<strong>Halifax</strong> Water Integrated Resource Plan<br />
Recommended IRP and Analysis<br />
Table 6.1<br />
Recommended IRP Components and Timing<br />
IRP<br />
Driver<br />
IRP Objective<br />
Recommended IRP Strategy<br />
Asset<br />
Renewal<br />
Growth<br />
8. Implement Optimal Level of Asset<br />
Renewal.<br />
9. Enhance the Reliability of Critical<br />
Water and Wastewater Assets.<br />
10. Evaluate Existing Stormwater System<br />
Adequately Sized for Minor Storm<br />
Conveyance.<br />
11. Adapt to Future Climate Change.<br />
12. Reduce Energy Consumption,<br />
Operating Costs and Greenhouse Gas<br />
Contributions.<br />
13. Provide <strong>Regional</strong> Water, Wastewater<br />
and Stormwater Infrastructure<br />
Needed to Support Planned Growth.<br />
14. Manage Flow Capacity Allocations.<br />
• Enhanced asset renewal based on risk-based<br />
composite asset renewal program balancing failure<br />
consequences and renewal expenditures. The<br />
composite specifies an individual level of renewal for<br />
each asset category (See Volume 3, Appendix E).<br />
• Implement water system security program based on<br />
Five-Year Capital Plan modified through the IRP.<br />
• Ten years for stormwater capacity evaluation<br />
program.<br />
• Three years for climate change program<br />
development.<br />
• Implement energy reduction projects based on the<br />
Energy Management Plan as per the Five-Year<br />
Capital Plan.<br />
• Timing for wastewater projects/programs as per<br />
RWWFP; timing for water projects/programs as per<br />
IRP.<br />
• I/I, water efficiency and other demand reduction<br />
projects.<br />
• Timing as per RWWFP or as previously programmed<br />
in Five-Year Capital Plan.<br />
The total 30-year NPV for the recommended plan inclusive of capital and O&M costs is<br />
$2,579 million.<br />
The timing of expenditures (in $2012) is shown in Figure 6.1, which indicates significant<br />
expenditures around years 10, 20 and 30. This corresponds to the following projects:<br />
• Year 10 – WWTF Nutrient Upgrades.<br />
• Year 20 – WSER HHSP WWTF Upgrades.<br />
• Year 30 – Enhanced Overflow Control Program.<br />
Revision: 2012-10-29 Integrated Resource Plan 77<br />