Kooloonbung Creek Footbridge Options Study ... - Hastings Council

Kooloonbung Creek Footbridge Options Study ... - Hastings Council Kooloonbung Creek Footbridge Options Study ... - Hastings Council

hastings.nsw.gov.au
from hastings.nsw.gov.au More from this publisher

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

<strong>Options</strong> <strong>Study</strong> Report<br />

Ref: T-N0115.00/2REP<br />

Proposal Prepared for Port Macquarie-<strong>Hastings</strong><br />

<strong>Council</strong> – August 2012


<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

<strong>Options</strong> <strong>Study</strong> Report<br />

August 2012<br />

Prepared for Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

Opus International Consultants (NSW) Pty Ltd<br />

Newcastle Office<br />

Suite 2, 8-14 Telford Street, Newcastle NSW 2300<br />

PO Box 734, Newcastle NSW 2300<br />

Australia<br />

Prepared By<br />

Reviewed By<br />

Telephone: +61 2 4907 7600<br />

Jason Parrott Facsimile: +61 2 4926 1190<br />

Senior Bridge Engineer<br />

Date: 15 th August 2012<br />

Reference: T-N0115.00/2REP<br />

Status: Draft<br />

Devin Wardill<br />

Senior Bridge Engineer<br />

Approved By<br />

Hugh Tait<br />

Business Manager Newcastle<br />

© Opus International Consultants (NSW) Pty Ltd 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

Contents<br />

1. EXECUTIVE SUMMARY ..................................................................................................................................... 2<br />

2. INTRODUCTION ............................................................................................................................................... 3<br />

3. SITE INFORMATION.......................................................................................................................................... 5<br />

4. DESIGN CRITERIA ............................................................................................................................................. 7<br />

5. SPAN ARRANGEMENTS AND MATERIALS ......................................................................................................... 8<br />

6. FOOTBRIDGE OPTIONS................................................................................................................................... 11<br />

7. SIGNIFICANT CONSTRUCTION HEALTH AND SAFETY & RISK ISSUES ............................................................... 16<br />

8. SIGNIFICANT ENVIRONMENTAL RISK ISSUES .................................................................................................. 17<br />

9. CONCLUSION AND RECOMMENDATIONS....................................................................................................... 18<br />

10. REFERENCES ................................................................................................................................................... 20<br />

APPENDIX A – CONCEPTUAL ILLUSTRATIONS ............................................................................................................ A1<br />

T-N0115.00 1<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

1. EXECUTIVE SUMMARY<br />

The Port Macquarie- <strong>Hastings</strong> <strong>Council</strong> continuously strives to improve its infrastructure and in doing so it has engaged<br />

Opus International Consultants to investigate the options for the proposed footbridge over Kooloongbung <strong>Creek</strong> in<br />

Port Macquarie Town Centre.<br />

It is proposed to improve the pedestrian crossing which currently consists of a narrow footpath on either side of the<br />

Buller Street Bridge, thus providing betterment of economical service and operational safety.<br />

Four footbridge options have been evaluated and discussed in this report and are listed below along with their<br />

estimated constructions costs (costs for relocation of utility services have not been included).<br />

Option 1 – Single Span Steel Truss <strong>Footbridge</strong> $510,000<br />

Option 2 – Single Span Timber Truss <strong>Footbridge</strong>- $550,000<br />

Option 3 – Cable Stay <strong>Footbridge</strong> $545,000<br />

Option 4 – Multi Span Prefabricated Deck System $445,000<br />

Opus recommends, following <strong>Council</strong> approval, to progress the preferred Cable Stay Option into the preliminary<br />

design phase. We believe that this Cable Stay option best meets with the <strong>Council</strong>’s footbridge objectives. There is<br />

considerable benefit with the aesthetics of this form of footbridge as it will provide an eye catching structure, which<br />

will harmonise with the rest of the proposed masterplan developments in Port Macquarie. The cable stay mast will<br />

also be in keeping with the nautical theme in the port environment.<br />

T-N0115.00 2<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

2. INTRODUCTION<br />

Opus was invited by Port Macquarie-<strong>Hastings</strong> <strong>Council</strong> to provide a detailed options study to consider the feasibility of<br />

various footbridge concept designs for the crossing at <strong>Kooloonbung</strong> <strong>Creek</strong> in Port Macquarie.<br />

Port Macquarie-<strong>Hastings</strong> <strong>Council</strong> is looking to provide a footbridge that will both be aesthetically pleasing and fit into<br />

the overall vision of the town’s masterplan. The bridge concept therefore seeks to be visually pleasing, whilst<br />

providing a practical link between the east and west shores of <strong>Kooloonbung</strong> <strong>Creek</strong>. The masterplan proposals will<br />

increase tourism visitations and encourage an active use of the area around the proposed site (see below), in which<br />

the footbridge would be a key landmark.<br />

Figure 1 : Location Plan<br />

This report investigates and evaluates a variety of solutions based on technical, financial constructability and<br />

environmental factors and concludes with recommendations, which are considered the optimum given the constraints<br />

and conditions of the bridge site. The merits of, and considerations into, the feasibility of each option have been<br />

discussed in this report and are presented in section 5.<br />

At this stage of the project, for the purpose of evaluating concept designs, the assumption has been made that the<br />

footbridge would be located to the north and parallel to Buller Street Bridge, shown in figure 1. Should further<br />

progress with the Port Macquarie Foreshore Masterplan identify that the location should change; the concept designs<br />

recommended in this report would be subject to further evaluation at an additional cost to the <strong>Council</strong>. The additional<br />

costs expected will generally increase by a similar factor to the percentage increase in required span, which take into<br />

account the design complexity, increased foundation requirements, quantity of materials and construction time.<br />

T-N0115.00 3<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

The report also concentrates on the following criteria to assist with evaluating the most appropriate options:<br />

• Understanding and appreciating the requirements desired by Port Macquarie – <strong>Hastings</strong> <strong>Council</strong> so that<br />

Opus formulates an option that best fits <strong>Council</strong>’s objectives as well as value for money.<br />

• Formulating the option that is most suitable to the site and its existing conditions and constraints.<br />

• Provide bridge engineering recommendations on the preferred concept design option and advise<br />

whether this option meets engineering good practice and current Australian standards.<br />

• Provide information/issues of significance that may need to be addressed further following on from the<br />

concept.<br />

• Advise Port Macquarie-<strong>Hastings</strong> <strong>Council</strong> of any further information that needs to be obtained<br />

at/following the concept design stage.<br />

Opus has reviewed the concept design options with in accordance with the criteria listed above, along with<br />

information obtained during the site visit and has prepared this report for <strong>Council</strong>s Consideration.<br />

T-N0115.00 4<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

3. SITE INFORMATION<br />

The proposed bridge will be located to the north of Buller Street Bridge on William Street in Port Macquarie, NSW<br />

(shown in photo PO1 below). The footbridge will cross Koolongbung <strong>Creek</strong> to provide both pedestrians and cyclists<br />

safe passage for their recreational movements within the town centre.<br />

Photograph P01 – View on North side of Buller St. Bridge<br />

The structure is located in an urban area which is enjoyed by many of the local community, and carries a very popular<br />

footpath, which does not currently provide adequate width for pedestrians in accordance with Australian Standards.<br />

The topography of the surrounding land is fairly flat, with significant recreational and commercial features in the area<br />

which include and are not restricted to:<br />

• The commercial marinas, located to the north of the proposed site (see figure 2 overleaf), which provide<br />

a visually interesting and colourful foreshore environment, and which can be accessed from the<br />

proposed bridge via a footpath leading to a curved timber boardwalk;<br />

• The historically significant pilots boat shed, located at the western end of Clarence Street, again accessed<br />

from the proposed bridge via a footpath on the east embankment of the creek; and<br />

• The four storey Mid-Pacific Motel which has a strong visual presence along the foreshore.<br />

T-N0115.00 5<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

Figure 2 : Extract from Port Macquarie Foreshore Masterplan<br />

Utility Services<br />

The site inspection identified that an overhead power utility is present near to the proposed location of the<br />

footbridge, which consists of an 11KV line. Liaison with Essential Energy is underway to determine the scope to<br />

incorporate their service into a conduit within the footbridge, or on Buller Street Bridge.<br />

Dial before you dig enquiries have been made which identified the following:<br />

• Essential Energy – Assets have been identified within the extent of the proposed works. Please see<br />

Appendix B for details.<br />

• Optus – No Assets affected;<br />

• Telstra – No Assets affected; and<br />

• Nextgen Networks - No Assets affected.<br />

Geotechnical Information<br />

The geotechnical investigation will be carried out upon confirmation of the preferred concept design. Should the<br />

ground conditions be found to be inadequate, the concept designs may be subject to change.<br />

T-N0115.00 6<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

4. DESIGN CRITERIA<br />

For the purpose of evaluating concept designs, the assumption has been made that the footbridge would be located<br />

to the north and parallel to Buller Street Bridge, shown in figure 1 in section 1 of this report. The cumulative span<br />

requirement in this position would be a total of approximately 40m. Should further progress with the Port Macquarie<br />

Foreshore Masterplan identify that the location should change; the concept designs recommended in this report<br />

would be subject to further evaluation.<br />

The footbridge and related works shall be designed in accordance with Port Macquarie-<strong>Hastings</strong> <strong>Council</strong> Aus Spec in<br />

addition to Australian Bridge Design Standard AS5100 and AUSTROADS.<br />

The applied loadings to be considered in the analysis for the design is as follows<br />

• Footway, walkway or footbridge live loading<br />

-5KN/m2<br />

• Special loading<br />

-Dynamic Loading (For Cable Stay <strong>Options</strong>).<br />

-Wind Loading.<br />

-Impact Loading.<br />

The proposed bridge soffit level would be no lower than that of the existing road bridge adjacent. This level has been<br />

assumed to be clear of previously recorded flood events.<br />

T-N0115.00 7<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

5. SPAN ARRANGEMENTS AND MATERIALS<br />

With consideration of both the proposed location of the bridge and the total span distance required, several span<br />

arrangements can be considered:<br />

• Single span simply supported deck structure;<br />

• Single span suspended structure (cable stay or suspension bridge);<br />

• Multi-span simply supported deck structures.<br />

Single span simply supported deck structures<br />

Several design concepts are available which can span over 40m within feasible constraints. These include suspended<br />

structures, arches and trusses. The truss typically consists a triangulated framework of elements that act primarily in<br />

tension and compression and can be constructed from timber or steel. It is a light-weight yet very stiff form of<br />

construction. Trusses may be used as girders below the deck level, or as through girders with the deck at the bottom<br />

chord level. Such through truss girders minimise the effective construction depth, and the length of approach<br />

embankments. Hence, they are particularly suited to footbridges. The image below shows a Warren truss bridge,<br />

fabricated and supplied by Outdoor Structures, based in Queensland.<br />

They are considered expensive<br />

to fabricate today, being labour<br />

intensive and also leave several<br />

maintenance issues which have<br />

to be carefully addressed (for<br />

example, ease of access).<br />

However, they can still show<br />

advantages in particular<br />

applications such as<br />

footbridges.<br />

Single span suspended structures<br />

Where support piers are not feasible or cost effective, the span of beams and/or truss type footbridges may be<br />

extended by the assistance of cables. This involves building towers at one or both ends of the bridge that are tall<br />

enough to achieve effective angles for the support cables. The more conventional type of suspension bridge uses<br />

continuous cables supported by towers at each end of the bridge which hang in a catenary to support vertical hanging<br />

cables from which the bridge deck is suspended. In modern day engineering the use of cable stay structures has been<br />

more widely used due to the relative ease in the construction phase, over that of the suspension bridge, although the<br />

concept for both remain the same. A schematic outline of these type of bridges is shown in Figure 3, below.<br />

T-N0115.00 8<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

Figure 3 - Schematic of Cable Stayed and Suspension (PBWorks,2008)<br />

The bridge deck may be flexible or rigid but must be strong enough to support the live loads between the support<br />

cables and also to resist wind, dynamic and hydraulic loading.<br />

The main applications of cable type footbridges, suspension and suspended, are for spans over 20 to 25m where<br />

intermediate pier supports are impractical. They are a cost-effective solution for footbridges carrying pedestrians and<br />

cyclists, for medium to long spans.<br />

Multi-span simply supported deck structures<br />

Multi-beam steel, timber or composite<br />

decks are very competitive for bridges<br />

in the short span range. They comprise<br />

a deck slab or cross members which are<br />

supported on top of several girders. The<br />

image to the left shows a timber<br />

footbridge, fabricated and supplied by<br />

WRD, Oregon USA.<br />

For simple spans up to 25m, rolled universal steel beams are economic and are available in a range of sizes ‘off the<br />

shelf’. Very little fabrication is required, usually only the fitting of stiffeners for bearings and the attachment of<br />

bracing. Sections may also be bent to provide precamber and/or horizontal curvature.<br />

For longer span bridges, deeper girders can be fabricated from plates or more spans can be constructed. This however<br />

often means that intermediate piers are required in unfavourable locations. This gives scope to vary the web and<br />

flange sizes and the steel grades for an efficient design. Variable depth girders are often used to give greater<br />

economy, and also to enhance aesthetics. Such plate girders can be readily fabricated with curvature in plan and<br />

elevation.<br />

T-N0115.00 9<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

Materials<br />

For the same weight there is not a great deal of difference in the strength of steel and hardwoods. However, for the<br />

same section size, steel is stronger and therefore designs are generally more compact using this material. Steel is<br />

therefore particularly suited to construction of truss type bridges where joining of the members is also easier than for<br />

timber.<br />

Provided steel is adequately protected against corrosion, it will have a considerably longer life than that of timber.<br />

Protection by simple hand methods of brushing or spraying is likely to be more effective than for timber and<br />

maintenance necessity would be less frequent.<br />

The only disadvantage of using steel over timber is that more complex tools and equipment are required in the<br />

construction. In most cases construction will need to be in a workshop and components or sections would then be<br />

transported to site for assembly.<br />

Several types of Fibre Reinforced Polymers are available on the market today and are being used more and more<br />

frequently where previously timber was the material of choice. FRP’s have an advantage over timber as they provide a<br />

durable and long lasting alternative which is not significantly more expensive when a whole life cost is evaluated.<br />

Companies such as Wagners CFT can offer glass fibre composite sections which weigh around 1/3 of an equivalent<br />

timber girder. The glass fibre composites are not susceptible to durability issues which timber, as well as steel, suffer<br />

from (for example termite attack, borers, decay, corrosion etc.). Wagners CFT girders have also been fatigue tested to<br />

1.2 million cycles and exhibit no loss in strength or stiffness. Typically more expensive than steel, glass fibre<br />

composites can often work out an economic alternative when the whole life costing is considered.<br />

T-N0115.00 10<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

6. FOOTBRIDGE OPTIONS<br />

Concept <strong>Options</strong><br />

Following a review of the market, identifying the availability and cost of prefabricated footbridge concepts, Opus have<br />

short listed 4 concept designs to review and discuss the merits. These concepts incorporate the <strong>Council</strong>’s<br />

requirements, which were outlined in the Engineering Design Scope of Works, May 2012 (Ref BC-1201-001).<br />

The concepts have been summarised in this section of the report and are shown conceptually in Appendix A of this<br />

report.<br />

Option 1 – Single Span Steel Truss <strong>Footbridge</strong><br />

Option 1 proposes to span <strong>Kooloonbung</strong> <strong>Creek</strong> onto concrete abutments using a steel truss. These types of footbridge<br />

are available in prefabricated form from several companies in Australia as well as bespoke design options.<br />

The photograph to the right, is a<br />

prefabricated steel truss footbridge<br />

designed and supplied by Outdoor<br />

Structures, Queensland.<br />

The photograph to the left, is a bespoke steel footbridge<br />

designed by Opus and constructed in Wattle Street,<br />

Sydney.<br />

As can be seen in the photograph (shown above), a covered footway can easily be incorporated in the truss footbridge<br />

concept, which provides addition protection to both the users of the creek crossing and components of the bridge<br />

which would otherwise be exposed and could corrode.<br />

This option provides a relatively simple solution, but is considered to have poor aesthetic properties when compared<br />

with other options, although a balustrade design (one example shown on page 15 of this report) could transform the<br />

visual impact. The concept of a single span option would be particularly beneficial in the construction phase as<br />

foundations would not be required in the creek.<br />

Estimated Construction Cost (Based on supply quotation from Outdoor Structures): $510,000<br />

T-N0115.00 11<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

Option 2 – Single Span Timber Truss <strong>Footbridge</strong><br />

Option 2 proposes to span <strong>Kooloonbung</strong> <strong>Creek</strong> onto concrete abutments using a timber truss. These types of<br />

footbridge are also available in prefabricated form and have the benefit that on site assembly would involve less<br />

complex tools and equipment.<br />

The photograph on the right of a<br />

single span timber through truss<br />

footbridge, is courtesy of Wood<br />

Research and Development and<br />

Outdoor Structures, Queensland.<br />

The photograph to the left, courtesy of<br />

Wheeler, shows a single span timber<br />

truss footbridge similar to, but on a<br />

smaller scale to the bridge pictured<br />

above.<br />

Different types of deck material can be utilised easily and therefore provide a more durable and low maintenance<br />

option.<br />

As with option 1 the concept of a single span option would be particularly beneficial in the construction phase as<br />

foundations would not be required in the creek. This option is considered to have more favourable aesthetics<br />

compared to option 2.<br />

Estimated Construction Cost (Based on supply quotation from WRD and Outdoor Structures): $550,000<br />

T-N0115.00 12<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

Option 3 – Cable Stay <strong>Footbridge</strong><br />

This option proposes a single pylon on the west bank of <strong>Kooloonbung</strong> <strong>Creek</strong>, which supports the bridge deck by way of<br />

cables, see below. These structures benefit from utilising a slender deck system, which is typically pleasing to the eye.<br />

The photograph to the left, is courtesy of Outdoor<br />

Structures and shows a prefabricated cable stay<br />

arrangement for a long span footbridge.<br />

The image to the right shows a typical arrangement for<br />

a single pylon cable stay bridge. (Stockton on Tees<br />

(Britton, 2001)<br />

There are various configurations available with the number of masts, the layout of the cables, the type of mast and<br />

the span proportions. The favoured cable stay configuration is shown is illustrated in the photo above and in Appendix<br />

A of this report. We believe due to the relatively short span for a cable stay bridge the single span pylon would be the<br />

most suitable option and the topography of the approach banks would best suit the location of the back span to be at<br />

the west approach.<br />

The deck construction can be designed using one of several different materials or a combination of, in order to<br />

achieve an aesthetic, and durable structure.<br />

As with option 1 the concept of a single span option would be particularly beneficial in the construction phase as<br />

foundations would not be required in the creek. The cable stay option also has the most appropriate and pleasing<br />

aesthetics in this high profile <strong>Creek</strong> location.<br />

Estimated Construction Cost (Based on supply quotation from Outdoor Structures): $545,000<br />

T-N0115.00 13<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

Option 4 – Multi Span Prefabricated Deck System<br />

Option 4 comprises a 3 span timber deck structure with two intermediate piers near to the creek shore lines. This<br />

concept benefits from having a slender deck system as oppose to some of the single span options as the length of<br />

each span is reduced.<br />

The photograph to the left, courtesy of Wagners<br />

CFT Manufacturing Pty Ltd, shows glass fibre<br />

composite pedestrian bridge structure. The<br />

structural components and the balustrade sections<br />

are all formed from glass fibre composite.<br />

The photograph to the right,<br />

courtesy of Outdoor Structures<br />

shows timber deck arrangement<br />

over several short spans.<br />

The photograph on the left, courtesy of Unibridge,<br />

shows a prefabricated modular footbridge<br />

As with each of the options, various types of deck material can be utilised easily and therefore provide a more<br />

durable and low maintenance option if required.<br />

Timber, glass fibre composite and steel could all be utilised easily in this concept, which could have durability<br />

and subsequently longevity benefits.<br />

Estimated Construction Cost (Based on Supply quotation from Wagners CFT): $445,000<br />

T-N0115.00 14<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

A decorative ballastrade can be incorporated into each of the 4 options outlined in this report. One example of a<br />

balustrade design is shown below (Extract from Scully’s Drawing No: GA-03):<br />

A comparative summary of the concept options to provide a footbridge over <strong>Kooloonbung</strong> <strong>Creek</strong> has been discussed<br />

in section 9 of this report. The evaluation has been carried out on the following basis:<br />

• Construction cost.<br />

• Whole life cost.<br />

• Ease of construction.<br />

• Future inspection and maintenance requirements.<br />

• Health and Safety issues.<br />

• Environmental issues.<br />

• Construction programme duration.<br />

• Disruption to the local community.<br />

The Preliminary cost estimates for proposed options have been built upon on quotations to supply and deliver<br />

prefabricated footbridges. Construction costs have been estimated based on past schemes and are for information at<br />

this stage of the project.<br />

T-N0115.00 15<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

7. SIGNIFICANT CONSTRUCTION HEALTH AND SAFETY & RISK ISSUES<br />

Health and Safety procedures and processes are to be followed to ensure OH&S considerations are incorporated in all<br />

aspects of execution of the project services. Port Macquarie- <strong>Hastings</strong> <strong>Council</strong> Policies, Procedures, inductions and<br />

special licences required to access and operate within the site will be adhered to. Opus believes that the safety and<br />

well-being of staff and other parties affected by our work is of primary importance.<br />

In order to provide a formal means of identifying the risks inherent in this project and to communicate them to other<br />

members of the design team and the contractor, a designer’s risk assessment shall carried out at the early stage of the<br />

design process. This will be carried out at an early stage of the design to address and help to eliminate the hazards<br />

associated with construction health and safety. This assessment would recommend mitigation measures to reduce<br />

risks from those hazards that cannot be eliminated.<br />

Prior to this designers risk assessment and the verification of the preferred concept design, the likely risks that are<br />

associated with this project will include:<br />

• Injuries to personnel;<br />

• Contaminating land and watercourse;<br />

• Injury through contact with / inhalation of hazardous materials during construction and maintenance;<br />

• Contact with skin causing irritation and vibration;<br />

• Injury through handling heavy materials;<br />

• Falling into water and drowning; and<br />

• Damage to neighbouring road bridge.<br />

Health and Safety issues are of paramount importance. All stages of construction and beyond should be considered<br />

during a full risk evaluation, and include identification of significant hazards which affect the workforce, public and<br />

future inspection, maintenance and demolition operations. Preliminary health and safety risk assessments have been<br />

undertaken and significant factors are noted below:<br />

• Longer construction periods present greater exposure to environmental risks, such as flooding.<br />

• Routes for emergency services shall be maintained, or diverted on agreed alternatives.<br />

• Manual handling operations should be minimised.<br />

T-N0115.00 16<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

8. SIGNIFICANT ENVIRONMENTAL RISK ISSUES<br />

Environmental issues are of equal importance to safety matters. All stages of construction and beyond should be<br />

considered during a full risk evaluation, and include identification of significant impacts which arise during the design,<br />

construction, and maintenance operations. Preliminary environmental risk assessments have been undertaken and<br />

significant factors are noted below:<br />

• The finished appearance of the work proposed should be in keeping with the surroundings.<br />

• Noise and dust emissions are likely to be significant and therefore working hour restrictions should be<br />

included in specification for the works.<br />

• Opportunities should be maximised during scheme design for recycling and use of reclaimed materials.<br />

• Statutory undertakers apparatus should be located and protected/diverted to avoid pollution events.<br />

• The scheme should seek to minimise vehicle movements, but this should be balanced against potential<br />

re-use of arisings on other <strong>Council</strong> schemes if appropriate.<br />

• Welfare facilities should be self-contained within the site extent.<br />

• Impact to local ecology should be minimised. Specialist advice should be sought for effects to any local<br />

designated sites and treatment of significant effects to biodiversity. Schemes with nominal land-take will<br />

have less effect on the local ecology.<br />

• The work is likely to involve earthworks and therefore the design shall strive to include retention of<br />

existing vegetation where practicable.<br />

The level of environmental impact resulting from the proposed works is expected to be low, as the likely and potential<br />

impacts would be localised, of short-duration and would result in minimal disturbance to the watercourse. It is<br />

expected that the causeway will have a marginally higher impact to the watercourse due to its extensive amount of<br />

concrete onto the river bed.<br />

It is our understanding that an environmental study would be carried out prior to commencement of the works.<br />

T-N0115.00 17<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

9. CONCLUSION AND RECOMMENDATIONS<br />

Following the summary of the options in section 6 of this report, Opus recommends to progress into the preliminary<br />

design phase with the Cable Stay Option, Option 3. The merits and constraints for each concept, considered in this<br />

report are discussed below. Illustrations of these options are shown in Appendix A.<br />

Option 1 – Single Span Steel Truss <strong>Footbridge</strong><br />

The truss concept is simplistic and fit for purpose has merits in the relatively short site construction time, the proven<br />

efficiencies in design and the need for only two abutments. However there are many complications and constraints<br />

which include fabrication complexity, more complex tools and equipment than that of a timber truss, cost and<br />

prefabrication time.<br />

The structure has the benefit of being durable and reasonably maintainable, over the timber truss option for example,<br />

although it will require painting. The design life of the structure will be significantly longer than that of a timber<br />

counterpart.<br />

The potential requirements to divert or isolate the adjacent power line in both the design and construction phase<br />

would be less adverse than that of the Cable stay footbridge.<br />

With the council’s requirements for aesthetics are considered independently, this option is not considered to fulfil the<br />

requirements, as in comparison to a cable stay bridge for example, the footbridge would not be a landmark feature.<br />

Option 2 – Single Span Timber Truss <strong>Footbridge</strong><br />

The timber truss concept is a simplistic traditional structural form that due to its arched configuration can span the full<br />

40m and additionally provide an aesthetically pleasing structure. This form of structure has a similar structural<br />

appearance to a bridge that has been used elsewhere in the town..<br />

Due to this footbridge consisting of predominantly timber elements it has long term cost implications due to greater<br />

maintenance requirements during its life span. The design life of the structure will also be less than the other options<br />

considered.<br />

The potential requirements to divert or isolate the adjacent power line in both the design and construction phase<br />

would be less adverse than that of the Cable stay footbridge.<br />

This option fulfils the <strong>Council</strong>’s requirements of an aesthetic pleasing structure. Although, there is long term cost<br />

implications due to greater maintenance requirements.<br />

Option 3 – Cable Stay <strong>Footbridge</strong><br />

The cable stays greatest merit is that it is aesthetically pleasing. In addition the more slender deck component requires<br />

less quantity of materials to construct it, as the structural integrity is assisted by the cables.<br />

Again the structure has the benefit of being durable and reasonably maintainable, over the timber truss option for<br />

example, although it will require painting. The design life of the structure will be significantly longer than that of a<br />

timber counterpart when either steel or FRP is used for the deck components.<br />

Some complexity in the construction phase in turn means that construction time would be longer than some of the<br />

other options; however innovation in the methodology could subsequently reduce this.<br />

T-N0115.00 18<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

The overhead power lines located at the site are a concern when proposing a large pylon in close vicinity. Further<br />

liaison with Essential Energy is required, as with all of the other options, however it is more likely the service would<br />

need to be diverted should this option progress.<br />

This option fulfils the <strong>Council</strong>’s requirements of an eye catching and aesthetic structure.<br />

Option 4 – Multi Span Prefabricated Deck System<br />

The multi span prefabrication concept will allow the use of standardised off the shelf elements that will provide<br />

benefits in both cost and shorter construction periods. However, pier supports will be required in the creek that will<br />

significantly increase the construction complexity and will limit the time and cost saving gained form the<br />

superstructure.<br />

These additional piers within the creek also have the disadvantage of creating additional obstructions to water traffic<br />

and risk from impacts from flood debris.<br />

The potential requirements to divert or isolate the adjacent power line in both the design and construction phase<br />

would be less adverse than that of the Cable stay footbridge.<br />

With the council’s requirements for aesthetics are considered independently, this option is not considered to fulfil the<br />

requirements, as in comparison to a cable stay bridge for example, the footbridge would not be a landmark feature.<br />

Recommendations<br />

The other more conventional <strong>Options</strong> 1 and 4 are dismissed on the grounds that the <strong>Council</strong> prefers an aesthetic<br />

footbridge that is required to be an eye catching structure, which is to harmonise with the rest of the proposed<br />

revitalisation of the town. Although Option 2 also is considered to possess pleasing aesthetics it lacks an elevated focal<br />

point that is provided from a cable stay mask, which will harmonises with the nautical environment of the port. Option<br />

2 also necessity greater maintenance requirements during its life span.<br />

The cable stay footbridge has also been chosen over other forms of aesthetic complex bridges, such as suspension<br />

footbridges, because it has the advantage of reduced construction costs due to reduction in number of elements such<br />

as fewer towers, cables and anchor points required.<br />

T-N0115.00 19<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

10. REFERENCES<br />

Britton, (2001). The Teesquay Millennium <strong>Footbridge</strong>, Stockton on Tees. Retrieved August 11, 2012 from<br />

http://www.freefoto.com/preview/11-43-19/The-Teesquay-Millennium-<strong>Footbridge</strong>--Stockton-on-Tees<br />

PB Works, (2008).BRIDGES. Retrieved August 10, 2012 from the structures art web site: http://structuresart.pbworks.com/w/page/11233762/Bridges<br />

T-N0115.00 20<br />

August 2012


<strong>Options</strong> <strong>Study</strong> Report<br />

<strong>Kooloonbung</strong> <strong>Creek</strong> <strong>Footbridge</strong><br />

Port Macquarie – <strong>Hastings</strong> <strong>Council</strong><br />

APPENDIX A – CONCEPTUAL ILLUSTRATIONS<br />

T-N0115.00<br />

August 2012<br />

A1

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!