21.01.2014 Views

OES Annual Report 2012 - Ocean Energy Systems

OES Annual Report 2012 - Ocean Energy Systems

OES Annual Report 2012 - Ocean Energy Systems

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

123<br />

05 / DEVELOPMENT OF THE INTERNATIONAL<br />

OCEAN ENERGY INDUSTRY: PERFORMANCE<br />

IMPROVEMENTS AND COST REDUCTIONS<br />

ESB OCEAN PROJECT INDICATIVE PROJECT REQUIRED TRL LEVEL REQUIRED COST ENVELOPE<br />

Phase 1 Project Pre-Commercial Array (5-10MW) TRL 8 Table 1(b)<br />

Phase 2 Project Small Commercial Array (25MW+) TRL 9 Table 2<br />

Phase 3 Project Large Scale Array (50MW+) TRL 9 Table 3<br />

TABLE 6: TRL and Economic Requirements for ESB <strong>Ocean</strong> <strong>Energy</strong> Projects<br />

<strong>Ocean</strong> <strong>Energy</strong> Cost Trajectories<br />

Based on the cost envelopes in Tables 1 to 3, it is possible to extract realistic cost trajectories that ocean<br />

energy must achieve for commercial acceptability. For example, consider a wave energy technology that has<br />

been verified to TRL8 and is assessed to have a potential capacity factor of 25% (based on the application of<br />

specifications such as IEC 62600-100 and 62600-101 as well a realistic allowance for availability). Assuming<br />

that investors are happy that annual operational expenditure (Opex) can be kept at or below €250k per<br />

MW per year then the affordable capital expenditure (Capex) according to table 1(b) is €6.24m/MW. If this<br />

is sufficient to fund a phase 1 project, then as the industry grows for subsequent projects there is potential<br />

for overall project Capex and Opex to fall while energy yields increase. Table 7 below sets out a realistic<br />

trajectory for wave energy technology costs through the three phases. In this case, ultimate project Capex<br />

is projected to be €3.3m/MW, a little less than offshore wind, though Opex is a little higher, perhaps<br />

owing to accessibility to high wave energy sites. Figure 1 is based on this same logic, though it should<br />

be considered that different technologies will have varying expectations of capacity factor and Opex so<br />

many such Capex curves could be produced. It is only important that Capex, Opex and capacity factor are<br />

collectively within acceptable envelopes (Tables 1 to 3) at each stage.<br />

PROJECT PHASE PROJECTED CAPACITY FACTOR PROJECTED OPEX TARGET CAPEX<br />

1<br />

5-10MW<br />

25%<br />

based on TRL8 testing and application<br />

of IEC standards and allowance<br />

for poor reliability initially.<br />

€250k/MW/year<br />

based on allowance for poor reliability,<br />

increased need for intervention and lack<br />

of dedicated supply chain / vessels<br />

€6.2m/MW<br />

(from table 1b)<br />

2<br />

25MW+<br />

30%<br />

based on phase 1 project performance<br />

and demonstrated reliability (TRL9)<br />

€200k/MW/yr<br />

based on improved reliability<br />

and supply chain experience<br />

€5.0m/MW<br />

(from table 2)<br />

3<br />

50MW+<br />

35%<br />

based on improved reliability, design<br />

and access to more energetic sites.<br />

€130k/MW/yr<br />

based on bespoke supply chain facilities, vessels<br />

and much reduced need for repair intervention.<br />

€3.3m/MW<br />

(from table 3)<br />

TABLE 7: Realistic Cost Projections for Wave <strong>Energy</strong> Conversion Projects<br />

Project Cost Breakdown<br />

The costs given above are total project costs and it is useful to consider what cost breakdown is expected<br />

for wave and tidal energy projects. These costs can be broken down in various ways [4], [5] but will be<br />

broken down here under the below headings. Offshore wind is a useful guide [6] to understand the typical<br />

breakdown that is targeted. Opex is not considered here, so this is a breakdown of Capex only.<br />

ÌÌ<br />

Development – This is typically 4% of total Capex for offshore wind, it is expected that this will be similar<br />

for wave and tidal farms with similar consenting requirements.<br />

ÌÌ<br />

Converters – WECs / TECs – In offshore wind, turbines are typically 40% of the total Capex, uninstalled.<br />

It is expected that this will be closer to 45-50% for both wave and tidal farms due to the potential for<br />

savings in other Capex components.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!