLAN<br />

Sl. No. Name <strong>of</strong> Company No. <strong>of</strong> orders<br />

1 M/s Techpro System Pvt Ltd. 11<br />

2 M/s L&T 7<br />

3 M/s Elecon Engineering Co. Ltd. 6<br />

4 M/s TRF Ltd. 3<br />

5 M/s ThyssenKrupp Industries India 3<br />

6 Others 27@<br />

7 Orders yet to be placed 11<br />

Total 68*<br />

@ Includes single EPC contracts <strong>for</strong> BOPs which may have further awarded sub-contracts<br />

to the above vendors.<br />

* Number <strong>of</strong> vendors are based on the in<strong>for</strong>mation available in CEA<br />

No. <strong>of</strong> Coal Handling <strong>Plant</strong>s required during 12 th Plan : 70<br />

8


MAJOR ORDERS PLACED FOR ASH HANDLING<br />

PLANT FOR 11 TH PLAN<br />

Sl.<br />

No<br />

Name <strong>of</strong> Company<br />

No. <strong>of</strong> orders<br />

1 M/s Indure 12<br />

2 M/s Mecawber Beekay 11<br />

3 M/s D C Industrial <strong>Plant</strong> Services 5<br />

4 M/s Mahindra Ash Technology 4<br />

5 M/s Techpro Ash Tech. Ltd. 5<br />

6 M/s Macnally Bharat 3<br />

7 Others 19@<br />

8 Orders yet to be placed 10<br />

Total 69*<br />

@ Includes single EPC contracts <strong>for</strong> BOPs which may have further awarded subcontracts<br />

to the above vendors.<br />

* Number <strong>of</strong> vendors are based on the in<strong>for</strong>mation available in CEA<br />

No. <strong>of</strong> Ash Handling <strong>Plant</strong>s required during 12 th Plan : 70<br />

9


MAJOR ORDERS PLACED FOR DM PLANT<br />

FOR 11 TH PLAN<br />

Sl.<br />

No.<br />

Name <strong>of</strong> Company<br />

No. <strong>of</strong> orders<br />

1 M/s Driplex Water Engg Ltd. 10<br />

2 M/s Doshi Ion Exchange 6<br />

3 M/s Ion Exchange, Faridabad 5<br />

4 M/s Thermax Ltd 4<br />

5 M/s Triveni 4<br />

7 Others 28@<br />

8 Orders yet to be placed 12<br />

Total 69 *<br />

@ Includes single EPC contracts <strong>for</strong> BOPs which may have further awarded sub-contracts<br />

to the above vendors.<br />

* Number <strong>of</strong> vendors are based on the in<strong>for</strong>mation available in CEA<br />

No. <strong>of</strong> DM <strong>Plant</strong>s required during 12 th Plan : 70<br />

10


Sl.<br />

No.<br />

MAJOR ORDERS PLACED FOR COOLING TOWERS<br />

FOR 11 TH PLAN<br />

Name <strong>of</strong> Vendor<br />

No. <strong>of</strong> orders<br />

1 M/s Paharpur Cooling Towers 25 [49]<br />

2 M/s Gammon (I) Ltd. 17 [30]<br />

3 M/s BGR 4 [4]<br />

4 M/s NBCC 2 [2]<br />

5 Others 21[41]@<br />

6 Orders yet to be placed 10 [19]<br />

Total 79[145] *<br />

@ Includes single EPC contracts <strong>for</strong> BOPs which may have further awarded sub-contracts<br />

to the above vendors.<br />

Figures in [ ] indicate number <strong>of</strong> cooling towers.<br />

* Number <strong>of</strong> vendors are based on the in<strong>for</strong>mation available in CEA<br />

No. <strong>of</strong> Cooling Towers required during 12 th Plan : 70 [148]<br />

11


MAJOR ORDERS PLACED FOR CHIMNEY<br />

FOR 11 TH PLAN<br />

Sl.<br />

No.<br />

Name <strong>of</strong> Vendor<br />

No. <strong>of</strong> orders<br />

1 M/s Gammon (I) Ltd. 13 [16]<br />

2 M/s NBCC 10 [12]<br />

3 M/s Simplex 6 [6]<br />

4 M/s Lanco Infrastructures Ltd. 5 [9]<br />

5 Others 35 [61]@<br />

6 Orders yet to be placed 10 [13]<br />

Total 79 [117]*<br />

@ Includes single EPC contracts <strong>for</strong> BOPs which may have further awarded sub-contracts<br />

to the above vendors.<br />

Figures in [ ] indicate number <strong>of</strong> flues.<br />

* Number <strong>of</strong> vendors are based on the in<strong>for</strong>mation available in CEA<br />

No. <strong>of</strong> Chimneys required during 12 th Plan : 77<br />

12


COMPONENTS OF MAJOR BOPs<br />

Each <strong>Balance</strong> <strong>of</strong> <strong>Plant</strong> activity consists <strong>of</strong> various<br />

components which includes:-<br />

• Civil works<br />

• Structural works<br />

• Electro mechanical equipments and various types<br />

<strong>of</strong> motors, etc<br />

• Control & Instrumentation<br />

13


ISSUES FOR COMPLETION OF BOPs IN TIME<br />

1. Placement <strong>of</strong> Order<br />

<br />

Timely placement <strong>of</strong> order <strong>for</strong> BOPs.<br />

2. Review <strong>of</strong> Pre-qualification Requirements <strong>for</strong> BOP<br />

vendors<br />

<br />

CEA already recommended revised PQ to allow entry <strong>of</strong><br />

new players<br />

3. Enhancement <strong>of</strong> vendor base <strong>for</strong> <strong>Balance</strong> <strong>of</strong> <strong>Plant</strong>s<br />

(BOPs) as the requirement has increased manifold<br />

during 11th plan and will further increase in 12th<br />

Plan.<br />

<br />

<br />

There are limited number <strong>of</strong> suppliers in each category and<br />

each having more work than what it can handle.<br />

Favourable conditions to be developed <strong>for</strong> new / additional<br />

vendors.<br />

14


ACTIONS FOR COMPLETION OF BOPs IN TIME<br />

Vendors must take approval <strong>for</strong> appointment <strong>of</strong><br />

sub-contractors in advance from the project<br />

authorities.<br />

Vendors must place the orders <strong>for</strong> civil works as<br />

well as procurement <strong>of</strong> mechanical equipments in<br />

time.<br />

Timely releasing <strong>of</strong> civil construction drawings<br />

from consultants and construction agencies.<br />

Availability <strong>of</strong> adequate construction machinery at<br />

project site.<br />

Deployment <strong>of</strong> adequate skilled / unskilled<br />

manpower at site.<br />

Proper coordination among various executing<br />

agencies engaged at project site.<br />

15


LOSS TO THE UTILITIES ON ACCOUNT OF DELAY IN<br />

COMPLETION OF PROJECTS<br />

Cost <strong>of</strong> delay (Either due to Main <strong>Plant</strong> or BOPs)<br />

<br />

<br />

<br />

Loss on account <strong>of</strong> purchase <strong>of</strong> costlier power from alternate<br />

sources – Rs. 2.5 to 6 crores / day <strong>for</strong> a 500 MW pithead unit.<br />

Increase in IDC and consequently the fixed cost Component <strong>of</strong><br />

tariff - Rs. 45 lakhs / day <strong>for</strong> a 500 MW coal based unit.<br />

Loss <strong>of</strong> return to developer - Rs. 25 lakhs / day <strong>for</strong> a 500 MW<br />

Unit @ 14% ROE.<br />

Point to be considered :<br />

The Utilities should keep the above costs in view while deciding<br />

contractual matters.<br />

16


Central Electricity Authority