9) The Contract of the work shall be awarded only to the agencies who have got proven and recorded<br />
competency in shop fabrication of welded steel structure/channel sleepers and facilities for testing of<br />
welds for which necessary credentials should be submitted along with the tenders. They should<br />
submit the proof of having tested welders and qualified supervisors for welding work in their<br />
organisation. The Tenderer(s)/Contractor(s) shall submit along with the Tender attested Photostat<br />
copies of credentials for having successfully executed works as per eligibility criteria stipulated in<br />
previous para. He shall also produce evidence that he possesses the organisation and is technically<br />
resourceful to undertake this work.Tenders not accompanied with these documents will not be<br />
considered.<br />
10) Payment of the M.S.Grooved pad plates will be made as per the original tonnage of the plates used.<br />
No deduction or enhancement will be considered for grooves made or welding done.<br />
11) The basic cost, items & quantities are only approximate and for guidance of tenderer(s). This may<br />
vary as per the site conditions and no claim what-so-ever on this account will be entertained.<br />
12) Period of completion :<br />
The entire work should be completed within 03 Three) months from the date of issue of Letter of<br />
Acceptance.<br />
13) The work is to be executed with contractor’s materials and labour under the supervision and direction<br />
of PWI/BRI & DEN/AEN-in-charge of work.<br />
14) The rates quoted and accepted by the Rly. Are inclusive of all charges and taxes including sales tax,<br />
Octroi etc. as leviable by the Central Govt/State Govt/Civil Authorities.<br />
15) After completion of work, the same should be maintained for a period of six months. Any<br />
defect noticed during this period will be rectified by the Contractor at his own cost failing<br />
which the same will be rectified by the Railway Administration and the cost will be<br />
recovered from amounts due to the contractor including the Security Deposit.The security<br />
amount will be refunded after successful completion of maintenance period and certified<br />
by the Engineer-In-Charge.<br />
16) The work is to be carried out under traffic block. The block will be arranged by the Rly.<br />
However, Rly. will not be responsible for idling of man, materials and machinery due to<br />
non-availability of blocks.<br />
17) The tenderer should mention the place/workshop where they intend to manufacture/galvanize the<br />
channel sleepers & fittings.<br />
18. INSPECTION :<br />
a) The finished steel channel sleepers and Grooved Steel Plates which are inspected and<br />
passed for the work by the nominated Railway Officials, not below the rank of an<br />
Assistant Engineer, should only be brought to the work site by the contractor. The<br />
inspection shall be in two stages:<br />
i) Before galvanising (to check up the quality of fabrication)<br />
ii) After galvanising (to check up the quality of galvanising)<br />
b) The inspection will be carried out at the premises of the manufacturer.<br />
c) Necessary dye penetration test and Radio-active test should be conducted for all welding while<br />
passing the fabrication. Inspecting official nominated by Chief Bridge Engineer, East Central<br />
Railway will issue necessary Inspection Certificate as a proof of passing the channel sleepers<br />
after his inspection. Materials shall be despatched to site of work by the Contractor in full sets<br />
i.e., channel sleepers with all matching components fittings complete.