Policy Department D: Budgetary Affairs<br />
____________________________________________________________________________________________<br />
Comprehensive document: 'Strategy of Bohunice V1 NPP Decommissioning':<br />
Was based on older document 'Bohunice V1 NPP Decommissioning Strategy Report' (2010). This 'Report'<br />
defined all steps necessary for successful end of decommissioning works in 2025 even before<br />
issuance 1 st stage decommissioning licence.<br />
New document 'Strategy of Bohunice V1 NPP Decommissioning' was elaborated and approved in<br />
2012 and it provided a substantial improvement and enlargement of <strong>the</strong> previous 'Bohunice V1 NPP<br />
Decommissioning Strategy Report'. The document provided mainly:<br />
- comprehensive 'roadmap' of all decommissioning activities;<br />
- database of all decommissioning projects till 2025 (decommissioning completion);<br />
- logistic scheme of all projects split up according <strong>to</strong>:<br />
i) types of activities,<br />
ii)<br />
respective decommissioning phase;<br />
- logistic scheme including interfaces among projects;<br />
- identification of BIDSF projects eligible for grant allocation <strong>to</strong>ge<strong>the</strong>r with time schedule of<br />
projects` granting;<br />
- identification of 'KPI' (key performance indica<strong>to</strong>rs) for decommissioning projects;<br />
- chart depicting implementation phases of all projects<br />
IPBTS ('Integral Project Baseline Time Schedule'):<br />
Managerial Tool (based on 'MS Project' application) with complete database of all decommissioning<br />
projects, <strong>the</strong>ir time schedule (including prepara<strong>to</strong>ry phase, tender prepara<strong>to</strong>ry phase, tender phase<br />
and implementation phase). IPBTS is being updated on weekly basis.<br />
The identified decision breakpoints in that plan (technical, regula<strong>to</strong>ry and financial<br />
dependencies, decision base, etc.)<br />
Main decision break-points:<br />
a) The first decision break point was early decision of Slovak republic <strong>to</strong> construct and operate<br />
<strong>the</strong> nuclear back-end cycle infrastructure, <strong>to</strong>ok in 1980’s and 1990’s. JAVYS thus already<br />
operates all facilities necessary for successful and complex decommissioning activities:<br />
- Interim Spent Fuel S<strong>to</strong>rage,<br />
- RAW Treatment Centre, and<br />
- National reposi<strong>to</strong>ry of radioactive waste<br />
b) The second main breakpoint was establishment of National Nuclear Fund already in in 1995,<br />
which was set up <strong>to</strong> continuously collect funds for later decommissioning purposes<br />
(according <strong>to</strong> planned lifetime of nuclear powerplants).<br />
c) Selection of decommissioning alternative. Outcomes of BIDSF projects B6.1 (The V1 NPP<br />
Conceptual Decommissioning Plan) and B6.2 (The Environmental Impact Assessment Report<br />
of V1 NPP Decommissioning) resulted in selection of <strong>the</strong> 'Immediate Dismantling Option'<br />
(IDO) consisting of Decommissioning Phase 1 (2011-2014) and Phase 2 (2015-2025).<br />