14.01.2014 Views

Link to the study - European Parliament - Europa

Link to the study - European Parliament - Europa

Link to the study - European Parliament - Europa

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Policy Department D: Budgetary Affairs<br />

____________________________________________________________________________________________<br />

2.3. ECONOMIC BASIS OF DECOMMISSIONING PROJECTS<br />

2.3.1. Reliability of decommissioning cost estimates<br />

The costs for decommissioning projects can only be reliably estimated on <strong>the</strong> following basis:<br />

A detailed decommissioning plan that covers all work <strong>to</strong> be performed, all technologies <strong>to</strong> be<br />

applied, all necessary personnel and external services required ('Detailed decommissioning<br />

plan');<br />

Masses, types, activation and contamination characteristics of all materials <strong>to</strong> be removed<br />

('Material inven<strong>to</strong>ry');<br />

The necessary treatment, decontamination, conditioning 6 , packaging of all materials <strong>to</strong> be s<strong>to</strong>red<br />

and later disposed or that are <strong>to</strong> be immediately disposed ('Waste management plan').<br />

Cost estimates performed on a more generic and less precise basis can only yield raw figures, <strong>the</strong>se<br />

can prove <strong>to</strong> be false when detailed data becomes available. Cost figures that are taken from a<br />

smaller or different reac<strong>to</strong>r type, from a reac<strong>to</strong>r with a very different operating his<strong>to</strong>ry, etc., cannot be<br />

reliably converted <strong>to</strong> ano<strong>the</strong>r reac<strong>to</strong>r.<br />

2.3.2. Relevant decommissioning cost fac<strong>to</strong>rs<br />

Decommissioning costs not only depend on <strong>the</strong> above named fac<strong>to</strong>rs but can easily be higher by up<br />

<strong>to</strong> a fac<strong>to</strong>r of 1.5 or 2, e.g.<br />

if previous basic decisions are changed,<br />

if previously underestimated risks materialize,<br />

if <strong>the</strong> whole plan has <strong>to</strong> be restructured while decommissioning work is in progress,<br />

if <strong>the</strong> work in a time-critical step requires longer than estimated,<br />

if previously untested technologies fail and have <strong>to</strong> be re-adjusted or refitted,<br />

if <strong>the</strong> whole waste management schemes or <strong>the</strong> conditioning facilities have <strong>to</strong> be changed<br />

substantially, e.g. due <strong>to</strong> external fac<strong>to</strong>rs such as major changes in acceptance criteria of <strong>the</strong><br />

receiving s<strong>to</strong>rage or disposal facilities.<br />

These fac<strong>to</strong>rs limit <strong>the</strong> reliability of cost estimates in general, so that only facility-specific figures that<br />

are compatible with <strong>the</strong> above requirements and are regularly updated <strong>to</strong> reflect changes should be<br />

used.<br />

6<br />

Conditioning means all <strong>the</strong> measures that are necessary <strong>to</strong> bring a waste in<strong>to</strong> a condition that is fully<br />

compatible with <strong>the</strong> waste acceptance criteria of <strong>the</strong> receiving s<strong>to</strong>rage or disposal facility.<br />

44

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!