<strong>Halifax</strong> Water Integrated Resource Plan<br />
Recommended IRP and Analysis<br />
Table 6.2 shows the results of the end-of-period value analysis. The current asset value<br />
is estimated as $3,838 million ($2012). Comparison of the A, B and C levels of asset<br />
renewal show an approximately $600 million difference in end-of-period value across<br />
the levels. The A level asset renewal combined with the timing and scale of the<br />
Recommended IRP capital additions results in an increased end-of-period value of<br />
$1,037 million. In contrast, the C level asset renewal combined with the timing and scale<br />
of the Recommended IRP capital additions results in an increased end-of-period value of<br />
$419 million. End-of-period asset value increases in all cases for the wastewater system<br />
showing the impact of the large capital additions over the 30-year period. Water system<br />
end-of-period asset value increases only for the A level asset renewal while the<br />
stormwater system end-of-period value stays about the same for all cases with a decline<br />
of $128 million in asset value. The composite asset renewal program presents an endof-period<br />
value a little less than the B level plus Recommended IRP capital program. The<br />
composite asset renewal is part of the overall Recommended IRP with an increase in<br />
end-of-period value of $729 million or about 19% of current asset value.<br />
Table 6.2 End-Of-Period Value Analysis ($ million 2012)<br />
Asset Renewal<br />
Level/Plan<br />
Asset System<br />
Starting Asset<br />
Value<br />
End-of-Period<br />
Value<br />
Change In<br />
Asset Value<br />
Water $1,247 $1,379 +$132<br />
A Level Asset Renewal Plus<br />
Recommended IRP Capital<br />
Expenditures<br />
Wastewater $1,774 $2,807 +$1,033<br />
Stormwater $817 $689 -$128<br />
Total $3,838 $4,875 +$1,037<br />
Water $1,247 $1,243 -$4<br />
B Level Asset Renewal Plus<br />
Recommended IRP Capital<br />
Expenditures<br />
Wastewater $1,774 $2,711 +$937<br />
Stormwater $817 $689 -$128<br />
Total $3,838 $4,643 +$805<br />
Water $1,247 $1,127 -$120<br />
C Level Asset Renewal Plus<br />
Recommended IRP Capital<br />
Expenditures<br />
Wastewater $1,774 $2,441 +$667<br />
Stormwater $817 $689 -$128<br />
Total $3,838 $4,257 +$419<br />
Composite Asset Renewal<br />
Plus Recommended IRP<br />
Capital Expenditures<br />
(Recommended IRP Plan)<br />
Water $1,247 $1,161 -$86<br />
Wastewater $1,774 $2,717 +$943<br />
Stormwater $817 $689 -$128<br />
Total $3,838 $4,567 +$729<br />
Revision: 2012-10-29 Integrated Resource Plan 86<br />