Nuclear Decommissioning: Management of Costs and Risks<br />

____________________________________________________________________________________________<br />

ANNEX 5 - WRITTEN ANSWERS FROM JAVYS, SLOVAKIA<br />

(Underlined text refers <strong>to</strong> <strong>the</strong> questionnaire)<br />

The conceptual planning within <strong>the</strong> Project<br />

The overall plan of <strong>the</strong> Project, it’s major work packages, it’s ordering and serial flow, etc.<br />

It is manda<strong>to</strong>ry for all Slovak nuclear power plants <strong>to</strong> prepare and periodically update Conceptual<br />

decommissioning plans already during construction and operation of <strong>the</strong> power plant. This was also<br />

<strong>the</strong> case of strategic preparedness of V1 NPP for its due decommissioning. These conceptual<br />

documents were later replaced by detailed 1 st Stage Decommissioning licence documentation and<br />

overall V1 NPP Decommissioning Strategy.<br />

Conceptual Plan:<br />

Conceptual Planning of Bohunice NPP V1 decommissioning was commenced in frame of <strong>the</strong> project<br />

titled 'Conceptual Planning'.<br />

The mentioned project was completed in 2007. Multicriterial analysis resulted in selection of <strong>the</strong><br />

Immediate Decommissioning Option ('IDO') out of 4 analysed alternatives. This option assumes 2<br />

decommissioning stages of Bohunice NPP V1 and decommissioning activities completion by 2025.<br />

The project was followed by consecutive activities:<br />

1) The Environmental Impact Assessment Report of V1 NPP Decommissioning,<br />

2) The V1 NPP Decommissioning 1st Stage Plan & O<strong>the</strong>r Documentation, and<br />

3) Decommissioning Database<br />

Later on, <strong>the</strong> outputs from abovementioned projects were used for development of <strong>the</strong> Bohunice V1<br />

NPP Decommissioning Strategy Report (2010), later replaced by updated and renamed version called<br />

Strategy of Bohunice V1 NPP Decommissioning (described in detail below).<br />

Based on <strong>the</strong> abovementioned projects were identified and defined single decommissioning projects<br />

packets as follows:<br />

Packet of decommissioning projects (sorted by criterion: Types of activities):<br />

”A” block: Projects related <strong>to</strong> NPP modification for decommissioning activities and development of<br />

comprehensive documentation<br />

”B” block:<br />

”C” block:<br />

Projects related <strong>to</strong> decommissioning licencing<br />

Projects related <strong>to</strong> wastes and RAW management<br />

”D” block: Projects related <strong>to</strong> systems dismantling & buildings demolition (i.e. decommissioning)<br />

Packets of decommissioning projects (sorted by criterion: Implementation time frame):<br />

- Projects <strong>to</strong> be implemented in Stage 1 of Bohunice NPP V1 decommissioning (2011-2014),<br />

- Projects <strong>to</strong> be implemented in Stage 2 of Bohunice NPP V1 decommissioning (2015-2025),<br />