SPECIAL PROVISIONS<br />

Project No. C-28(492)<br />

This project is governed by the General Requirements and Covenants of the <strong>Douglas</strong> <strong>County</strong><br />

Standard Specifications for Highway Construction, 2000, as may be modified by these Special<br />

Provisions.<br />

The Construction Details shall be as specified by the City of Omaha Standard Specifications for<br />

Public Works Construction, 2003 and latest supplements thereto, the attached Supplemental<br />

Specifications and these Special Provisions.<br />

PRE-CONSTRUCTION MEETING<br />

As soon as practical after award of contract, but prior to beginning work on this project, the<br />

contractor shall attend a pre-construction meeting unless the requirement for such meeting is waived<br />

by the <strong>County</strong> Engineer.<br />

The purpose of this meeting shall be the specific planning of how the work is to be accomplished,<br />

which shall include but not be limited to a written time schedule for the closing to traffic of any<br />

streets or roads, utility work, access to properties and major items of work required by the plans such<br />

as grading or paving.<br />

LIQUIDATED DAMAGES<br />

Time is of the essence for the faithful and timely performance of the terms of the Contract. The<br />

parties hereto agree that it is not possible to predetermine an amount in actual damages due <strong>Douglas</strong><br />

<strong>County</strong> whenever timely completion is not accomplished; therefore, in lieu of actual damages, the<br />

parties to this Contract agree, as per Subsection 108.07 of the <strong>Douglas</strong> <strong>County</strong> Standard<br />

Specifications for Highway Construction, Liquidated Damages shall be charged at a rate of One<br />

Thousand Dollars, $1,000.00 per calendar day for each day that the construction of this project<br />

extends beyond the number of calendar days as specified in the Contract with any additional days<br />

granted by the engineer, provided that full safe use of the newly constructed phase of the facility is<br />

denied the public.<br />

BARRICADES, DANGER, WARNING AND DETOUR SIGNS<br />

1. All barricades, warning signs, lights, temporary signals and other protective devices must<br />

conform with the latest edition of the Manual of Uniform Traffic Control Devices for Streets and<br />

Highways published by the U. S. Government Printing Office. All barricades and signs shall be<br />

constructed and erected in accordance with the plans furnished.<br />

2. The contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient<br />

lights, hazard beacons, other signs, provide a sufficient number of watchmen and take all necessary<br />

precautions for the protection of the work and the safety of the public. All lights shall be kept<br />

burning from sunset to sunrise.<br />

3. The contractor shall erect warning signs in advance of any place within the project limits where<br />

operations interfere with the use of the road by traffic, and at all intermediate points where the new<br />

work crosses or coincides with an existing road. Such warning signs shall be constructed and<br />

erected in accordance with the plans furnished.<br />