iii)<br />
iv)<br />
Page -27 of 40<br />
The adjustment i.e. re-imbursement/recovery based on price indices shall be<br />
made only if, and to the extent, the amount to be adjusted is in excess of 5% of the<br />
amount payable to the contractor as per accepted rates.<br />
The price variation clause will be applicable to all extensions of time granted to<br />
the date of completion except that granted under Clause 17.B of GCC,2001.<br />
C) Method of calculation adjustments :<br />
i) The amount of adjustment i.e. increase/decrease in total payable amount shall be<br />
calculated by the following formula for each component of input, i.e. labour, material,<br />
fuel, explosive, detonator. There shall be a fixed component also on which no adjustment<br />
shall be made :<br />
a) L = R x(I – 10)/10 x P/100<br />
b) M = R x(W – Wo)/W0 x Q/100<br />
c) U = R x (F – Fo)/Fo x Z/100<br />
d) X = R x (E – Eo)/Eo x S/100<br />
e) N = R x (D – Do)/Do x T/100<br />
Where :-<br />
L = Amount of price variation in labour<br />
M = Amount of price variation in materials<br />
U = Amount of price variation in fuel<br />
X = Amount of price variation in explosives<br />
N = Amount of price variation in detonators.<br />
R = Gross value of the work done by the contractor as per on-account bill(s)<br />
excluding cost of materials supplied by Railway free or at a fixed price. This will also exclude specific<br />
payment, if any, to be made to the consultants engaged by the contractors (such payment will be indicated<br />
in the contractor’s offer).<br />
Io = Consumer price index number for Industrial workers. All India – Published in<br />
RBI Bulletin for the base period.<br />
I = Average consumer price index number for industrial workers – All India –<br />
published in RBI Bulletin for the three months of the quarter under consideration.<br />
Wo = Index number of whole sale prices – By groups and subgroups – All<br />
commodities – as published in the RBI bulletin for the base period.<br />
W = Average index number of whole sale prices – by groups and subgroups – all<br />
commodities – as published in the RBI Bulletin for the three months of the quarter under consideration.<br />
Fo = Index number of whole sale prices – by groups and subgroups for fuel, power,<br />
light and lubricants as published in the RBI bulletin for lthe base period.<br />
F = Average index number of whole sale prices – by groups and subgroups for fuel,<br />
power, light and lubricants as published in the RBI bulletin for the three months of the quarter under<br />
consideration.<br />
Eo = Cost of explosive as fixed by DGS&D in the relevant rates contract of the firm<br />
from whom purchases of explosives are made by the contractor for the base period.<br />
E = Average cost of explosives as fixed by DGS&D in the relevant rate contract of<br />
the firm from whom purchase of explosives are made by the contractor for the three months of the quarter<br />
under consideration.<br />
SIGNATURE OF TENDERER(S)/CONTRACTOR(S)