<strong>Watercare</strong> Services Limited<br />

<strong>2011</strong> ANNUAL REPORT<br />

FINANCIAL COMMENTARY (continued)<br />

Water revenue was $131.44 million for the year, 2.2% lower than the budget of $134.34 million due to lower than expected water sales volumes.<br />

Wastewater revenue was $203.77 million for the year, 1.2% lower than the budget of $206.29 million due to lower than expected volumes.<br />

Trade waste revenue was $14.0 million for the year and was higher than the budget by 2.4% due to higher than expected production for<br />

some customers.<br />

Other revenue was $23.8 million for the year and was 20.4% above budget due to higher miscellaneous revenue.<br />

<strong>2011</strong> <strong>2011</strong> <strong>2011</strong> 2010 2012<br />

actual budget Variance to Budget Actual Budget<br />

$000 $000 $000 $000<br />

Price adjustment<br />

Water - - - - -<br />

Wastewater - - - - -<br />

Trade waste - - - - -<br />

- - - - -<br />

Price adjustments are unbudgeted discretionary payments. The Directors determine the amount, and the distribution between customer groups,<br />

after having regard to the financial position of the company and future expenditure requirements. The Directors decided that no price adjustment<br />

would be made for <strong>2011</strong> (2010 – $Nil).<br />

<strong>2011</strong> <strong>2011</strong> <strong>2011</strong> 2010 2012<br />

actual budget Variance to Budget Actual Budget<br />

$000 $000 $000 $000<br />

Operating expenses<br />

Water<br />

Asset operating costs 19,577 21,909 10.6% 13,019 24,878<br />

Maintenance 18,361 21,987 16.5% 7,660 19,846<br />

Other expenses 25,591 23,769 (7.7%) 17,628 27,372<br />

63,529 67,665 6.1% 38,307 72,095<br />

Wastewater<br />

Asset operating costs 36,493 38,882 6.1% 22,467 41,110<br />

Maintenance 20,651 21,314 3.1% 11,615 24,349<br />

Other expenses 35,867 38,782 7.5% 16,345 44,659<br />

93,011 98,977 6.0% 50,427 110,118<br />

Total<br />

Asset operating costs 56,070 60,791 7.8% 35,486 65,987<br />

Maintenance 39,012 43,301 9.9% 19,275 44,195<br />

Other expenses 61,458 62,551 1.7% 33,973 72,031<br />

156,540 166,642 6.1% 88,734 182,213<br />

Asset operating costs for the year were 7.8% below budget. The main driver for the favourable variance was due to the savings in chemical and<br />

energy costs due to lower flows in the summer months. Savings in other asset costs were due to biosolids production volume being down and<br />

lower information systems operating costs than budgeted following integration.<br />

Maintenance costs were 9.9% lower than budget. The favourable variance was primarily due to deferral of the primary sedimentation tank at the<br />

Rosedale Wastewater Treatment Plant and savings across the water treatment plants and network maintenance programme.<br />

<strong>2011</strong> Financial <strong>Report</strong><br />

Other expenses for the year were 1.7% lower than budget due primarily to professional services and net labour costs being lower than budget.<br />

Professional services savings were achieved across the company due primarily to reprioritisation of spend in this area and staff focus on<br />

integration. The savings in net labour was mainly due to lower headcount than budgeted especially in the infrastructure and information systems<br />

groups. Other overhead savings were also achieved in training and travel due to staff focus on the integration of the retail business.<br />