SPECIAL CONDITION OF CONTRACT ( PART – II )<br />

1) The rate of item No.01 is inclusive of trial assembling and fixing minimum 10 sleeper (selected at<br />

random) on a nominated bridge. The large scale manufacturing is to be taken up only when<br />

satisfactory performance will be obtained on trial.<br />

2) Payment schedule : Galvanised Channel Sleepers and its complete fittings and fixtures (For item<br />

No.01 of the tender schedule)<br />

a) On arrival of galvanised channel sleepers with all matching fittings for the numbers of<br />

sleepers received for item No.01 of Sch.A at Bridge works site _____60% (duly passed by<br />

inspecting officials and supported by relevant test/inspection certificate).<br />

b) Fixing of channel sleepers on the girder after dismantling the existing bridge timbers and<br />

completion of linking of running and guard rails over the channel sleeper with all fittings and<br />

fixtures in correct gauge, level and alignment as per IRPWM ______20%.<br />

c) Transportation and stacking of the released materials (small fittings, bridge timbers, etc.) to<br />

the Store Depot of concerned PWI ---- 20%.<br />

3) Galvanising of Steel Channel Sleepers and M.S. fittings shall be done by hot dip process of thickness<br />

100 ± 5 microns with Zinc conforming to IS:869-77 and IS:2629-85.<br />

4) Fixing of all elastomeric pads must be done by Epoxy adhesives approved by Rly’s Engineers<br />

supplied by contractor at his cost.<br />

a) Painting the sleeper seat by one coat of red lead paint conforming to IS:102 which will be<br />

supplied by the contractor.<br />

5) For all the supplied items the contractor has to give one Indemnity Bond and has to keep the items in<br />

safe custody by deputing day and night Watchman up to the completion of the work - Railway will<br />

have no responsibility on this account for theft, damage, loss etc. Payment will be entertained taking<br />

into account the materials fitted and fixed on the running lines. For the materials paid for as per 2(a)<br />

but not fixed on a bridge, prorata recovery will be made.<br />

6) Out of two holes for hook bolts, hole on one side of sleeper will be made in the work shop along with<br />

the fabrication of the channel sleepers and the hole on the other side will be drilled on actual<br />

measurement at site to ensure correct alignment of track after final assembly on the bridge.<br />

7) Care should be taken during transportation, loading, unloading, drilling holes, welding, etc. to ensure<br />

that no damage is done to the galvanising. However, galvanised surfaces inadvertently damaged, should<br />

be painted as detailed below :-<br />

a) Application of two coats of paint Red lead conforming to IS:102 as priming coats on an approved<br />

surface.<br />

b) Application of two coats of paint aluminum conforming to IS:2339 as covering coats as per the<br />

approval of the Engineer-in-charge.<br />

SIGNATURE OF TENDERER(S)/CONTRACTOR(S)