Policy Department D: Budgetary Affairs<br />

____________________________________________________________________________________________<br />

- Projects progress<br />

- Financial and accounting management<br />

can be described in a simplified form as follows:<br />

Tools for project management, used in JAVYS<br />

In <strong>the</strong> process of project management, JAVYS uses <strong>the</strong> following basic levels of management: Project<br />

Manager, Project Engineer, Steering Committee, and Board of Direc<strong>to</strong>rs:<br />

- The project manager is a full-time employee of JAVYS and personally manages one or several<br />

decommissioning sub-projects and leads appointed project team(s), consisting of experts from<br />

different fields. The project has appointed professional guaran<strong>to</strong>r (being a relevant division<br />

direc<strong>to</strong>r), who directs <strong>the</strong> strategic concept and <strong>the</strong> main direction of <strong>the</strong> project.<br />

- Project Engineer is responsible for overall project management of V1 NPP decommissioning set<br />

by <strong>the</strong> project management system and he is <strong>the</strong> representative of <strong>the</strong> operational project<br />

management (and in <strong>the</strong> case of <strong>the</strong> supply model he is also representative <strong>to</strong> <strong>the</strong> contrac<strong>to</strong>r in<br />

accordance with <strong>the</strong> applied rules and contractual FIDIC conditions).<br />

- The Steering Committee consists of <strong>the</strong> Head of PMU (Project Management Unit) and of<br />

representatives of o<strong>the</strong>r JAVYS’ divisions involved in <strong>the</strong> V1 NPP decommissioning project<br />

activities. They address <strong>the</strong> interfaces with o<strong>the</strong>r JAVYS’ projects, as well as o<strong>the</strong>r business<br />

activities in JAVYS.<br />

- The Board of Direc<strong>to</strong>rs represents <strong>the</strong> highest governing body addressing <strong>the</strong> fundamental<br />

questions of project scope, management and <strong>the</strong> budget.<br />

Project management in addition <strong>to</strong> internal meetings is also performed on <strong>the</strong> monthly progress<br />

meeting of V1 NPP decommissioning project, involving <strong>the</strong> representatives of <strong>the</strong> <strong>European</strong> Bank for<br />

Reconstruction and Development (EBRD) and PMU Consultant (Project Management Unit).<br />

Project management process continues in <strong>the</strong> external environment of JAVYS company, through <strong>the</strong><br />

Ministry of Economy as <strong>the</strong> sole JAVYS’ shareholder and decommissioning coordina<strong>to</strong>r at <strong>the</strong> national<br />

level. The next level of management is through so-called The Joint Committee of <strong>the</strong> Slovak Republic<br />

and <strong>the</strong> EBRD, in which operate, in addition <strong>to</strong> <strong>the</strong> above-mentioned entities, also relevant Slovak<br />

authorities, including <strong>the</strong> State Nuclear Regula<strong>to</strong>ry Authority, <strong>the</strong> National Nuclear Fund, Ministry of<br />

Finance, Office of <strong>the</strong> Government, etc. Information about decommissioning is presented also <strong>to</strong> <strong>the</strong><br />

Slovak Government every year.<br />

This management structure is fully functional for escalation and subsequent decisions making in<br />

managing of questions, problems and risks in risk and changes management.<br />

Risk management<br />

Within <strong>the</strong> document 'Bohunice V1 NPP Decommissioning Strategy Report' a conceptual risk<br />

management for <strong>the</strong> overall V1 NPP decommissioning project has been developed. Risk management<br />

for <strong>the</strong> overall V1 NPP decommissioning project identifies risk categories (from very low <strong>to</strong> very high,<br />

probability criteria and impact criteria) with 6 major risks defined. Each major risk includes <strong>the</strong> type,<br />

definition, risk fac<strong>to</strong>r with assigned probability of occurrence and potential impact on <strong>the</strong><br />

decommissioning project.<br />

182