iv)<br />

The calculations for adjustment in the amount payable to the contractor shall be<br />

made on the value of work done in each quarter by the contractor. Quarterly periods shall<br />

be counted commencing from the month following the month in which tender had been<br />

opened. Refer (D) below also.<br />

v) The calculations for adjustments should be based on the average price index of<br />

the three months of the quarter.<br />

vi)<br />

The demands of escalation of the cost may be allowed on the basis of provisional<br />

indices made available by the Reserve Bank of India. Any adjustment needed to be done<br />

based or the finally published indices shall be made as and when they become available.<br />

Base period for determining price variation clause should be either from the month of<br />

opening of the tender or if required from the month of negotiation as the case may be.<br />

vii) Price variation clause will not apply, if the price variation is upto 5%<br />

reimbursement/recovery due to variation in prices will continue to be made only for the<br />

amount in excess of 5% of the amount payable to the Contractor.<br />

a) For contracts upto two years duration :<br />

The total amount of reimbursement/recovery due to variation in prices of the several<br />

components, shall be limited to 10% (i.e. 15% - 5% floor price) of the amount finally payable to<br />

the contractor.<br />

b) For contracts of more than 2 years duration :<br />

The total amount of reimbursement/recovery due to variation in price of the several<br />

components shall be limited to 20% (25%-5% floor price) of amount finally payable to<br />

the contractor.<br />

D) Making adjustments for price variation :<br />

i) The adjustments for price variation i.e. extra payment in case of increase and<br />

recovery in case of decrease as required shall be made once every quarter in the onaccount<br />

payments. If more than one on-account payment is made to the contractor in a<br />

ii)<br />

quarter, the adjustment, if required, shall be made in each bill.<br />

It shall be contractor’s responsibility to submit the values of various price indices<br />

for appropriate points of time along with proof/authenticity thereof, to enable the Railway<br />

to calculate the price variation.<br />

E) Method of operation of this clause :<br />

i) Since the adjustments in payments are based on the amount of work done by<br />

contractor in each quarter, measurements of the actual work done must be taken and<br />

recorded in the measurement books and signed by the contractor at the end of each<br />

quarter, if not frequently.<br />

ii)<br />

iii)<br />

Since the various indices are published by RBI/Ministry of Labour of few months<br />

later than the months to which they pertain, the normal on account bills based on<br />

quarterly measurements will be prepared as per current procedure on the accepted rates<br />

without considering the price variation clause. The adjustments for price variation shall<br />

be done subsequently, through separate series of on account bills, called Escalation onaccount<br />

bill Nos. 1,2 etc. The adjustments bills and the normal on account bills will be<br />

kept independent of each other for facility of executions.<br />

Since the adjustments due to price variation are done on the basis of payments<br />

made for each type work as defined in Para-C(ii) above, it will be advisable to record<br />

measurements and prepare Abstracts for each type of work separately in each normal on<br />

accounts bills, so that the on accountBill/measurements do not have to be worked<br />

upon again at the time of preparing escalation account bills<br />

SIGNATURE OF TENDERER(S)/CONTRACTOR(S)