14.01.2014 Views

Link to the study - European Parliament - Europa

Link to the study - European Parliament - Europa

Link to the study - European Parliament - Europa

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Nuclear Decommissioning: Management of Costs and Risks<br />

____________________________________________________________________________________________<br />

4.4.2. Comparison and evaluation of <strong>the</strong> national organisations with best practice<br />

The change processes in <strong>the</strong> two best practice examples EWN and EDF were very different. The<br />

organisation and processes at EWN were changed rapidly because it was already clear at an early<br />

stage that decommissioning was <strong>the</strong> only option and that this requires a completely different<br />

approach (project management). The setup process at EDF only started after <strong>the</strong> basic decision for<br />

decommissioning was taken, but <strong>the</strong>n was consistent and complete.<br />

Compared <strong>to</strong> <strong>the</strong>se two examples, <strong>the</strong> change processes in Bulgaria, Lithuania and Slovakia were<br />

considerably slower, required more interim steps and in some aspects are still not sufficiently<br />

effective. Several reasons played a role in <strong>the</strong> past:<br />

The decision <strong>to</strong> shut <strong>the</strong> plants down was seen as possibly reversible. That kept responsible<br />

management and workforce from adopting <strong>the</strong> task early and with <strong>the</strong> necessary rigor.<br />

Decommissioning was not seen as an ambitious task but much less demanding than operation<br />

of <strong>the</strong> facility. The complexity of this undertaking was generally underestimated.<br />

In <strong>the</strong> first phase <strong>the</strong> management of <strong>the</strong> reac<strong>to</strong>rs had no experiences at all with <strong>the</strong> new<br />

situation and tried <strong>to</strong> manage <strong>the</strong> changed situation with some additions or 'add-ons' <strong>to</strong> <strong>the</strong>ir<br />

organisation until this, years later, proved <strong>to</strong> be inadequate.<br />

In this phase nearly no exchange between <strong>the</strong> three countries was established so that learning<br />

from more advanced countries (e.g. Slovakia) or a systematic, planned and well-organized<br />

experience exchange with <strong>the</strong> o<strong>the</strong>r affected countries and/or with countries having advanced<br />

experiences in decommissioning did not occur.<br />

Organisational issues were in general underestimated so that continuity in <strong>the</strong> established<br />

structures was chosen and kept as long as possible.<br />

These aspects do not play a role any more. From our interviews, site visits and from <strong>the</strong> answers <strong>to</strong><br />

our questionnaire we evaluate <strong>to</strong>day’s internal structures, <strong>the</strong> self-confidence of <strong>the</strong> management<br />

and <strong>the</strong> awareness about <strong>the</strong> necessary changes are well-established in all three countries.<br />

Ano<strong>the</strong>r aspect that was over long periods very different from EWN and EDF’s principal practices was<br />

that <strong>the</strong> main managing and planning instrument, <strong>the</strong> PMU, was constructed outside <strong>the</strong> managing<br />

organisation. The PMU unit consisted of two different member categories:<br />

Experts as employed by, nominated by, reporting <strong>to</strong> and under full control of <strong>the</strong> managing<br />

organisation;<br />

External consultants, as selected, controlled and fully administered by EBRD.<br />

This construction was not in line with <strong>the</strong> framework agreement between <strong>the</strong> countries and EBRD,<br />

which defined <strong>the</strong> task <strong>to</strong> establish PMUs as part of <strong>the</strong> managing organisation and under national<br />

control (see <strong>the</strong> respective text of such an agreement on page 103). Decision-making, not only on<br />

operational but also in strategic issues (see chapter 2.4.3), previously a task between <strong>the</strong> internal PMU<br />

and its controlling ministry, was shifted <strong>to</strong>wards <strong>the</strong> external PMU and EBRD. This PMU design is<br />

shown in Figure 36.<br />

109

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!