Name of the Work :<br />
Page -11 of 40<br />
East Central Railway<br />
(Schedule of rates)<br />
(Rates are to be quoted by the Tenderer/s)<br />
Supply and fixing of new galvanised steel channel sleepers with all fittings & fixtures<br />
after dismantling the existing bridge timbers / sleepers on Bridge No. 34(A) and 371<br />
(UP & DN) ( Total 108nos. ) under AEN(1)/GMO &GJD of Dhanbad Division.<br />
3 (Three) month from the date of issue of acceptance letter.<br />
Date of Completion :<br />
Schedule – A:<br />
Sl.<br />
No. Description of work<br />
1) Fabrication, transportation, supply and fixing of the new<br />
galvanised steel channel sleepers made from standard<br />
rolled section (conforming to IS-2062 Grade-B) after<br />
dismantling the existing track and bridge<br />
timbers/sleepers as per the approved drawings as<br />
mentioned in Annexure-A (containing details of the<br />
bridge, section of AEN, span details, section & length of<br />
channels sleepers, no. of sleepers etc.) including supply<br />
and fixing of all other required fittings and fixtures as<br />
per Annexure-B, read along with the Note below these<br />
Annexure and also special conditions of contract (Part –<br />
I, II & III) attached with this tender schedule, duly<br />
galvanized as per specifications indicated in the<br />
approved drawings at contractor’s cost complete.<br />
The work includes (1) cutting of steel<br />
plates/sections by mechanized means to size and shape,<br />
drilling, assembling, welding, riveting, bolting, holing,<br />
milling, grinding, machining, galvanizing of steel<br />
components, fixation by Epoxy adhesive as specified in<br />
drawing; (2) Removal and linking the running and guard<br />
rails including cutting and drilling of guard rail and<br />
running rails. (3) Transportation and stacking of the<br />
released materials {with not more than 2% (two percent)<br />
accountal loss} except rails to a nearest PWI/Store<br />
Depot at GMO/PRP according to the demand of<br />
requirement of the work and as per instructions of<br />
Engineering In-charge. (4) Supply of all fittings as<br />
mentioned in the relevant drawings including<br />
galvanizing of MS fittings. MS grooved/pad/packing<br />
plate may have to be welded with sleepers as shown in<br />
relevant drawings. However, payment of manufacture,<br />
transportation, supply and fixing including welding with<br />
sleepers if required of MS grooved/ pad/packing plates<br />
duly galvanized will be made separately under item<br />
No.2.<br />
Aprox.<br />
Qty.<br />
Unit<br />
Rate in<br />
figure<br />
Rate in<br />
words<br />
Sr.DEN(2)/DHN<br />
SIGNATURE OF TENDERER(S)/CONTRACTOR(S)