Link to the study - European Parliament - Europa

Link to the study - European Parliament - Europa Link to the study - European Parliament - Europa

europarl.europa.eu
from europarl.europa.eu More from this publisher
14.01.2014 Views

Policy Department D: Budgetary Affairs ____________________________________________________________________________________________ Figure 19: Development of work force from 2011 till 2119 and from 2011 till 2021 Source: (NAO 2012) As can be seen from the upper figure ('Long term manpower profile') the concept that these numbers are based on cannot be called a 'safe enclosure period' strategy because of the extremely high employment rates over several decades (until the year 2119). It is unclear from those figures what these many employees shall perform over this very long period. It looks like the work is simply delayed but not structured in conformance with subprojects and work steps. An integration of the curves yields roughly 430,000 man∙years in the lower case and roughly 560,000 man∙years in the upper case. With an average cost figure for wages of £ 50,000/man∙year over the whole period, those wages alone would add up to £ 21,500 million (EUR 26,000 million) in the lower case and £ 28,000 million (EUR 33,000 million) in the higher case. This indicates that either the cost calculation (see chapter 3.3.6) or the employment estimate here are inconsistent, differing by more than a factor of 100. One argument for choosing the NMP as new Parent Body was that there is the chance to use the expert knowledge available at its parent companies. With this outside expertise the performance in Sellafield was intended to be improved. But critics note the extremely high costs for the external workforce (House of Commons 2013). In 2011-2012 Sellafield Ltd had 16 executives from its parent body and NDA reimbursing their salaries and other costs, e.g. relocation packages. Between November 2008 and March 2012 this summed up to £ 32 million (NAO 2012). The parent body NMP also uses specialists known as 'reachback' for e.g. managing critical projects and programmes. NDA reimburses the costs plus an additional 10 % contribution to overheads of the parent companies. In 2011-2012 the total cost for the reachback was £ 17 million. In February 2012 the NDA identified decencies in the use of reachback resources. This resulted in the development of a reachback deployment strategy (NAO 2012). Other worries concern knowledge management over the long-term since foreign staff normally stays for only 2 to 3 years and all undocumented experience and knowledge gained is lost. 76

Nuclear Decommissioning: Management of Costs and Risks ____________________________________________________________________________________________ Sellafield Ltd works together with subcontractors. In 2011-2012 £ 986 million were spent on subcontractors. Of this 6 % was spent on subcontracts with the companies of the Parent body Nuclear Management Partners (NAO 2012). According to the National Audit Office gaps in the capability of subcontractors to undertake the required work have been identified (NAO 2012). The supply chain lacks capacity (NAO 2012). Therefore Sellafield Ltd produced a Procurement strategy in order to identify how to build up the supply chain to meet the requirements of the site (NAO 2012), e.g. waiting days should be reduced etc. Sellafield Ltd (in Sellafield Ltd 2011) now aims to prefer long term contracts with the supply chain organisations instead of the earlier usual short term contracts. 3.3.8. Financial control The NDA receives funds from the Department of Energy and Climate Change as grant-in aid to manage the site. NDA then reimburses Sellafield Ltd for all allowable costs including the costs for the executives and 'reachback' staff from the parent body. This means Sellafield Limited does not bear risks for delay and cost increases, because the contract with NDA requires it to reimburse Sellafield Limited for all allowable costs (NAO 2012). Additionally, NDA uses fees to incentivize efficiencies and achieve milestones which mean that NDA pays Sellafield Ltd fees according to the performance. But although the performance is less than planned, fees were still paid in the last years (NAO 2012, House of Commons 2013). The payments for fees in the period 2008-2009 until 2011-2012 are shown in Figure 20. 77

Nuclear Decommissioning: Management of Costs and Risks<br />

____________________________________________________________________________________________<br />

Sellafield Ltd works <strong>to</strong>ge<strong>the</strong>r with subcontrac<strong>to</strong>rs. In 2011-2012 £ 986 million were spent on<br />

subcontrac<strong>to</strong>rs. Of this 6 % was spent on subcontracts with <strong>the</strong> companies of <strong>the</strong> Parent body Nuclear<br />

Management Partners (NAO 2012).<br />

According <strong>to</strong> <strong>the</strong> National Audit Office gaps in <strong>the</strong> capability of subcontrac<strong>to</strong>rs <strong>to</strong> undertake <strong>the</strong><br />

required work have been identified (NAO 2012). The supply chain lacks capacity (NAO 2012).<br />

Therefore Sellafield Ltd produced a Procurement strategy in order <strong>to</strong> identify how <strong>to</strong> build up <strong>the</strong><br />

supply chain <strong>to</strong> meet <strong>the</strong> requirements of <strong>the</strong> site (NAO 2012), e.g. waiting days should be reduced<br />

etc. Sellafield Ltd (in Sellafield Ltd 2011) now aims <strong>to</strong> prefer long term contracts with <strong>the</strong> supply chain<br />

organisations instead of <strong>the</strong> earlier usual short term contracts.<br />

3.3.8. Financial control<br />

The NDA receives funds from <strong>the</strong> Department of Energy and Climate Change as grant-in aid <strong>to</strong><br />

manage <strong>the</strong> site. NDA <strong>the</strong>n reimburses Sellafield Ltd for all allowable costs including <strong>the</strong> costs for <strong>the</strong><br />

executives and 'reachback' staff from <strong>the</strong> parent body. This means Sellafield Limited does not bear<br />

risks for delay and cost increases, because <strong>the</strong> contract with NDA requires it <strong>to</strong> reimburse Sellafield<br />

Limited for all allowable costs (NAO 2012).<br />

Additionally, NDA uses fees <strong>to</strong> incentivize efficiencies and achieve miles<strong>to</strong>nes which mean that NDA<br />

pays Sellafield Ltd fees according <strong>to</strong> <strong>the</strong> performance. But although <strong>the</strong> performance is less than<br />

planned, fees were still paid in <strong>the</strong> last years (NAO 2012, House of Commons 2013). The payments for<br />

fees in <strong>the</strong> period 2008-2009 until 2011-2012 are shown in Figure 20.<br />

77

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!