Water Projects<br />
Page 1 of 4<br />
Project<br />
ID<br />
Project Name<br />
Driver<br />
All $ in 000's<br />
Y1 Y2 Y3 Y4 Y5 Y6-10 Y11 - 15 Y16 - 20 Y21 - 25 Y26 - 30<br />
AR G C 2012-2013 2013-2014 2014-2015 2015-2016 2016-2017<br />
Sub Total<br />
Y1 to Y5<br />
2017-18 to<br />
2021-22<br />
2022-23 to<br />
2026-27<br />
2027-28 to<br />
2031-32<br />
2032-33 to<br />
2036-37<br />
2037-38 to<br />
2041-42<br />
Sub Total Y6<br />
to Y30<br />
Total<br />
Y1 to Y30<br />
Comments<br />
Projects >=$1.5M Estimate prepared or<br />
Budget Cost (Estimate not yet prepared)<br />
Water - Land<br />
3.33 Watershed Land Acquisition $0 $0 $200 $200 $400 $0 $400<br />
$0 $0 $0<br />
Water - Land -- T O T A L S $0 $0 $200 $200 $0 $400 $0 $0 $0 $0 $0 $0 $400<br />
Water - Transmission<br />
3.42 Critical Trans Main Valve Replacement Program $250 $250 $500 $1,000 $0 $1,000<br />
3.43 Bedford South CCC - Nine Mile Drive Extension $35 $35 $0 $35<br />
3.44 Bedford South Trans Main Oversizing - Non CCC $40 $40 $0 $40<br />
3.45 Bedford West CCC - Various Phases $10 $20 $30 $25 $25 $110 $150 $150 $260<br />
3.47 Twin Brooks Phase 2 Trans. Oversizing - Non CCC $110 $110 $0 $110<br />
3.48 Governor's Brook Phase 3 Oversizing $65 $35 $100 $0 $100<br />
2.130 Integrated Resource Plan (split 50/50 WW/W) $165 $200 $200 $565 $0 $565<br />
Asset Management Implementation Program<br />
(W/WW/SW)<br />
$88 $300 $300 $300 $200 $1,188 $833 $1,000 $1,167 $1,333 $1,500 $5,833 $7,021<br />
Years 1 to 5 based on AMA report. Year 6+ placeholder<br />
costs<br />
Dunbrack Trans Main Sliplining Phase 2 $6,900 $200 $7,100 $0 $7,100 Estimate prepared in project file<br />
3.08<br />
Pockwock Transmission Main Replacement - Twin<br />
Culverts to Bluewater Rd<br />
$2,500 $2,500 $4,500 $4,500 $7,000 Internal Staff Estimate prepared *<br />
Morris Lake Estates CCC $15 $15 $0 $15<br />
Birch Cove North CCC $330 $330 $0 $330<br />
3.19 Lucasville Road Transmission Main - Phase 1 $350 $350 $350 $1,050 $1,750 $1,750 $2,800<br />
3.20 Lucasville Road Transmission Main - Phase 2 $0 $2,950 $2,950 $2,950<br />
) Internal Staff Estimate prepared *<br />
)<br />
3.13<br />
3.14<br />
Bedford Connector Transmission Main Phase 3 $0 $2,400 $2,400 $2,400 Internal Staff Estimate prepared *<br />
Windmill Road Transmission Main Replacement - Ph 1<br />
(Wright to Princess Marg)<br />
Windmill Road Transmission Main Replacement - Ph 2<br />
(Princess Marg to Albro Lake Rd)<br />
$0 $2,700 $2,700 $2,700<br />
$0 $2,250 $2,250 $2,250<br />
3.10 North End Feeder Tunnel Slip-lining $0 $3,500 $3,500 $3,500 Internal Staff Estimate prepared *<br />
3.12<br />
Pockwock Transmission Main Replacement-Bluewater<br />
Rd to Hammonds-Kearney Control<br />
) Internal Staff Estimate prepared *<br />
)<br />
$0 $7,100 $7,100 $7,100 Internal Staff Estimate prepared *<br />
3.15 Spruce Hill Transmission Main Replacement $0 $2,750 $2,750 $2,750 Internal Staff Estimate prepared *<br />
3.11 Peninsula Low 24" Sliplining $0 $7,360 $7,360 $7,360 Internal Staff Estimate prepared *<br />
3.16 Peninsula Low North 27" Sliplining $0 $7,800 $7,800 $7,800 Internal Staff Estimate prepared *<br />
3.17 Peninsula Intermediate - 15" Rehab $0 $4,715 $4,715 $4,715 Internal Staff Estimate prepared *<br />
3.18<br />
Port Wallace Transmission Main Connection Phase 1<br />
(Shubie Park Connection)<br />
Port Wallace Transmission Main Phase 2 (Port Wallace<br />
/Caledonia Rd area)<br />
$0 $2,400 $2,400 $2,400 Internal Staff Estimate prepared *<br />
$0 $6,400 $6,400 $6,400 Internal Staff Estimate prepared *<br />
3.21 Burnside - Bedford Connector Transmission Main $0 $7,800 $7,800 $7,800 Internal Staff Estimate prepared *<br />
Eastern Passage Transmission Main Replacement -<br />
Norah Lane to Cow Bay Road<br />
$0 $2,200 $2,200 $2,200 Internal Staff Estimate prepared *<br />
Gaston Road Transmission Main Replacement $0 $1,600 $1,600 $1,600 Internal Staff Estimate prepared *<br />
Herring Cove Road Transmission Main Replacement<br />
Sussex Drive to Princeton Avenue<br />
Pockwock Transmission Sliplining - Twin Culverts to<br />
Highway 102<br />
$0 $4,700 $4,700 $4,700 Internal Staff Estimate prepared *<br />
$0 $13,000 $13,000 $13,000 Internal Staff Estimate prepared *<br />
$0 $0 $0<br />
Water - Transmission -- T O T A L S $7,413 $805 $930 $1,375 $3,620 $14,143 $57,408 $32,450 $1,167 $1,333 $1,500 $93,858 $108,001<br />
October 31 2012 Page 163 of 272<br />