Page -21 of 40<br />

9) The Contract of the work shall be awarded only to the agencies who have got proven and recorded<br />

competency in shop fabrication of welded steel structure/channel sleepers and facilities for testing of<br />

welds for which necessary credentials should be submitted along with the tenders. They should<br />

submit the proof of having tested welders and qualified supervisors for welding work in their<br />

organisation. The Tenderer(s)/Contractor(s) shall submit along with the Tender attested Photostat<br />

copies of credentials for having successfully executed works as per eligibility criteria stipulated in<br />

previous para. He shall also produce evidence that he possesses the organisation and is technically<br />

resourceful to undertake this work.Tenders not accompanied with these documents will not be<br />

considered.<br />

10) Payment of the M.S.Grooved pad plates will be made as per the original tonnage of the plates used.<br />

No deduction or enhancement will be considered for grooves made or welding done.<br />

11) The basic cost, items & quantities are only approximate and for guidance of tenderer(s). This may<br />

vary as per the site conditions and no claim what-so-ever on this account will be entertained.<br />

12) Period of completion :<br />

The entire work should be completed within 03 Three) months from the date of issue of Letter of<br />

Acceptance.<br />

13) The work is to be executed with contractor’s materials and labour under the supervision and direction<br />

of PWI/BRI & DEN/AEN-in-charge of work.<br />

14) The rates quoted and accepted by the Rly. Are inclusive of all charges and taxes including sales tax,<br />

Octroi etc. as leviable by the Central Govt/State Govt/Civil Authorities.<br />

15) After completion of work, the same should be maintained for a period of six months. Any<br />

defect noticed during this period will be rectified by the Contractor at his own cost failing<br />

which the same will be rectified by the Railway Administration and the cost will be<br />

recovered from amounts due to the contractor including the Security Deposit.The security<br />

amount will be refunded after successful completion of maintenance period and certified<br />

by the Engineer-In-Charge.<br />

16) The work is to be carried out under traffic block. The block will be arranged by the Rly.<br />

However, Rly. will not be responsible for idling of man, materials and machinery due to<br />

non-availability of blocks.<br />

17) The tenderer should mention the place/workshop where they intend to manufacture/galvanize the<br />

channel sleepers & fittings.<br />

18. INSPECTION :<br />

a) The finished steel channel sleepers and Grooved Steel Plates which are inspected and<br />

passed for the work by the nominated Railway Officials, not below the rank of an<br />

Assistant Engineer, should only be brought to the work site by the contractor. The<br />

inspection shall be in two stages:<br />

i) Before galvanising (to check up the quality of fabrication)<br />

ii) After galvanising (to check up the quality of galvanising)<br />

b) The inspection will be carried out at the premises of the manufacturer.<br />

c) Necessary dye penetration test and Radio-active test should be conducted for all welding while<br />

passing the fabrication. Inspecting official nominated by Chief Bridge Engineer, East Central<br />

Railway will issue necessary Inspection Certificate as a proof of passing the channel sleepers<br />

after his inspection. Materials shall be despatched to site of work by the Contractor in full sets<br />

i.e., channel sleepers with all matching components fittings complete.