Water Projects<br />

Page 3 of 4<br />

Project<br />

ID<br />

Project Name<br />

Driver<br />

All $ in 000's<br />

Y1 Y2 Y3 Y4 Y5 Y6-10 Y11 - 15 Y16 - 20 Y21 - 25 Y26 - 30<br />

AR G C 2012-2013 2013-2014 2014-2015 2015-2016 2016-2017<br />

Sub Total<br />

Y1 to Y5<br />

2017-18 to<br />

2021-22<br />

2022-23 to<br />

2026-27<br />

2027-28 to<br />

2031-32<br />

2032-33 to<br />

2036-37<br />

2037-38 to<br />

2041-42<br />

Sub Total Y6<br />

to Y30<br />

Total<br />

Y1 to Y30<br />

Comments<br />

Projects >=$1.5M Estimate prepared or<br />

Budget Cost (Estimate not yet prepared)<br />

Water - Treatment Facilities<br />

3.30 JD Kline WSP Upgrade Program $0 $0 $0<br />

3.31 Lake Major WSP Upgrade program $0 $0 $0<br />

3.32 Non-Urban Core WSP Upgrade program $0 $0 $0<br />

Miller Lake Small System - Extension of Well Supply<br />

Line<br />

J D Kline - Chemical Feed Pump Replacement<br />

Program<br />

$250 $250 $0 $250<br />

$120 $120 $120 $120 $120 $600 $0 $600<br />

J D Kline - Chlorination System Replacement Design $100 $100 $0 $100<br />

J D Kline - Chlorination System Replacement $2,400 $2,400 $0 $2,400 Internal Staff Estimate prepared *<br />

Lake Major WSP - Control Room Renovations $14 $14 $0 $14<br />

Lake Major WSP - Lime System Upgrade $38 $38 $0 $38<br />

Lake Major WSP - Ventilation in Motor Control Room $20 $20 $0 $20<br />

J D Kline - Replacement program for Filter Valve<br />

Actuators<br />

J D Kline - Replace Valve Actuators at the Pumping<br />

Station<br />

$45 $45 $45 $45 $180 $0 $180<br />

$95 $95 $0 $95<br />

J D Kline - Entrance Road Paving Renewal $85 $85 $0 $85<br />

J D Kline - Mechanical Mixers in the Mixing Tanks $1,550 $1,000 $2,550 $0 $2,550 Internal Staff Estimate prepared *<br />

J D Kline - Parking Lot Resurfacing $120 $120 $0 $120<br />

J D Kline - Removal of Aluminium in the process<br />

wastewater<br />

$2,700 $2,700 $1,150 $1,150 $3,850 Internal Staff Estimate prepared *<br />

J D Kline - Lobby Upgrades $0 $180 $180 $180<br />

J D Kline - Replace Pump Motors #1 and #3 $0 $280 $280 $280<br />

J D Kline - Flow Splitting Improvements in the Pre-Mix $1,300 $1,300 $1,300<br />

Lake Major WSP - New Diesel Generator $225 $225 $225<br />

Bennery Lake WSP - Future Process Improvements<br />

(from 2008 Aerotech Servicing Study)<br />

Bennery Lake WSP - Raw Water Supply from Grand<br />

Lake<br />

$0 $1,850 $1,850 $1,850 Internal Staff Estimate prepared *<br />

$0 $3,800 $3,800 $3,800 Internal Staff Estimate prepared *<br />

Bennery WTP Upgrades $140 $140 $140 $140 $140 $700 $0 $700<br />

$0 $0 $0<br />

$0 $0 $0<br />

Water - Treatment Facilities -- T O T A L S $682 $305 $4,435 $4,125 $305 $9,852 $4,985 $3,800 $0 $0 $0 $8,785 $18,637<br />

Water - Energy<br />

Heat Recovery Study and Upgrade $300 $300 $600 $0 $600<br />

JD Kline - Industrial Process Pumps Upgrade $110 $110 $0 $110<br />

JD Kline - Raw Water Supply Pump Energy Study $50 $50 $0 $50<br />

Various - Chamber HVAC Retro-commissioning $150 $150 $150 $150 $600 $0 $600<br />

JD Kline - Wind Energy Development - 4.6 MW $0 $11,200 $11,200 $11,200 Estimate with Jeff Knapp<br />

Lake Major - Wind Energy Development - 11.5 MW $0 $26,200 $26,200 $26,200 Estimate with Jeff Knapp<br />

Long Lake - Wind Energy Development - 4.6 MW $0 $11,200 $11,200 $11,200 Estimate with Jeff Knapp<br />

PRV Energy Recovery Pilot Project - Orchard Central<br />

Chamber<br />

$100 $410 $510 $0 $510<br />

$0 $0 $0<br />

$0 $0 $0<br />

Water - Energy -- T O T A L S $450 $860 $260 $150 $150 $1,870 $48,600 $0 $0 $0 $0 $48,600 $50,470<br />

October 31 2012 Page 165 of 272<br />

M:\026 (Genivar)\026_42 (<strong>Halifax</strong> Water)\026_42_01 (IRP)\Resource Plan\R_3-0911816 Appendices\B\Copy of Appendix B - Capital Projects IRP Draft v3Water