<strong>Halifax</strong> Water Integrated Resource Plan<br />

Appendices<br />

Table 2.12<br />

Proposed Transmission Main Projects<br />

Project<br />

Length<br />

(m)<br />

Diameter<br />

(mm)<br />

Description<br />

Project<br />

Cost<br />

$ million<br />

(2012 $)<br />

In-Service<br />

Date<br />

East Region<br />

E1 1,390 400<br />

E2 1,540 400<br />

Windmill Road Transmission Main<br />

Replacement - Phase 1<br />

Windmill Road Transmission Main<br />

Replacement - Phase 2<br />

$2.27 2022<br />

$2.52 2022<br />

E3 3,610 900 Port Wallace Transmission Main - Phase 1 $10.05 2016<br />

E4 820 600<br />

E5 1,280 400<br />

Gaston Road Transmission Main Replacement -<br />

Phase 2<br />

Eastern Passage Transmission Main<br />

Replacement<br />

$1.56 2027<br />

$2.09 2027<br />

E6 2,605 900 Port Wallace Transmission Main - Phase 2 $7.25 2027<br />

E7 1 Burnside - Bedford Booster Pumping Station $1.00 2042<br />

E8 5,740 750<br />

E9 1,350 600<br />

Burnside - Bedford Connector Transmission<br />

Main<br />

Burnside - Bedford Connector Transmission<br />

Main Extension of 600 mm Main on Glendale<br />

Dr. to HWY 102<br />

$14.51 2037<br />

$2.57 2017<br />

Sub-Total East Region $43.83<br />

Central Region<br />

C1 980 750 Bedford Connector 30" Replacement - Phase 3 $2.48 2017<br />

C2 1,515 600 Windgate Drive Transmission Main $2.89 2027<br />

C3 620 600 Stokil Tank Connection to Windgate Drive $1.18 2032<br />

C4 5,470 750<br />

Lucasville Road Transmission Main - Phase 1<br />

(includes Beaverbank Reinforcement)<br />

$13.83 2017<br />

C5 5,515 750 Lucasville Road Transmission Main - Phase 2 $13.94 2022<br />

C6 1,000 600 Nordic Crescent Upgrading $1.91 2032<br />

Sub-Total Central Region $36.22<br />

West Region<br />

W1 1,485 1200<br />

W2 1,620 1200<br />

Pockwock Transmission Main Replacement<br />

Kearney Lake Road (Twin Culverts to Bluewater<br />

Road)<br />

Pockwock Transmission Main Replacement<br />

Kearney Lake Road (Bluewater Road to Ham-<br />

Kearney Connector)<br />

$5.60 2014<br />

$6.11 2017<br />

Revision: 2012-10-29 Integrated Resource Plan –Appendices F-30<br />

October 31 2012 Page 209 of 272