Page1 GRAM: TRANSGRID Phone No.(02836) 245784 Fax No.(02836) 241588 CONSTRUCTION DIVISION OFFICE, 220KV COMPOUND S/S ANJAR, ANJAR - KUTCH – 370 110. E - Mail:- eeconstanj@yahoo.co.in TECHNICAL B I D NAME OF WORK: Civil work for Dayapar feeder bay at 66 kV switch yard of KLTPS, Panandhro.

Page1<br />

GRAM: TRANSGRID Phone No.(02836) 245784<br />

Fax No.(02836) 241588<br />

CONSTRUCTION DIVISION OFFICE,<br />

220KV COMPOUND S/S ANJAR,<br />

ANJAR - KUTCH – 370 110.<br />

E - Mail:- eeconstanj@yahoo.co.in<br />

TECHNICAL B I D<br />

NAME OF WORK:<br />

Civil work for Dayapar feeder bay at<br />

66 kV switch yard of KLTPS, Panandhro.


Page2<br />

GUJARAT ENERGY TRANSMISSION CORPORATION LTD.<br />

CONSTRUCTION DIVISION<br />

ANJAR (KUTCH)<br />

NAME OF WORK: - Civil work for Dayapar feeder bay at 66<br />

kV switch yard of KLTPS, Panandhro.<br />

SR.<br />

NO.<br />

(TECHNICAL BID)<br />

INDEX<br />

PARTICULARS<br />

1 Tender Notice 3-4<br />

2 General Instruction 5-7<br />

3 Terms & Condition 8-10<br />

4 Section I 11<br />

PAGE NO.<br />

6 Special Condition 12-13<br />

7 Special Condition for use of Cement in work 14-15<br />

Price Bid 16<br />

8 Note for Schedule “B” 17<br />

9 Schedule “B” 18-20<br />

10 Schedule “C” 21<br />

11 Schedule “D” 22<br />

12 Schedule “E” 23<br />

13 Schedule “F” 24<br />

14 Drawing (Bid purpose only) See Note<br />

15 Detailed Specification for Civil Work booklet See Note<br />

(Inclusive 114 Pages)<br />

16 Tender and Contract for works booklet See Note<br />

NOTE:<br />

Booklet for “Tender and Contract for Works” and “General Specification for Civil<br />

works (Effective 01-04-1991)” and detailed drawings, are available in the Office of<br />

Under signed for reference and it is binding upon to Contractor and Presumed that<br />

the same is read and gone through. (If not attached with Tender Copies).


Page3<br />

(Technical & Commercial Bid)<br />

GUJARAT ENERGY TRANSMISSION CORPORATION LIMITED<br />

TRANSMISSION CIRCLE, ANJAR.<br />

CONSTRUCTION DIVISION – ANJAR.<br />

FAX : (02836) 245784 PHONE No: (02836) 245784<br />

E-mail: eeconstanj@yahoo.co.in, eeconstanjar@gebmail.com<br />

Sealed percentage rate tenders are invited in two separate sealed covers super scribed technical<br />

bid and price bid for “Civil work for Dayapar feeder bay at 66 kV switch yard of KLTPS,<br />

Panandhro” from Registered Contractors in appropriate class with<br />

GETCO/Central/State Government / Railway/Semi. Govt. and who has executed<br />

similar nature of work and magnitude successfully by Executive Engineer (Const.),<br />

GETCO, 220 kV S/S Compound, Bhuj Road, Anjar (Kutch).<br />

Sr.<br />

No.<br />

Name of Work<br />

1 Civil work for Dayapar feeder<br />

bay at 66 kV switch yard of<br />

KLTPS, Panandhro.<br />

Estimated<br />

Cost Rs.<br />

Time<br />

Limit<br />

1,89,327.50 1<br />

Month<br />

Tender<br />

Fee Rs.<br />

E.M.D.<br />

Rs.<br />

190.00 1900.00<br />

1. Last date of submission of tender: (Technical and Price bids): .11.2010 (Only by RPAD / Speed<br />

post, During working Hrs. up to 15.00 Hrs.)<br />

2. Due date of opening of Technical bid: .11.2010 (at 16.00 Hrs., if possible)<br />

3. Validity of tender: 180 Days from the date of opening of Technical Bid.<br />

No tender shall be accepted / opened in case of receipt after due date and time of tender,<br />

irrespective of delay due to postal services or any other reasons and the GETCO shall not assume<br />

any responsibility for late receipt of tender.<br />

The tenders are to be submitted by the intending bidders in single envelop with two separate sealed<br />

and super scribed envelopes as listed below:<br />

Envelope No.1: Technical bid and pre qualification requirement, bid data, details specification.<br />

Envelope No.2: Price Bid.<br />

Technical and pre qualification requirement bid details specification (envelope No.1) will be opened<br />

first and subject to evaluation based on the qualification criteria contained in the individual bid<br />

document.<br />

Price bids (Envelope No.2) of bidders who are assessed and declared as substantially technically<br />

responsive on evaluation of the technical bid will be opened for further commercial evaluation.<br />

The Earnest Money Deposit and Tender fee will be accepted by Demand Draft on any nationalized<br />

bank only situated at “ANJAR”, drawn in favor of “GUJARAT ENERGY TRANSMISSION<br />

CORPORATION LTD.”. Tender without EMD and tender fee shall be rejected. Two separate<br />

demand drafts for Tender fee and EMD should be submitted with technical bid.<br />

Tender document can be down loaded from our web site WWW.gseb.com<br />

Interested party requested to visit our Web Site as mentioned.


Page4<br />

The Tenderer should have to submit with Tender on latter pad along with attested copies of the<br />

certificate of (1) PAN No. (2) Registration from GETCO (3) Solvency Certificate from Schedule Bank<br />

/ Revenue Bank, (4) Partnership deed, (5) Latest Registration Certificate for provident fund of<br />

Employees / Labors and P.F. Code No. and its latest receipt, (6) Experience Certificate (7) Vat<br />

Registration (8) Service Tax Registration (9) Payment of Tender Fee & EMD in D.D. in favour<br />

GETCO, ANJAR.<br />

The GETCO reserves the rights to reject any or all tenders or accept any tender without assigning<br />

any reason thereof.<br />

Executive Engineer<br />

Construction Division<br />

GETCO, ANJAR.


Page5<br />

GENERAL INSTRUCTION TO BIDDER<br />

1. The tender should be submitted in a sealed envelope on which it should be distinctly<br />

indicated the name of work. Bidder should quote percentage for civil work of<br />

“Construction of Revetment wall for protection of 220 kV tower foundation at Loc. No.<br />

03, 41, 47 & 53 of 220 kV Nanikhakhar – Shivlakha line LILO at 220 kV Kukma s/s.” as<br />

per Schedule “B” of the tender specification.<br />

2. Bidder must be confirming their full acceptance to various terms and conditions of<br />

GETCO’s specification. They should also confirm that offers are based strictly on the<br />

specification data in all respects.<br />

3. An earnest money deposit of Rs. 3550/- shall have to remitted by the bidder by way of<br />

Cash or Demand Draft payable to “<strong>Gujarat</strong> Energy Transmission corporation Ltd.”<br />

drawn on a schedule bank in Anjar with the tender only. Cheques or in any other form<br />

towards payment of earnest money deposit will not be accepted and the bid will be<br />

disqualified. Registered contractors shall deposit the amount in accordance with the<br />

conditions of registration with the GETCO.<br />

4. The bidder is required to quote only firm prices for all items. No variation on price<br />

statutory or otherwise on raw materials or finished products on any clause will be<br />

accepted.<br />

5. The bidders should note that the completion of above works in all respect in accordance<br />

with the time limit given below is very important and should be strictly adhered to<br />

“Completion in 1 (ONE) Month from the date of issue of letter for commencement of<br />

the work. Failing to complete the work within the period stipulated the contractor will<br />

have to pay compensation as per terms of the agreement; penalty will be levied as per<br />

rules.<br />

6. The bidders should furnish a list of similar works executed by them and clearly mention<br />

the name of the party for whom the works have been completed. The reference of order<br />

number and date performance report of such works is furnished in attached bidding at<br />

Schedule “C”.<br />

7. The bids should be valid for a minimum period of 6 months from the date of opening.<br />

8. The prospective bidder shall have executed satisfactorily similar works of large<br />

magnitude in time and have full fledge Engineering Organization to handle this highly<br />

specialized skilled work and such experience will be one of the major consideration in<br />

evaluating and finalizing this tender.<br />

9. The works covered under these specification shall be carried out and governed by<br />

“Tender and contractor for works” booklet appended herewith except where condition<br />

specified in this specifications.<br />

10. COORDINATION WITH OTHERS:<br />

11. The contractor shall have to execute the above works with the concern agencies that<br />

required. The Contractor shall co-operate in all aspects and exchange the necessary<br />

technical data/drawings with the consultants/Architects/Structural Engineers/ Contractors<br />

with permission from Engineer-In-Charge to ensure proper co-ordination and satisfactory<br />

completion of the work in time.<br />

12. Any more information of the proposed work may be referred from the office of the<br />

Superintending Engineer (TR)/ Executive Engineer (Const.) GETCO Transmission<br />

Circle/ Construction Division Anjar: Kutch during the office hours.<br />

13. The successful contractor shall have to sign an agreement as per <strong>Gujarat</strong> Energy<br />

Transmission Corporation Ltd. rules on a stamp paper and necessary stamp duty charge<br />

shall be borne by the contractor.


Page6<br />

14. The bid shall accompany by a covering letter in which the bidder shall give all<br />

information as called for in the specification and any other points which he would like to<br />

consider along with the tender. If such covering letter if not received along with the bid,<br />

it will be presumed that the bidder agreed entirely with the specifications and general<br />

terms and conditions of the contract booklet.<br />

15. Following certified copy of documents are required to be Attached with tender submitted<br />

by you:<br />

a. Solvency certificate latest issued by schedule Bank.<br />

b. Work experience i.e. similar work done, order placed by GEB/GETCO or other<br />

department.<br />

c. Labour License<br />

d. Registration of appropriate class certificate.<br />

e. Provident Fund No.<br />

f. Company Registration copy.<br />

g. Partnership deed copy (if any).<br />

h. Power of Attorney if given.<br />

i. Service Tax Registration<br />

j. Pan Card No.<br />

k. VAT No.<br />

Above documents are required to be attached with tender submitted. Failing which<br />

tender/offer will be rejected/ ignored and no correspondence will entertain in this matter<br />

of future.<br />

16. The work shall commence immediately after the order for commencement is issued.<br />

17. Bidder shall indicate in Schedule-“F” the equipment in his possession and propose to<br />

bring to the site, in case the work is awarded.<br />

18. The complete specification comprises of the following:<br />

General Instruction to Bidders<br />

General Conditions of Contract<br />

Safety Code<br />

Technical Specifications<br />

Bidding Schedule<br />

All these sections are supplementary to each other and the particulars and requirements<br />

contained have in shall covering the execution “Civil work for Dayapar feeder bay at 66 kV<br />

switch yard of KLTPS, Panandhro.”<br />

19. The testing of materials, concrete cube tests shall be done by the contractor. The alltesting<br />

charges shall be borne by the contractor.<br />

20. No collection of materials shall be made before it is got approved from the Engineer-In-<br />

Charge.<br />

21. Materials, if and when rejected by the Engineer-In-Charge shall be immediately removed<br />

from the Site.<br />

22. All installations pertaining to water supply and fixtures thereof as well as drainage lines<br />

and sanitary fitting shall be deemed to be completed only after giving satisfactory tests<br />

by the contractor.


Page7<br />

23. Approval to the samples of various materials, given by the E.I.C. shall not absolve the<br />

Contractor from the responsibility of replacing defective material brought on site or<br />

materials used in the work found defective at a latter date. The contractor shall have no<br />

claim to any payment of compensation whatsoever on account of any such material being<br />

rejected by E.I.C.<br />

24. Approval to any of the executed item for the work does not in any way relieve the<br />

contractor of his responsibility for the correctness, soundness and strength of the<br />

structure as per the drawing and specification.<br />

25. High yield strength steel deformed bars be either cold twisted or hot rolled shall confirm<br />

No. IS 1739-1966 and IS 1139-1966 respectively. It shall also comply with relevant part<br />

of IS 456-1978.<br />

26. Contractor has to utilize the mechanical vibrator for proper compaction for all concreting<br />

work as per the directions of Engineer-In-Charge.<br />

27. The drawings if any attached with the tender for bid purpose. However contractor shall<br />

have to carryout the work as per the construction drawing issued from time to time.<br />

28. The contractor shall have a separate Provident Fund code of RPFC and the contractor<br />

who not posses separate P.F. code shall not be considered for acceptance of tender.<br />

Contractor has to submit such Certificate showing separate P.F.Code along with tender.<br />

EXECUTIVE ENGINEER (CONST.)<br />

CONSTRUCTION DIVISION<br />

ANJAR.


Page8<br />

<strong>Gujarat</strong> Energy Transmission Corporation Ltd.,<br />

Construction Division, Anjar.<br />

TERMS & CONDITIONS<br />

1. Terms & Condition :<br />

General terms and conditions, commercial terms and conditions for Construction of Revetment wall for<br />

protection of 220 kV tower foundation at Loc. No. 03, 41, 47 & 53 of 220 kV Nanikhakhar – Shivlakha<br />

line LILO at 220 kV Kukma s/s including service deposit, payment terms, warranty, income tax, handing over<br />

and documents of Transmission line, schedules and other formats applicable to this order shall be as per the<br />

tender specification of GETCO as you have to agree to all the terms and condition of our tender specification<br />

in total except to the extent specifically indicated hereunder.<br />

2. Prices & Scope of the work:<br />

The prices and scope of the work quoted for Construction of Revetment wall for protection of 220 kV tower<br />

foundation at Loc. No. 03, 41, 47 & 53 of 220 kV Nanikhakhar – Shivlakha line LILO at 220 kV Kukma s/s<br />

are indicated in the Price Bid + Service Tax as applicable.<br />

3. Security Deposit cum Performance Bank Gaurantee :<br />

Security Deposit is for satisfactory execution of the contract and as Performance Guarantee. Security<br />

Deposit should be in the form of Bank Guarantee. The bank guarantee furnished should have clear one time<br />

validity till the completion of the order in all respect & up to expiry of the guarantee period of 2 (two) years<br />

from the date of commissioning of transmission line. The contractor will have to pay the Security Deposit at<br />

5% of the order value. On placing the order, 2.5% will have to paid in demand draft in favor of „GUJARAT<br />

ENERGY TRANSMISSION CORPORATION LTD‟ within 7 days from the date of the issue of LOI, and the<br />

remaining 2.5% will be recovered from the first two R.A. Bills and higher percentage of security deposit may<br />

be fixed at the direction of The Executive Engineer.<br />

4. Completion Period :<br />

You have to commence the survey activity from the commencement date and shall have to complete survey<br />

and route alignment of transmission lines within 01 Month completing all the activities including preparing<br />

BOQ consisting of quantity of towers and extensions & type of foundations for transmission lines listed in the<br />

Price Bid.<br />

5. Penalty for Delay :<br />

The completion time allowed shall be strictly observed. In case of failure to complete contract work within the<br />

stipulated completion period, you shall be liable to pay penalty at the rate of ½ % value of delayed work per<br />

week or part thereof the contract value subject to ceiling of 10% of the total contract value.<br />

This will deducted from the bills payable either against this contract or any bank guarantee or any other<br />

amount payable under any other contract with the <strong>Board</strong>.<br />

6. Force Majeure :<br />

6.1 Force Majeure is herein defined as any cause which is beyond the control of the contractor or the<br />

owner as the case may be, which they could not foresee or with a reasonable amount of diligence<br />

could not have foreseen and which substantially affects the performance of the contract such as:<br />

a. Natural phenomena including but not limited to floods, droughts, earthquakes and epidemics;<br />

b. Acts of any Government, domestic or foreign including but not limited to war, declared or<br />

undeclared, priorities, guarantees and embargoes.<br />

Provided either party shall within fifteen (15) days from the occurrence of such a cause notify the<br />

other in writing of such causes.<br />

6.2 The contractor or the owner shall not be liable for delays in performing his obligations resulting from<br />

any force majeure cause as referred to and/or defined above.<br />

The date of completion will subject to herein after provided be extended by a reasonable time even<br />

through such cause may occur after contractor‟s performance of obligation has been delayed due to<br />

other causes.<br />

7. Terms of Payment :<br />

Normally, one R.A. Bills will be paid every month, however, looking to the progress of the work it will be<br />

reviewed mutually and 90% of the cost of work done will be paid to the Contractor on his presentation of R.A.<br />

Bill giving the material account thereof. Remaining 10% Payment will be made after the entire work is


Page9<br />

completed satisfactorily in all respect. The payment will be made through Account Payee Cheque only. The<br />

Bill should be submitted to our Deputy Engineer (Civil) BHUJ with a copy to Executive Engineer (Const.),<br />

Anjar. Final bill will be prepared by our Deputy Engineer (Civil) BHUJ within about fortnight from the date<br />

of completion of the work by the Contractor.<br />

8. Presentation of Bills :<br />

Final bill for the concern work in original with one copy shall be submitted to E.E. (Const), Anjar for passing<br />

and processing for payment.<br />

9. Agreement / Indemnity Bond :<br />

You shall have to execute the contract agreement at your own cost on the stamp paper of Rs. 100/- and<br />

have also to submit Indemnity bond on the stamp paper of Rs. 100/- as per the prescribed format appended<br />

with the specification enclosed.<br />

10. Progress :<br />

The progress of concern work shall be reviewed by the GETCO from time to time by way of meeting and you<br />

have to submit the fortnightly progress report in prescribed proforma to the Ex. Engineer (Const), Anjar<br />

regularly without fail.<br />

11. General Conditions :<br />

1) The tenders shall remain open for acceptance at least for a period of Six Months, from the date of<br />

opening of tenders.<br />

2) The <strong>Gujarat</strong> Energy Transmission Corporation Limited does not bind itself to accept the lowest or any<br />

tender. The Executive Engineer (Const.), ANJAR reserves the right to reject any or all tender without<br />

signing any reasons whatsoever.<br />

3) The contractor should employee as Supervisor with sufficient qualification and experience who could<br />

supervise the execution of work thought. He should always be present on the site.<br />

4) The work should be commenced immediately from the date of receipt of instructions from office and<br />

should be completed within thereafter.<br />

5) The tender includes all minor accessories and items of work which hay not have been specifically<br />

mentioned in the specification schedule etc. but are essential for completion of work. The contractor<br />

will not be eligible for any extra payment in respect of such minor accessories and items of work.<br />

6) Tenderer should be qualified only who have P. F. Registration, Service Tax Registration, Vat<br />

Registration & Work Registration.<br />

7) Service tax will be paid as per prevailing norms on production of service tax registration. And against<br />

production of payment proof.<br />

8) No higher rate of revised rate will be applicable for the work, if work is held up/ closed due to<br />

whatever so reasons.<br />

9) In case of any dispute/ doubt, the decision of Executive Engineer (Const), GETCO, ANJAR shall be<br />

unchallengeable, final and binding to the contractor.<br />

10) 10% retention money will be deducted from each R.A. Bills.<br />

11) The tendered should furnished details of past experience of such jobs of similar nature completed by<br />

him satisfactorily within the time limit in GETCO without this certificate offer shall be rejected out<br />

rightly.<br />

12) The quantum of the work as mention in estimate/ schedule –„B‟ is tentative and it can be very differ as<br />

per site condition. The payment shall be made only on actual work executed or order quantity,<br />

whichever is less.<br />

13) The tenderer will be abide by and fulfill all the terms and provisions of the “Tender & Contract” for<br />

works as applicable and incase of any default there to the GETCO shall for fit the S.D. or any other<br />

action as may be decided by Executive Engineer (Const), GETCO, ANJAR.<br />

14) The time limit for the work may be reduced and contractor should make all his efforts to complete the<br />

work within stipulated time limit as may be given by the Engineer in charge depending upon<br />

emergency of work, GETCO reserves the right to reduce the time limit without giving any notice.<br />

15) The contractor has to remain in close day contact with D.E. (Civil), concern S/Dn Engineer in charge<br />

of work who in turn shall issue detailed instruction for the commencement of the work.<br />

16) Contractor will abide by and fulfill all the terms and conditions and general terms and condition of the<br />

contract for works available in the office.<br />

17) All other general terms and conditions as prevailing in the GETCO shall be applicable to the contract.<br />

18) The contractor will have to complete entire job as per directive and instruction of Engineer in charge.<br />

If he fails to do so entire work will be carried out at contractor‟s risk and cost.<br />

19) The tender shall be issued to only the experience and contractor who has completed such job of<br />

similar nature and magnitude satisfactorily in time. However, issuance of blank tender, will does not<br />

qualifies the tenderer to offer the bid.


Page10<br />

20) Tender offer without payment of EMD required certificate, documents, bar chart list of tools, tackles,<br />

equipments etc. required for execution of job will be out rightly rejected without assigning any reason<br />

thereof and decision of Executive Engineer (Const), Anjar will be final and unchallengeable.<br />

21) The Contractor will be governed by The GETCO‟s general conditions of works contract. The Booklet<br />

will be available in the concerned office in any working days. In the event of placing order, the<br />

contractor will have to sign this booklet along with other document and agreement. All the usual terms<br />

and conditions of the GETCO, through the same might have not been mentioned in this specification<br />

or contractor booklet will applicable to this contract, and the decision of the Executive Engineer/<br />

Superintending Engineer shall be binding on the contractor.<br />

22) Specification in any items mentioned in tender are subject to change without any prior notice and<br />

binding to the contractor.<br />

23) GETCO shall deduct the Income-Tax and other taxes as per prevailing rules from each and every bill.<br />

24) If required by GETCO you shall have to provide free to and fro traveling facility to our Junior Engineer<br />

or Technical staff for the work.<br />

25) The contractor shall not refuse to execute the work order at any time and it will be his sole<br />

responsibility to execute and complete this work as per the instruction of Engineer in charge.<br />

26) The contractor has to carry out all the works in accordance with revised and latest provision under<br />

I.E. Rules Act made there under and as per instruction of Engineer in charge.<br />

27) Registered class „A‟ contractors with the GETCO and having furnished Rs. 5 Lacs bank guarantee<br />

towards lump sum permanent deposit are exempted from to renew / extend the validity of registration<br />

and bank guarantee well in time before expiry dates.<br />

28) The S.S.I. Industries will be exempted from the payment of Security Deposit provided a competency<br />

certificate is issued by the Regional Division Officer of the National Small Scale Industries<br />

Corporation to the effect that the firm is capable of executing the order.<br />

29) No subcontractor, Power of Attorney shall be allowed.<br />

30) No part rate or reduced rate shall be allowed in final bill.<br />

31) The undersign reserve rights to reject any or all the tenders without assigning any reasons thereof.<br />

Issuance of blank tender does not automatically qualifies the tenderers for award.<br />

32) No tools, tackles, manpower, etc will be provided by the GETCO.<br />

33) The contractor has to follow all labour laws, safety rules and regulations. The GETCO does not take<br />

any responsibility in case of accident or injury to the workers. The safety/ security of men, materials<br />

and equipments shall be sole responsibility of the contractor.<br />

34) The compliances of all Central/ State Govt. rules, safety and insurance rules etc. and that of local<br />

body, is a must condition for the agency.<br />

35) The bidder shall specifically note that GETCO will not pay any extra amount towards any type of<br />

claim except for the description indicated in Schedule – „B‟. The party has to carry out all other/<br />

additional required activities/ works as directed by Engineer in charge which is not mentioned in<br />

Schedule but required to be completed as per site condition and for this work no extra payment shall<br />

be made by GETCO.<br />

36) The contractor shall co-operate with the GETCO in recording measurement etc as expeditiously as<br />

possible and he shall fulfill all the requirements which are necessary to finalize the accounts on the<br />

basis of its records and pay him such amount as if found due to him together with the amount of<br />

security deposit. If any remaining payable to him after deduction there from the amount due by him to<br />

the GETCO. The GETCO shall not entertain further claim from thereafter.<br />

37) The contractor shall not refuse to execute this work order at any time and it will be his sole<br />

responsibility to execute and complete this work as per the instruction of Engineer in charge.<br />

38) <strong>Electricity</strong> Rules:- All the works shall be carried out in accordance with latest rules<br />

under <strong>Electricity</strong> Act.<br />

39) The interpretation of specifications doubts etc.:- In case of any doubts about what is mentioned<br />

in specification or schedule or elsewhere, the tenderer should get all doubts cleared from the<br />

Department in writing and in advance of filling in the Tender. In case of difference of opinion about<br />

interpretation of specification etc the decision of Executive Engineer will be final and shall be binding<br />

to the contractor.<br />

Executive Engineer (Const.)<br />

GETCO,D.O., ANJAR.


Page11<br />

GUJARAT ENERGY TRANSMISSION CORPORATION LTD.<br />

CONSTRUCTION DIVISION, ANJAR (KUTCH).<br />

SECTION: I<br />

GENERAL CONDITIONS OF CONTRACT FOR CIVIL CONSTRUCTION WORK CONSTRUCTION OF<br />

REVETMENT WALL FOR PROTECTION OF 220 KV TOWER FOUNDATION AT LOC. NO. 03, 41, 47<br />

& 53 OF 220 KV NANIKHAKHAR – SHIVLAKHA LINE LILO AT 220 KV KUKMA S/S.”<br />

1.0 SAFETY CODE:<br />

1.01 There shall be maintained in a readily accessible place first aid appliances<br />

including adequate supply of sterilized dressings and cotton wool.<br />

1.02 An injured person shall be taken to a public hospital without loss of time, in case<br />

where the injury necessities hospitalization.<br />

1.03 Suitable and strong scaffolds should be provided for workmen for all works that<br />

cannot safely be done from ground.<br />

1.04 No portable single ladder shall be over 8 meters in length. The width between<br />

the side rails shall not be less than 30cm (clear) and the distance between two<br />

adjacent runs shall not be more than 30cm. When a ladder is used and extra<br />

mazdoor shall be ensured for holding the ladder.<br />

1.05 No floor, roof or other part of the structure shall be overloaded with debris or<br />

materials as to render it unsafe.<br />

1.07 (1) No paint containing lead or lead products shall be used expect in form of paste<br />

or ready-made paint.<br />

(2) Suitable facemasks should be supplied for use by the workers when the<br />

paint is applied in the fork of spray or surface having lead paint dry rubber<br />

and scrapped.<br />

1.08 The contractor shall supply over all and adequate facilities shall to enable the<br />

working painters to wash during the period of cessation of work.<br />

1.09 Carpentry Tools and tackle used in the works including their attachments,<br />

anchorage and supports shall be in perfect conditions.<br />

1.10 The ropes used in the hoisting or lowering or as suspension shall be durable<br />

quality and adequate strength and free from defects.<br />

EXECUTIVE ENGINEER (CONST.)<br />

CONSTRUCTION DIVISION<br />

ANJAR.


Page12<br />

GUJARAT ENERGY TRANSMISSION CORPORATION LTD.<br />

CONSTRUCTION DIVISION, ANJAR (KUTCH)<br />

SPECIAL CONDITIONS<br />

Following are the GETCO’s special conditions for this project and wherever these special<br />

conditions contradict with similar conditions in this tender document, the following special<br />

conditions shall prevail.<br />

1.0 ARBITRATION<br />

In view of Government of <strong>Gujarat</strong>’s directive the Arbitration Clause provided at Sr.No.30 of<br />

the Chapter in Booklet of “TENDER AND CONTRACTOR THE WORKS” in Tender<br />

specification and other related reference for Arbitration now stands deleted.<br />

In its place following clause is to be substituted:<br />

“ALL QUESTIONS, DISPUTED, DIFFERENCES, WHATSOEVER WHICH MAY AT ANY TIME ARISE<br />

BETWEEN THE PARTIES TO THIS CONTRACT IN CONNECTION WITH THE CONTRACT OR ANY<br />

MATTER ARISING OUT OF OR IN RELATION THERE TO, SHALL BE REFERRED TO THE<br />

“GUJARAT PUBLIC WORKS CONTRACTS DISPUTE ARBITRATION TRIBUNAL” AS PER THE<br />

PROVISIONS OF THE GUJARAT PUBLIC WORKS CONTRACTS DISPUTES ARBITRATIKON<br />

TRIBUNAL ACT, 1992”<br />

1.1 The reference to arbitration proceeding under this clause shall not:<br />

(a) Affect the right of the Engineer-in-charge to take possession of all or any tools, plants<br />

materials and stores, in our upon the work or site thereof belonging to the contractor or<br />

produced by him and intended to be used for the execution of the work or any part<br />

thereof.<br />

(b) Preclude the Engineer-in-charge from utilizing the materials purchased by the<br />

Contractor in any work or from removing such materials to other place, during the<br />

period the work is stopped or suspended in pursuance of notice given to the contractor<br />

under General Conditions.<br />

(c) Entitle the contractor to stop the progress of the work or carrying out the additional or<br />

altered work in accordance with the provisions of General conditions or the work where<br />

there is no specification.<br />

(d) Preclude party is entitled to bring a claim to arbitration latest by thirty days after the<br />

expiration of the defects liability period.<br />

1.2 Neither party is entitles to bring a claim to arbitration latest by thirty days after the<br />

expiration of the defects liability period.<br />

1.3 The provisions of the Arbitration Act.1992, <strong>Gujarat</strong> Public Works Contract Disputes<br />

Arbitration Tribunal Act, 1992, and rules made there under shall apply to the arbitration<br />

proceeding under this clause.<br />

2.0 The successful Bidder, on receipt of letter of intent will submit within a week’s time his<br />

planning/ programme of works, for scrutiny of <strong>Gujarat</strong> Energy Transmission<br />

Corporation Ltd. in a Pert/Bar Chart format, clearly indication GETCO’s inputs also.


Page13<br />

3.0 Contractor will plan his works such that on all the fronts released by GETCO<br />

simultaneous work should progress in such a way that entire job is completed in<br />

schedule time limit.<br />

4.0 The successful bidder will have to depute his authorized representative to attend<br />

progress review meetings to be held either at the site or at GETCO’s, TR Circle Office/<br />

Construction Division office at Anjar.<br />

5.0 Security Deposit (5% of contract value) shall be payable by the contractor within fifteen<br />

(15) days from the date of issue of intent. Security Deposit in approved form of Bank<br />

Guarantee valid during the contractual period shall be acceptable. However, such Bank<br />

Guarantee should not be reduced on the basis of the work actually done and the Bank<br />

Guarantee should be kept valid till the maintenance period is over or passing of banal<br />

bill after due scrutiny by technical and accounts section whichever is later. This shall<br />

be refunded as per GETCO’s norm.<br />

6.0 The contractor will be responsible for complying with all rules and regulations and<br />

labour laws applicable to him and GETCO will responsible for any lapse committed by<br />

them If there is any claim from any Government authority pertaining to the contract, the<br />

same amount will be deducted from the Contractor’s bill.<br />

7.0 The GETCO will not give the land required for office, godowns and for Labour Camp.<br />

The contractor has to arrange at his cost.<br />

8.0 THE TIME LIMIT FOR COMPLETION OF WORK IS STIPULATED AS<br />

CALENDER MONTHS, WILL BE ADHERED TO.<br />

9.0 As per tender conditions, the Electric Power shall be given at on mutually agreed point;<br />

further distribution will have to be carried out by the contractor as per their<br />

requirements at their cost. Necessary connection and consumption charges will be<br />

recovered as per GETCO’s tariff/rate from time to time, as per GETCO’s rules.<br />

10.0 The contractor’s rates should be firm and no variation clause is to be quoted by the<br />

contractor’s and GETCO will not accept the same, during contractual period including<br />

extended time limit if any.<br />

11.0 THE GETCO WILL NOT PAY ANY TYPE OF ADVANCES INCLUDING<br />

MOBILISATION ADVANCE.<br />

EXECUTIVE ENGINEER (CONST.)<br />

CONSTRUCTION DIVISION<br />

ANJAR.


Page14<br />

GUJARAT ENERGY TRANSMISSION CORPORATION LTD.<br />

CONSTRUCTION DIVISION, ANJAR (KUTCH)<br />

Special Condition for use of Cement and steel in work:<br />

1. The Rates in Schedule “B” is inclusive of Cement Cost. Contractor has to<br />

Purchase Fresh 43/53 grade & PPC Cement Confirming to as per IS 8112<br />

and approved brand by GETCO.<br />

2. Contractor has to construct “Pucca Godown” at site of the work so that Cement bags<br />

can be properly preserved to avoid damage due to any kind of Water.<br />

3. Contractor has to bring sufficient Quantities of Cement Bags and at No time less<br />

then 200 (Two Hundred) bags to maintain progress of work. The work should not<br />

suffer for want of Cement.<br />

4. Cement should give the required strength of Cement Concrete.<br />

5. To bring sufficient and timely Cement at site is full responsibility of Contractor.<br />

Nothing extra will be paid on account of any reason to maintain progress of work<br />

and to complete the work in schedule time.<br />

6. Contractor has to submit material A/C for consumption of Cement used with every<br />

bill. In case of not submitting the same, bill will not be passed. Contractor has to<br />

submit the copy of Cement Purchase Bill along with Each R.A. Bill / Final bill.<br />

7. No negative variation will be allowed for consumption in Cement then prescribed as<br />

per Booklet of Technical Specification of <strong>Board</strong> / Mix Design and nothing will be<br />

paid extra for over consumption.<br />

8. Contractor is fully responsible for safety of Cement at site; nothing will be paid<br />

extra on account of safety.<br />

9. If <strong>Board</strong>’s authorized representative wants to check cement stock at site, contractor<br />

has to allow for the same at any time.<br />

10. Contractor has to maintain day-to-day cement consumption / balance account at site.<br />

11. As for as possible, Contractor has to maintain supply of cement of only one brand &<br />

grade through out the work and on account of closer / shortage of approved brand,<br />

cement of other brand in accordance of condition no (1) will be allowed by<br />

Engineer-in-charge.<br />

12. Minimum Cement consumption considered for Cement Concreting having Grade of<br />

M-15 / M-20 / M-25 is 300 Kgs / 320 Kgs / 340 Kgs. Respectively. Contractor has<br />

to use minimum Cement as above. Contractor should not use less than the prescribed<br />

quantities of Cement even in the case of Mix-design recommends lower quantity.<br />

13. Contractor will be allowed to carry out work only after Physical Verification of<br />

Cement brought at site.<br />

EXECUTIVE ENGINEER (CONST.)<br />

CONSTRUCTION DIVISION<br />

ANJAR.


Page15<br />

GUJARAT ENERGY TRANSMISSION CORPORATION LTD.<br />

CONSTRUCTION DIVISION, ANJAR (KUTCH)<br />

Cement and Steel of the following companies/ suppliers who are the manufacturing for<br />

supplying are to be provided by Contractor:-<br />

Name of Manufacturer of Cement<br />

Name of Manufacturer/supplier of<br />

structural steel/coils/bars etc.<br />

Narmada Cement company Ltd.<br />

<strong>Gujarat</strong> Ambuja Cement Co. Ltd.<br />

Saurashtra Cement.<br />

Siddhi Cement.<br />

J.K Cement.<br />

Ultratech Cement.<br />

Shri Digvijay Cement Co. Ltd.<br />

Binani Cement.<br />

Vikram Cement.<br />

Sanghi Cement.<br />

Steel Authority Of India.<br />

Tata Iron & Steel Co. Ltd.<br />

Jindal.<br />

Lloyds.<br />

Essar Steel Ltd.<br />

Ispat.<br />

Bhawalka Steel Ind. Ltd. Mumbai<br />

Sun Vijay Rolling & Engineer, N,pur<br />

Shri Bajranga Alloys, Ltd. Raipur<br />

Unique Structures and Towers Ltd.<br />

Shah Alloys Ltd. Ahmedabad<br />

Sanghi Steel<br />

Neelkanth Steel (Kamdhenu)<br />

Wellspun Steel.<br />

EXECUTIVE ENGINEER (CONST.)<br />

CONSTRUCTION DIVISION<br />

ANJAR


Page16<br />

GRAM: TRANSGRID Phone No.(02836) 245784<br />

Fax No.(02836) 241588<br />

CONSTRUCTION DIVISION OFFICE,<br />

220KV COMPOUND S/S ANJAR,<br />

ANJAR - KUTCH – 370 110.<br />

E - Mail:- eeconstanj@yahoo.co.in<br />

price B I D<br />

NAME OF WORK:<br />

Construction of Revetment wall for protection of 220 kV tower<br />

foundation at Loc. No. 03, 41, 47 & 53 of 220 kV Nanikhakhar –<br />

Shivlakha line LILO at 220 kV Kukma s/s.


Page17<br />

GUJARAT ENERGY TRANSMISSION CORPORATION LTD.<br />

CONSTRUCTION DIVISION, ANJAR (KUTCH)<br />

NOTES FOR SCHEDULE: „B‟<br />

All the columns in schedule should be filled in INK.<br />

1) Rate quoted include clearance of site prior to commencement of work and after<br />

completion of work in all respects and hold good for work under all conditions site,<br />

moisture, weather etc.<br />

2) The quantities given in Schedule “B” are approximate. It may very at the time of<br />

execution and contractor shall have to execute the work as per approved drawings<br />

given at the time of execution.<br />

3) Certain changes may be incorporated during construction and as a result, there may<br />

be increase in the above stated quantities. In such an event, it should be noted that<br />

the contractor should not claim anything extra. These will be paid on the basis of<br />

actual quantities executed.<br />

4) The percentage rate shall be quoted both in the words and figures. Should there be<br />

any discrepancy between the rate quoted in words and figures, rate quoted in words<br />

shall prevail.<br />

5) Further, should there by any discrepancy between the rate and amount, the rate will<br />

prevail.<br />

SIGNATURE: -<br />

NAME: -<br />

STATUS: -<br />

Whether authorized Attorney<br />

Of the Tendering Company<br />

Name of the Tender Company


Page18<br />

GUJARAT ENERGY TRANSMISSION CORPN. LTD.<br />

ANJAR CIVIL SUB DIVISION.<br />

Sr.<br />

No.<br />

NAME O NAME OF WORK: Civil work for Dayapar feeder bay at 66 kV<br />

switch yard of KLTPS, Panandhro.<br />

"SCHEDULE-B"<br />

DESCRIPTION QTY. UNIT RATE AMOUNT<br />

1 Excavation for foundation up to 1.5m depth<br />

including strutting, shoring wherever<br />

necessary & refilling the side of the<br />

trenches, sorting out and stacking of useful<br />

materials and disposing of the surplus stuff<br />

up to 200meter lead.(A) DENSE SOIL (<br />

SOR SR NO 1 , ITEM NO 0.0 ( B ))<br />

2 Filling in plinth/trenches with earth in<br />

150mm, thick layers including water,<br />

ramming, consolidating etc., complete as<br />

directed by EIC. - yellow earth/murrum of<br />

approved quality brought from out side.(<br />

SOR SR NO 8 , ITEM NO 0.0 )<br />

3 Providing and laying cement concrete 1::3:6<br />

(1 Cement : 3Course sand : 6 black crushed<br />

stone aggregate 40mm nominal size ) and<br />

curing complete- Foundation and plinth. (<br />

SOR SR NO 3 , ITEM NO 5.3.2 )<br />

4 Providing & laying control cement concrete<br />

M-20 as per mix design exposed work with<br />

curing etc. complete excluding the cost of<br />

ply wood / steel sheathing form work &<br />

adjustable tubular steel supports / Props.but<br />

excluding the cost of reinforcement.<br />

G.F+F.F+Stair Cabin Columns and coping.<br />

( SOR SR NO 33 , ITEM NO 0.0 ( B - 2 ) )<br />

5 Providing block masonary in foundation and<br />

up to plinth in C.M. (1:6) including racking<br />

out joint up to 12mm depth<br />

,scaffolding,curing,filling up the gapa<br />

between the joints complete as directed by<br />

EIC., upto plinth (SOR SR.No.45,Item<br />

No.12.7.75)<br />

6 Providing Thermo Mechanically treated bars<br />

(TMT bars) confirmed to IS 1786 FE 415 for<br />

RCC work including bending, binding and<br />

placing in position etc. complete for RCC<br />

work.( SOR SR NO 14 A , ITEM NO 5.4.11<br />

( a ) )<br />

30.00 Cmt 60.00 1800.00<br />

225.00 Cmt 226.00 50850.00<br />

4.00 Cmt 2069.00 8276.00<br />

25.00 Cmt 5805.00 145125.00<br />

25.00 Cmt 2315.00 57875.00<br />

1000.00 Kg 51.00 51000.00


Page19<br />

7 Providing and laying Rubble soling 225mm<br />

thk using required stone in required slope<br />

and alignment with all tools, tackles,<br />

equipment and labour. Including filling the<br />

interstices with stone chips and SAND,<br />

including flooding with water and<br />

compacting by rammer or compactor as per<br />

the requirement and site conditions etc.<br />

complete as directed by the site-in-charge &<br />

Providing cement pointing on jionts of<br />

rubble piching in CM 1:1 curing etc.<br />

complete as directed by EIC.( AS PER<br />

NEW 66 KV APPROVED ESTIMATE )<br />

8 Providing form work of steel / ply wood<br />

planking so as to give a smooth exposed<br />

finish including centering (steel adjustable<br />

tubular supports). Shuttering strutting and<br />

propping etc. for any height of propping<br />

and centering below supporting floor to<br />

ceiling , and removal of the same for<br />

reinforced concrete and plain concrete. for<br />

footing,teowall,column beams etc for all<br />

floors.( SOR SR NO 1 , ITEM NO 9.1 ( C )<br />

9 Providing & Laying TMT (Thermo Mechanically<br />

Treated) reinforcement bars confirming to Fe-<br />

415-IS-1786 including cutting, bending, hooking<br />

and binding the reinforcement with approved<br />

quality of binding wire etc. compl. As per design<br />

(Providing chairs and supports etc., will be paid<br />

for under the item) and as directed by EIC etc.<br />

complete. SOR PG NO 26, SR NO 14-A, ITEM<br />

NO 5.4.11 ( A )<br />

10 Precast concrete block masonry (including<br />

quoin blocks Jamb blocks, closer etc.) with solid<br />

concrete blocks of approved size made of<br />

cement concrete 1:3:6 mix (1 Cement : 3<br />

Coarse sand : 6 graded stone aggregate of<br />

20mm and down gauge) in foundation and<br />

plinth in cement mortar (1:4) 1 Cement : 4<br />

Coarse Sand. SOR PG NO 45, SR NO 12,<br />

ITEM NO 7.75<br />

11 Providing 15 mm. thick cement plaster in C.M.<br />

(1:3) including finishing the surfaces with<br />

smooth cement finishing, necessary drip<br />

molding, scaffolding, curing etc., for block<br />

masonry before starting plaster cement duo<br />

(Cement slurry should be applied on the block<br />

surface.) SOR PG NO 76 ITEM NO 2.17.60( I )<br />

12 Steel work welded in built up section framed<br />

work including cutting, hoisting, fixing in position<br />

and applying priming coat of red lead paint for<br />

M.S. Angles, channels girders etc., for purling,<br />

rafters, columns etc., including welding the<br />

section as per instruction & drawing making<br />

holes & 3 coats of oil painting of approved<br />

shade & make etc., complete. (ALL<br />

MATERIALS SHALL BE BROUGHT BY THE<br />

CONTRACTOR.) SOR PG NO 57, SR NO 2,<br />

ITEM NO 11.4 ( A )<br />

265.00 Smt 120.00 31800.00<br />

70 Smt 112 7840<br />

0.70 MT 40210.00 28147.00<br />

2.50 CMT 2315.00 5787.50<br />

25.00 SMT 78.00 1950.00<br />

30.00 KG 64.00 1920.00


Page20<br />

13 Providing and placing 50 mm thick & 300 mm<br />

vide pre stressed concrete cover ( For clear<br />

span up to 1.20 mtr) in proportion 1:1 1/2:3 or<br />

M - 20 with reinforcement of 4 mm dia. HT steel<br />

wire 4 nos. bars and 6 mm dia. distribution bars<br />

at 150 mm c/c as per drawing & design<br />

including providing necessary M.S. hook for<br />

lifting arrangement & vibrating, finishing the<br />

surfaces, curing by placing in water pond for 10<br />

days, lifting arrangement etc. complete as<br />

directed by Engineer in charge including<br />

loading- unloading , transportation, placing,<br />

stacking etc. complete. As per new 66Kv s/s<br />

A/T<br />

14 Supplying of crushed stone aggregate hard<br />

stone of 25 to 40 mm size free of disintegrated.<br />

{SOR P. No: 115, 125 & 217, I. No: 12.26.70 +<br />

64.0.0 + 3.2.1(B)(AL-4)}<br />

15 Fabrication, cutting, threading including hot dip<br />

galvanizing including supply of MS rods of<br />

appropriate size for foundation bolts with two<br />

nos. of Nuts for each foundation bolts as per<br />

drawings/instructions of EIC. As per new 66 kV<br />

s/s A/T.<br />

10.00 SMT 403.00 4030.00<br />

15.00 Cmt. 789.00 11835.00<br />

150.00 Kg 79.00 11850.00<br />

Total Amount Rs. 1,89,327.50<br />

{ Rupees One Lac Eighty Nine Thousand Three Hundred Twenty Seven and Fifty Paisa Only}<br />

Service Tax as applicable. The service tax will be reimbursed to party on production<br />

of proof of payment to the appropriate authority.<br />

Ex. Engineer(Const.)<br />

GETCO, ANJAR<br />

I/We am/are willing to carry out the above work at ____ % above/below the<br />

estimated cost and amount works out at Rs.____________________<br />

Signature of the Contractor with seal


Page21<br />

GUJARAT ENERGY TRANSMISSION CORPORATION LTD.<br />

CONSTRUCTION DN. ANJAR: KACHCHH<br />

SCHEDULE: „C‟<br />

Schedule of Bidder Experience (To be filled in and signed by the Bidder)<br />

The Bidder shall furnish here a list of Similar Jobs Executed by him to whom a reference may<br />

be made by the <strong>Board</strong> in case <strong>Board</strong> consider such a reference necessary.<br />

Sr.<br />

No.<br />

Name & Description of<br />

Work<br />

Value of<br />

Work<br />

Period of<br />

Construction<br />

& Date<br />

Client<br />

Remarks<br />

1 2 3 4 5 6<br />

SIGNATURE: -<br />

NAME: -<br />

STATUS: -<br />

Place:<br />

Whether authorized Attorney<br />

Of the Bidding Company<br />

Date:<br />

Name of the Bidding Company


Page22<br />

GUJARAT ENERGY TRANSMISSION CORPORATION LTD.<br />

CONSTRUCTION DN. ANJAR: KACHCHH<br />

SCHEDULE: „D‟<br />

Schedule of Deviation from Technical Specification<br />

(To be filled in and signed by the Bidder)<br />

All Deviation from the Specification shall be filled in by the Bidder Clause by Clause<br />

In this Schedule.<br />

Sr. Section Specification Clause No Deviations<br />

No.<br />

1 2 3 4 5<br />

The Bidder hereby Certified that the above mentioned are the Only Deviations from the<br />

Technical Specification of the Inquiry.<br />

SIGNATURE: -<br />

NAME: -<br />

STATUS: -<br />

Place:<br />

Date:<br />

Whether authorized Attorney<br />

Of the Bidding Company<br />

Name of the Bidding Company


Page23<br />

GUJARAT ENERGY TRANSMISSION CORPORATION LTD.<br />

CONSTRUCTION DN. ANJAR: KACHCHH<br />

SCHEDULE: „E‟<br />

Schedule of Deviation from General Specification<br />

(To be filled in and signed by the Bidder)<br />

All Deviation from the General Conditions shall be filled in by the Bidder Clause by Clause in<br />

this Schedule.<br />

Sr. Section Specification Clause No Deviations<br />

No.<br />

1 2 3 4 5<br />

The Bidder hereby Certified that the above mentioned are the Only Deviations from the<br />

General Conditions of the Inquiry and Tender and Contract for Works.<br />

SIGNATURE: -<br />

NAME: -<br />

STATUS: -<br />

Place:<br />

Date:<br />

Whether authorized Attorney<br />

Of the Bidding Company<br />

Name of the Bidding Company


Page24<br />

GUJARAT ENERGY TRANSMISSION CORPORATION LTD.<br />

CONSTRUCTION DN. ANJAR: KACHCHH<br />

SCHEDULE: „F‟<br />

Schedule of Equipments (To be filled in and signed by the Bidder)<br />

The Bidder Shall Indicate herein below the Equipments, He has in Possession and Equipments<br />

He proposed to bring to the Site, in case the Work is awarded to Him.<br />

Sr. Type & Description of Numbers the Bidder Number He Proposed to<br />

No. the Equipment has in Possession Bring on to Side<br />

1 2 3 4<br />

The Bidder hereby confirms that the Quantity and Type of tools He will employ for<br />

Construction will not be less than these listed above, and agree to bring more equipment, if so<br />

required, in the Opinion of the Engineer-In-Charge.<br />

SIGNATURE: -<br />

NAME: -<br />

STATUS: -<br />

Place:<br />

Date:<br />

Whether authorized Attorney<br />

Of the Bidding Company<br />

Name of the Bidding Company.