Link to the study - European Parliament - Europa

Link to the study - European Parliament - Europa Link to the study - European Parliament - Europa

europarl.europa.eu
from europarl.europa.eu More from this publisher
14.01.2014 Views

Policy Department D: Budgetary Affairs ____________________________________________________________________________________________ an international consultant. The PMU is responsible for all aspects of program and project management from planning and engineering to procurement, contract management and invoice control. It draws on expertise from other departments in the recipient’s organization and advises the recipient’s management on strategic issues. The PMU liaises with the Bank on all aspects of project implementation through regular reviews and the formal 'non objection process' (see project implementation). The services of the international consultant are procured through open tender. The scope and structure of the consultant’s involvement can vary significantly, essentially depending on the resources and competencies available in the recipient organization. The consultant should complement the recipient’s skills and provide, in particular, state-of-the-art technical, procurement and project management expertise. The Bank works in partnership with the recipients, and initially it is for the recipient to identify the areas in which support is required. The Bank reviews specifications for these consultancy services as diligently as for any other project. The Bank does however carry out capacity assessments, in particular with regard to procurement capabilities (which covers a broad range from the preparation of technical and commercial documents for tendering to contract management) and it may employ external experts to assess project management arrangements when necessary. PMU organisational structures and interfaces with the recipient are constantly under review and are periodically amended to introduce improvements based on the analysis of past experience, in order to adapt to different requirements at different stages of the decommissioning process and to take into account the transfer of knowledge from consultant to recipient. To date, all three recipient organizations have undergone significant organizational changes during implementation of the decommissioning programs. All three started as operating organizations and were at times responsible for shutdown and operating units. In Kozloduy and Bohunice, organizations responsible for closed units have been separated from operating utilities (something that is not required in Ignalina where all units are closed). The necessary changes are, of course, a responsibility of the organizations and national authorities concerned. However, the Bank, as manager of the decommissioning support funds, takes an active interest in any changes that may impact the implementation of programs financed from the PP&R 26 apply with the limitation that tenders are open only to companies from donor countries (in this case including all member countries of the European Union) or the Bank’s countries of operation IDSFs. In cases where the recipient’s organization changes, the Bank engages in discussions with the recipient to assess whether the organization still fulfills all requirements, and encourages both the use of experience from international best practice and input from the PMU Consultant to ensure that efficient decommissioning management structures are being put in place and maintained. The Funds also finance training programs for recipient’s staff in project management, procurement and other relevant disciplines, with a particular emphasis on decommissioning. The recipient enters into contracts with suppliers on the basis of the Grant Agreement with the Bank. The Bank is not a party to these contracts and the recipient is fully responsible. The PMU processes invoices, certifies that all contractual requirements are fulfilled and requests the Bank to pay. The Bank reviews invoices against contracts and against the, provisions of the Grant Agreement (and in 26 PP&R apply with the limitation that tenders are open only to companies from donor countries (in this case including all member countries of the European Union) or the Bank’s countries of operation 196

Nuclear Decommissioning: Management of Costs and Risks ____________________________________________________________________________________________ some cases other conditions imposed by the Assembly of Contributors) and disburses directly to the contractor. Grant Agreements can be suspended and terminated if the recipient fails to comply with its provisions. The Bank obliges the recipient to adhere strictly to the Bank’s Environmental and Social Policy. The Bank appraises each potential project on its merits before it presents it to the Assembly but always attaches great importance to the availability of a coherent strategic framework in which individual projects have a logical place. This is true for energy sector projects but even more so for a complex decades-long process such as the decommissioning of a nuclear power plant. In all three countries significant work has been done on decommissioning strategies and regulatory requirements for decommissioning planning. It was a high priority for the Bank to assist the recipients in developing high quality decommissioning plans. The Bank has supported involvement of PMU consultants and external experts using funding from the Funds to achieve this goal. Detailed decommissioning plans, approved by the respective regulatory authorities, are now available for all three NPPs. These define sequences, projects and schedule and take into account the most recent inventory of radioactive materials. It is true that decommissioning plans should ideally be available ahead of closure and some aspects of decommissioning should already be taken into account in the design of the plant. However, the three recipients did not find themselves in an ideal situation. In Soviet times, early planning for decommissioning was underdeveloped in most countries. The decision to close the plants early further reduced the preparatory time available, and reluctance to close (at some political, management and workforce levels) was not conducive to thorough and genuine decommissioning planning. The Bank has created technical advisory bodies for all its funds. These are comprised of independent experts nominated on the merit of their expertise. These groups have provided high level technical guidance on strategic topics and were particularly helpful in the early phase of the programs when strategic decisions on the direction of the program and on individual urgent projects had to be taken in the absence of fully developed decommissioning plans. Project Implementation Project implementation is primarily a task for the recipient and its PMU. The Bank is, however, closely involved. The Bank employs a senior program manager for each Fund, dedicated to overseeing work one of that Fund. He (she) follows projects on a day-to-day basis and typically spends about half his time at project sites for project review meetings and in depth analysis of project and procurement documents. Project review includes all project and contract management areas, including the PMU’s quality assurance and risk management approaches, and any technical or commercial issues impacting progress. The Bank is entitled to receive any project-related documentation. It receives detailed monthly reports from the PMUs. One example of a monthly report (BIDSF) is attached as requested. The recipient and its PMU develop technical specifications and cost and schedule estimates for projects to be funded from the Fund. Occasionally, the recipient may propose a project which may also be used for a purpose other than that of the decommissioning fund. It may, for instance, make sense to design a waste facility so that it can be used for the treatment of historic waste, as well as for 197

Nuclear Decommissioning: Management of Costs and Risks<br />

____________________________________________________________________________________________<br />

some cases o<strong>the</strong>r conditions imposed by <strong>the</strong> Assembly of Contribu<strong>to</strong>rs) and disburses directly <strong>to</strong> <strong>the</strong><br />

contrac<strong>to</strong>r. Grant Agreements can be suspended and terminated if <strong>the</strong> recipient fails <strong>to</strong> comply with<br />

its provisions.<br />

The Bank obliges <strong>the</strong> recipient <strong>to</strong> adhere strictly <strong>to</strong> <strong>the</strong> Bank’s Environmental and Social Policy.<br />

The Bank appraises each potential project on its merits before it presents it <strong>to</strong> <strong>the</strong> Assembly but<br />

always attaches great importance <strong>to</strong> <strong>the</strong> availability of a coherent strategic framework in which<br />

individual projects have a logical place. This is true for energy sec<strong>to</strong>r projects but even more so for a<br />

complex decades-long process such as <strong>the</strong> decommissioning of a nuclear power plant. In all three<br />

countries significant work has been done on decommissioning strategies and regula<strong>to</strong>ry<br />

requirements for decommissioning planning. It was a high priority for <strong>the</strong> Bank <strong>to</strong> assist <strong>the</strong> recipients<br />

in developing high quality decommissioning plans. The Bank has supported involvement of PMU<br />

consultants and external experts using funding from <strong>the</strong> Funds <strong>to</strong> achieve this goal. Detailed<br />

decommissioning plans, approved by <strong>the</strong> respective regula<strong>to</strong>ry authorities, are now available for all<br />

three NPPs. These define sequences, projects and schedule and take in<strong>to</strong> account <strong>the</strong> most recent<br />

inven<strong>to</strong>ry of radioactive materials.<br />

It is true that decommissioning plans should ideally be available ahead of closure and some aspects<br />

of decommissioning should already be taken in<strong>to</strong> account in <strong>the</strong> design of <strong>the</strong> plant. However, <strong>the</strong><br />

three recipients did not find <strong>the</strong>mselves in an ideal situation. In Soviet times, early planning for<br />

decommissioning was underdeveloped in most countries. The decision <strong>to</strong> close <strong>the</strong> plants early<br />

fur<strong>the</strong>r reduced <strong>the</strong> prepara<strong>to</strong>ry time available, and reluctance <strong>to</strong> close (at some political,<br />

management and workforce levels) was not conducive <strong>to</strong> thorough and genuine decommissioning<br />

planning.<br />

The Bank has created technical advisory bodies for all its funds. These are comprised of independent<br />

experts nominated on <strong>the</strong> merit of <strong>the</strong>ir expertise. These groups have provided high level technical<br />

guidance on strategic <strong>to</strong>pics and were particularly helpful in <strong>the</strong> early phase of <strong>the</strong> programs when<br />

strategic decisions on <strong>the</strong> direction of <strong>the</strong> program and on individual urgent projects had <strong>to</strong> be taken<br />

in <strong>the</strong> absence of fully developed decommissioning plans.<br />

Project Implementation<br />

Project implementation is primarily a task for <strong>the</strong> recipient and its PMU. The Bank is, however, closely<br />

involved. The Bank employs a senior program manager for each Fund, dedicated <strong>to</strong> overseeing work<br />

one of that Fund. He (she) follows projects on a day-<strong>to</strong>-day basis and typically spends about half his<br />

time at project sites for project review meetings and in depth analysis of project and procurement<br />

documents. Project review includes all project and contract management areas, including <strong>the</strong> PMU’s<br />

quality assurance and risk management approaches, and any technical or commercial issues<br />

impacting progress.<br />

The Bank is entitled <strong>to</strong> receive any project-related documentation. It receives detailed monthly<br />

reports from <strong>the</strong> PMUs. One example of a monthly report (BIDSF) is attached as requested.<br />

The recipient and its PMU develop technical specifications and cost and schedule estimates for<br />

projects <strong>to</strong> be funded from <strong>the</strong> Fund. Occasionally, <strong>the</strong> recipient may propose a project which may<br />

also be used for a purpose o<strong>the</strong>r than that of <strong>the</strong> decommissioning fund. It may, for instance, make<br />

sense <strong>to</strong> design a waste facility so that it can be used for <strong>the</strong> treatment of his<strong>to</strong>ric waste, as well as for<br />

197

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!