Nuclear Decommissioning: Management of Costs and Risks<br />
____________________________________________________________________________________________<br />
ANNEX 5 - WRITTEN ANSWERS FROM JAVYS, SLOVAKIA<br />
(Underlined text refers <strong>to</strong> <strong>the</strong> questionnaire)<br />
The conceptual planning within <strong>the</strong> Project<br />
The overall plan of <strong>the</strong> Project, it’s major work packages, it’s ordering and serial flow, etc.<br />
It is manda<strong>to</strong>ry for all Slovak nuclear power plants <strong>to</strong> prepare and periodically update Conceptual<br />
decommissioning plans already during construction and operation of <strong>the</strong> power plant. This was also<br />
<strong>the</strong> case of strategic preparedness of V1 NPP for its due decommissioning. These conceptual<br />
documents were later replaced by detailed 1 st Stage Decommissioning licence documentation and<br />
overall V1 NPP Decommissioning Strategy.<br />
Conceptual Plan:<br />
Conceptual Planning of Bohunice NPP V1 decommissioning was commenced in frame of <strong>the</strong> project<br />
titled 'Conceptual Planning'.<br />
The mentioned project was completed in 2007. Multicriterial analysis resulted in selection of <strong>the</strong><br />
Immediate Decommissioning Option ('IDO') out of 4 analysed alternatives. This option assumes 2<br />
decommissioning stages of Bohunice NPP V1 and decommissioning activities completion by 2025.<br />
The project was followed by consecutive activities:<br />
1) The Environmental Impact Assessment Report of V1 NPP Decommissioning,<br />
2) The V1 NPP Decommissioning 1st Stage Plan & O<strong>the</strong>r Documentation, and<br />
3) Decommissioning Database<br />
Later on, <strong>the</strong> outputs from abovementioned projects were used for development of <strong>the</strong> Bohunice V1<br />
NPP Decommissioning Strategy Report (2010), later replaced by updated and renamed version called<br />
Strategy of Bohunice V1 NPP Decommissioning (described in detail below).<br />
Based on <strong>the</strong> abovementioned projects were identified and defined single decommissioning projects<br />
packets as follows:<br />
Packet of decommissioning projects (sorted by criterion: Types of activities):<br />
”A” block: Projects related <strong>to</strong> NPP modification for decommissioning activities and development of<br />
comprehensive documentation<br />
”B” block:<br />
”C” block:<br />
Projects related <strong>to</strong> decommissioning licencing<br />
Projects related <strong>to</strong> wastes and RAW management<br />
”D” block: Projects related <strong>to</strong> systems dismantling & buildings demolition (i.e. decommissioning)<br />
Packets of decommissioning projects (sorted by criterion: Implementation time frame):<br />
- Projects <strong>to</strong> be implemented in Stage 1 of Bohunice NPP V1 decommissioning (2011-2014),<br />
- Projects <strong>to</strong> be implemented in Stage 2 of Bohunice NPP V1 decommissioning (2015-2025),<br />