SPECIAL PROVISIONS<br />
Project No. C-28(492)<br />
labor, equipment, tools and incidentals required to place the Type III barricade. The<br />
minimum length of a Type III barricade shall be eight (8) feet.<br />
B. The furnishing, erecting and maintaining of all other traffic control and<br />
protection devices shown on the plans or as ordered by the engineer shall not be<br />
measured and paid for directly, but they shall be considered subsidiary to the items<br />
for which the contract provides that direct payment will be made.<br />
CONTRACT START DATE<br />
Work under this contract will begin on or about August 26, 2013. Contractor’s request for an earlier<br />
start date will be considered. The contract days for this project will be strictly enforced.<br />
CONTRACT PAYMENT<br />
Payment for work under this contract will be made for only those items listed in the proposal. The<br />
cost of all other work, materials and miscellaneous items necessary to construct this project in<br />
accordance with the plans and specifications, shall be considered incidental to the unit bid prices of<br />
the items listed in the proposals.<br />
NPDES PERMIT<br />
This project has been authorized to discharge storm water under NPDES General Permit<br />
NER110000. The authorization number is NER113798. The contractor is responsible for<br />
compliance with the terms and conditions of this permit and the Storm Water Pollution Prevention<br />
Plan (SWPPP) which are housed at the <strong>Douglas</strong> <strong>County</strong> Engineer’s Office and available for review<br />
upon request.<br />
STATUS <strong>OF</strong> UTILITIES<br />
At this point, all known utility companies in the area have been contacted and are shown on the<br />
plans for the convenience of the contractor. It is the responsibility of the contractor to properly<br />
locate all utilities in the field, both shown and not shown in the plans. Below is a list of known local<br />
utilities and their current status:<br />
Omaha Public Power District<br />
OPPD has reviewed the 90% plans for the project listed above. There is a three phase overhead<br />
line on the south side in conflict and will be relocated to new right of way.<br />
OPPD has notified <strong>Douglas</strong> <strong>County</strong> that the conflicting poles will be relocated concurrently with the<br />
project and after removal of the trees on the south side of Fort Street.<br />
Contact: Joe Ostblom - (402) 636-3513<br />
CenturyLink<br />
CenturyLink has a 9 way duct structure running east and west on the south side of Fort Street. This<br />
is running around 22' to 24' Rt and will need to be moved /adjusted for the grade cuts in this area.<br />
At first glance I would like to lower this in place concurrently with the project, if the general<br />
contractor would remove grade from the northside first then allow our contractor to move in to drop<br />
SP - 4