Page -28 of 40<br />

Do = Cost of detonators as fixed by DGS&D in the relevant rate contract of the firm<br />

from whom purchases of detonators are made by the contractor for the base period.<br />

D = Average cost of detonators as fixed by DGS&D in the relevant rate contract of<br />

the firm from whom purchases of detonators are made by the contractor for the three months of the<br />

quarter under consideration.<br />

P = % of labour component<br />

Q = % of material component<br />

Z = % of fuel component<br />

S = % of explosive component<br />

T = % of detonators component<br />

ii) Index Number :<br />

The base index number shall be that published by RBI for the month of opening of the tender and<br />

the quarters will commence from the month following the month of opening of the tender.<br />

The percentages P, Q, Z, S, T of various components i.e. labour, material,etc. for different types<br />

of work shall be as follows :<br />

Earthwork item :<br />

Labour component - 50%<br />

Fuel component - 20%<br />

Other material components- 15%<br />

Fixed component - 15%<br />

Ballast and quarry product items :<br />

Labour component - 55%<br />

Fuel component - 15%<br />

Other material components- 15%<br />

Fixed component - 15%<br />

Tunneling items :<br />

Labour component - 45%<br />

Fuel component - 15%<br />

Explosive component - 15%<br />

Detonators component - 05%<br />

Other material components- 05%<br />

Fixed component - 15%<br />

Other works items :(Applicable to the tendered work)<br />

Labour component - 30%<br />

Material component - - 30%<br />

Fuel component - 15%<br />

Fixed component - 15%<br />

iii)<br />

The amount on which the adjustment is to be calculated shall be the amount<br />

payable to the contractor for the item of items of various types of works given in © (ii)<br />

above, Refer (E) below for procedure of calculation of adjustment.<br />

SIGNATURE OF TENDERER(S)/CONTRACTOR(S)