10) Fixing of Steel Channel Sleepers at site :<br />
The Channel Sleepers shall be provided on the nominated bridges by the contractor. Following<br />
points are to be taken care of during execution of work:-<br />
Working in the vicinity of Railway Track :<br />
All works, which may affect the safety of Railway working, shall only be done under traffic<br />
block and written authority and also under the direct supervision of the Engineer-in-charge at site or his<br />
authorised representative for the said bridge. The Contractor shall in consultation with the Engineer,<br />
decide the sequence of work required to be done for efficient provision of channel sleepers.<br />
The gauge, level, alignment of the track shall be adjusted by the Contractor suitably as per<br />
satisfaction of the Engineer and as per tolerances laid down in <strong>Indian</strong> Railway Permanent Way Manual<br />
for New Track.<br />
11) The fabricator’s name & Drg. No. should be indicated on all Channel Sleepers suitably on a plaque<br />
fixed on the web of the channel sleeper at one end.<br />
12) Galvanised Steel Channel Sleepers are to be supplied and fixed on the bridges as shown in<br />
Annexure-A, Part I , under AEN/GMO & GJD. The existing track on the bridge is to be dismantled<br />
including guard rails,running rails, bridge timbers removing all the fittings & fastenings. New<br />
channel sleepers are to be fixed as per Drg. No. mentioned in Item No.1 of Sch-A with alteration and<br />
correction uptodate. The track is to be re-linked over the channel sleepers with the same or new<br />
running and guard rails by the fittings and fixtures supplied by the Contractor as per Item 1(Annexure<br />
B,) of Schedule of Items.<br />
13) Works has to be executed in the running traffic condition or under the traffic blocks. The will be<br />
made available as per the convenience of the Railway depending on the position of the trains. Block<br />
and caution orders will be taken and cancelled by the authorised Railway officials only.<br />
14) Released Unserviceable small fittings, Bridge Timbers and worn-out rails (if any) etc. will have to be<br />
transported by the contractor to the Store Depot of concerned PWI at his own expenditures and as<br />
instructed by Engineer-in-charge at site.<br />
15) Dip-lorries for the transportation of the materials has to be arranged by the Contractor at his own<br />
cost. However, Railway may supply Rly.’s dip lorry on hire charge basis as per General Condition of<br />
Contract- Vol. II, if available.<br />
16) Carrying of materials and protection of Dip lorries by trained staff will have to be done by contractor<br />
ensuring safe running of traffic under the supervision of Railway representative.<br />
17) Contractor has to arrange for adequate number of skilled workers and competent supervisors for the<br />
execution of this work, their safety during dismantling, transporting and linking of the track over the<br />
girders will be the sole responsibility of the contractor.<br />
18) Serviceable materials released from dismantling of the track should be properly accounted and kept<br />
in the custody of contractor for re-use. Unserviceable materials will be made good by the Railway (<br />
For rails, F/bolts Fish plates etc.).<br />
19) Materials supplied free of cost by the Railway to the contractor will not form part of the value of the<br />
contract entered into and will fall outside the purview of the price variation clause.<br />
20) All the mild steel fittings and fixtures have to be galvanised at the contractors cost before use.<br />
The above conditions are read/understand and accepted by me/us with the rates offered by me/us<br />
as above.<br />
SIGNATURE OF TENDERER(S)/CONTRACTOR(S)