Page -25of 40<br />

19) APPOINTING TECHNICAL STAFF : The Contractor shall employ the following Technical<br />

Staff during the execution of the work :-<br />

i) One Graduate Engineer /Retired JE/P. Way or Works or Bridges of <strong>Railways</strong>.<br />

Technical Staff should be available at site on all working days to take instructions. In<br />

case the contractor fails to employ the technical staff as aforesaid, he shall be liable to pay of Rs.<br />

5000/- for each month’s default to provide Graduate Engineer.<br />

The decision of the Engineer-in-charge as to the period for which required technical staff was not<br />

employed by the contractor shall be final and binding on the contractor.<br />

20) PROCUREMENT OF MACHINERY BY CONTRCTOR : It should be clearly understood<br />

that it is entirely contractor’s responsibility and liability to find and procure all the machinery, tools<br />

and plants and their spare parts that are required in connection with execution of work. Delay in<br />

procurement of such items due to their non-availability or import difficulties or any other cause,<br />

what-so-ever shall not be taken as an excuse for slow progress or non-performance of the work.<br />

21) NON-ITEMWISED WORKS : Where items not covered by the Schedules are to be executed,<br />

the rates for such non-item wised works shall be negotiated before the commencement of such work or<br />

got executed through any other agency at the discretion of the Railway Administration.<br />

22) TIME IS THE ESSENCE OF CONTRACT : Time being the essence of contract all the works<br />

are required to be completed in all respect as stipulated by the Railway within the completion date.<br />

Progress shall be maintained strictly in accordance with programme given by the Engineer-in-charge from<br />

time to time.<br />

23) LEAD AND LIFT ON <strong>RAILWAY</strong>/CONTRACTOR’s MATERIALS : No lead and lift for the<br />

contractor’s materials is payable for the works executed under this contract.<br />

24)ACCEPTED RATES : The rates quoted by tenderer and accepted by the Railway<br />

Administration shall hold good till the completion of the work and no additional, individual claim shall be<br />

admissible on account of fluctuation in market rates, new impositions/increase in taxes, any other<br />

levies/tolls etc.<br />

25) OBSERVANCE OF BONDED LABOUR SYSTEM : (Abolition Ordinance Act,1975) “The<br />

Bonded Labour System (Abolition Ordinance Act,1975) would apply to the present contract. The<br />

contractors shall duly observe the provisions thereof”.<br />

26) It is the responsibility of the contractor for the safe loading, transportation and unloading and any loss<br />

or damage cause to adjacent Railway property will have to be made good by the Contractor at<br />

his/their own cost , failing which recoveries shall be effected from the running bill of the contractor<br />

as per the Clause No.13(iii) of the G.C.C.<br />

27) The liability arising out of accidents, if any, to persons will be met by the contractors and the Railway<br />

will not be responsible for any damage or compensation thereof. The contractor shall follow the<br />

provisions laid down in Contract Labour Act,1972.<br />

28) The Contractor shall be entirely responsible for ensuring safety of his labour, vehicles, plant or<br />

equipment while working along or near the track and highways and shall programme his working so<br />

as not to interfere with the movement of trains and road traffic. No extra payment shall be allowed to<br />

the contractor for all safety precautions to be observed during the execution of the work. The cost of<br />

all such precautions shall be deemed to be included in the rates for all items of the schedule.<br />

SIGNATURE OF TENDERER(S)/CONTRACTOR(S)