OHIO DEPARTMENT OF TRANSPORTATION<br />

DISTRICT 4<br />

<strong>2013</strong> CONSTRUCTION PROGRAM<br />

SERVING ASHTABULA, MAHONING, PORTAGE, STARK, SUMMIT AND TRUMBULL COUNTIES.<br />

JOHN R. KASICH, OHIO GOVERNOR | JERRY WRAY, ODOT DIRECTOR | ANTHONY M. URANKAR, DISTRICT DEPUTY DIRECTOR


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

<strong>2013</strong> Construction Program<br />

Total Costs: $445.4 million<br />

Construction Costs: $409.3 million<br />

Thank you for your interest in <strong>Ohio</strong> <strong>Department</strong> <strong>of</strong> <strong>Transportation</strong> - District 4’s <strong>2013</strong> Construction<br />

Program. This publication is intended to provide a general overview <strong>of</strong> projects that currently are<br />

under construction and those scheduled to be awarded or begin construction in <strong>2013</strong>.<br />

The <strong>2013</strong> Construction Program is divided into six sections, one representing each county in District<br />

4. Award dates, expected completion dates, project descriptions, project locations, cost and<br />

maintenance <strong>of</strong> traffic are listed. Total costs include preliminary engineering, right-<strong>of</strong>-way and<br />

construction. County maps have also been included for your reference.<br />

Please keep this book on hand throughout the upcoming construction season. Information regarding<br />

construction projects is continually changing; therefore, if you have any questions or require<br />

additional information, please do not hesitate to contact us. Also, District 4 is now on Facebook!<br />

Please like us at our <strong>Ohio</strong> <strong>Department</strong> <strong>of</strong> <strong>Transportation</strong> Akron / Canton District 4 page.<br />

District 4 Public Information Office<br />

330-786-2208<br />

Printed: April <strong>2013</strong><br />

OVERVIEW 2


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

In 2012 the District 4 Public Information Office began using Closure<br />

Notification Brochures which are used to identify construction projects<br />

that have large maintenance <strong>of</strong> traffic impacts or that affect numerous<br />

businesses.<br />

The Closure Notification Brochures explain the construction project, the<br />

maintenance <strong>of</strong> traffic, the amount <strong>of</strong> time motorists and businesses will<br />

be impacted and include a detailed detour maps for the area.<br />

If a project is deemed to have a Closure Notification Brochure created,<br />

these documents are handed out to local <strong>of</strong>ficials and businesses. A<br />

representative from the District 4 Public Information Office will<br />

distribute the brochures door to door to businesses within or near the<br />

construction project.<br />

Projects marked with an asterisk (*) in this book are projects that the<br />

Public Information Office will include Closure Notification Brochures<br />

for during the <strong>2013</strong> construction season.<br />

Also in 2012, District 4 began placing signs along construction projects<br />

that provided a contact information number if motorists had questions<br />

regarding a construction project or a closure associated with the project.<br />

The orange signs would let motorists know that a roadway would be<br />

closed for a certain number <strong>of</strong> days and provided a phone number to the<br />

Public Information Office if they had any questions.<br />

ROAD WILL BE<br />

CLOSED MAY 14<br />

FOR 90 DAYS<br />

INFO: 330-786-2208<br />

OVERVIEW 3


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Ashtabula County<br />

Construction Costs:<br />

Active: $111.6 million Upcoming: $16.4 million<br />

Total: $128 million<br />

MAHONING COUNTY 4


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Ashtabula County Active Projects<br />

West Avenue<br />

City <strong>of</strong> Ashtabula<br />

PID: 78399 PROJECT: 13-0186<br />

CONSTRUCTION COST: $1.8 million TOTAL COST: $1.8 million<br />

START DATE: May <strong>2013</strong> COMPLETION DATE: October <strong>2013</strong><br />

PROJECT DESCRIPTION: Re-decking and various bridge repairs to West Ave.<br />

over West 30 th St. and West Ave. over the Conrail Railroad.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained in each<br />

direction on West Ave. at all times. W. 30 th St. will be closed for 30 days. A detour<br />

will be posted. Access to all residences and businesses will be maintained at all<br />

times throughout construction.<br />

US Route 6 & State Route 534<br />

City <strong>of</strong> Geneva, Geneva, Hartsgrove & Trumbull townships<br />

PID: 84607 PROJECT: 13-0149<br />

CONSTRUCTION COST: $1.7 million TOTAL COST: $1.7 million<br />

START DATE: May <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> two sections <strong>of</strong> SR 534 from US 6 to<br />

Barrett Rd and from US 20 to the southern Geneva-on-the-Lake corporation limit.<br />

In addition, resurfacing on US 6 between Hyde Rd. and SR 534. This project also<br />

includes various bridge repairs.<br />

MAINTENANCE OF TRAFFIC: Traffic will be maintained by flaggers during<br />

construction.<br />

Interstate 90<br />

City <strong>of</strong> Conneaut; Kingsville Township<br />

PID: 25869 PROJECT: 10-1078<br />

CONSTRUCTION COST: $41.6 million TOTAL COST: $44.6 million<br />

START DATE: April 2011 COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Pavement replacement from directly east <strong>of</strong> the<br />

Conneaut River bridge to the Pennsylvania State line. The project also includes<br />

bridge rehabilitations to six bridges on I-90 and six overhead bridges. Work that<br />

was completed in 2012 included the installation <strong>of</strong> intermediate pavement in the<br />

westbound direction, intersection improvements at SR 7 and the replacement and<br />

re-decking <strong>of</strong> three bridges on I-90. Work to be performed in <strong>2013</strong> includes the<br />

replacement <strong>of</strong> eastbound pavement, surface course <strong>of</strong> asphalt on both eastbound<br />

and westbound I-90 and the replacement and re-decking <strong>of</strong> three bridges on I-90.<br />

MAINTENANCE OF TRAFFIC: Two lanes <strong>of</strong> traffic will be maintained in each<br />

direction <strong>of</strong> I-90 during construction during peak traffic hours. Traffic will be<br />

maintained via flaggers on SR 7 over I-90. South Ridge Rd. and Furnace Rd. will<br />

be closed for 90 days. All detours will be posted. Access to all residences and<br />

businesses will be maintained at all times throughout construction.<br />

State Route 534<br />

Windsor Township<br />

PID: 88204 PROJECT: 12-0597<br />

CONSTRUCTION COST: $400,000 TOTAL COST: $400,000<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Bin wall repairs on SR 534 just north <strong>of</strong> US 322.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained by flaggers during construction.<br />

MAHONING COUNTY 5


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Ashtabula County Active Projects Continued<br />

Interstate 90<br />

Austinburg, Saybrook & Plymouth townships<br />

PID: 76747 PROJECT: 12-0625<br />

CONSTRUCTION COST: $68 million TOTAL COST: $70.6 million<br />

START DATE: February <strong>2013</strong> COMPLETION DATE: Nov. 2016<br />

PROJECT DESCRIPTION: Pavement replacement on I-90 from just east <strong>of</strong> Clay<br />

St. to the Penn Central Railroad. This project also includes modifications to the SR<br />

11 and I-90 interchange. As well as bridge rehabilitations to two bridges on I-90<br />

and five overhead bridges.<br />

MAINTENANCE OF TRAFFIC: Two lanes <strong>of</strong> traffic will be maintained in each<br />

direction <strong>of</strong> I-90 during peak hours. One lane <strong>of</strong> traffic will be maintained in each<br />

direction <strong>of</strong> I-90 over SR 11. State Rd. will be closed for 210 days beginning in the<br />

spring. A detour will be posted. Access to all businesses and residences will be<br />

maintained at all times throughout construction.<br />

State Route 193<br />

Dorset Township<br />

PID: 85231 PROJECT: 13-0060<br />

CONSTRUCTION COST: $400,000 TOTAL COST: $400,000<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: October <strong>2013</strong><br />

PROJECT DESCRIPTION: Replacement <strong>of</strong> a bridge on SR 193 over Mill Creek<br />

between Allen-Comp Rd. and SR 307.<br />

MAINTENANCE OF TRAFFIC: SR 193 will be closed for 45 days. A detour will<br />

be posted. At all other times, a minimum <strong>of</strong> one lane <strong>of</strong> traffic will be maintained.<br />

Access to all residences and businesses will be maintained at all times throughout<br />

construction.<br />

State Route 193<br />

Sheffield & Kingsville townships<br />

PID: 82932 PROJECT: 12-0657<br />

CONSTRUCTION COST: $1.2 million TOTAL COST: $1.2 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Oct. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 193 from Sheffield-Monroe Rd. to<br />

just south <strong>of</strong> I-90. This project also includes minor bridge repairs and the<br />

replacement <strong>of</strong> the SR 193 bridge over the Ashtabula River.<br />

MAINTENANCE OF TRAFFIC: SR 193 will be closed for a period <strong>of</strong> 30 days. At<br />

all other times a minimum <strong>of</strong> one lane <strong>of</strong> traffic will be maintained. A detour will<br />

be posted. Access to all residences and businesses will be maintained at all times<br />

throughout construction.<br />

MAHONING COUNTY 6


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Ashtabula County Upcoming Projects<br />

State Route 166<br />

Trumbull Township<br />

PID: 92313<br />

ESTIMATED CONSTRUCTION COST: $500,000<br />

ESTIMATED TOTAL COST: $600,000<br />

AWARD DATE: October <strong>2013</strong> COMPLETION DATE: August 2014<br />

PROJECT DESCRIPTION: Replacement <strong>of</strong> a culvert on SR 166 over Trumbull<br />

Creek between Dawsey Rd. and Graham Rd.<br />

MAINTENANCE OF TRAFFIC: SR 166 will be closed for 45 days. A detour will<br />

be posted. At all other times, a minimum <strong>of</strong> one lane <strong>of</strong> traffic will be maintained.<br />

Access to all residences and businesses will be maintained at all times throughout<br />

construction.<br />

State Route 531<br />

Geneva Township<br />

PID: 78883<br />

ESTIMATED CONSTRUCTION COST: $7.6 million<br />

ESTIMATED TOTAL COST: $8.3 million<br />

AWARD DATE: May <strong>2013</strong> COMPLETION DATE: September 2014<br />

PROJECT DESCRIPTION: Slope erosion repairs on the north side <strong>of</strong> SR 531<br />

between Myers Rd. and Nineveh Rd. This project also includes resurfacing and<br />

drainage improvements.<br />

MAINTENANCE OF TRAFFIC: SR 531 will be closed for a period <strong>of</strong> 120 days.<br />

A detour will be posted. At all other times, a minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained. Access to all residences and businesses will be maintained at all times<br />

throughout construction.<br />

US Route 322<br />

Village <strong>of</strong> Orwell; Orwell, Colebrook & Wayne townships<br />

PID: 84606<br />

ESTIMATED CONSTRUCTION COST: $3 million<br />

ESTIMATED TOTAL COST: $3 million<br />

AWARD DATE: July <strong>2013</strong> COMPLETION DATE: November <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> US 322 between the Orwell eastern<br />

corporation limit and SR 193. This project also includes various bridge work to<br />

three structures over Rock Creek, Mosquito Creek and over SR 11.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained with flaggers during construction.<br />

MAHONING COUNTY 7


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Mahoning County<br />

Construction Costs:<br />

Active: $22 million Upcoming: $29.2 million<br />

Total: $49.2 million<br />

MAHONING COUNTY 8


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Mahoning County Active Projects<br />

Elm St.<br />

City <strong>of</strong> Youngstown<br />

PID: 82086<br />

PROJECT:13-8001<br />

CONSTRUCTION COST: $1.9 million TOTAL COST: $2.3 million<br />

START DATE: March <strong>2013</strong> COMPLETION DATE: June 2014<br />

PROJECT DESCRIPTION: Replacement <strong>of</strong> the Elm St bridge over Crandall Run<br />

between Tod Ln. and Saranac Ave.<br />

MAINTENANCE OF TRAFFIC: Elm St. will be closed for 250 days. A detour<br />

will be posted. At all other times, a minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained. Access to all residences and businesses will be maintained at all times<br />

throughout construction.<br />

Fairground Blvd.<br />

City <strong>of</strong> Canfield<br />

PID: 90208 PROJECT: 13-0206<br />

CONSTRUCTION COST: $200,000 TOTAL COST: $200,000<br />

START DATE: May <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Installation <strong>of</strong> sidewalks on Fairground Blvd. between<br />

SR 46 and Hood Dr.<br />

State Route 7<br />

Boardman Township<br />

PID: 87618 PROJECT: 13-0072<br />

CONSTRUCTION COST: $700,000 TOTAL COST: $1 8 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Drainage improvements on SR 7 between Karago<br />

Ave. and Boardman Blvd.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained by flaggers during construction.<br />

State Route 11<br />

Beaver Township<br />

PID: 82940 PROJECT: 13-0204<br />

CONSTRUCTION COST: $3.2 million TOTAL COST: $3.3 million<br />

START DATE: May <strong>2013</strong> COMPLETION DATE: October <strong>2013</strong><br />

PROJECT DESCRIPTION: Re-decking <strong>of</strong> two structures; one on SR 11 over SR<br />

46 and one on SR 11 over Calla Rd.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in both directions <strong>of</strong> SR 11 at all times.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained by flaggers during construction.<br />

MAHONING COUNTY 9


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Mahoning County Active Projects Continued<br />

State Route 46<br />

Green Township<br />

PID: 82933 PROJECT: 13-0205<br />

CONSTRUCTION COST: $700,000 TOTAL COST: $700,000<br />

START DATE: May <strong>2013</strong> COMPLETION DATE: Dec. <strong>2013</strong><br />

PROJECT DESCRIPTION: Replacement <strong>of</strong> two bridges on SR 46 between Lesher<br />

Rd. and Cook Rd. and on SR 46 between Western Reserve Rd. and Dublin Rd.<br />

MAINTENANCE OF TRAFFIC: SR 46 will be closed for14 days between Lesher<br />

Rd. and Cook Rd. and SR 46 will be closed for 75 days between Western Reserve<br />

Rd. and Dublin Rd. These closures will not occur at the same time. All detours will<br />

be posted. At all other times, a minimum <strong>of</strong> one lane <strong>of</strong> traffic will be maintained.<br />

Access to all residences and businesses will be maintained at all times throughout<br />

construction.<br />

State Route 164, 165 & 14T<br />

City <strong>of</strong> Columbiana; Beaver, Goshen & Green townships<br />

PID: 84600 PROJECT: 13-0071<br />

CONSTRUCTION COST: $2.7 million TOTAL COST: $2.8 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> three routes: SR 165 between SR 14<br />

and SR 46, SR 164 between the Mahoning County line to SR 7 and SR 14T from<br />

SR 14 to the Mahoning County line. This project also includes various bridge<br />

repairs on all three routes.<br />

MAINTENANCE OF TRAFFIC: SR 165 will have two separate 30 day closures<br />

for bridge repairs. At all other times a minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained. All detours will be posted. Access to all residences and businesses will<br />

be maintained at all times throughout construction.<br />

State Route 165<br />

Beaver Township<br />

PID: 25292 PROJECT: 12-379<br />

CONSTRUCTION COST: $2.3 million TOTAL COST: $3 million<br />

EXPECTED COMPLETION DATE: September 30, <strong>2013</strong><br />

PROJECT DESCRIPTION: Replacement <strong>of</strong> the bridge on SR 165 over Mill Creek<br />

between Basinger Rd. and Blosser Rd. This project also includes re-decking <strong>of</strong> the<br />

SR 165 bridge over SR 11. Work completed in 2012 included the completion <strong>of</strong><br />

the re-decking <strong>of</strong> SR 165 over SR 11. Work to be completed in <strong>2013</strong> will include<br />

the bridge painting <strong>of</strong> SR 165 over SR 11 and the replacement <strong>of</strong> SR 165 over Mill<br />

Creek.<br />

MAINTENANCE OF TRAFFIC: SR 165 over Mill Creek will be closed for 90<br />

days and SR 11 under SR 165 will have various daily restrictions. A detour will be<br />

posted. Access to all residences and businesses will be maintained throughout<br />

construction.<br />

State Route 534<br />

Milton Township<br />

PID: 85894 PROJECT: 12-0642<br />

CONSTRUCTION COST: $200,000 TOTAL COST: $200,000<br />

START DATE: March <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Culvert replacement on SR 534 between Palmyra Rd.<br />

and Stoltz Rd.<br />

MAINTENANCE OF TRAFFIC: SR 534 will be closed for 14 days. A detour will<br />

be posted. Access to all residences and businesses will be maintained throughout<br />

construction.<br />

MAHONING COUNTY 10


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Mahoning County Active Projects Continued<br />

State Route 616 & US Route 422 *<br />

Coitsville Township & City <strong>of</strong> Campbell<br />

PID: 77871<br />

PROJECT:12-0680<br />

CONSTRUCTION COST: $1.6 million TOTAL COST: $2 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Oct. 2014<br />

PROJECT DESCRIPTION: Bridge replacement <strong>of</strong> two structures at the<br />

intersection <strong>of</strong> US 422 and SR 616 over Dry Run Creek. This project also includes<br />

signal upgrade and geometric improvements to the intersection.<br />

MAINTENANCE OF TRAFFIC: US 422 and SR 616 will each be closed for a 90<br />

day period. These closures will not occur at the same time. All detours will be<br />

posted. Access to all residences and businesses will be maintained throughout<br />

construction.<br />

Interstate 680<br />

City <strong>of</strong> Youngstown<br />

PID: 25508<br />

PROJECT:10-0579<br />

CONSTRUCTION COST: $12.6 million TOTAL COST: $14.1 million<br />

START DATE: April 2011 COMPLETION DATE: July <strong>2013</strong><br />

PROJECT DESCRIPTION: Rehabilitation to seven bridges including the Silliman<br />

St. entrance ramp to I-680 southbound, I-680 over Price Rd. and Mill Creek,<br />

Woodland Ave. over I-680, I-680 over US 62/SR 7, I-680 over Delason Ave.,<br />

I-680 over the railroad and Williamson Ave. over I-680. Work completed in 2012<br />

included the completion <strong>of</strong> the I-680 bridges over US 62 / SR 7, Delason Ave. and<br />

Youngstown and Southeastern railroad as well the completion <strong>of</strong> resurfacing on I-<br />

680. Work to be completed in <strong>2013</strong> will include various bridge painting and bridge<br />

deck sealing.<br />

MAINTENANCE OF TRAFFIC: I-680 will have occasional lane restrictions<br />

during non-peak traffic times.<br />

(*) Indicates a Closure Notification Brochure will be created and distributed<br />

for this project.<br />

MAHONING COUNTY 11


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Mahoning County Upcoming Projects<br />

State Route 46<br />

Green Township<br />

PID: 92443<br />

ESTIMATED CONSTRUCTION COST: $1.7 million<br />

ESTIMATED TOTAL COST: $1.9 million<br />

AWARD DATE: May <strong>2013</strong> COMPLETION DATE: September <strong>2013</strong><br />

PROJECT DESCRIPTION: Intersection improvements with an additional turning<br />

lane at SR 46 and the South Range school complex between Cook Rd. and W<br />

Middletown Rd. The project also includes the installation <strong>of</strong> a pedestrian tunnel<br />

under SR 46.<br />

MAINTENANCE OF TRAFFIC: SR 46 will be closed for 14 days in late July. A<br />

detour will be posted. At all other times, a minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained. Access to all residences and businesses will be maintained at all times<br />

throughout construction.<br />

US Route 62 & State Route 170<br />

Cities <strong>of</strong> Struthers &Youngstown; Boardman Township<br />

PID: 84562<br />

ESTIMATED CONSTRUCTION COST: $2 million<br />

ESTIMATED TOTAL COST: $2 million<br />

AWARD DATE: Sept. <strong>2013</strong> COMPLETION DATE: Sept. 2014<br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> US 62 from McHenry St. to the<br />

Trumbull County line and SR 170 from Powers Way to Glenwood Ave.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction.<br />

US Route 62<br />

City <strong>of</strong> Youngstown<br />

PID: 92800<br />

ESTIMATED CONSTRUCTION COST: $700,000<br />

ESTIMATED TOTAL COST: $700,000<br />

AWARD DATE: May <strong>2013</strong> COMPLETION DATE: October <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> six entrance and exit ramps on US 62.<br />

I-680 north to US 62 north, South Ave. entrance ramp to US 62 north, US 62<br />

south to I-680 south / Williamson Ave., US 62 south exit ramp to Woodland Ave.,<br />

US 62 exit ramp to I-680 north and I-680 south exit ramp to US 62 north.<br />

MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times<br />

throughout construction.<br />

US Routes 62 & US 422<br />

City <strong>of</strong> Youngstown<br />

PID: 94516<br />

ESTIMATED CONSTRUCTION COST: $2.3 million<br />

ESTIMATED TOTAL COST: $2.5 million<br />

AWARD DATE: November <strong>2013</strong> COMPLETION DATE: November 2014<br />

PROJECT DESCRIPTION: Re-decking <strong>of</strong> US 422 over US 62/SR7. This project<br />

also includes slope repairs on US 62 at the intersection <strong>of</strong> SR 7 and also includes<br />

sign replacements.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction. Various ramp closures will occur during<br />

construction. All detours will be posted. Access to all residences and businesses<br />

will be maintained at all times throughout construction.<br />

MAHONING COUNTY 12


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Mahoning County Upcoming Projects Continued<br />

State Route 164 (Western Reserve Rd.)<br />

Beaver Township<br />

PID: 84754<br />

ESTIMATED CONSTRUCTION COST: $4.9 million<br />

ESTIMATED TOTAL COST: $5.4 million<br />

AWARD DATE: October <strong>2013</strong> COMPLETION DATE: October 2014<br />

PROJECT DESCRIPTION: Replacement and widening <strong>of</strong> the SR 164 (Western<br />

Reserve Rd.) bridge over I-680. This project also includes intersection<br />

improvements with an additional turning lane added to the I-680 northbound<br />

entrance ramp from SR 164 (Western Reserve Rd).<br />

MAINTENANCE OF TRAFFIC: Access will be maintained from I-680 to and<br />

from SR 164 (Western Reserve Rd.).<br />

US Route 224<br />

City <strong>of</strong> Canfield<br />

US Route 224 *<br />

Village <strong>of</strong> Poland; Boardman Township<br />

PID: 79864<br />

ESTIMATED CONSTRUCTION COST: $5 million<br />

ESTIMATED TOTAL COST: $5.7 million<br />

AWARD DATE: April <strong>2013</strong> COMPLETION DATE: October <strong>2013</strong><br />

PROJECT DESCRIPTION: Replacement and widening <strong>of</strong> two bridges on US 224<br />

over I-680 and over Yellow Creek just east <strong>of</strong> I-680. This project also includes the<br />

realigning <strong>of</strong> the I-680 southbound exit ramp to US 224 and the addition <strong>of</strong> a<br />

signalized intersection. In addition the realignment <strong>of</strong> the entrance ramp from US<br />

224 to I-680 north will also occur.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained in each<br />

direction on US 224 throughout construction. Occasional ramp closures at the<br />

I-680 and US 224 interchange may occur. All detours will be posted. Access to all<br />

residences and businesses will be maintained at all times throughout construction.<br />

(*) Indicates a Closure Notification Brochure will be created and distributed<br />

for this project.<br />

PID: 92643<br />

ESTIMATED CONSTRUCTION COST: $200,000<br />

ESTIMATED TOTAL COST: $200,000<br />

START DATE: August <strong>2013</strong> COMPLETION DATE: October <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> US 224 from SR 46 to Talsman Dr.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained with<br />

flaggers during construction.<br />

MAHONING COUNTY 13


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Mahoning County Upcoming Projects Continued<br />

US Route 224<br />

Berlin & Milton townships<br />

PID: 84601<br />

ESTIMATED CONSTRUCTION COST: $3.8 million<br />

ESTIMATED TOTAL COST: $3.8 million<br />

AWARD DATE: July <strong>2013</strong> COMPLETION DATE: November <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> US 224 from the Mahoning County<br />

line to just west <strong>of</strong> SR 534 and SR 534 from US 224 to the Trumbull County line.<br />

This project also includes concrete overlays <strong>of</strong> seven structures. As well as<br />

resurfacing on US 224 and SR 534 in Portage and Trumbull counties<br />

Interstate 680<br />

Beaver & Boardman townships<br />

PID: 23905<br />

ESTIMATED CONSTRUCTION COST: $4.7 million<br />

ESTIMATED TOTAL COST: $4.7 million<br />

AWARD DATE: November <strong>2013</strong> COMPLETION DATE: November 2014<br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> I-680 between US 224 and the <strong>Ohio</strong><br />

Turnpike.<br />

MAINTENANCE OF TRAFFIC: Two lanes <strong>of</strong> traffic will be maintained in each<br />

direction during peak traffic hours. A minimum <strong>of</strong> one lane in each direction will<br />

be maintained during non-peak traffic times.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained with<br />

flaggers during construction.<br />

MAHONING COUNTY 14


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Portage County<br />

Construction Costs<br />

Active: $14.9 million Upcoming: $15.6 million<br />

Total: $30.5 million<br />

PORTAGE COUNTY 15


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Portage County Active Projects<br />

Crain Avenue<br />

City <strong>of</strong> Kent<br />

PID: 18466 PROJECT: 09-1058<br />

CONSTRUCTION COST: $13.7 million TOTAL COST: $17.3 million<br />

START DATE: September 2009 COMPLETION DATE: Fall 2012<br />

PROJECT DESCRIPTION: Improvements to the intersections <strong>of</strong> SR 43 and Crain<br />

Ave.; SR 43 and Fairchild Ave.; and Crain Ave., N. Water St. and Lake St. This<br />

will include the replacement and relocation <strong>of</strong> the Crain Ave. bridge over the<br />

railroad. The new bridge location will align the western end <strong>of</strong> the bridge with the<br />

intersection <strong>of</strong> Fairchild Ave. and SR 43. The eastern end <strong>of</strong> the bridge will<br />

intersect in a T alignment with N. Water St. In 2012, the old Crain Ave. bridge was<br />

removed and the new pedestrian bridge was constructed. In <strong>2013</strong>, painting and<br />

sealing <strong>of</strong> bridges will be completed and the final course <strong>of</strong> pavement will be<br />

placed.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained on SR 43 and Lake St. throughout construction.<br />

State Route 14<br />

City <strong>of</strong> Streetsboro<br />

PID: 82907 PROJECT: 12-0647<br />

CONSTRUCTION COST: $1.2 million TOTAL COST: $1.2 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: August. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 14 from the I-480 exit ramp to the<br />

eastern portion <strong>of</strong> the SR 303/SR 14 split. Project also includes minor bridge<br />

repairs.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction on SR 14.<br />

State Route 5 *<br />

Ravenna Township<br />

PID: 85296 PROJECT: 13-0210<br />

CONSTRUCTION COST: $1.1 million TOTAL COST: $1.1 million<br />

START DATE: May <strong>2013</strong> COMPLETION DATE: October <strong>2013</strong><br />

PROJECT DESCRIPTION: Reconfigure SR 5 at the New Milford Rd. intersection<br />

to restrict thru traffic and left turns from New Milford Rd.<br />

MAINTENANCE OF TRAFFIC: SR 5 will be maintained with flaggers during<br />

construction. New Milford Rd. will be closed for the duration <strong>of</strong> the project. A<br />

detour will be posted. Access to all residences and businesses will be maintained at<br />

all times throughout construction.<br />

(*) Indicates a Closure Notification Brochure will be created and distributed<br />

for this project.<br />

US Route 224<br />

Suffield, Randolph & Atwater Townships<br />

PID: 82919 PROJECT: 13-0160<br />

CONSTRUCTION COST: $5.7 million TOTAL COST: $5.8 million<br />

START DATE: May <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> US 224 from the Summit County line<br />

to SR 183. Project also includes bridge repairs and the addition <strong>of</strong> left turn lanes at<br />

the intersections <strong>of</strong> US 224 and SR 43 and US 224 and SR 44.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained with<br />

flaggers during construction. US 224 will be closed for seven days between<br />

Congress Lake Rd. and SR 43. A detour will be posted. Access to all residences<br />

and businesses will be maintained at all times throughout construction.<br />

PORTAGE COUNTY 16


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Portage County Upcoming Projects<br />

Rock Spring Rd.<br />

Charlestown Township<br />

PID: 88372<br />

ESTIMATED CONSTRUCTION COST: $1.8 million<br />

ESTIMATED TOTAL COST: $1.9 million<br />

AWARD DATE : July <strong>2013</strong> COMPLETION DATE: May 2014<br />

PROJECT DESCRIPTION: Bridge rehabilitation on Rock Spring Rd. over West<br />

Branch Reservoir between SR 5 and Cable Line Rd.<br />

MAINTENANCE OF TRAFFIC: Rock Spring Rd. will be closed for 120 days<br />

after November 1, <strong>2013</strong>. A detour will be posted. Access to all residences and<br />

businesses will be maintained at all times throughout construction.<br />

US Route 224<br />

Deerfield Township<br />

PID: 84601<br />

ESTIMATED CONSTRUCTION COST: $3.8 million<br />

ESTIMATED TOTAL COST: $3.8 million<br />

AWARD DATE: July <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> US 224 from the SR 14/SR225<br />

intersection the Mahoning County line. This project also includes resurfacing and<br />

bridge repairs on SR 534 and US 224 in Mahoning and Trumbull Counties.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained with<br />

flaggers during construction.<br />

State Routes 14, 183 & 225<br />

Edinburg, Atwater & Deerfield townships<br />

PID: 84593<br />

ESTIMATED CONSTRUCTION COST: $3.1 million<br />

ESTIMATED TOTAL COST: $3.1 million<br />

AWARD DATE: June <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 14 from SR 183 to SR 225 and the<br />

resurfacing <strong>of</strong> SR 183 from US 224 to SR 14. Project also includes bridge repairs<br />

and the replacement <strong>of</strong> a culvert on SR 225 just south <strong>of</strong> Yale Rd.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained with<br />

flaggers on SR 14 and SR 183. SR 225 will be closed for 21 days. A detour will be<br />

posted. Access to all residences and businesses will be maintained at all times<br />

throughout construction.<br />

PORTAGE COUNTY 17


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Stark County<br />

Construction Costs:<br />

Active: $26.5 million Upcoming: $21.9 million<br />

Total: $48.4 million<br />

SUMMIT COUNTY 18


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Stark County Active Projects<br />

Various Routes<br />

Cities <strong>of</strong> Canton & Massillon<br />

PID: 94048 PROJECT: 12-0024<br />

CONSTRUCTION COST: $300,000 TOTAL COST: $300,000<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Miscellaneous bridge repairs to the US 30 bridge over<br />

SR 21, the I-77 northbound ramp to US 30 eastbound and the I-77 bridge over<br />

Cleveland Ave. This project also includes various bridge repairs Summit County.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction during non-peak traffic hours along US 30 and I-77.<br />

Various ramp closures will occur on weekends. 15 th St. will be closed for seven<br />

days. All detours will be posted. Access to all residences and businesses will be<br />

maintained at all times throughout construction.<br />

State Route 21<br />

Village <strong>of</strong> Navarre; Bethlehem Township<br />

PID: 83578 PROJECT: 12-0591<br />

CONSTRUCTION COST: $3.7 million TOTAL COST: $4.1 million<br />

START DATE: February <strong>2013</strong> COMPLETION DATE: October <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 21 from the Tuscarawas County<br />

line to US 62. Project also includes replacement <strong>of</strong> the bridge on SR 21 over the<br />

Tuscarawas River just south <strong>of</strong> the Navarre Corp. limit. Project also includes other<br />

miscellaneous bridge repairs along SR 21.<br />

MAINTENANCE OF TRAFFIC: SR 21 will be closed for 240 days. A minimum<br />

<strong>of</strong> one lane <strong>of</strong> traffic will be maintained during all other times. A detour will be<br />

posted. Access to all residences and businesses will be maintained at all times<br />

throughout construction.<br />

Interstate 77<br />

Bethlehem, Pike & Canton Townships<br />

PID: 77885 PROJECT: 12-0463<br />

CONSTRUCTION COST: $14.2 million TOTAL COST: $14.3 million<br />

EXPECTED COMPLETION DATE: June 30, 2015<br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> I-77 from the Tuscarawas County line<br />

to the southern Canton corporation limit. Project also includes bridge repairs to ten<br />

bridges including two over Gracemont St., two over Downing Rd., two over Prairie<br />

Rd., two over Rinker St., Dueber Ave. over I-77 and Fohl St. over I-77. In 2012 I-<br />

77 was resurfaced from Haut St. to Brinker St. In <strong>2013</strong>, the I-77 northbound<br />

structure over Gracemont Ave. will be constructed and I-77 will be resurfaced<br />

from Brinker St. to SR 800.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> two lanes <strong>of</strong> traffic will be<br />

maintained in each direction <strong>of</strong> I-77 during peak traffic hours. A minimum <strong>of</strong> one<br />

lane <strong>of</strong> traffic will be maintained in each direction <strong>of</strong> I-77 during non-peak traffic<br />

hours. Duber Ave. will be closed for 75 days. A detour will be posted. Access to<br />

all residences and businesses will be maintained at all times throughout<br />

construction.<br />

US Route 30<br />

City <strong>of</strong> Canton; Canton Township<br />

PID: 76335 PROJECT: 13-0138<br />

CONSTRUCTION COST: $2.3 million TOTAL COST: $2.3 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> US Route 30 from SR 43 to Trump<br />

Ave. Project also includes bridge repairs.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained in each<br />

direction <strong>of</strong> US 30.<br />

SUMMIT COUNTY 19


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Stark County Active Projects Continued<br />

US Route 62 & State Route 183<br />

City <strong>of</strong> Alliance<br />

PID: 84568 PROJECT: 13-0108<br />

CONSTRUCTION COST: $1.1 million TOTAL COST: $1.1 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: August <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> US Route 62 between Freshley Ave.<br />

NE and N. Federal Ave. and between McKinley Ave. and SR 183. The project also<br />

includes the resurfacing <strong>of</strong> SR 183 from College St. to Mill St.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained with flaggers during construction.<br />

Interstate 77 & US Route 30<br />

City <strong>of</strong> Canton<br />

PID: 90554 PROJECT: 12-0694<br />

CONSTRUCTION COST: $200,000 TOTAL COST: $200,000<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Repairs and upgrades to lighting system at the I-77<br />

and US 30 interchange.<br />

MAINTENANCE OF TRAFFIC: Traffic will be maintained on I-77 and US 30.<br />

Various ramp closures will occur during construction. All detours will be posted.<br />

Access to all residences and businesses will be maintained at all times throughout<br />

construction.<br />

State Route 172 *<br />

City <strong>of</strong> Massillon<br />

PID: 81597 PROJECT: 12-0551<br />

CONSTRUCTION COST: $500,000 TOTAL COST: $500,000<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: July <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 172 from 17 th St. to 27 th St.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained with flaggers during construction.<br />

(*) Indicates a Closure Notification Brochure will be created and distributed<br />

for this project.<br />

State Route 172<br />

City <strong>of</strong> Canton<br />

PID: 82934 PROJECT: 13-0137<br />

CONSTRUCTION COST: $1.2 million TOTAL COST: $1.6 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Rehabilitation <strong>of</strong> the bridge on SR 172 over a branch<br />

<strong>of</strong> the Nimishillen Creek between Riverside Dr. NE and Warner Rd. SE.<br />

MAINTENANCE OF TRAFFIC: SR 172 will be closed for 120 days. A detour<br />

will be posted. Access to all residences and businesses will be maintained at all<br />

times throughout construction.<br />

SUMMIT COUNTY 20


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Stark County Active Projects Continued<br />

State Route 172 *<br />

Perry Township<br />

PID: 86510 PROJECT: 12-0219<br />

CONSTRUCTION COST: $1.8 million TOTAL COST: $2.2 million<br />

START DATE: March <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 172 from Eden Ave. N.W. to<br />

Woodlawn Ave. N.W. Project also includes drainage repairs and access<br />

improvements.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction on SR 172 throughout construction.<br />

(*) Indicates a Closure Notification Brochure will be created and distributed<br />

for this project.<br />

State Route 172<br />

City <strong>of</strong> Massillon<br />

PID: 93686 PROJECT: 13-0085<br />

CONSTRUCTION COST: $200,000 TOTAL COST: $300,000<br />

START: DATE: April <strong>2013</strong> COMPLETION DATE: July <strong>2013</strong><br />

PROJECT DESCRIPTION: Heat straightening <strong>of</strong> bridge beams on SR 172 over<br />

SR 21.<br />

State Route 183<br />

City <strong>of</strong> Alliance<br />

PID: 82092 PROJECT: 12-0568<br />

CONSTRUCTION COST: $4.5 million TOTAL COST: $5.9 million<br />

START DATE: January <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Lower the roadway grade to create more vertical<br />

clearance for the Norfolk Southern railroad bridge on SR 183 in Alliance.<br />

MAINTENANCE OF TRAFFIC: SR 183 will be closed for 180 days. Ely St. will<br />

be closed for 45 days. These closures will not occur at the same time. All detours<br />

will be posted. Access to all residences and businesses will be maintained at all<br />

times throughout construction.<br />

State Route 800<br />

Pike Township<br />

PID: 91456 PROJECT: 13-0211<br />

CONSTRUCTION COST: $400,000 TOTAL COST: $400,000<br />

START DATE: May <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Slide repair on SR 800 just north <strong>of</strong> the Village <strong>of</strong><br />

East Sparta.<br />

MAINTENANCE OF TRAFFIC: SR 800 will be closed for 45 days. A detour will<br />

be posted. Access to all residences and businesses will be maintained at all times<br />

throughout construction.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained by flaggers on SR 172. SR 21 southbound will be closed for 20 days<br />

and SR 21 northbound will be closed for 17 days. All detours will be posted.<br />

Access to all residences and businesses will be maintained at all times throughout<br />

construction.<br />

SUMMIT COUNTY 21


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Stark County Upcoming Projects<br />

Navarre Rd. SW<br />

City <strong>of</strong> Canton<br />

PID: 76007<br />

ESTIMATED CONSTRUCTION COST: $1.7 million<br />

ESTIMATED TOTAL COST: $1.7 million<br />

AWARD DATE: June <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Upgrade traffic signals along 14 intersections on<br />

Navarre Rd. SW from Harrison Ave. SW to Market Ave. SW, on 15 th St. from<br />

Harrison Ave. SW to Cleveland Ave. SW and on Cleveland Ave. SW from Market<br />

Ave. to 9 th St.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane will be maintained with<br />

flaggers during construction.<br />

US Route 30 & State Route 183<br />

Village <strong>of</strong> Minerva; Paris & Washington townships<br />

PID: 84586<br />

ESTIMATED CONSTRUCTION COST: $3.1 million<br />

ESTIMATED TOTAL COST: $3.1 million<br />

AWARD DATE: August <strong>2013</strong> COMPLETION DATE: June 2014<br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> US Route 30 from Hart Ave. to the<br />

Columbiana County line and the resurfacing <strong>of</strong> SR 183 from Market St. to Beech<br />

St. Project also includes minor bridge repairs.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained with<br />

flaggers during construction. SR 183 will be closed for five days for bridge repairs.<br />

A detour will be posted. Access to all residences and businesses will be maintained<br />

at all times throughout construction.<br />

US Route 30 & Harrison Ave.<br />

City <strong>of</strong> Canton<br />

PID: 93089<br />

ESTIMATED CONSTRUCTION COST: $1.7 million<br />

ESTIMATED TOTAL COST: $1.7 million<br />

AWARD DATE: April <strong>2013</strong> COMPLETION DATE: Oct. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> Harrison Ave. from Navarre Rd. to<br />

15 th St. The project also includes bridge deck overlays and bridge painting to four<br />

structures on US 30.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained with<br />

flaggers during construction. Weekend closures will occur for each bridge. All<br />

detours will be posted. Access to all residences and businesses will be maintained<br />

at all times throughout construction.<br />

US Route 30<br />

Paris Township<br />

PID: 87798<br />

ESTIMATED CONSTRUCTION COST: $800,000<br />

ESTIMATED TOTAL COST: $900,000<br />

AWARD DATE: May <strong>2013</strong> COMPLETION DATE: Oct. <strong>2013</strong><br />

PROJECT DESCRIPTION: Slide repair on US Route 30 between Rosehill St. SE<br />

and Freedmont Rd. SE.<br />

MAINTENANCE OF TRAFFIC: US 30 will be closed for 60 days. A detour will<br />

be posted. Access to all residences and businesses will be maintained at all times<br />

throughout construction.<br />

SUMMIT COUNTY 22


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Stark County Upcoming Projects Continued<br />

State Routes 44 & 171<br />

Village <strong>of</strong> Waynesburg; Sandy & Osnaburg townships<br />

PID: 82924<br />

ESTIMATED CONSTRUCTION COST: $2.3 million<br />

ESTIMATED TOTAL COST: $2.3 million<br />

AWARD DATE: April <strong>2013</strong> COMPLETION DATE: Oct. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 44 from SR 43 to US 30 and the<br />

resurfacing <strong>of</strong> SR 171 from SR 183 to the Carroll County line. Project also<br />

includes bridge repairs and three culvert replacements one on SR 44 between<br />

Mapleton St. and Church St., one on SR 44 between Mapleton St. and Orchard<br />

View St. and one on SR 171 just west <strong>of</strong> the Carroll County line.<br />

MAINTENANCE OF TRAFFIC: Traffic will be maintained with flaggers during<br />

resurfacing. SR 44 will be closed for three days at each culvert location and SR<br />

171 will be closed for 28 days. All detours will be posted. Access to all residences<br />

and businesses will be maintained at all times throughout construction.<br />

State Route 172<br />

Village <strong>of</strong> East Canton; Osnaburg and Paris townships<br />

PID: 84590<br />

ESTIMATED CONSTRUCTION COST: $2.2 million<br />

ESTIMATED TOTAL COST: $2.2 million<br />

AWARD DATE: May <strong>2013</strong> COMPLETION DATE: Oct. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 172 from Village <strong>of</strong> East Canton<br />

western corporation limit to the Columbiana County line. This project also<br />

includes two bridge deck overlays.<br />

State Route 241<br />

Jackson Township<br />

PID: 84572<br />

ESTIMATED CONSTRUCTION COST: $1.2 million<br />

ESTIMATED TOTAL COST: $1.2 million<br />

AWARD DATE: July <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 241 from the northern Massillon<br />

corporation limit to Shady Hollow Rd. and from just north <strong>of</strong> SR 687 to the<br />

Summit County line. The project also includes the addition <strong>of</strong> a northbound left<br />

turn lane at Oakdale St. NW and signal improvements.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained with<br />

flaggers during construction.<br />

State Route 619<br />

Village <strong>of</strong> Hartville<br />

PID: 90580<br />

ESTIMATED CONSTRUCTION COST: $400,000<br />

ESTIMATED TOTAL COST: $400,000<br />

AWARD DATE: April <strong>2013</strong> COMPLETION DATE: Oct. <strong>2013</strong><br />

PROJECT DESCRIPTION: Upgrade, interconnect and coordinate four traffic<br />

signals on SR 619 between Market Ave. NW and Kent Ave. NW in the village <strong>of</strong><br />

Hartville.<br />

MAINTENANCE OF TRAFFIC: Traffic will be maintained with flaggers during<br />

construction.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained with<br />

flaggers during construction.<br />

SUMMIT COUNTY 23


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Summit County<br />

Construction Costs:<br />

Active: $24.8 million Upcoming: $79.5 million<br />

Total: $104.3 million<br />

SUMMIT COUNTY 24


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Summit County Active Projects<br />

Highland Rd. Railroad Grade Separation<br />

City <strong>of</strong> Macedonia<br />

PID: 23064 PROJECT: 11-0110<br />

CONSTRUCTION COST: $7.9 million TOTAL COST: $10.5 million<br />

START DATE: April 2011 COMPLETION DATE: August <strong>2013</strong><br />

PROJECT DESCRIPTION: Construction <strong>of</strong> a railroad grade separation bridge<br />

over the Norfolk-Southern railroad on Highland Rd. between South Bedford Rd.<br />

and Shepard Rd. In 2012, the Roll and Hold intersection was completed as well as<br />

the Mechanically Stabilized Earth walls for the bridge. In <strong>2013</strong>, the bridge will be<br />

constructed over the railroad.<br />

MAINTENANCE OF TRAFFIC: Highland Rd. will be closed at various locations<br />

near the Norfolk-Southern railroad for 270 days. All detours will be posted.<br />

Access to all businesses and residences will be maintained throughout<br />

construction.<br />

Various Routes<br />

City <strong>of</strong> Akron & Village <strong>of</strong> Richfield<br />

PID: 94048 PROJECT: 13-0024<br />

CONSTRUCTION COST: $300,000 TOTAL COST: $300,000<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Miscellaneous bridge repairs to the I-77 bridge over<br />

SR 303 and to the SR 764/Wilbeth Rd. bridge over I-77. This project also includes<br />

various bridge repairs Stark County.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction on I77 during non-peak travel times. SR 303 will be<br />

closed for five days. A detour will be posted. Access to all residences and<br />

businesses will be maintained at all times throughout construction.<br />

State Road *<br />

City <strong>of</strong> Cuyahoga Falls<br />

PID: 81605<br />

PROJECT:13-8008<br />

CONSTRUCTION COST: $8.3 million TOTAL COST: $9.2 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Fall 2014<br />

PROJECT DESCRIPTION: Widening <strong>of</strong> State Rd. from Bath Rd. to Steels<br />

Corners Rd. Project also includes the addition <strong>of</strong> turn lanes, drainage and signal<br />

improvements.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction on State Rd. except for brief periods where one lane<br />

<strong>of</strong> traffic will be maintained by flaggers.<br />

(*) Indicates a Closure Notification Brochure will be created and distributed<br />

for this project.<br />

State Route 93 *<br />

Coventry Township<br />

PID: 76437 PROJECT: 13-0077<br />

CONSTRUCTION COST: $4.5 million TOTAL COST: $7.9 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: August 2014<br />

PROJECT DESCRIPTION: Widening <strong>of</strong> SR 93 (Manchester Rd.) to five lanes<br />

from south <strong>of</strong> Robinson Ave. to north <strong>of</strong> Cormany Rd. The project also includes<br />

widening/improvements to Robinson Ave. at SR 93.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction at all times. Robinson Ave. will have various closures<br />

at SR 93. Various short term side street closures will also occur. All detours will be<br />

posted. Access to all residences and businesses will be maintained at all times<br />

throughout construction.<br />

(*) Indicates a Closure Notification Brochure will be created and distributed<br />

for this project.<br />

SUMMIT COUNTY 25


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Summit County Active Projects Continued<br />

Interstates 76 & 77<br />

City <strong>of</strong> Akron<br />

PID: 93749 PROJECT: 13-0165<br />

CONSTRUCTION COST: $1.4 million TOTAL COST: $1.4 million<br />

AWARD DATE: March <strong>2013</strong> COMPLETION DATE: August <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> I-76 at the Central Interchange and on<br />

I-77 from the Kenmore Leg (I-76) to SR 162/Copley Rd. The project also includes<br />

two bridge overlays on I-76 eastbound and westbound at the Central Interchange<br />

over I-77 northbound and SR 8.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction during non-peak traffic hours. Various weekend ramp<br />

closures will occur. All detours will be posted. Access to all residences and<br />

businesses will be maintained at all times throughout construction.<br />

Interstate 77<br />

City <strong>of</strong> Akron<br />

PID: 93028 PROJECT: 13-0166<br />

CONSTRUCTION COST: $900,000 TOTAL COST: $900,000<br />

AWARD DATE: March <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Painting <strong>of</strong> five bridges on I-77 including SR<br />

764/Wilbeth Rd. over I-77, I-77 over Catawba Ave., I-77 over Cole Ave., I-77 over<br />

Lovers Lane and I-77 over LaFollette Ave.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction during non-peak traffic hours. Various weekend ramp<br />

closures will also occur. All detours will be posted. Access to all residences and<br />

businesses will be maintained at all times throughout construction.<br />

State Route 91<br />

City <strong>of</strong> Stow<br />

PID: 87756<br />

CONSTRUCTION COST: $300,000 TOTAL COST: $300,000<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Replace bridge on SR 91 over the Cuyahoga River<br />

just north <strong>of</strong> SR 59.<br />

MAINTENANCE OF TRAFFIC: SR 91 will be closed for a maximum <strong>of</strong> 10 days.<br />

A detour will be posted. Access to all residences and businesses will be maintained<br />

at all times throughout construction.<br />

Interstate 271<br />

Village <strong>of</strong> Richfield; Richfield Township<br />

PID: 18710 PROJECT: 13-0147<br />

CONSTRUCTION COST: $46.7 million TOTAL COST: $49.8 million<br />

START DATE: May <strong>2013</strong> COMPLETION DATE: Nov. 2015<br />

PROJECT DESCRIPTION: Pavement replacement <strong>of</strong> I-271 from Broadview Rd.<br />

to the <strong>Ohio</strong> Turnpike. Project also includes repairs to nine bridges including two<br />

bridges over I-77, SR 303 over I-271, SR 176 over I-271, Brecksville Rd. over I-<br />

271 and various ramps at the I-77/I-271 interchange.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> two lanes <strong>of</strong> traffic will be<br />

maintained on I-271 during peak traffic times through a contraflow traffic pattern.<br />

The I-271 northbound ramp to I-77 northbound ramp will be closed for 90 days.<br />

One lane <strong>of</strong> traffic will be maintained via a traffic signal on Brecksville Rd. over I-<br />

271. All detours will be posted. Access to all residences and businesses will be<br />

maintained at all times throughout construction.<br />

SUMMIT COUNTY 26


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Summit County Active Projects Continued<br />

State Route 303<br />

City <strong>of</strong> Hudson<br />

PID: 82914 PROJECT: 12-0650<br />

CONSTRUCTION COST: $1.5 million TOTAL COST: $1.5 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 303 from the western Hudson<br />

Corporation limit to the eastern Hudson Corporation limit. The project also<br />

includes minor bridge repairs and the replacement <strong>of</strong> the SR 8 northbound exit<br />

ramp to SR 303.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained on SR 303<br />

with flaggers. The SR 8 northbound exit ramp to SR 303 will be closed for 10<br />

days. A detour will be posted. Access to all businesses and residences will be<br />

maintained throughout construction.<br />

State Route 619<br />

City <strong>of</strong> Green<br />

PID: 81599 PROJECT: 13-0164<br />

CONSTRUCTION COST: $1.5 million TOTAL COST: $1.5 million<br />

AWARD DATE: March <strong>2013</strong> COMPLETION DATE: Oct. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 619 from the eastern New Franklin<br />

corporation limit to the Stark County line. The project also includes the<br />

replacement <strong>of</strong> a bridge on SR 619 over the Tuscarawas River just west <strong>of</strong> the<br />

Stark County line and the replacement <strong>of</strong> a culvert just east <strong>of</strong> Myersville Rd.<br />

MAINTENANCE OF TRAFFIC: SR 619 will be closed for 28 days. At all other<br />

times traffic will be maintained with flaggers. A detour will be posted. Access to<br />

all residences and businesses will be maintained at all times throughout<br />

construction.<br />

State Route 619<br />

City <strong>of</strong> New Franklin<br />

PID: 76436 PROJECT: 13-0163<br />

CONSTRUCTION COST: $1.3 million TOTAL COST: $2 million<br />

START DATE: May <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Widen SR 619 at the intersection <strong>of</strong> SR 93 to include<br />

left turn lanes and signal upgrades.<br />

MAINTENANCE OF TRAFFIC: SR 619 east <strong>of</strong> SR 93 will be closed for 90 days.<br />

SR 619 west <strong>of</strong> SR 93 will be closed for 90 days. These closures will not occur at<br />

the same time. All detours will be posted. Access to all residences and businesses<br />

will be maintained at all times throughout construction.<br />

SUMMIT COUNTY 27


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Summit County Upcoming Projects<br />

State Street<br />

City <strong>of</strong> Barberton<br />

PID: 92719<br />

ESTIMATED CONSTRUCTION COST: $700,000<br />

ESTIMATED TOTAL COST: $700,000<br />

AWARD DATE: June <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> State St. from Robinson Ave. to<br />

Highland Ave.<br />

MAINTENANCE OF TRAFFIC: One lane <strong>of</strong> traffic will be maintained with<br />

flaggers during construction.<br />

State Route 59 (Akron Innerbelt)<br />

City <strong>of</strong> Akron<br />

PID: 76849<br />

ESTIMATED CONSTRUCTION COST: $7.3 million<br />

ESTIMATED TOTAL COST: $7.3 million<br />

AWARD DATE: Sept. <strong>2013</strong> COMPLETION DATE: August 2014<br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 59 (Akron Innerbelt) from I-76 to<br />

E. Market St. Project also includes minor bridge repairs to 21 structures.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction <strong>of</strong> SR 59 (Akron Innerbelt) during non-peak travel<br />

times. A minimum <strong>of</strong> two lane <strong>of</strong> traffic will be maintained in each direction<br />

during peak travel times. Occasional weekend closures will occur for bridge<br />

overlays. All detours will be posted. Access to all residences and businesses will be<br />

maintained at all times throughout construction.<br />

Interstate 76<br />

City <strong>of</strong> Norton<br />

PID: 84629<br />

ESTIMATED CONSTRUCTION COST: $3.1 million<br />

ESTIMATED TOTAL COST: $3.7 million<br />

AWARD DATE: October <strong>2013</strong> COMPLETION DATE: Nov. 2014<br />

PROJECT DESCRIPTION: The replacement <strong>of</strong> two bridges on I-76, Clark Mill<br />

Rd. over I-76 and Summit Rd. over I-76.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction <strong>of</strong> I-76 during non-peak travel times. A minimum <strong>of</strong><br />

two lane <strong>of</strong> traffic will be maintained in each direction during peak travel times.<br />

Clark Mill Rd. and Summit Rd. will each be closed for a 90 day period. All detours<br />

will be posted. Access to all residences and businesses will be maintained at all<br />

times throughout construction.<br />

State Route 82<br />

Northfield Center Township<br />

PID: 91051<br />

ESTIMATED CONSTRUCTION COST: $2.7 million<br />

ESTIMATED TOTAL COST: $2.7 million<br />

AWARD DATE: June <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Concrete overlay and sealing <strong>of</strong> bridge on SR 82 at<br />

the Cuyahoga/Summit County line, over the Cuyahoga River, Cuyahoga Valley<br />

National Railroad and Bike Path.<br />

MAINTENANCE OF TRAFFIC: Traffic will be maintained with flaggers. SR 82<br />

will be closed for a maximum <strong>of</strong> seven days. A detour will be posted. Access to all<br />

residences and businesses will be maintained at all times throughout construction.<br />

SUMMIT COUNTY 28


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Summit County Upcoming Projects Continued<br />

State Route 162<br />

Copley Township; City <strong>of</strong> Akron<br />

PID: 25552<br />

ESTIMATED CONSTRUCTION COST: $2.3 million<br />

ESTIMATED TOTAL COST: $2.3 million<br />

AWARD DATE: April <strong>2013</strong> COMPLETION DATE: Fall <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 162 (Copley Rd.) from the Medina<br />

County line to the I-77 interchange.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained with flaggers during construction.<br />

SUMMIT COUNTY 29


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Trumbull County<br />

Construction Costs:<br />

Active: $28.7 million Upcoming: $38.2 million<br />

Total: $66.9 million<br />

TRUMBULL COUNTY 30


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Trumbull County Active Projects<br />

Five Points Hartford Rd.<br />

Hartford Township<br />

PID: 82407 PROJECT: 13-0016<br />

CONSTRUCTION COST: $800,000 TOTAL COST: $1 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Sept. <strong>2013</strong><br />

PROJECT DESCRIPTION: Replacement <strong>of</strong> a bridge on Five Points Hartford Rd.<br />

over Big Yankee creek between Bushnell Campbell Rd. and Cadwallader Sonk Rd.<br />

MAINTENANCE OF TRAFFIC: Five Points Hartford Rd. will be closed for 120<br />

days. A detour will be posted. Access to all residences and businesses will be<br />

maintained at all times throughout construction.<br />

State Route 5/82<br />

Braceville, Warren, Bazetta & Champion townships<br />

PID: 76407 PROJECT: 12-0018<br />

CONSTRUCTION COST: $7.7 million TOTAL COST: $7.7 million<br />

EXPECTED COMPLETION DATE: September 30, <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 5 from approximately one half mile<br />

west <strong>of</strong> W. Market St. to the SR 5/82 split. Project includes minor bridge repairs to<br />

25 structures throughout the project. Work completed in 2012 included all bridge<br />

re-decking and all resurfacing. Work to be completed in <strong>2013</strong> includes bridge deck<br />

sealing, striping and raised pavement markings.<br />

State Route 5<br />

Braceville Township<br />

PID: 82937 PROJECT: 12-0689<br />

CONSTRUCTION COST: $600,000 TOTAL COST: $600,000<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Aug. <strong>2013</strong><br />

PROJECT DESCRIPTION: The replacement <strong>of</strong> the bridge over the Mahoning<br />

River between the eastern Newton Falls corporation limit and the <strong>Ohio</strong> Turnpike.<br />

MAINTENANCE OF TRAFFIC: SR 5 will be closed for 21 days. A detour will be<br />

posted. Access to all residences and businesses will be maintained at all<br />

times throughout construction.<br />

State Route 7<br />

Kinsman Township<br />

PID: 88204 PROJECT: 12-0597<br />

CONSTRUCTION COST: $400,000 TOTAL COST: $400,000<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: August <strong>2013</strong><br />

PROJECT DESCRIPTION: Bin wall repairs on SR 7 just north <strong>of</strong> SR 87.<br />

MAINTENANCE OF TRAFFIC: Traffic will be maintained with flaggers during<br />

construction.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction on SR 5 at all times throughout construction.<br />

TRUMBULL COUNTY 31


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Trumbull County Active Projects Continued<br />

State Routes 45 & 534<br />

Farmington & Bristol townships<br />

PID: 82938 PROJECT: 12-0624<br />

CONSTRUCTION COST: $300,000 TOTAL COST: $400,000<br />

START DATE: June <strong>2013</strong> COMPLETION DATE: Oct. <strong>2013</strong><br />

PROJECT DESCRIPTION: Replacement <strong>of</strong> two bridges, one on SR 45 just north<br />

<strong>of</strong> SR 88 and one on SR 534 approximately one mile south <strong>of</strong> SR 88.<br />

MAINTENANCE OF TRAFFIC: SR 45 and SR 534 will both be closed for 14<br />

days. All detours will be posted. Access to all residences and businesses will be<br />

maintained throughout construction.<br />

State Route 45<br />

Village <strong>of</strong> Lordstown<br />

PID: 87373 PROJECT: 13-0078<br />

CONSTRUCTION COST: $2.1 million TOTAL COST: $2.3 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: Oct. <strong>2013</strong><br />

PROJECT DESCRIPTION: Replacement <strong>of</strong> a bridge on SR 45 over the Norfolk<br />

Southern railroad between Hallock Young Rd. and Salt Springs Rd.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction <strong>of</strong> SR 45<br />

State Route 45<br />

Bloomfield Township<br />

PID: 84571 PROJECT: 13-0109<br />

CONSTRUCTION COST: $1.1 million TOTAL COST: $1.1 million<br />

START DATE: April <strong>2013</strong> COMPLETION DATE: August <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 45 between Leach Rd. and the<br />

Ashtabula county line.<br />

MAINTENANCE OF TRAFFIC: Traffic will be maintained with flaggers during<br />

construction.<br />

State Routes 46 & 169<br />

City <strong>of</strong> Niles<br />

PID: 25076 PROJECT: 12-0651<br />

CONSTRUCTION COST: $1.5 million TOTAL COST: $1.8 million<br />

START DATE: March <strong>2013</strong> COMPLETION DATE: Fall <strong>2013</strong><br />

PROJECT DESCRIPTION: The replacement <strong>of</strong> the bridge on SR 46/169 over<br />

Mosquito Creek between Vienna Ave. and N. Main St.<br />

MAINTENANCE OF TRAFFIC: SR 46/SR 169 will be closed for 180 days. A<br />

detour will be posted. Access to all residences and businesses will be maintained<br />

throughout construction.<br />

TRUMBULL COUNTY 32


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Trumbull County Active Projects Continued<br />

Interstate 80<br />

Liberty & Hubbard townships<br />

PID: 76411<br />

PROJECT:12-3009<br />

CONSTRUCTION COST: $9.8 million TOTAL COST: $10.4 million<br />

START DATE: January <strong>2013</strong> COMPLETION DATE: Oct. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> I-80 from SR 193 to Mt. Everett Rd.<br />

Project includes re-decking and widening <strong>of</strong> bridges over Logan Way Rd. and<br />

Sampson Rd.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction on I-80 over Logan Way Rd. and Samson Rd. I-80<br />

will also have various restrictions for resurfacing during non-peak traffic times.<br />

US Route 422<br />

City <strong>of</strong> Warren; Warren Township<br />

State Route 534<br />

Mesopotamia Township<br />

PID: 23967 PROJECT: 12-0301<br />

CONSTRUCTION COST: $3.8 million TOTAL COST: $4.9 million<br />

START DATE: February <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing on SR 534 from just north <strong>of</strong> SR 87 to<br />

approximately one mile south <strong>of</strong> the Ashtabula County line. Project also includes<br />

widening <strong>of</strong> the shoulders approximately eight feet to accommodate horse drawn<br />

vehicles and the widening <strong>of</strong> the SR 534 bridge over Garden Creek between SR 87<br />

and Wilcox Rd. and <strong>of</strong> the bridge on SR 534 over Grapevine Creek between<br />

Wilcox Rd. and Donley Rd.<br />

MAINTENANCE OF TRAFFIC: SR 534 will be closed for a period <strong>of</strong> 120 days.<br />

A detour will be posted. Access to all residences and businesses will be maintained<br />

at all times throughout construction.<br />

PID: 25229 PROJECT: 12-0076<br />

CONSTRUCTION COST: $4.6 million TOTAL COST: $5.2 million<br />

EXPECTED COMPLETION DATE: October 31, <strong>2013</strong><br />

PROJECT DESCRIPTION: The replacement and widening <strong>of</strong> the bridge on US<br />

422 over the Mahoning River approximately one mile east <strong>of</strong> SR 5/82. Project also<br />

includes widening and intersection improvements to US 422 from N. Leavitt Rd.<br />

NW to Tod Ave. NW. Work completed in 2012 included the replacement and<br />

widening <strong>of</strong> the westbound side <strong>of</strong> the bridge. Work to be completed in <strong>2013</strong><br />

includes the replacement and widening <strong>of</strong> the eastbound side <strong>of</strong> the bridge along<br />

with various drainage improvements.<br />

MAINTENANCE OF TRAFFIC: US 422 will be reduced to one lane in each<br />

direction during construction. US 422 will also close for one night. A detour will<br />

be posted. Access to all residences and businesses will be maintained at all times<br />

throughout construction.<br />

TRUMBULL COUNTY 33


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Trumbull County Upcoming Projects<br />

<strong>Ohio</strong> Ave.<br />

Village <strong>of</strong> McDonald<br />

PID: 91033<br />

ESTIMATED CONSTRUCTION COST: $500,000<br />

ESTIMATED TOTAL COST: $500,000<br />

AWARD DATE: May <strong>2013</strong> COMPLETION DATE: October <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> <strong>Ohio</strong> Ave. between Marshall Rd. and<br />

Olive St. The project also includes various drainage improvements and curb<br />

improvements.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained with flaggers during construction.<br />

Olive St.<br />

Village <strong>of</strong> McDonald; City <strong>of</strong> Niles<br />

PID: 82420<br />

ESTIMATED CONSTRUCTION COST: $5.9 million<br />

ESTIMATED TOTAL COST: $6.6 million<br />

AWARD DATE: October <strong>2013</strong> COMPLETION DATE: Sept. 2014<br />

PROJECT DESCRIPTION: Replacement <strong>of</strong> a bridge on Olive St. over the<br />

Mahoning River and B&O Railroad between Summit Ave. and <strong>Ohio</strong> Ave.<br />

MAINTENANCE OF TRAFFIC: Olive St. is currently closed and will remain<br />

closed throughout the project. A detour is posted. Access to all residences and<br />

businesses will be maintained at all times throughout construction.<br />

West Park Ave.<br />

Weathersfield Township<br />

PID: 90983<br />

ESTIMATED CONSTRUCTION COST: $400,000<br />

ESTIMATED TOTAL COST: $400,000<br />

AWARD DATE: May <strong>2013</strong> COMPLETION DATE: October <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> West Park Ave. between Austintown<br />

Warren Rd. and Sharky Rd.<br />

MAINTENANCE OF TRAFFIC: Traffic will be maintained with flaggers during<br />

construction.<br />

State Route 46<br />

Mecca & Greene townships<br />

PID: 85202<br />

ESTIMATED CONSTRUCTION COST: $1.5 million<br />

ESTIMATED TOTAL COST: $1.8 million<br />

AWARD DATE: May <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 46 between SR 88 and the<br />

Ashtabula county line. Project also includes various bridge repairs, culvert<br />

replacements and drainage improvements to eleven structures on SR 46 between<br />

SR 88 and Trumbull county line.<br />

MAINTENANCE OF TRAFFIC: Traffic will be maintained with flaggers on SR<br />

46 during resurfacing. SR 46 will be closed for 50 days for several culvert<br />

replacements between SR 87 and SR 88. SR 46 will also be closed for 30 days<br />

between York St. and the Ashtabula County line. All detours will be posted.<br />

Access to all residences and businesses will be maintained at all times throughout<br />

construction.<br />

TRUMBULL COUNTY 34


<strong>2013</strong> DISTRICT 4 CONSTRUCTION PROGRAM<br />

Trumbull County Upcoming Projects Continued<br />

U.S. Route 62<br />

Hubbard Township<br />

PID: 90699<br />

ESTIMATED CONSTRUCTION COST: $100,000<br />

ESTIMATED TOTAL COST: $100,000<br />

AWARD DATE: October <strong>2013</strong> COMPLETION DATE: August 2014<br />

PROJECT DESCRIPTION: Culvert replacement on US 62 at the intersection <strong>of</strong><br />

Fairlawn Ave.<br />

MAINTENANCE OF TRAFFIC: US 62 will be closed for 14 days. A detour will<br />

be posted. Access to all residences and businesses will be maintained at all times<br />

throughout construction.<br />

Interstate 80<br />

Hubbard Township<br />

PID: 81510<br />

ESTIMATED CONSTRUCTION COST: $16.3 million<br />

ESTIMATED TOTAL COST: $17.7 million<br />

AWARD DATE: December <strong>2013</strong> COMPLETION DATE: SEPT. 2016<br />

PROJECT DESCRIPTION: The replacement <strong>of</strong> two bridges on I-80 over Mt.<br />

Everett Rd. Project also includes the re-alignment <strong>of</strong> Mt. Everett Rd. under I-80.<br />

MAINTENANCE OF TRAFFIC: Two lanes <strong>of</strong> traffic will be maintained in each<br />

direction <strong>of</strong> I-80 during peak traffic hours. A minimum <strong>of</strong> one lane <strong>of</strong> traffic will<br />

be maintained in each direction during non-peak traffic hours. Mt. Everett Rd. will<br />

be closed throughout the duration <strong>of</strong> the project. A detour will be posted. Access to<br />

all residences and businesses will be maintained at all times throughout<br />

construction.<br />

State Route 82<br />

City <strong>of</strong> Warren; Howland Township<br />

PID: 76413<br />

ESTIMATED CONSTRUCTION COST: $5.2 million<br />

ESTIMATED TOTAL COST: $5.2 million<br />

AWARD DATE: July <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 82 between SR 5 and just west <strong>of</strong><br />

SR 46. The project also includes re-decking and various bridge work on six<br />

structures on SR 82.<br />

MAINTENANCE OF TRAFFIC: A minimum <strong>of</strong> one lane <strong>of</strong> traffic will be<br />

maintained in each direction on SR 82 during non-peak traffic hours. Various three<br />

day closures will occur during bridge repairs. All detours will be posted. Access to<br />

all residences and businesses will be maintained at all times throughout<br />

construction.<br />

State Route 534<br />

Newton Township<br />

PID: 84601<br />

ESTIMATED CONSTRUCTION COST: $3.8 million<br />

ESTIMATED TOTAL COST: $3.8 million<br />

AWARD DATE: July <strong>2013</strong> COMPLETION DATE: Nov. <strong>2013</strong><br />

PROJECT DESCRIPTION: Resurfacing <strong>of</strong> SR 534 from the Trumbull county line<br />

to Hallock Young Rd. This project also includes resurfacing on US 224 and SR<br />

534 in Portage and Mahoning counties. As well as various work to seven bridges<br />

on US 224 in Portage County and SR 534 Mahoning County.<br />

MAINTENANCE OF TRAFFIC: Traffic will be maintained with flaggers during<br />

construction.<br />

TRUMBULL COUNTY 35


O UR M I S S I O N<br />

To provide easy conveyance <strong>of</strong> people<br />

and goods from place to place, we will:<br />

Take care <strong>of</strong> what we have;<br />

Make our system work better;<br />

Improve safety;<br />

Enhance capacity<br />

O UR V I S I O N<br />

A long-term, reliable, pr<strong>of</strong>essional and<br />

highly productive organization<br />

For more information, contact the ODOT District 4 Public Information Office at (330) 786-2208.<br />

Like us on Facebook:<br />

www.facebook.com/ODOT<strong>D4</strong><br />

Follow us on Twitter:<br />

www.twitter.com/ODOT_Akron<br />

Statewide Traffic Information:<br />

www.Ohgo.com<br />

For general information, call (330) 786-2230 or visit District 4’s Web site at: www.transportation.ohio.gov/dist4