3.4.5. Regula<strong>to</strong>ry approach<br />
Requirements<br />
German nuclear regulation, as applicable for <strong>the</strong> EWN project, consists of different levels. In respect <strong>to</strong><br />
decommissioning <strong>the</strong> following framework is relevant 11 :<br />
The phase between shutdown and issuance of <strong>the</strong> decommissioning permit is regulated as<br />
ongoing operation (post-operational phase). Removal, deconstruction or alternative use of items<br />
that are not relevant for safety is possible and requires <strong>the</strong> consent of <strong>the</strong> supervising regula<strong>to</strong>r.<br />
The opera<strong>to</strong>r’s overall plan for decommissioning describes <strong>the</strong> deconstruction phases, <strong>the</strong><br />
necessary means and <strong>to</strong>ols and <strong>the</strong> measures that are foreseen <strong>to</strong> guarantee <strong>the</strong> safety of <strong>the</strong><br />
public and of <strong>the</strong> workers. With <strong>the</strong>se documents, <strong>to</strong>ge<strong>the</strong>r with <strong>the</strong> environmental impact<br />
<strong>study</strong>, <strong>the</strong> opera<strong>to</strong>r applies for a permit. Additional underlying documents might be necessary. If<br />
<strong>the</strong> regula<strong>to</strong>r’s review of <strong>the</strong>se documents ends with a positive finding, <strong>the</strong> permit is granted<br />
(general decommissioning license). The decommissioning permit spans all phases of <strong>the</strong> project,<br />
usually adds fur<strong>the</strong>r license conditions and is not time-limited.<br />
During decommissioning <strong>the</strong> opera<strong>to</strong>r designs, plans and describes sub-projects or work<br />
packages that detail and substantiate <strong>the</strong> overall plan, in accordance with its general license.<br />
Depending upon practice, <strong>the</strong> opera<strong>to</strong>r has <strong>to</strong> seek regula<strong>to</strong>ry consent with <strong>the</strong>se plans or has <strong>to</strong><br />
apply for formal approval of <strong>the</strong> supervising agency.<br />
The role of <strong>the</strong> (general) decommissioning license as an end <strong>to</strong> <strong>the</strong> operating license and as a basic<br />
permit <strong>to</strong> decommission <strong>the</strong> facility is illustrated in Figure 26.<br />
Figure 26: The decommissioning license under German regulation<br />
Source: Authors<br />
Specific <strong>to</strong> German regula<strong>to</strong>ry practice is <strong>the</strong> continued regula<strong>to</strong>ry oversight. It includes sub-project<br />
applications and approvals, on-site control (e.g. expert accompanied inspections, double checking,<br />
etc.), independent assessments (e.g. independent sampling, exemplary proof by second party). The<br />
necessary approval processes can be closely adapted <strong>to</strong> <strong>the</strong> decommissioning project’s phases and <strong>to</strong><br />
<strong>the</strong>ir progress.<br />
11<br />
For a comprehensive description of <strong>the</strong> complete German regula<strong>to</strong>ry framework see: BfS 2009<br />