Policy Department D: Budgetary Affairs<br />

____________________________________________________________________________________________<br />

Comprehensive document: 'Strategy of Bohunice V1 NPP Decommissioning':<br />

Was based on older document 'Bohunice V1 NPP Decommissioning Strategy Report' (2010). This 'Report'<br />

defined all steps necessary for successful end of decommissioning works in 2025 even before<br />

issuance 1 st stage decommissioning licence.<br />

New document 'Strategy of Bohunice V1 NPP Decommissioning' was elaborated and approved in<br />

2012 and it provided a substantial improvement and enlargement of <strong>the</strong> previous 'Bohunice V1 NPP<br />

Decommissioning Strategy Report'. The document provided mainly:<br />

- comprehensive 'roadmap' of all decommissioning activities;<br />

- database of all decommissioning projects till 2025 (decommissioning completion);<br />

- logistic scheme of all projects split up according <strong>to</strong>:<br />

i) types of activities,<br />

ii)<br />

respective decommissioning phase;<br />

- logistic scheme including interfaces among projects;<br />

- identification of BIDSF projects eligible for grant allocation <strong>to</strong>ge<strong>the</strong>r with time schedule of<br />

projects` granting;<br />

- identification of 'KPI' (key performance indica<strong>to</strong>rs) for decommissioning projects;<br />

- chart depicting implementation phases of all projects<br />

IPBTS ('Integral Project Baseline Time Schedule'):<br />

Managerial Tool (based on 'MS Project' application) with complete database of all decommissioning<br />

projects, <strong>the</strong>ir time schedule (including prepara<strong>to</strong>ry phase, tender prepara<strong>to</strong>ry phase, tender phase<br />

and implementation phase). IPBTS is being updated on weekly basis.<br />

The identified decision breakpoints in that plan (technical, regula<strong>to</strong>ry and financial<br />

dependencies, decision base, etc.)<br />

Main decision break-points:<br />

a) The first decision break point was early decision of Slovak republic <strong>to</strong> construct and operate<br />

<strong>the</strong> nuclear back-end cycle infrastructure, <strong>to</strong>ok in 1980’s and 1990’s. JAVYS thus already<br />

operates all facilities necessary for successful and complex decommissioning activities:<br />

- Interim Spent Fuel S<strong>to</strong>rage,<br />

- RAW Treatment Centre, and<br />

- National reposi<strong>to</strong>ry of radioactive waste<br />

b) The second main breakpoint was establishment of National Nuclear Fund already in in 1995,<br />

which was set up <strong>to</strong> continuously collect funds for later decommissioning purposes<br />

(according <strong>to</strong> planned lifetime of nuclear powerplants).<br />

c) Selection of decommissioning alternative. Outcomes of BIDSF projects B6.1 (The V1 NPP<br />

Conceptual Decommissioning Plan) and B6.2 (The Environmental Impact Assessment Report<br />

of V1 NPP Decommissioning) resulted in selection of <strong>the</strong> 'Immediate Dismantling Option'<br />

(IDO) consisting of Decommissioning Phase 1 (2011-2014) and Phase 2 (2015-2025).<br />

166