Permit To Work (Mod 03) Rev. 4.2 - Brunei Shell Petroleum

Permit To Work (Mod 03) Rev. 4.2 - Brunei Shell Petroleum Permit To Work (Mod 03) Rev. 4.2 - Brunei Shell Petroleum

30.12.2013 Views

Brunei Shell Petroleum Company Sendirian Berhad BSP-02 –Procedure-1622 M O D U L E 0 3 P E R M I T T O W O R K P R O C E D U R E T H I S I S A C R I T I C A L P R O C E D U R E S U P P O R T I N G T H E E X E C U T I O N A C T I V I T Y P R O C E S S E S B S P - 0 9 , 1 2 , 7 1 , 7 2 & 7 3 A N D I S M A N D A T O R Y F O R : - - C O N S T R U C T I O N O F N E W F A C I L I T I E S ; - M O D I F I C A T I O N , M A I N T E N A N C E O R O P E R A T I O N O F E X I S T I N G F A C I L I T I E S ; - D R I L L I N G , R E P A I R O R M O D I F I C A T I O N O F W E L L S Revision 4.2 Document Owner: Author: HSE HSE/4

<strong>Brunei</strong> <strong>Shell</strong> <strong>Petroleum</strong> Company Sendirian Berhad<br />

BSP-02 –Procedure-1622<br />

M O D U L E 0 3<br />

P E R M I T T O W O R K<br />

P R O C E D U R E<br />

T H I S I S A C R I T I C A L P R O C E D U R E<br />

S U P P O R T I N G T H E E X E C U T I O N A C T I V I T Y<br />

P R O C E S S E S B S P - 0 9 , 1 2 , 7 1 , 7 2 & 7 3 A N D<br />

I S M A N D A T O R Y F O R : -<br />

- C O N S T R U C T I O N O F N E W<br />

F A C I L I T I E S ;<br />

- M O D I F I C A T I O N , M A I N T E N A N C E<br />

O R O P E R A T I O N O F E X I S T I N G<br />

F A C I L I T I E S ;<br />

- D R I L L I N G , R E P A I R O R<br />

M O D I F I C A T I O N O F W E L L S<br />

<strong>Rev</strong>ision<br />

<strong>4.2</strong><br />

Document Owner:<br />

Author:<br />

HSE<br />

HSE/4


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Document Control<br />

DOCUMENT TYPE DOCUMENT OWNER SECURITY CLASSIFICATION<br />

Procedure HSE Unclassified<br />

DOCUMENT REFERENCE AUTHOR APPROVED BY<br />

BSP-02 - Procedure - 1622 HSE/4 HSE<br />

KEY WORDS<br />

<strong>Permit</strong> to work, Isolation certificates, zoned areas, hazardous area classification<br />

Suggestions for improvement in this document should be addressed to the Document Owner via a Document<br />

Change Proposal Form in accordance with:<br />

Document Control Procedure (BSP-02-Procedure-001)<br />

REV REVISION DESCRIPTION DATE<br />

0.0 Original Issue of Manual for 1992 revision of PTW System. Used for piloting<br />

training courses.<br />

October 1992<br />

1.0 <strong>Rev</strong>ision after post-implementation system review. December 1995<br />

2.0 <strong>Rev</strong>ision following 1995, 1996 & 2000 PTW Level 1 Audit; incorporated all<br />

previous <strong>Mod</strong>ule 00 amendment; TMS format; Conversion to MS-Word; update<br />

of EDP validity from 12 hrs to 9 days; deletion of appointment cards in favour of<br />

PSL.<br />

3.0 Incorporation of PTW Level 1 Audit actions (December 2001& September 2002)<br />

Non Compliance With <strong>Permit</strong> <strong>To</strong> <strong>Work</strong>.<br />

4.0 Incorporation of WLS and WHM Handover Form where PTW is not required for<br />

‘Standard’ WLS & WHM activities for unmanned platform. IMT PTW<br />

requirement. Variation displays at PIP. Additional 4 new <strong>Permit</strong> Location Board<br />

Pictorial Markers for EDP, V, WLS and WHM. Minor update on Excavation<br />

Certificate, Diving Operation <strong>Permit</strong> and Hot work On Live Production Facility,<br />

Tier 1 responder included in Safety Checklist.<br />

4.1 Incorporation of PTW Level 1 Audit actions (Mar 2004), <strong>Rev</strong>ised Appendix 5<br />

(Attachment 2 Form B and Attachment 3 Form C), Details on PIP Coordinator,<br />

<strong>Rev</strong>ised Appendix 1. Incorporate recommendations from HSE-MS Audit (May<br />

2004) and recommendations from Diving Incident in East.<br />

<strong>4.2</strong> Incorporation of PTW Level 1 Audit actions (July 2006), EPA Regional PTW<br />

Audit (August 2007) and Learnings from AMPA-9 Incident (April 2008)<br />

<strong>Rev</strong>ision Record<br />

July 2001<br />

October 2002<br />

January 2004<br />

December 2004<br />

February 2009<br />

The life of this document is limited to a maximum of 5 years after the last revision date. Beyond this, the<br />

document must be assessed for relevancy and validated in accordance with TMS0436. The current validity<br />

of this revision should be confirmed with the Document Owner prior to application.<br />

Distribution Control<br />

No hard copies are made available for distribution. The document can be found and made available to all<br />

users via the BSP Intra web > Corporate> HSE > HSE Documentation or by accessing bsp.com.bn website.<br />

Notice and Warning<br />

Copyright © 2001, <strong>Brunei</strong> <strong>Shell</strong> <strong>Petroleum</strong> Company Sendirian Berhad.<br />

This document is the property of <strong>Brunei</strong> <strong>Shell</strong> <strong>Petroleum</strong> Sendirian Berhad (BSP), KB3534, Negara <strong>Brunei</strong><br />

Darussalam. Circulation is restricted to BSP and its designated associates, contractors and consultants. It<br />

must not be copied or used for any other purpose other than which it is supplied, without the expressed<br />

written authority of BSP.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 2 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Except where provided for purposes of contractual requirements, BSP disclaims any responsibility or liability<br />

for any use or misuse of the document by any person and makes no warranty as to the accuracy or<br />

suitability of the information to any third party. Any misuse of the document is re-dressable by BSP.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 3 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

Table of Contents<br />

BSP-02-Procedure-1622<br />

1. INTRODUCTION .......................................................................................................... 11<br />

1.1 Objective .................................................................................................................................... 11<br />

1.2 <strong>Permit</strong> to <strong>Work</strong> Application Process ............................................................................................ 12<br />

1.3 Responsibilities related to the <strong>Permit</strong> to <strong>Work</strong> System................................................................. 13<br />

1.4 Documentation Storage .............................................................................................................. 15<br />

2 DESCRIPTION OF THE PERMIT TO WORK SYSTEM............................................................... 16<br />

2.1 The <strong>Permit</strong> to <strong>Work</strong> Structure ..................................................................................................... 16<br />

2.2 Types of <strong>Permit</strong> and Use ............................................................................................................. 17<br />

2.3 Obtaining the Correct Type of <strong>Permit</strong> .......................................................................................... 18<br />

2.4 Hot <strong>Work</strong> Categories................................................................................................................... 18<br />

3 OPERATION OF THE PERMIT TO WORK SYSTEM ................................................................. 20<br />

3.1 Completing a Cold <strong>Work</strong>, Hot <strong>Work</strong> and Equipment Disjointing <strong>Permit</strong> ....................................... 20<br />

3.2 Completing an Equipment Disjointing <strong>Permit</strong> ............................................................................. 24<br />

3.3 <strong>Work</strong>site Preparations for Cold, Hot and Equipment Disjointing <strong>Permit</strong>s..................................... 26<br />

3.4 Gas Testing Requirements .......................................................................................................... 26<br />

3.5 Acceptance and Authorisation of Cold, Hot and Equipment Disjointing <strong>Permit</strong>s .......................... 29<br />

3.6 Box 8 - <strong>Permit</strong> Re-Authorisation ................................................................................................. 31<br />

3.7 <strong>Permit</strong> Suspension ..................................................................................................................... 32<br />

3.8 Remarks Box.............................................................................................................................. 33<br />

3.9 <strong>Permit</strong> Cancellation .................................................................................................................... 33<br />

3.10 Completing a Diving Operations <strong>Permit</strong> ................................................................................... 35<br />

3.11 Briefing of the <strong>Work</strong>force - "<strong>To</strong>olbox Talk (TBT)" ....................................................................... 41<br />

3.12 Supervision of the <strong>Work</strong>site ..................................................................................................... 41<br />

4 CERTIFICATES AND HAZARD CHECKLIST.......................................................................... 42<br />

4.1 PTW Certificates ......................................................................................................................... 42<br />

<strong>4.2</strong> Use of Certificates....................................................................................................................... 42<br />

4.3 Electrical Documentation ........................................................................................................... 52<br />

5 ISOLATIONS .............................................................................................................. 53<br />

5.1 Planning Safe Isolation Boundaries............................................................................................. 53<br />

5.2 Recording of Isolations ............................................................................................................... 54<br />

5.3 Authorisation of Isolations.......................................................................................................... 54<br />

5.4 Securing of Isolations ................................................................................................................. 55<br />

5.5 Tagging of Isolation Points .......................................................................................................... 55<br />

5.6 De-Isolation on Completion of <strong>Work</strong>............................................................................................ 56<br />

5.7 Extended Period Isolations (EPIs)................................................................................................ 57<br />

5.8 Master Isolations ........................................................................................................................ 58<br />

6 PERMIT ISSUE POINTS (PIPS)........................................................................................ 62<br />

6.1 <strong>Permit</strong> Issue Point Control.......................................................................................................... 62<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 4 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

6.2 Display of <strong>Permit</strong>s and Isolations................................................................................................ 63<br />

7 HAZARDOUS AREA CLASSIFICATION................................................................................ 67<br />

7.1 Classification of Areas ................................................................................................................ 67<br />

7.2 Hazardous Area Classification Drawings..................................................................................... 68<br />

8 RULES & RESTRICTIONS.............................................................................................. 69<br />

8.1 Actions Following a General Alarm ............................................................................................. 69<br />

8.2 Changes to <strong>Permit</strong>s to <strong>Work</strong> ....................................................................................................... 69<br />

8.3 Testing After Maintenance .......................................................................................................... 69<br />

8.4 Preparation for Equipment Disjointing........................................................................................ 69<br />

8.5 Interfaces between Drilling Rigs and Tenders and Fixed Offshore Installations............................ 69<br />

8.6 Non Compliance With <strong>Permit</strong> to <strong>Work</strong> Requirements................................................................... 70<br />

9 WORK NOT NORMALLY REQUIRING A PERMIT ................................................................... 72<br />

10 MONITORING, AUDITING AND REVIEW OF THE PTW SYSTEM ................................................ 73<br />

10.1 Definitions .............................................................................................................................. 73<br />

10.2 Objectives ............................................................................................................................... 73<br />

10.3 Auditing of the <strong>Permit</strong> to <strong>Work</strong> System .................................................................................... 74<br />

10.4 Audit Reports .......................................................................................................................... 78<br />

10.5 Audit Archiving ....................................................................................................................... 79<br />

10.6 System Management <strong>Rev</strong>iew.................................................................................................... 79<br />

11 REFERENCES ............................................................................................................ 80<br />

12 LIST OF APPENDICES................................................................................................... 81<br />

APPENDIX 1: TRAINING AND APPOINTMENT OF SIGNATORIES AND SUPERVISORS ......... 82<br />

APPENDIX 2- PTW DOCUMENTS ..................................................................................... 86<br />

APPENDIX 3 PTW FORMS .............................................................................................. 88<br />

APPENDIX 4 CERTIFICATES, SAFETY CHECK LISTS & TAGS........................................... 97<br />

APPENDIX 5 - PTW AUDIT FORMS ................................................................................115<br />

APPENDIX 6 - WELL HANDOVER FORM FOR STANDARD WIRELINE AND WELLHEAD<br />

MAINTENANCE..............................................................................................................123<br />

APPENDIX 7 - PTW APPOINTMENT RECORD..................................................................125<br />

APPENDIX 8 - PTW APPOINTMENT FLOW CHART ..........................................................128<br />

APPENDIX 9 - LIST OF APPOINTED AREAS & PTW AUTHORITY CARD.........................................129<br />

APPENDIX 10 - TEMPORARY ASSET HOLDER HANDOVER LETTER.............................................131<br />

APPENDIX 11 - MAPPABLE CHANGES FORM ..................................................................132<br />

APPENDIX 12 – 3 WHATS ................................................................................................133<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 5 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

ABBREVIATIONS<br />

AA<br />

AD<br />

AEP<br />

AGT<br />

AOS<br />

AS<br />

COS<br />

CSR<br />

CEP<br />

CWP<br />

DSV<br />

DSV<br />

DWSS<br />

EDP<br />

EPI<br />

EPTW<br />

Area Authority<br />

Asset Director<br />

Authorised Electrical Person<br />

Authorised Gas Tester<br />

Area Operations Superintendent, see also OIM<br />

Authorised Signatory<br />

Complex Operations Superintendent<br />

Company Site Representative<br />

Competent Electrical Person<br />

Cold <strong>Work</strong> <strong>Permit</strong><br />

Diving Support Vessel<br />

Drilling Supervisor<br />

Diving <strong>Work</strong>site Supervisor<br />

Equipment Disjointing <strong>Permit</strong><br />

Extended Period Isolation<br />

Electrical <strong>Permit</strong> to <strong>Work</strong><br />

ESR BSP Electrical Safety Rules, BSP-02-Standard-1629 (<strong>Mod</strong>ule 10)<br />

FOS<br />

HCL<br />

HIP<br />

HWP<br />

LEL<br />

LSA<br />

MOS<br />

OIM<br />

PIP<br />

PLB<br />

PTW<br />

ROV<br />

SAEP<br />

SOS<br />

TBT<br />

WSS<br />

xOP<br />

Field Operations Superintendent<br />

Hazard Check List<br />

Hazard Identification Plan<br />

Hot <strong>Work</strong> <strong>Permit</strong><br />

Lower Explosive Limit<br />

Low Specific Activity Scale<br />

Maintenance Operations Superintendent<br />

Onshore/Offshore Installation Manager, see also AOS<br />

<strong>Permit</strong> Issue Point<br />

<strong>Permit</strong> Location Board<br />

<strong>Permit</strong> to <strong>Work</strong><br />

Remotely Operated Vehicle<br />

Senior Authorised Electrical Person<br />

Senior Operations Supervisor<br />

<strong>To</strong>olbox Talk<br />

<strong>Work</strong> Site Supervisor<br />

Asset Operations Representative on Drilling Tenders/Jack-Ups<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 6 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

TERMINOLOGY<br />

In the documents of the <strong>Brunei</strong> <strong>Shell</strong> Emergency Response Management System the following words are used<br />

to express the level of authoritative requirement for actions described within the text:<br />

Must, Shall, Will : Means mandatory. Such actions must be followed.<br />

Should: : Means strongly recommended.<br />

May : Means acceptable and to be considered.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 7 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

GLOSSARY OF TERMS<br />

Applicant<br />

BSP-02-Procedure-1622<br />

The person who applies for a <strong>Permit</strong> and completes the <strong>Work</strong> Description sections for<br />

approval by the Authorised Signatory. The Applicant represents the Performing<br />

Authority and should be responsible for supervising the worksite.<br />

Approved<br />

<strong>Permit</strong><br />

Appointing<br />

Authority<br />

Area Authority<br />

(AA)<br />

Asset Holder<br />

Audit Authority<br />

Authorised Gas<br />

Tester<br />

Authorised<br />

Signatory (AS)<br />

Authorised/<br />

Re-authorised<br />

<strong>Permit</strong><br />

Cancelled<br />

<strong>Permit</strong><br />

Certificate<br />

Cold <strong>Work</strong><br />

<strong>Permit</strong><br />

Containment<br />

Electrical<br />

Safety Rules<br />

Electrical<br />

<strong>Permit</strong> to <strong>Work</strong><br />

A permit that has been signed by an Authorised Signatory to agree the work description<br />

and allow worksite preparations, but not the work contained in the work description<br />

section of Box 1 to proceed. This permit is held in the planned section of the PTW rack<br />

until it is accepted and authorised.<br />

The person responsible for carrying out interviews and formally appointing the PTW<br />

applicants into their roles upon demonstrating competence at the appointment interview.<br />

The Asset Holder’s formally appointed representative with operational responsibility for<br />

an area. The AA is directly responsible for the safety of an area, and the assets within it,<br />

and for the control of work that may be carried out in that area at any particular time.<br />

The AA is the person responsible for authorising the work identified by the <strong>Work</strong><br />

Description in Box 1 of the permit to commence and for the re-authorisation of permits.<br />

The AA must have completed successfully the appropriate PTW courses (PTW-2 and 3<br />

(5)) and have been formally appointed as an AA for the area over which they have<br />

responsibility.<br />

The Postholder defined in the BSP Asset Holder list as being responsible for a particular<br />

item or area of BSP property. In this document the term is used also to describe the<br />

persons formally appointed to represent them at any asset, elsewhere referred to as the<br />

Asset Custodian.<br />

The person responsible for authorising the various levels of audits of the PTW System.<br />

A person who has completed successfully the Authorised Gas Tester and either the PTW<br />

Authorised Signatory or <strong>Work</strong>site Supervisor course and has been formally appointed as<br />

an Authorised Gas Tester for the location where is work is to take place. Only<br />

Authorised Gas Testers may carry out gas tests and sign certificates.<br />

A person who signs a permit to approve the work in principle and to agree the work<br />

description, the preparations and controls required and to set the validity period for the<br />

work. The AS must have completed successfully the appropriate PTW courses (PTW-2<br />

and 3 (5)) and be formally appointed as an AS for the area over which they have<br />

responsibility.<br />

A permit carrying an authorising or re-authorising signature for the current working<br />

period which has been signed by the Area Authority indicating that they are satisfied<br />

that it is safe for the work specified in the work description to start. The permit and<br />

associated documents must be formally accepted or re-accepted by the <strong>Work</strong>site<br />

Supervisor before work may commence.<br />

A permit, which has been cancelled by the appropriate signatories. No further work may<br />

be carried out under that permit.<br />

A formal document, which is attached to, and forms part of the work permit to provide<br />

additional support, information or controls to those included on the permit.<br />

A permit for work that does not involve the use of open flames, the production of a<br />

source of ignition, provide spark potential or breaking containment when flammable<br />

toxic or corrosive material will be encountered.<br />

Is any physical barrier that prevents any physical element escaping into the environment<br />

and specifically to the sea.<br />

A set of rules which describe a safe system of electrical work and contain mandatory<br />

standards and procedures for work on high and low voltage electrical systems. The<br />

Process Owner of the Electrical Safety Rules is SEN/4.<br />

A permit used for the control of work on equipment attached to high voltage electrical<br />

equipment (above 1,000 volts AC, 1,500 volts DC) and equipment supplied with high<br />

voltage.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 8 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Equipment<br />

Disjointing<br />

<strong>Permit</strong> (EDP)<br />

Extended<br />

Period of<br />

Isolation<br />

Gas Testing<br />

Hazard Check<br />

List<br />

Hazard<br />

Identification<br />

Plan<br />

Hot <strong>Work</strong><br />

<strong>Permit</strong><br />

Isolation<br />

Isolation<br />

Boundary<br />

Live <strong>Permit</strong><br />

Method<br />

Statement<br />

Operating Area<br />

Override<br />

Performing<br />

Authority<br />

<strong>Permit</strong> User<br />

<strong>Permit</strong> Issue<br />

Point (PIP)<br />

Coordinator<br />

<strong>Permit</strong><br />

Signatories<br />

<strong>Permit</strong> System<br />

Auditor<br />

Planned <strong>Permit</strong><br />

Process Owner<br />

Suspended<br />

<strong>Permit</strong><br />

A permit covering the controls required when breaking into live plant or equipment<br />

where there is a potential for release of flammable, toxic, corrosive or other harmful<br />

substances that are present.<br />

An isolation, which remains in place without, work being carried out within its<br />

boundary. It is used, for example, where work has commenced on equipment but is<br />

suspended whilst spares are awaited.<br />

The checking of the worksite prior to and during hot work and confined space entry to<br />

provide warning of the presence of flammable and/or toxic gas or an oxygendeficient/enriched<br />

atmosphere.<br />

A Hazard Check List documents the most effective controls for certain potentially<br />

hazardous activities. Standard Hazard Check Lists are provided. A Hazard Check List is<br />

used only to support a permit, and cannot be used instead of one.<br />

A document that identifies the hazards associated with any proposed work, assesses<br />

their significance in terms of risk and describes how the hazard will be eliminated or<br />

controlled and the response should control be lost. A HIP may be used in addition to the<br />

HCL.<br />

A permit designed to control work that involves an open flame or that might result in the<br />

production of a source of ignition.<br />

A physical barrier between a source of energy and a place of work.<br />

The physical isolation (mechanical or electrical) or other similar devices used to establish<br />

an area in which work may take place safe from hazards caused by mechanical or<br />

electrical energy.<br />

A permit that has been approved, accepted and authorised for work to proceed.<br />

A detailed step-by-step procedure for the work to be undertaken that includes the<br />

resources (materials and manpower) to be used. It incorporates a Hazard Identification<br />

Plan.<br />

All areas where BSP has a direct and physical operating presence and influence, or<br />

carries out hydrocarbon processing, construction, repair or maintenance, administrative,<br />

residential, recreational, educational or other related activities. It does not normally<br />

include contractor premises whether or not within a BSP concession area.<br />

The temporary bypass of a safeguarding device, to allow certain work to proceed without<br />

causing an unnecessary activation of the safeguarding system e.g. fire detector<br />

overridden during welding operation.<br />

The BSP department or Contractor company responsible for undertaking the work<br />

covered by a permit, represented at the worksite by the WSS.<br />

A person who carries out the work for which the permit has been approved, accepted<br />

and authorised.<br />

A person who has successfully completed the appropriate PTW courses (PTW-2 & 3 (5))<br />

and has been formally appointed by an Appointing Authority to maintain the<br />

management and visibility of the <strong>Permit</strong> Rack and Location Board in an Installation PIP.<br />

Persons who approve and authorise permits, reauthorise and confirm cancellation of<br />

permits (AS/AA).<br />

A person who has completed successfully the appropriate PTW courses (PTW-2, 3 (5) and<br />

4) and who has been appointed by the Asset Holder as a PTW System Auditor.<br />

A permit for which the intended work and its preparation has been approved, but which<br />

has not been accepted or authorised for the work to begin.<br />

The Process Owner for the PTW procedure is the Head of HSE department who approves<br />

the issue of the document. Support to the Process Owner is divided into three areas,<br />

Document Holder, Asset Holder and Training Service Provider.<br />

A permit, which is within its validity period, has been accepted, authorised or reauthorised,<br />

but is not re-authorised currently to allow work to proceed.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 9 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Training<br />

Service<br />

Provider<br />

<strong>Work</strong>site<br />

<strong>Work</strong>site<br />

Supervisor<br />

(WSS)<br />

Responsible for ensuring sufficient resources and facilities are available to meet the<br />

training requirements of the suite of PTW courses.<br />

A place where any activity is conducted for BSP, by BSP staff, BSP contractors and 3 rd<br />

party.<br />

A person who has successfully completed the appropriate PTW courses (PTW-1 and 2 (5))<br />

and has been formally appointed by an Appointing Authority to be in charge of a<br />

worksite. The WSS is responsible for ensuring that the permit users comply with the<br />

controls of the permit. The WSS is the person who should apply for a permit and who<br />

completes the work description sections of the permit for approval by the AS. The WSS<br />

is responsible for ensuring that the work is properly supervised at all times. This<br />

supervision must be by the WSS who must be appointed for the area in which the work<br />

will take place.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 10 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

1 . I N T R O D U C T I O N<br />

1.1 Objective<br />

The overall objectives of the PTW system are:<br />

• to ensure that all necessary measures are taken to provide a safe working environment by<br />

identifying the potential hazards and risks ahead of starting work;<br />

• to ensure that everyone involved in the work is fully aware of the content of the work, any potential<br />

hazards and the controls for the hazards identified and any recovery measures necessary should<br />

control or controls fail;<br />

• to prevent incidents that may lead to harm to People, Environment, Asset or Reputation (PEAR).<br />

Meeting the objectives:<br />

<strong>To</strong> ensure that these objectives are met, all elements of the PTW system must be operated effectively. It<br />

is important to understand that the system is not just completion of the permit forms, certificates and<br />

safety checklists, but requires the proper application of the following:<br />

Audit<br />

Authorisation<br />

A process to verify that the requirements of the <strong>Permit</strong> to <strong>Work</strong> Procedures are being<br />

met and identify that common standards are being applied.<br />

Authorisation, both before work starts and restarts after a significant break, confirms<br />

that all controls have been checked as being in place and that the worksite is properly<br />

prepared for work to start or restart.<br />

Communication Full communication between AS/AA/WSS is necessary at all stages in the life cycle of<br />

the permit.<br />

Competence<br />

Co-ordination<br />

Housekeeping<br />

Planning<br />

Controls<br />

Supervision<br />

<strong>To</strong>olbox Talks<br />

Training<br />

Demonstration by AS/AA/WSS/AGT of having the necessary knowledge, experience<br />

and application skills to fulfill their role in the system. Competence is assessed during<br />

training, appointment and audit.<br />

The process designed to ensure that any work that would conflict with other work is<br />

not authorised to proceed at the same time and at the same location.<br />

Ensuring that the worksite is properly prepared, clean, clear, safe and free from<br />

obstructions whilst the work is progressing, when it is complete and when the<br />

worksite is unattended.<br />

The process that ensures work is properly prepared, including the completion of the<br />

appropriate job hazard analysis and certificates or method statement required.<br />

The process that ensures the conditions under which work can proceed.<br />

The process of preparation of each worksite, and the responsibility of supervising<br />

activities at the worksite to ensure compliance with the controls specified on the<br />

<strong>Permit</strong> to <strong>Work</strong>.<br />

The process of discussion at the worksite to inform all those involved in the work of its<br />

content, how it will be carried out, allocating individual responsibilities and identifying<br />

the necessary controls and recovery measures that should be in place before the work<br />

starts.<br />

Formal instruction prior to appointment to provide adequate understanding of the<br />

system.<br />

<strong>Work</strong> Description A clear and detailed description of the proposed work.<br />

The PTW System will only meet its objectives if everyone involved carries out their role within it<br />

effectively. These roles are described in Section 1.3 of this procedure.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 11 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

For all work covered by a permit, everyone associated with the job:<br />

UNDERSTANDS<br />

The work and how it will be carried out;<br />

The work environment and any problems associated with it;<br />

The potential hazards, and the controls that are required;<br />

Their own responsibilities;<br />

Any recovery measures that may be necessary should control fail.<br />

COMPLIES<br />

REMEMBER<br />

with all of the controls on the permit, to ensure the continued safety of those doing<br />

the work and the installation on which it is being done.<br />

THE ISSUE OF A PERMIT DOES NOT GUARANTEE THAT NO INCIDENTS MAY<br />

OCCUR AT A WORKSITE. TO PREVENT INCIDENTS OCCURRING, THE HAZARD<br />

AND EFFECT MANAGEMENT PROCESS IN WHICH THE HAZARDS HAVE BEEN<br />

IDENTIFIED, ASSESSED AND CONTROLS PUT IN PLACE MUST BE COMPLIED<br />

WITH THROUGHOUT THE DURATION OF THE WORK.<br />

1.2 <strong>Permit</strong> to <strong>Work</strong> Application Process<br />

P IP<br />

Ap plicant<br />

W orksite Supervisor<br />

fills in B ox 1 an d s upp orting<br />

do cum ents<br />

Plan<br />

A uthorised S uspended Expired<br />

Ap proval<br />

A uthorised Sig natory<br />

fills in B ox 2, 3, 4 , 5, 5a (HW P )<br />

Task B ox & N um b er Box an d<br />

checks HC L an d certific ates<br />

appro priate for the w ork.<br />

EP I<br />

Acceptance<br />

W orksite Sup ervisor<br />

fills in B ox 6 a fter Area<br />

A uthority h as ch ecke d<br />

co ntro ls are in place .<br />

(F or Hot W ork)<br />

G as T ester fills in Box 5 b<br />

prior to acce ptan ce by W orksite<br />

Sup ervisor<br />

Authorisation<br />

Area A uthority<br />

fills in B ox 7.<br />

P IP<br />

Plan<br />

Authorised Suspended Expired<br />

C arry out W ork<br />

W orksite Supervis or<br />

fills in B ox 8c<br />

C arry out W ork<br />

W /Site S upervisor<br />

fills in B ox 8a<br />

Are a A uthority<br />

fills in B ox 8b<br />

E xpired<br />

(H o t W ork) G a s T ester<br />

fills in B ox 5c<br />

P IP<br />

W ork Com pleted/<br />

N ot C om pleted<br />

W /Site S u pervisor<br />

fills in B ox 9a, 10 a<br />

Area Authority<br />

fills in B ox 9b , 1 0b<br />

Plan<br />

A uthorised S uspended Expired<br />

Archived<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 12 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

1.3 Responsibilities related to the <strong>Permit</strong> to <strong>Work</strong> System<br />

1.3.1 Principal Responsibilities<br />

Installation owners (Asset Director) must ensure that:<br />

• an appropriate PTW system is introduced<br />

• training programmes and competence standards are established and maintained<br />

• monitoring/auditing/reviewing of the PTW system is established and maintained.<br />

The Installation Manager (AOS/OIM) must ensure that:<br />

• all personnel who operate and use the PTW system are competent to do so<br />

• the planning, issue and return of permits is properly co-ordinated<br />

• a secure method of electrical and process/mechanical isolations is implemented<br />

• adequate time is allowed during shift changes to ensure effective transfer of information on<br />

outstanding permits<br />

• the system is regularly monitored to ensure that the PTW system is implemented effectively.<br />

1.3.2 PTW Process Owner & PTW System Custodian<br />

The Process Owner of the <strong>Permit</strong> to <strong>Work</strong> Procedure is the Head of HSE Department. The process<br />

owner is assisted by a system custodian, the Head of Operational Safety.<br />

The PTW Process Owner will:<br />

• <strong>Rev</strong>iew all proposed updates of the PTW Procedure.<br />

• Ensure that only formally approved changes are incorporated in any of the PTW documentation.<br />

• Approve the PTW Procedure.<br />

• Ensure that any updates/changes are communicated with the relevant parties.<br />

The PTW System Custodian will:<br />

• Provide advice & guidance on the PTW System.<br />

• Monitor the performance of the PTW System.<br />

• <strong>Rev</strong>iew the learning from incidents and the periodic inspections of work controlled by permits.<br />

• Specify the technical content of PTW training courses.<br />

• Update the Hazard Check Lists.<br />

• Co-ordinate/lead the annual PTW Level 1 Audit (see Section 10.3 & 10.6).<br />

• Verify that all documentation (modules, certificates, checklists, tags, forms, etc.) are produced to<br />

the correct standard.<br />

• Ensure that there is a distribution system that allows departments to call off supplies of current<br />

documentation under the procedure described in Appendix 2.<br />

1.3.3 Applicant<br />

The Applicant (person who applies for a <strong>Permit</strong>) must be an appointed <strong>Work</strong>site Supervisor (WSS) who is<br />

responsible for completing Box 1 (1a and b EDP) <strong>Work</strong> Description sections for approval by the AS. The<br />

WSS represents the Performing Authority and is responsible for ensuring that the work is properly<br />

supervised at all times. This supervision must be by the WSS who must be appointed for the area in<br />

which the work will be carried out.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 13 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

1.3.4 Authorised Signatory (AS)<br />

An AS signs and is responsible for approving the work in principle and agreeing to the work description,<br />

the preparations and controls required and to set the validity period for the work. The AS must have<br />

successfully completed the appropriate PTW courses (PTW-2, 3 & 4 or PTW-5 when expired) and be<br />

formally appointed by the Appointing Authority.<br />

Controls include, but are not necessarily limited to, checking that the necessary Hazard Check Lists<br />

and required certificates (isolation, overriding, excavation etc.) have been attached and that the<br />

requirements of the check lists and certificates are identified on the permit. The AS must ensure that<br />

all controls identified on the Hazard Check Lists are transferred to the permit.<br />

The following table typically identifies Authorised Signatories<br />

Area<br />

Offshore<br />

• Manned Complexes<br />

• Field Areas<br />

• Drilling Rig (Jack-ups & Tender)<br />

• Installations under CPRA<br />

Onshore<br />

• Manned complexes (e.g. SCOT, NGCP)<br />

• Field areas<br />

• Drilling Rigs<br />

• Non operational assets and services<br />

Authorised Signatory<br />

• Complex Operation Supervisor (COS)<br />

• Field Operation Supervisor (FOS)<br />

• Drilling Supervisor (DSV), can be delegated to <strong>To</strong>olpusher<br />

• Drilling Supervisor (DSV)<br />

• Terminal Operation Supervisor (TOS); NGCP Supervisor<br />

• Field Operation Supervisor (FOS)<br />

• Drilling Supervisor (DSV)<br />

• Section Head<br />

1.3.5 <strong>Work</strong>site Supervisor (WSS)<br />

The <strong>Work</strong>site Supervisor (WSS) is a person who has successfully completed the PTW <strong>Work</strong>site<br />

Supervisors course PTW-1 & 2 (or PTW-5) and been formally appointed by the Appointing Authority to be<br />

in charge of a worksite in a specific area. The WSS must ensure that the:-<br />

- permit users comply with the requirements of the permit;<br />

- work is properly supervised throughout execution.<br />

The WSS must be appointed for the area in which the work will be performed. The WSS must comply<br />

with the requirements of PTW in Box 2 whether to be continuously present at the worksite or not.<br />

1.3.6 Area Authority (AA)<br />

The Area Authority (AA) is the Asset Holder’s formally appointed representative with operational<br />

responsibility for an area. The AA is directly responsible for authorising and re-authorising the work<br />

identified in the <strong>Work</strong> Description to commence or re-commence during their period of duty. The AA<br />

must have successfully completed the appropriate PTW courses (PTW-2, 3 & 4 or PTW-5 when expired)<br />

and have been formally appointed. The AA must comply to the requirements of Box 2 of the permit<br />

should it require them to be continuously present at the worksite.<br />

1.3.7 <strong>Permit</strong> Issue Point Coordinator (PIP Coordinator)<br />

The PIP Coordinator is a person who has successfully completed the appropriate PTW courses (PTW-2,<br />

3 and 4 or 5 when expired) and been formally appointed by the relevant AU Appointing Authority to be in<br />

charge of and responsible for managing the PIP daily activities associated with the PTW process<br />

maintaining visibility at all times of the current status of all permits. The PIP Coordinator is<br />

responsible for overseeing the PTW activities within their area to ensure compliance is maintained<br />

through constant communication with those responsible for applying it.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 14 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

The PIP Coordinator will:<br />

• Ensure the PIP location board information is kept up-to-date especially the plot plan layout.<br />

• Ensure up-to-date filing of EPI & FSR variations are maintained and make site visits to the location<br />

to ensure site isolation tags for EPI are still readable and in good condition.<br />

• Maintain an up-date list of appointed WSS, AS, AA and Gas Testers for their respective areas.<br />

• Be competent in applying the PTW Procedure (<strong>Mod</strong>ule <strong>03</strong>).<br />

• Be responsible for overseeing the PTW process from Application to Cancellation of permits and<br />

subsequent archiving.<br />

• Check all permits at application to ensure that the HEMP process has been properly conducted and<br />

all authorised permits to ensure controls required are complied with.<br />

• Discuss with the relevant Supervisor proposed permits to minimise disruption to operational<br />

activities due to PTW delays.<br />

• Prepare PTW audit schedules for Levels 4, 3 and 2, ensure action items are inputted in FOUNTAIN<br />

and ensure the necessary action is taken by the relevant action parties.<br />

• Organise & update Portable Gas Detectors inventory.<br />

• Check and ensure PTW documents are correctly filled-in and completed prior to archiving.<br />

• Keep a set of master isolation certificates of each platform or area under their responsibility.<br />

• Provide coaching where necessary.<br />

1.4 Documentation Storage<br />

When a permit and the associated certificates have been cancelled, they are removed from the permit<br />

rack together with the accompanying check lists or hazard analysis. These plus any tags that may have<br />

been used and/or certificates are stored in the PIP. <strong>Permit</strong>s are stored by type initially for a period of 1<br />

month for immediate access. After 1 month, they can be put into bulk storage and remain there for 6<br />

months. They can then be disposed of using the BSP approved Waste Disposal Process UNLESS they are<br />

linked to an incident.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 15 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

2 D E S C R I P T I O N O F T H E P E R M I T T O W O R K S Y S T E M<br />

2.1 The <strong>Permit</strong> to <strong>Work</strong> Structure<br />

CORPORATE HSE<br />

MANAGEMENT SYSTEM<br />

ELECTRICAL<br />

SAFETY RULES<br />

PERMIT TO WORK SYSTEM<br />

ELECTRICAL PTW<br />

PERMITS TO WORK<br />

(Hot, Cold, EDP &<br />

Diving)<br />

PERMIT<br />

CERTIFICATES<br />

SANCTION FOR<br />

TEST<br />

ELECTRICAL<br />

ISOLATION<br />

LIMITATION OF<br />

ACCESS<br />

CONFINED SPACE,<br />

MECHNICAL, ISOLATION,<br />

EXCAVATION etc.<br />

SAFETY SYSTEM OVERRIDE<br />

HOTWORK ON LIFE<br />

PRODUCTION FACILITIES<br />

ELECTRICAL SAFETY<br />

OPERATIONAL<br />

PROCEDURES<br />

STANDBY PERSON INSTRUCTIONS<br />

Fire Watcher, Confined Space etc.<br />

HIP’s, Hazard Check<br />

Lists, TBT and 3<br />

Whats<br />

CHECKLISTS<br />

PTW Document Structure<br />

There must be a clear relationship between permit forms and other<br />

certificates and documents used in the PTW system. The relationship is<br />

shown schematically above.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 16 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

2.2 Types of <strong>Permit</strong> and Use<br />

BSP-02-Procedure-1622<br />

Type of <strong>Permit</strong><br />

Cold <strong>Work</strong> <strong>Permit</strong><br />

see Appendix 3, Fig. 1<br />

Hot <strong>Work</strong> <strong>Permit</strong><br />

see Appendix 3, Fig. 2<br />

Equipment Disjointing<br />

<strong>Permit</strong><br />

see Appendix 3, Fig. 3<br />

Electrical <strong>Permit</strong><br />

see Appendix 3, Fig. 4<br />

Diving <strong>Permit</strong><br />

see Appendix 3, Fig. 5 & 6<br />

Use<br />

All work requiring a permit except hot work, equipment<br />

disjointing, diving and electrical work. The procedure for<br />

completing this type of permit is described in Section 3.1.<br />

All work in hazardous areas, that involves, or may result in, an<br />

open flame or the production of a source of ignition or has a spark<br />

potential.. The procedure for completing this type of permit is<br />

described in Section 3.1.<br />

A permit covering the controls required when breaking into live<br />

plant or equipment where there is a potential for release of<br />

flammable, toxic, corrosive or other harmful substances that are<br />

present. The procedure for completing this type of permit is<br />

described in Section 3.2.<br />

All work defined in the ESRs (Electrical Safety Rules), BSP-02-<br />

Standard-1629 (<strong>Mod</strong>ule 10), as requiring an Electrical PTW. The<br />

procedure for completing this type of permit is described in the<br />

ESRs.<br />

All diving work must be covered by a Diving Operations <strong>Permit</strong>.<br />

The procedure for completing this type of permit is described in<br />

Section 3.10.<br />

Restrictions on Number of Concurrent Hot <strong>Work</strong> Activities<br />

For each installation, the SOS is to set a limit on the number of Hot <strong>Work</strong> <strong>Permit</strong>s that may be<br />

authorised at any one time. This limit should also take into consideration whether the installation is<br />

live (SIMOPS) or shutdown and during night time or hours of darkness and has containment. The<br />

limit should be determined by the weekly cumulative risk assessment (BSP-02-Guideline-022,<br />

HAZID), and must be formally recorded at all times in the PIP.<br />

<strong>Work</strong> Incompatible with Hot <strong>Work</strong><br />

Hot work in progress, other than in pressurised non-hazardous areas (habitat) is to be stopped if any<br />

of the following activities are to take place on the same platform or jacket offshore or within 15<br />

meters radius onshore.<br />

a) Flammable liquids are to be transferred.<br />

b) Spray Painting.<br />

c) Hydrocarbons are or may be, released by bleeding down a process system, breaking containment,<br />

pressure testing, pig launching/receiving etc.<br />

d) Any other work considered by the AOS or SOS to be incompatible with the hot work in progress.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 17 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

2.3 Obtaining the Correct Type of <strong>Permit</strong><br />

For any work, the minimum number of permits should be raised.<br />

observed:<br />

BSP-02-Procedure-1622<br />

The following rules must be<br />

<strong>Work</strong> Includes …..<br />

Raise ….<br />

HOT & COLD <strong>Work</strong><br />

ELECTRICAL <strong>Work</strong> with associated<br />

COLD <strong>Work</strong><br />

HOT &<br />

Separate permits<br />

Single ELECTRICAL PERMIT for the electrical<br />

work, with linked HOT or COLD work permits<br />

Breaking containment of process equipment<br />

Complex method statement (containing<br />

numerous work activities<br />

<strong>Work</strong> spread over an area larger than that<br />

covered by a single AA<br />

EQUIPMENT DISJOINTING PERMIT with linked<br />

HOT or COLD work permits<br />

PERMITS for each separate work activity<br />

EACH AA issue a separate permit CLEARLY<br />

defining the boundaries of their area<br />

2.4 Hot <strong>Work</strong> Categories<br />

2.4.1 Category 1 Hot work:<br />

Requires the use of a ‘Hot <strong>Work</strong> on a Live Production Facility Certificate’ (see Appendix 4, Fig. 17)<br />

and needs to be approved by SOS and verified by AOS (see section 2.4.3). The following are examples<br />

of Category 1 hot work, however this is not a definitive list:<br />

- <strong>Work</strong> involving open flames (Welding, Cutting, Grinding)<br />

- Electrical welding<br />

- Induction pre-heating/stress relieving and high temperature calibration<br />

- Use of blowers and electric drills<br />

- Operation of internal combustion Engines not rated for use in a Hazardous Area.<br />

2.<strong>4.2</strong> Category 2 Hotwork:<br />

Needs to be approved by FOS/COS and verified by SOS (see section 2.4.3). The following are<br />

examples of Category 2 hot work, however this is not a definitive list:<br />

- Grit/shot blasting<br />

- Mechanical de-scaling<br />

- Use of non-intrinsically safe or EX rated equipment<br />

- Use of battery operated cameras, video recorders or computers in hazardous areas<br />

- Opening of live junction boxes in hazardous areas<br />

- Use of air/hydraulic powered tools<br />

- Use of cartridge operated fixing tools<br />

- Operation of internal combustion engines in Non-Hazardous Area<br />

- Soldering irons/braising torches<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 18 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

2.4.3 Verification of Hotwork<br />

Hotwork has to be verified by AOS for Category 1 and SOS for Category 2. The verification of hot<br />

work activities by the AOS/SOS is on a case-by-case basis by using the RAM and cumulative risk<br />

assessment output, e.g. number of Hot work activities see also section <strong>4.2</strong>.9. The AOS/SOS countersigns<br />

in Box 5. For cumulative risk assessment refer to BSP-02-Guideline-022 (HAZID).<br />

Application - WSS<br />

<strong>Permit</strong> <strong>Rev</strong>iewed by<br />

PIP Coordinator<br />

HOT WORK<br />

PERMIT<br />

WEEKLY<br />

CATEGORY<br />

CATEGORY<br />

RISK<br />

ONE<br />

TWO<br />

ASSESSMENT<br />

AOS/SOS/<br />

COS/MOS<br />

SOS (AS)<br />

FOS/COS (AS)<br />

COLD WORK<br />

PERMIT<br />

FOS/COS (AS)<br />

AOS<br />

VERIFICATION<br />

SOS<br />

VERIFICATION<br />

PIP to place <strong>Permit</strong> in APPROVAL<br />

WSS and AA - to check controls in place<br />

WSS Sign off HIP and/or HCL<br />

confirming checks are made and controls in place, 3 Whats and TBT given<br />

Commence <strong>Work</strong><br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 19 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3 O P E R A T I O N O F T H E P E R M I T T O W O R K S Y S T E M<br />

This chapter describes in detail the steps required to complete and process a <strong>Permit</strong> <strong>To</strong> <strong>Work</strong> Application<br />

Form .<br />

Note: For Electrical <strong>Permit</strong> applications please refer to BSP-02-Standard-1629 (<strong>Mod</strong>ule 10).<br />

3.1 Completing a Cold <strong>Work</strong>, Hot <strong>Work</strong> and Equipment Disjointing <strong>Permit</strong><br />

For details of the permit forms, reference is made to Appendix 4.<br />

3.1.1 Box 1 - The <strong>Work</strong> Description<br />

The person applying for a permit should be the WSS.<br />

The WSS must complete Box 1 of the permit, entering:<br />

• the work description<br />

• the installation and worksite<br />

• the planned start and finish dates and times for the work<br />

• previous permit number, if applicable<br />

• his name, signature, the date, the BSP dept. or contractor he works for and the BSP contact tel.<br />

no.<br />

• identify in the YES/NO box if electrical isolation is required.<br />

• The number of the appropriate certificate in Box 4 (if applicable) to make the link.<br />

Additionally, on a HOT WORK permit, justification for the hot work must be given and an indication of<br />

whether the task to be performed is hot work on a live production facility.<br />

When Box 1 is complete the WSS attaches any supporting documents, for example certificates on<br />

which he has completed the ‘Application’ section, to the permit.<br />

The WSS must ensure that:<br />

• the installation and work descriptions are clear.<br />

• the work described does not begin until the permit has been approved, accepted and authorised.<br />

NO WORK shall be carried out without the required signatures on the permit.<br />

• there is a WSS for all periods when work is carried out under the permit.<br />

• the permit passes through each stage of the permit process until it is cancelled when the work is<br />

complete, the permit is suspended or re-authorised.<br />

He then submits all copies of the permit and the supporting documents to the Authorised Signatory for<br />

review and approval.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 20 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.1.2 Box 2 - Protective Equipment and <strong>Work</strong>site Supervision, and Task Box<br />

The AS has to ensure that the Task and No Box is completed, and complete Box 2 following discussion<br />

with the WSS. During this discussion he will ensure he understands the work planned and therefore<br />

the protective equipment and level of supervision attention necessary.<br />

Continuous attendance of a WSS is mandatory for all hotwork activities, work must stop when the<br />

supervisor is not at the worksite.<br />

The hazardous area classification must be identified and the AS must ensure that the WSS<br />

understands the significance of the entry.<br />

If there is a need to temporarily re-classify the Area Classification drawing, the area affected<br />

should be highlighted on the drawing and attached to the permit.<br />

3.1.3 Box 3 - Hazard Identification and Special Precautions<br />

Before completing Box 3 the AS must discuss and agree with the WSS the possible hazards and the<br />

special precautions necessary to perform the work safely. PTW Application is to be supported by a<br />

Hazard Checklist, Hazard Identification Plan or both.<br />

The identified relevant controls listed in box 2 in the HCL should be transferred to the <strong>Permit</strong>, and<br />

worksite controls identified in box 10 of the SCL should reviewed by the AS together with the WSS.<br />

In addition the AS should check if there are any other controls identified in Part 5 of the HSE Case that<br />

may be applicable to the work.<br />

The information included in Box 3 must be clear and specific. Entries like ‘Follow HSE Standards’ and<br />

‘Refer to attached’ are not acceptable. The specific standard and the appropriate part of it must be<br />

identified,<br />

In addition, for a HOT WORK permit, the AS enters the precautions necessary to minimise the risk of<br />

fire and the gas testing frequency. Precautions will be indicated by ticks in the ‘Required’ boxes. The<br />

‘Check’ boxes remain blank at this stage.<br />

Standard precautions, e.g. obey platform alarms, need not be included.<br />

If the AS does not require any special precautions to be taken, and there are no potential hazards, he<br />

is to write ‘NONE’ in Box 3.<br />

The AS is responsible for:<br />

• agreeing in principle that the work may take place on the equipment concerned.<br />

• ensuring that the work description is clear, complete and correct.<br />

• agreeing worksite hazards, worksite preparations, control and recovery measures.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 21 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Where there are potential hazards of which the persons undertaking the work might be unaware, work<br />

on adjacent sites, chemical hazards, pressurised equipment adjacent to the worksite, overhead<br />

electrical power lines for example, the Authorised Signatory is to list them in Box 3.<br />

3.1.4 Box 4 - Supporting Documents and Certificates<br />

The AS also completes Box 4. The AS must discuss and agree with the WSS whether additional<br />

supporting documents and/or certificates are required.<br />

The AS ticks the appropriate columns to indicate those required. The AS is to ensure that the WSS<br />

completes the application section of any certificates required but not already attached to the permit.<br />

If electrical isolation is identified in Box 1, the AS must discuss and agree the appropriate electrical<br />

documentation required with the SAEP or AEP who raises and approves the electrical documentation.<br />

The AS is to ensure that the numbers of all certificates are entered in Box 4 and that all necessary<br />

certificates are attached to the permit.<br />

The ‘Initial Checked’ column will be left blank at this stage.<br />

When the Hazard Checklist (or Method Statement / HIP if checklist is not available) is attached to the<br />

permit, the AS is to ensure that he is satisfied with the contents.<br />

It is occasionally necessary to issue more than one permit for work on equipment which has been<br />

isolated, either Electrically or Mechanically, for example to carry out separate maintenance activities<br />

on a pump and motor set where an Isolation / De-isolation Certificate (Electrical) and / or an Isolation<br />

/ De-isolation Certificate (Mechanical) has been issued. In these cases the multiple permits shall be<br />

treated as separate elements of the same task and the additional procedure described in Chapter 4,<br />

para. <strong>4.2</strong> shall be used.<br />

Where there is a requirement to ‘Break the integrity of a system’ an Equipment Disjointing <strong>Permit</strong> is to<br />

be raised prior to the Hot or Cold <strong>Work</strong> <strong>Permit</strong> being approved in Box 5a).<br />

The AS is responsible for ensuring that all necessary preparations such as isolations, depressurising,<br />

purging, cleaning, scaffolding or the provision of special equipment have been identified and included<br />

on the permit and associated certificates.<br />

The Performing Authority (PA) must ensure that the personnel who sign permits on their behalf<br />

are competent to discuss the contents of the permit with the Authorised Signatory. If the Asset<br />

Holder is not satisfied with the performance of a PA, they may replace the PA concerned.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 22 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.1.5 Box 5 - Approval of the <strong>Permit</strong><br />

The term ‘Approval’ means that the information in Boxes 1, 2, 3 and 4 has been checked and accepted<br />

by the AS and that the work is agreed in principle. It does not mean that the work identified in the<br />

‘<strong>Work</strong> Description’ can start.<br />

Preparation of the worksite for the intended work may not start until the permit has the Approval of the<br />

AS at Box 5a. <strong>Work</strong>site preparations may include most items necessary in order to make the site safe<br />

for the intended work, including erection of barriers, valve isolations, sealing of drains, etc. Breaking of<br />

containment and / or the insertion of spades are NOT permitted as worksite preparation without the<br />

issue of an Equipment Disjointing <strong>Permit</strong> (see para. 3.1.2)<br />

The AS indicates the maximum period for which the permit will be valid.<br />

approved for periods longer than is necessary to complete the work.<br />

<strong>Permit</strong>s should not be<br />

- COLD WORK PERMIT ≤ 14 days;<br />

- HOT WORK PERMIT ≤ 7 days:<br />

- EQUIPMENT DISJOINTING PERMIT ≤ 9 days<br />

- DIVING OPERATION PERMIT ≤ 5 days<br />

The AS will refer to the planned work schedule in Box 1 to when setting the validity period.<br />

The AS communicates with any other departments or work groups whose actions may be affected by, or<br />

have an effect on, the proposed work.<br />

If electrical isolation is identified in Box 1 the Responsible Person Electrical (RPE) will also sign in Box 5<br />

to agree the electrical isolation and documentation required.<br />

<strong>To</strong> ensure that all hazards are identified and precautions and mitigations are in place, the AA must<br />

visit the worksite, together with the WSS, to plan the work before authorising the permit.<br />

All 3 copies of the permit are held in the ‘PLANNED’ section of the permit issue point rack until the<br />

permit is required to be authorised by the AA.<br />

3.1.6 Box 5b - Release by Asset Custodian<br />

It may occasionally be necessary for work to be carried out on an asset where the Asset Holder<br />

representative is not an appropriate person to accept responsibility for supervision of the works. This<br />

usually occurs where the works are of a specialist nature, or are outside the competencies of the Asset<br />

Holder. In these circumstances the Asset Holder representative may temporarily release all or part of<br />

the asset to the PA, who then accepts supervisory responsibility for the works as a temporary Asset<br />

Holder. The Asset Holder releases their assets for the work specified by signing box 5b.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 23 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.1.7 Box 5c - Acceptance by Temporary Asset Holder<br />

The temporary Asset Holder signs Box 5c as formal acceptance for the duration of the work. This<br />

agreement is terminated by completion of Box 9 of the permit<br />

3.2 Completing an Equipment Disjointing <strong>Permit</strong><br />

Where there is a requirement to ‘break the containment integrity of a system’, disjoint plant or<br />

equipment, an Equipment Disjointing <strong>Permit</strong> is to be raised prior to the Hot or Cold <strong>Work</strong> <strong>Permit</strong> being<br />

approved in Box 5a.<br />

3.2.1 Box 1 - The <strong>Work</strong> Description of Equipment to be Disjointed<br />

Box 1a - Description and Location of Equipment<br />

The applicant describes accurately the equipment to be disjointed and the exact location. Unique<br />

identification numbers must be quoted when these exist and reference to the associated Hot or Cold<br />

<strong>Work</strong> <strong>Permit</strong> must be included. A site plan may also be attached.<br />

All the information required to enable unique identification must be entered clearly on the permit<br />

including time schedule giving details of planned time and date of commencement and finish.<br />

Box 1b - Description and Location of Disjointing<br />

This box must identify the type of disjointing required (spading, blanking, line removal and blanking, for<br />

example) and its exact location.<br />

A sketch will often be helpful. If provided, it should be identified in this box.<br />

When Boxes 1a and 1b have been completed, the applicant submits all copies of the permit to the<br />

Authorised Signatory for review and approval.<br />

3.2.2 Box 2 - Protective Equipment and <strong>Work</strong>site Supervision<br />

The AS is to complete Box 2. The AS will tick the appropriate boxes to indicate the requirements for<br />

Personal Protective Equipment and other equipment required at the worksite. When a continuous<br />

worksite presence by a representative of the Asset Holder or the WSS is required, this is to be identified.<br />

Where continuous attendance of a WSS or Asset Holder representative is required, work must stop<br />

when that identified supervision is not available at the worksite.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 24 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Where continuous presence is not required the WSS or the Asset Holder is to satisfy themselves that the<br />

worksite is safe, but they may leave the worksite to perform other duties. The WSS must visit the<br />

worksite as frequently as is necessary to ensure that the controls established by the permit are being<br />

complied with. The Asset Holder's representative (normally represented by the AA) should make such<br />

visits to the site, as they considers necessary, depending on the potential hazards associated with the<br />

work.<br />

3.2.3 Box 3 - Hazard Identification and Special Precautions<br />

The AS completes Box 3 indicating the last proven condition of the system, the hazards involved and the<br />

special precautions necessary to control them.<br />

Standard precautions, obey platform alarms for example, need not be included.<br />

Where there are any potential hazards of which the persons undertaking disjointing should be aware,<br />

the AS is to list them in Box 3. This might include the release of high-pressure fluid when the flange is<br />

broken, any special care needed when unbolting, additional protective equipment required and<br />

preparedness for any ensuing spills.<br />

The authorised signatory enters that the EQUIPMENT HAS CONTAINED AT <br />

°C AND BARG.<br />

3.2.4 Box 4– Precaution Taken and Supporting Documents<br />

The AS is to:<br />

• identify and agree the hazards.<br />

• identify in the YES/NO Box controls required.<br />

• identify in the YES/NO Box controls taken.<br />

• tick in the Reqd column certificates required.<br />

• ensure the certificate number is entered on the Equipment Disjointing <strong>Permit</strong>.<br />

• attach associated documents to the Equipment Disjointing <strong>Permit</strong>.<br />

3.2.5 Box 5 - Approval of the <strong>Permit</strong><br />

The AS signs that they agree that worksite preparations for example valve isolations can begin. Their<br />

signature here does not allow the disjointing work to proceed.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 25 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.3 <strong>Work</strong>site Preparations for Cold, Hot and Equipment Disjointing <strong>Permit</strong>s<br />

The next stage in the process is to carry out all preparations required to make the worksite safe for the<br />

work to start. The original copy of the permit, with its supporting documents attached is removed from<br />

the ‘Planned’ section of the permit rack and displayed at the proposed worksite. This stage involves<br />

physical preparations such as providing fire fighting equipment and barriers, and immediately before<br />

hot work or confined space entry commences, gas/oxygen testing.<br />

Whilst worksite preparations are in progress the green and white copies of the permit are kept in the<br />

‘Planned’ section of the permit rack.<br />

3.3.1 Isolations<br />

For a detailed procedure on mechanical and electrical isolations, see Chapter 5.<br />

3.3.2 Recording <strong>Work</strong>site Preparations<br />

When the requirements of each certificate covering worksite preparations are met, the ‘Initial checked’<br />

section in Box 4 on the Hot or Cold <strong>Work</strong> <strong>Permit</strong> is completed by the AA.<br />

For an Equipment Disjointing <strong>Permit</strong>, all ‘YES/NO’ pairs must be completed by the AA.<br />

Where valve isolation or equipment disjointing is required at a location remote from the work, and<br />

under the control of a different Asset Holder, the AA of that area obtains a copy, which may be faxed,<br />

of the Isolation Certificate or Equipment Disjointing <strong>Permit</strong>, certifying that the other relevant isolation<br />

or disjointing is complete. These are kept together with the permit documentation at the permit issue<br />

point. The original of this isolation certificate is retained at the permit issue point controlling the area<br />

where the isolation was carried out.<br />

3.4 Gas Testing Requirements<br />

3.4.1 The Authorised Gas Tester<br />

Authorised Gas Testers (AGT) are appointed as described in Appendix 2. Before and during hot work,<br />

entry to confined spaces or excavations, an AGT must:<br />

• carry out gas tests as specified on the <strong>Permit</strong> or Confined Space Entry certificate, or when<br />

required by permit signatories.<br />

• sign all copies of the permit or certificate after carrying out a test indicating "SAFE" or "UNSAFE",<br />

with name, time and date.<br />

3.<strong>4.2</strong> Box 11a – Initial Gas Testing<br />

An initial gas test shall be carried out in the area affected by the proposed work, IMMEDIATELY prior<br />

to permit acceptance.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 26 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

The AGT carries out gas tests under the direction of the relevant AA, who is responsible for<br />

authorising the permit.<br />

THE GAS TESTER MUST ENSURE THAT HIS INSTRUMENTS ARE VALID, CALIBRATED AND<br />

FUNCTIONING CORRECTLY BEFORE CARRYING OUT THE TESTS.<br />

3.4.3 Procedure if Flammable Gas is Found When Testing for Hot <strong>Work</strong><br />

If gas or other potentially explosive / flammable concentrations are found then the WSS and the AA,<br />

are informed. No source of ignition is to be allowed to enter the affected area.<br />

Both the pink and green copies of the Hot <strong>Work</strong> <strong>Permit</strong> are to be handed back to the Area Authority<br />

who determines the cause and arranges to take whatever action is necessary to make the facility safe.<br />

All copies of the permit are returned to the planned section of its permit rack and repeat gas tests are<br />

performed until the area is considered safe for work.<br />

Only when the Gas Tester and AA are satisfied that the area is safe for hot work, shall permit copies be<br />

removed from the planned section of the permit rack.<br />

<strong>Work</strong> is not to proceed unless the permit has been accepted by the WSS and authorised by the AA.<br />

3.4.4 Box 11b - Record of Additional Gas tests.<br />

The AA must ensure that gas testing is carried out by an Authorised Gas Tester at the frequency<br />

stated on the permit and that these tests are recorded in Box 11b of the worksite copy of the Hot <strong>Work</strong><br />

<strong>Permit</strong>. Gas tests are to be carried out after each break and whenever the worksite is unattended for<br />

over 1 hour and as required by Box 3.<br />

If the gas tests are not carried out in accordance with the requirements of Boxes 3, 11a and 11b of the<br />

Hot <strong>Work</strong> <strong>Permit</strong> the WSS is to suspend all work and return the permit to the AA.<br />

If gas testing indicates it is not safe to work, the Authorised Gas Tester must IMMEDIATELY instruct<br />

the WSS to stop work, tick the ‘UNSAFE’ box and enter the time and result of the test and return the<br />

permit to the AA so that the permit can be suspended.<br />

If a hazardous atmosphere is found at any time the permit must be suspended as described in para.<br />

3.1.11.<br />

Further space for recording gas test results is provided on the reverse side of the worksite copy of the<br />

Hot <strong>Work</strong> <strong>Permit</strong>.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 27 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.4.5 Initial Gas/Oxygen Testing for Confined Space Entry<br />

Refer to BSP-02-Standard-1645 (<strong>Mod</strong>ule 07).<br />

When the permit includes confined space entry the work area is to be tested to ensure that it is free<br />

from flammable/toxic vapours, and is within required limits for oxygen concentration, IMMEDIATELY<br />

prior to acceptance of the permit.<br />

If oxygen deficiency or unacceptable concentrations of other hazardous gases are found, the AA and<br />

the WSS of the team due to enter the confined space must be informed.<br />

Both pink, blue and green copies of the work permit, including certificates, will be handed back to the<br />

AA who must take the necessary action to make the facility safe for the proposed entry.<br />

All permit documentation will be returned to the planned section of the permit rack and repeat gas<br />

tests taken until the confined space is safe for entry.<br />

When the Gas Tester and AA are satisfied the confined space is safe for entry, both the pink, blue and<br />

green copies of the work permit, including certificates, are to be removed from the planned section of<br />

the permit rack.<br />

The Authorised Gas Tester will enter the result in Box 3 of the Confined Space Entry certificate, with<br />

the time of the test and their signature.<br />

The permit must be accepted by the WSS and authorised by the AA before personnel can enter the<br />

confined space.<br />

If the gas tests are not carried out in accordance with the requirements of Box 3 of the Confined Space<br />

Entry certificate, the WSS must suspend all work and return the permit to the AA.<br />

3.4.6 Gas Tests<br />

Additional gas test records and re-validation for confined space entry must be recorded on the reverse<br />

side of a Confined Space Entry certificate.<br />

If flammable or toxic gases or oxygen outside the prescribed limits are found at any stage, the <strong>Permit</strong><br />

and Confined Space Entry certificate must be SUSPENDED (refer to operational <strong>Mod</strong>ule 07, Confined<br />

Space Entry).<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 28 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.5 Acceptance and Authorisation of Cold, Hot and Equipment Disjointing <strong>Permit</strong>s<br />

3.5.1 Box 6 - Acceptance by the <strong>Work</strong>site Supervisor<br />

By accepting the permit, the WSS confirms that:<br />

• they fully understands the work and all worksite controls given on the Hazard Check List are in<br />

place, signed off and worksite controls understood;<br />

• everyone engaged in the work (including shift / crew changes) is fully briefed about the work and<br />

precautions necessary.<br />

• all precautions, including those on any associated certificates, will be observed.<br />

• gas testing (as requested) has been completed in Box 11a<br />

• the permit is displayed at the worksite whenever work is in progress.<br />

• no work takes place unless the permit is authorised for that working period by the Area<br />

Authority.<br />

• the worksite and equipment affected by the work have been left in a safe condition at each shift<br />

change. On completion or suspension of work, he will sign Box 8c of the permit to confirm this.<br />

• they will stop work if the gas test required in Box 3 of the Hot <strong>Work</strong> <strong>Permit</strong> and/or the Confined<br />

Space Entry certificate are not carried out.<br />

• They will return the permit and any associated certificates are returned to the permit issue point<br />

whenever work stops for more than 4 hours and inform the AA of his action.<br />

The WSS is to be at the worksite at all times.<br />

By signing Box 6 in the presence of the AA, the WSS accepts responsibility to maintain the worksite in<br />

a safe condition during the proposed work.<br />

The WSS must not sign the permit acceptance unless he is satisfied that the worksite is safe.<br />

3.5.2 Box 7 - Authorisation by Area Authority (Hot/Cold <strong>Work</strong> and Equipment Disjointing <strong>Permit</strong>)<br />

For onshore work under the control of departments other than those in the operations function, the<br />

AA will be provided by the department carrying out the activity.<br />

Where the AA is provided by the department responsible for executing the work, Boxes 5b and 5c will<br />

be completed to transfer the asset temporarily to that department.<br />

Prior to Authorisaton of the permit the AA must visit the proposed worksite, together with the WSS to<br />

verify that:<br />

• all the controls and instructions listed on the permit have been carried out to his complete<br />

satisfaction.<br />

• all disjointing permits and valve isolations are in place and holding.<br />

• all certificates and isolation tags are attached to the appropriate copies of the permit and have<br />

been completed correctly. They initial the ‘Check’ column on the work permit in Box 4 to indicate<br />

this.<br />

• no other hazards have become evident or further precautions needed. If so they must amend the<br />

conditions on the permit or delay authorisation until the additional hazards have been controlled.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 29 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

• any required gas testing has been carried out with satisfactory results, and has been recorded in<br />

Box 11a of the Hot <strong>Work</strong> <strong>Permit</strong> and, if required, on the Confined Space Entry certificate.<br />

A WORKSITE SUPERVISOR MAY NOT SELF AUTHORISE A PERMIT - IT MUST BE AUTHORISED<br />

BY AN INDEPENDENT AREA AUTHORITY i.e. BOXES 6 AND 7 MUST BE SIGNED BY DIFFERENT<br />

PERSONS.<br />

Once the AA is satisfied that the worksite is safe for the work to commence AFTER formal acceptance<br />

by the WSS, they will complete Box 7 of the permit and specify the period for which the first<br />

authorisation is valid. This period must be no longer than 12 hours.<br />

NO WORK MAY TAKE PLACE UNDER THE PERMIT UNTIL IT HAS BEEN ACCEPTED BY THE<br />

WORKSITE SUPERVISOR AND AUTHORISED BY THE AREA AUTHORITY.<br />

3.5.3 Actions After Authorisation<br />

When the permit has been signed by both the AA and the WSS the top worksite copy is handed to the<br />

WSS together with the worksite copy of any associated certificates and the accompanied Hazard<br />

Checklist. The WSS is responsible for ensuring a proper TBT (see Section 3.11) will be held and the 3-<br />

whats (see Appendix 12) risk assessment will be carried out. The WSS has to ensure that the permit is<br />

displayed in a permit holder, at a prominent, safe position at the worksite. It remains there whilst<br />

work is being carried out.<br />

NO WORK IS TO BE CARRIED OUT UNLESS AN AUTHORISED PERMIT IS CLEARLY DISPLAYED<br />

AT THE WORKSITE.<br />

The remaining copies of the permit, any accompanied documents and any associated certificates, will<br />

be placed in the AUTHORISED section of the permit rack, at the permit issue point (PIP).<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 30 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.6 Box 8 - <strong>Permit</strong> Re-Authorisation<br />

3.6.1 Box 8a - <strong>Permit</strong> Re-accepted, Re-Authorisation<br />

When PTW’s are handed over to oncoming WSS & AS eg. at shift changes, the permit responsibilities<br />

are transferred to the oncoming WSS & AS who MUST sign as the respective new WSS & AA.<br />

AS accept responsibility for all the permits at their formal shift change handover.<br />

Box 8a - Acceptance by <strong>Work</strong>site Supervisor (Hot and Cold <strong>Work</strong> <strong>Permit</strong>s)<br />

The oncoming ( eg. after shift change, crew change, etc) WSS will satisfy themselves that the worksite<br />

is safe and that all safety controls stated on the permit are in place before signing to accept the permit.<br />

The WSS acceptance signature will be provided on both the worksite and permit rack copies of the<br />

permit.<br />

The WSS will display the worksite copy in a permit holder at a prominent place at the worksite. The<br />

permit rack copy will be placed in the AUTHORISED section of the permit rack.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 31 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.6.2 Box 8b - Re-Authorisation by Asset Holder (Hot and Cold <strong>Work</strong> <strong>Permit</strong>s)<br />

At the start of each new shift, an AA must re-authorise any permits required for that shift. He will do<br />

this by signing Box 8b of the PINK/BLUE and GREEN copies of the permit.<br />

The AA will specify in Box 8b of the permit form the period for which the re-authorisation is valid.<br />

This period must be no longer than 12 hours, or the end of the shift worked by the AA, whichever is<br />

the sooner.<br />

Before signing the permit to re-authorise it the AA is to carry out an inspection of the worksite.<br />

3.7 <strong>Permit</strong> Suspension<br />

A permit must be suspended if :<br />

• an unsafe condition develops which requires that the work is stopped (e.g. gas/oil leak, platform<br />

alarm occurs, reportable incident occurs, etc).<br />

• the work is delayed or interrupted for more that 4 hours.<br />

• the authorisation period expires.<br />

• the work needs to be stopped to allow conflicting work of a higher priority to proceed.<br />

• the gas test confirms that it is not safe to work<br />

• the asset holder intervenes to interrupt work or withdraw a permit before completion.<br />

• For testing of electrical equipment.<br />

Suspension of work must always be carried out in accordance with the procedure outlined below.<br />

Verbal communication is not acceptable except in the event of an emergency.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 32 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.7.1 Box 8c - <strong>Permit</strong> Suspension<br />

<strong>To</strong> suspend a permit the WSS takes the following actions:<br />

• check that the worksite and equipment affected by the work have been left in a safe condition.<br />

• take the permit to the permit issue point for retention until work is to re-start.<br />

• sign Box 8c of the PINK/BLUE and GREEN copies of the permit to confirm that work has been<br />

suspended.<br />

In areas where it is not possible to return the worksite copy of the permit to the permit issue point, the<br />

WSS is to sign Box 8c of the PINK/BLUE copy only. The WSS will place this in a secure location and<br />

notify the permit issue point by fax or radio that the work has been suspended and where he has left<br />

the permit.<br />

All copies of the permit together with associated certificates are to be placed in the SUSPENDED<br />

section of the permit rack.<br />

If work is to be suspended beyond the permit validity period given by the AS in box 5a, the permit<br />

must be cancelled. When a permit is SUSPENDED, no work covered by the permit may be carried out<br />

until it has been re-authorised. <strong>Work</strong>site and permit issue point copies of all suspended permits are to<br />

be retained in the permit rack by the Asset Holder.<br />

3.8 Remarks Box<br />

A remarks box is provided on the reverse of the worksite copy of the Hot and Cold <strong>Work</strong> <strong>Permit</strong>s. This<br />

may be used by the WSS to record the state of work on the completion of a working period for use by<br />

themselves and the AA.<br />

3.9 <strong>Permit</strong> Cancellation<br />

A permit is cancelled when any of the following conditions are satisfied:<br />

• the work is complete.<br />

• the work is to be suspended, and it is known that work will not re-start until a date outside the<br />

permit validity period.<br />

• the permit has reached the end of its validity period given for the work.<br />

• the content of the work is found to be different from that covered by the work description at Box 1,<br />

when a new permit will be raised.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 33 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.9.1 Box 9 - <strong>Permit</strong> Cancellation - <strong>Work</strong> Complete (Hot, Cold and Equipment Disjointing <strong>Permit</strong>)<br />

BOX 9a. PERMIT RETURN BY WORKSITE SUPERVISOR<br />

Box 9a of the WORKSITE and PIP copies of the permit will be signed by the WSS.<br />

It is their responsibility to ensure that:<br />

• the work has been properly performed and is complete.<br />

• the worksite, and the equipment affected by the work, have been left in a clean and safe condition,<br />

with all tools and equipment removed.<br />

When this box has been signed no further work may take place under the permit.<br />

BOX 9b. PERMIT CANCELLATION BY AREA AUTHORITY<br />

The AA shall satisfy to themselves that the work is complete through inspection of the worksite prior<br />

to completing / signing Box 9b of the WORKSITE and PIP copies of the permit, indicating either that<br />

he accepts that the work is:<br />

• confirm and that the equipment and worksite have been restored to normal and that all relevant<br />

isolation certificates have been signed off to confirm that all isolations have been removed.<br />

Or<br />

• complete, the equipment and worksite have been left in a safe condition but that the isolations<br />

have been retained. The AA must then enter the number of the relevant isolation certificate in Box<br />

9b.<br />

Note : when multiple permits have been issued under single electrical and / or mechanical isolations<br />

in accordance with the procedure at Section 4, para. <strong>4.2</strong>, the isolations must be retained until all the<br />

permits associated with the Isolation / De-isolation Certificates have been cancelled.<br />

3.9.2 Box 10 - <strong>Permit</strong> Cancellation - <strong>Work</strong> Not Complete (Hot Cold and Equipment Disjointing<br />

<strong>Permit</strong>)<br />

10a -<br />

PERMIT RETURN BY WORKSITE SUPERVISOR<br />

Hot and Cold <strong>Work</strong> <strong>Permit</strong>s<br />

The WSS must sign Box 10a of the WORKSITE and PIP copies of the Hot or Cold <strong>Work</strong> <strong>Permit</strong> to<br />

indicate that the work has halted, but is not complete, and that the worksite has been left in a safe<br />

condition with all tools and equipment removed.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 34 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

10b - PERMIT CANCELLATION BY AREA AUTHORITY FOR HOT & COLD WORK PERMITS<br />

When satisfied that the worksite has been left in a safe condition, and having verified this by<br />

inspection, the Area Authority is to enter in Box 10b the number of any subsequent permit or Isolation<br />

or EPI, delete the inappropriate statement and sign the WORKSITE and PIP copies of the Hot or Cold<br />

<strong>Work</strong> <strong>Permit</strong>.<br />

3.10 Completing a Diving Operations <strong>Permit</strong><br />

3.10.1 Box 1 - Application and Description of the <strong>Work</strong><br />

For a Diving <strong>Permit</strong> the Performing Authority (PA) may be either the CSR or the Diving Supervisor<br />

provided they have completed the appropriate courses PTW 2, 3 and 4 and been appointed.<br />

Prior to applying for the Diving Operations <strong>Permit</strong> the scope of the work has to be discussed and<br />

agreed between the Diving Supervisor or Company Site Representative (CSR) and the Operations<br />

Supervisor (FOS, COS or SOS).<br />

The Performing Authority (PA)<br />

The Diving Supervisor or CSR where appropriate applies for the permit. They complete the first two<br />

sections and submit the permit to the AS responsible for the area in which the diving and/or ROV<br />

work will take place. This should be done by fax for standard operation or in person for non-standard<br />

operation.<br />

If the application is by fax the AS will accept the faxed application by raising a new diving permit (from<br />

the details on the fax). They will cross-reference the new Diving <strong>Permit</strong> with the faxed application by<br />

entering the faxed number in Box 1 of the permit.<br />

1. APPLICATION by Performing Authority (Diving Supervisor or CSR)<br />

FOR THE ATTENTION OF:<br />

LOCATION<br />

Planned Time Date<br />

Continued from Fax<br />

<strong>Work</strong><br />

Start<br />

<strong>Permit</strong> No :<br />

___________________________<br />

Schedule<br />

Finish<br />

___________________________<br />

DSV Tel No: ________________________ DSV Fax No:______________________<br />

Supv/CSR Name:_______________Signature:_________________Date:____________Time:____________Ind:________<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 35 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.10.2 Box 2 - Description of the <strong>Work</strong><br />

The Applicant must specify the type of diving operations to be carried out. There are two types of<br />

diving operations, Routine and Non-Routine.<br />

“Routine Diving Operations” covers Underwater Inspection (DUI) using a ROV and/or diving personnel.<br />

Leak investigation using ROVs (but not divers in the water) is also considered a routine operation.<br />

Examples of Standard Diving Operations:<br />

• Structural Integrity Survey<br />

• Investigation on sub-sea pipeline for leaks by ROV<br />

“Non Routine Diving Operations” cover all other diving activities. For such activities the CSR or<br />

Diving Supervisor must discuss with the AS the work proposed and agrees the controls necessary in<br />

order to complete the Diving <strong>Permit</strong>. Diving <strong>Permit</strong>s do not only authorise divers to dive, but also carry<br />

out the activities described in Box 2 of the permit. Hot or Cold <strong>Work</strong> permits to perform work<br />

underwater are not required as they are covered by the Diving <strong>Permit</strong> but an EDP may be necessary in<br />

the event of mechanical isolation.<br />

Examples of Non Routine Diving Operations:<br />

• Underwater Construction <strong>Work</strong><br />

• Anode replacement<br />

• High pressure water jetting<br />

• Pipeline and riser repairs<br />

• High Voltage Cable surveys or replacement<br />

• Underwater inspection of Vent Jackets or Damaged structures<br />

• Diving near to Flares<br />

Note that: Some tasks may start as routine diving activities and then become non routine. E.g. Leak<br />

Investigation is initially a routine diving operation, but once a leak is verified and located then the leak<br />

repair will become a non-routine diving operation. In this case an EDP may be required in addition to<br />

the Diving <strong>Permit</strong>.<br />

2. DESCRIPTION OF WORK ROUTINE NON ROUTINE<br />

Is Electrical isolation Required Yes No<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 36 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.10.3 Box 3 - Safety Precautions during Diving Activities<br />

The AS, following discussions with the CSR/Diving Supervisor, identifies in Box 3 all safety controls<br />

required during the diving work. The AS ticks in the appropriate column to identify mechanical or<br />

electrical isolations required and/or other supporting documents. The AA initials ‘Initial Checked’<br />

column is to be left blank at this stage.<br />

If the application is by fax, and an Isolation/De-isolation Certificate (Electrical) is required, then the<br />

RPE who will ensure the electrical isolation is made will complete the application section of the<br />

Isolation/De-isolation Certificate (Electrical). The procedure is described in Section <strong>4.2</strong>.3.<br />

3. SAFETY PRECAUTIONS DURING DIVING ACTIVITIES (BSP-71.3.1.3.206.1)<br />

ACTIONS PRIOR TO DIVING OPERATIONS:<br />

1. Confirm requirements of BSP-71.3.1.3.206.1 are fully complied with.<br />

2. Sump to be cleared of all chemical waste prior to the start of operations<br />

and then cleared daily prior to re-validation of this permit.<br />

3. DIVERS DOWN boards to be placed at all access points to the platform<br />

(Main manned Complex only).<br />

4. No additional permit to be issued on the diving complex during diving<br />

operations, without discussion between C.S.R and Authorised Signatory.<br />

5. STL to be informed that no. boats are to approach within 500 metres of the<br />

diving operations without requesting permission from the diving C.S.R on<br />

VHF Ch. 15.<br />

6. The following isolations will be required:<br />

SUPPORTING DOCUMENTS ATTACHED<br />

Certificates √ Number<br />

Isolation<br />

Mechanical<br />

Isolation Electrical<br />

EDP<br />

SCL<br />

Area<br />

Authority,<br />

initial<br />

checked<br />

If the application is by fax and mechanical isolation is required, the AS will complete the application<br />

section of the Isolation/De-isolation Certificate (Mechanical). The procedure as described in <strong>4.2</strong>.2<br />

should be used.<br />

Where there are any potential hazards or special controls as discussed and agreed with the<br />

CSR/Diving Supervisor, the AS is to list them in Box 4.<br />

4. HAZARD IDENTIFICATION AND SPECIAL PRECAUTIONS<br />

3.10.4 Box 5 - Approval of the <strong>Permit</strong><br />

The permit requires the APPROVAL of the AS in Box 5 before worksite preparations can proceed.<br />

The term ‘Approval’ means the information in Boxes 1, 2, 3 and 4 has been checked and accepted by<br />

the AS. It does not mean that work can proceed.<br />

When satisfied with the work description and precautions, the AS signs Box 5 to approve the work and<br />

to indicate the period for which the diving work is valid.<br />

If the application is by fax, the AS is to attach the fax to the permit and all copies of the permit are to<br />

be held in the PLANNED section of the permit rack during worksite preparation until the Area<br />

Authority authorises the permit.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 37 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

5. APPROVAL by Asset Holder Authorised Signatory<br />

I have examined the <strong>Work</strong> Description, Preparations and Precautions stated above, I agree they are correct. This <strong>Permit</strong>,<br />

when properly authorised and accepted at Boxes 6 and 7 below, will be valid for a MAXIMUM of 5 DAYS. <strong>Work</strong>site<br />

Preparations and Isolations may now proceed.<br />

Name: ___________________________ Signature: ________________<br />

RPE IF ELECTRICAL WORK REQUIRED<br />

From Time: _________________________ on Date: _________________<br />

<strong>To</strong> Time: ___________________________ on Date: _________________<br />

Name: ________________________ Ind: _____________ Signature: _______________Time: ___________ Date:<br />

__________<br />

TO BE REAUTHORISED EVERY<br />

12 24<br />

HOURS (DELETE AS APPLICABLE)<br />

3.10.5 Box - 6 Authorisation of the <strong>Permit</strong><br />

THE MAXIMUM PERIOD FOR WHICH A DIVING PERMIT CAN BE USED WITHOUT RE-<br />

AUTHORISATION IS 24 HRS.<br />

Before authorisation is given for diving and/or ROV work to begin the AA must ensure that:<br />

• all of the controls and instructions listed on the permit have been completed to their<br />

COMPLETE SATISFACTION. The AA must initial the column on the Diving <strong>Permit</strong> in Box 3 to<br />

indicate that the isolations required have been carried out.<br />

• the Isolation/De-isolation certificates are attached and correct.<br />

• no other hazards have become evident or further precautions need to be taken.<br />

If additional hazards have been identified or further controls need to be made, the AA is to amend<br />

the conditions on the permit or delay authorisation until the additional hazards have been removed.<br />

The responsible AA must check the permit rack to ensure that no work is planned or underway that<br />

may conflict with the Diving <strong>Permit</strong> about to be authorised.<br />

When the AA is completely satisfied that all preparations have been made, the AA complete Box 6 of<br />

the permit authorising the diving and/or ROV operation to commence and specifies the period for<br />

which the first authorisation is valid.<br />

The Diving Operation <strong>Permit</strong> initial authorisation period is for 12 or 24 hours as agreed by the CSR<br />

/Diving Supervisor and the AA.<br />

If the application is by fax, the AA is to fax the Diving <strong>Permit</strong> and other associated documents<br />

including the Isolation/De-isolation certificates, if required, back to the applicant, and place all<br />

copies in the applicable live section (Planned, Authorised or Suspended) of the permit rack.<br />

6. AUTHORISATION BY Area Authority<br />

I certify that all isolations and depressurisation and actions necessary for Diving Operations to commence have been carried out. I<br />

authorise the work as described to be carried out subject to the above safety precautions. I will inform the diving vessel C.S.R<br />

immediately should it be necessary to deviate from or it becomes impossible to comply with, any of the safety precautions listed on this<br />

permit.<br />

Name: ________________________ Ind: _____________ Signature: _______________Time: ___________ Date: __________<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 38 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.10.6 Box 7 - Declaration and Acceptance by CSR/Diving Supervisor<br />

The CSR/ Diving Supervisor is to sign Box 7 on the permit formally accepting and agreeing to the<br />

conditions.<br />

By signing the permit the CSR/ Diving Supervisor agrees that they:<br />

• fully understand the work and the controls in place.<br />

• has ensured that everyone engaged in the work is fully briefed on the work and the controls<br />

necessary.<br />

• has ensured that no work takes place unless the permit is authorised for that working period by<br />

the AA.<br />

• has ensured that the worksite, and equipment affected by the work, will be left in a safe condition<br />

at each shift or crew change and on the completion of the work.<br />

When the CSR/Diving Supervisor has signed the declaration in Box 7, the Diving and/or ROV<br />

Supervisor may commence diving and/or ROV operations.<br />

7. DECLARATIONS AND ACCEPTANCE by Diving Supervisor/CSR<br />

I understand and declare that work will only take place when all of the above safety precautions are complied with. I understand that<br />

this <strong>Permit</strong> only applies for underwater work and must then be re-authorised as indicated in box 5.<br />

Name: ________________________ Ind: _____________ Signature: _______________Time: ___________ Date: __________<br />

3.10.7 Box 8 - Re-Authorisation<br />

Box 8 includes a section for verbal logging of communication with the relevant Asset Control Room,<br />

detailing the role of the person giving authority for re-authorisation of the permit that has been reauthorised<br />

at the work site by the CSR.<br />

Where necessary the permit may be re-authorised by the Area Authority for no more than 5 further<br />

periods.<br />

If the application is by fax, the CSR/ Diving Supervisor will request permit re-authorisation by first<br />

suspending the Diving and/or ROV <strong>Permit</strong> in Box 8c on page 2 of the permit (checking first that the<br />

permit numbers on pages 1 and 2 match). The CSR/ Diving Supervisor will then make a verbal<br />

request for re-authorisation and fax the permit back to the appropriate AA.<br />

The AA is to remove the original from the live section of the permit rack, re-authorise it by signing Box<br />

8b, fax the re-authorised permit back to the CSR/ Diving Supervisor and attach the requested<br />

suspended version to the other copies and replace them in the live section of the permit rack.<br />

On receipt of the re-authorised permit the CSR/ Diving Supervisor is to sign to accept the reauthorisation<br />

in Box 8a and the diving and/or ROV operation may continue.<br />

The re-authorisation process may be carried out by the CSR (provided they did not sign as WSS) in<br />

Box 7.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 39 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

If there is a shift or crew change of the CSR/ Diving Supervisor during the permit authorisation<br />

period, the hand-over is to be signed in the additional specimen signature box.<br />

8. RE-AUTHORISATION Continued from Fax <strong>Permit</strong> No:<br />

a. ACCEPTANCE BY Diving Supervisor/CSR b. RE-AUTHORISATION BY AREA AUTHORITY c. RE-AUTHORISATION BY CSR<br />

<strong>To</strong> be signed by the oncoming Diving CSR or Diving Supervisor<br />

whenever the <strong>Permit</strong> is re-authorised and whenever<br />

responsibility passes from one CSR or Diving Supervisor to<br />

another.<br />

ADDITIONAL DIVING CSR/DWSS<br />

Specimen Signature<br />

Re-authorisation by CSR (on behalf of the AA) is<br />

permitted subject to logged verbal communication with<br />

the asset that operations may proceed<br />

ADDITIONAL AREA AUTHORITY<br />

Specimen Signature<br />

Record of logged verbal<br />

communication with the asset control<br />

room. Record name of person spoken<br />

to on asset<br />

1) Name: ……………………………. Signature: …………………<br />

2) Name: ……………………………. Signature: …………………<br />

1) Name: ……………………………. Signature: …………………<br />

2) Name: ……………………………. Signature: …………………<br />

Name<br />

(AS/AA)<br />

Date/Time<br />

CSR Initial<br />

3) Name: ……………………………. Signature: …………………<br />

3) Name: ……………………………. Signature: …………………<br />

4) Name: ……………………………. Signature: …………………<br />

I have inspected the worksite and am satisfied that it is safe to<br />

continue work. I will ensure that the <strong>Permit</strong> conditions and<br />

controls are complied with.<br />

4) Name: ……………………………. Signature: …………………<br />

I am satisfied that it is safe for the work specified. I reauthorise<br />

the <strong>Permit</strong> for the period stated, provided the controls<br />

established by the <strong>Permit</strong> are complied with.<br />

WORK SUPERVISION<br />

<strong>To</strong> be signed below by the off going Diving<br />

C.S.R whenever work stops for more than<br />

4 hours, or when supervisory responsibility<br />

changes<br />

I have inspected the worksite. It has been<br />

left in a clear and safe condition.<br />

NAME<br />

DEPT<br />

RESPONSIBLE<br />

FROM<br />

SIGNATURE<br />

VALID FROM VALID UNTIL SIGNATURE TIME DATE<br />

SIGNATURE<br />

TIME<br />

DATE<br />

TIME DATE TIME DATE<br />

3.10.8 Boxes 9 and 10 - <strong>Permit</strong> Cancellation<br />

When the diving and/or ROV work is complete or not complete the appropriate section of the permit is<br />

to be signed by the CSR/ Diving Supervisor.<br />

The cancelled permit is then to be delivered or faxed to the AA for final cancellation.<br />

9. PERMIT CANCELLATION-WORK COMPLETE 10. PERMIT CANCELLATION-WORK NOT COMPLETE<br />

a) PERMIT RETURN BY Diving Supervisor/CSR b) PERMIT RETURN BY Diving Supervisor/CSR<br />

I declare that the underwater work described above has been completed all underwater<br />

equipment/rigging has been recovered and the site has been left in a safe and<br />

undamaged condition. This has been verified by ROV/Diver inspection.<br />

I declare that the underwater work described above is not completed all underwater<br />

equipment/rigging has been recovered and the site has been left in a safe and<br />

undamaged condition. This has been verified by ROV/Diver inspection.<br />

Name: ……………………………………………………… Time: …………………………..<br />

Name: ……………………………………………………… Time: …………………………..<br />

Signature: ………………………………………………….. Date: …………………………..<br />

Signature: ………………………………………………….. Date: …………………………..<br />

b) PERMIT CANCELLATION BY AREA AUTHORITY b) PERMIT CANCELLATION BY AREA AUTHORITY<br />

<strong>Work</strong> complete. <strong>Work</strong>site Clear and Safe.<br />

<strong>Work</strong> complete. <strong>Work</strong>site Clear and Safe.<br />

Delete as appropriate.<br />

Delete as appropriate.<br />

* Re-instatements/De-Isolations Complete.<br />

* <strong>Work</strong> continuing on <strong>Permit</strong> No: ……………………………………………………………..<br />

* Isolations retained under Cert. No (s) ……………………………………………………..<br />

* Isolations retained under Cert No(s): ………………………………………………………<br />

Name: ………………………………… Ind: ……………………….. Time: …………………<br />

Name: ………………………………… Ind: ……………………….. Time: …………………<br />

Signature: …………………………………………… Date: …………………………………..<br />

Signature: …………………………………………… Date: …………………………………..<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 40 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3.11 Briefing of the <strong>Work</strong>force - "<strong>To</strong>olbox Talk (TBT)"<br />

Safe working requires that both the worksite, and those who will work there have been properly<br />

prepared. Before work starts, the WSS must ensure that those involved with the work are fully aware<br />

of the work content, the potential hazards and the controls in place to prevent their release and their<br />

own responsibilities. This will be done by delivering a <strong>To</strong>olbox Talk at the worksite.<br />

<strong>To</strong>olbox talks are mandatory for all work. The WSS is to keep written records of toolbox talks<br />

consisting of the date, time, location, permit number for the work, those present and the items<br />

discussed. For more information see BSP-02-Guideline-020 - <strong>To</strong>olbox Talks Best Practices.<br />

<strong>To</strong>pics normally covered in a <strong>To</strong>olbox Talk are:<br />

General <strong>Work</strong>site Requirements<br />

• outline of activities of others in the area and any resulting hazard(s)<br />

• occasional reminder of access and escape routes, mustering instructions, ESD’s, kill knobs<br />

Specific <strong>Work</strong>site Requirements<br />

• objective of the job, targets to be achieved<br />

• permit requirements, precautions, worksite preparations, isolations, gas tests and specific<br />

controls identified on the Hazard Check List<br />

• plan and methods, (equipment and tools) including review of Method Statement or HIP/JSA<br />

• discussion of specific hazards and their controls and recovery measures, encourage open<br />

discussion and questions from the team<br />

• agreement of individual roles and responsibilities<br />

• asking open ended questions (what, who, when, why, where, how) to ensure understanding<br />

• any HSE newsflash or incident relevant to the task<br />

The WSS will use the 3-whats (Appendix 12) concept for a risk assessment as part of the TBT, and is<br />

meant to be carried out before starting any job.<br />

3.12 Supervision of the <strong>Work</strong>site<br />

Throughout the work the WSS remains responsible for ensuring that the controls on the permit are<br />

complied with.<br />

Continuous attendance by the WSS at the worksite is required, to ensure that the controls established<br />

by the permit are being maintained. The work must stop when the WSS is not at the worksite. The AA<br />

should make such visits to the site as they considered necessary depending on the potential hazards<br />

associated with the work and depending on the output of the weekly cumulative risk assessment.<br />

When gas testing is required during the course of the work, the AA is to ensure that the Gas Tester is<br />

fully briefed on the work content and controls in place. The Authorised Gas Tester (AGT) has been<br />

appointed by the Asset Holder to carry out gas testing ensure that the controls of the permit are<br />

complied with at all times.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 41 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

4 C E R T I F I C A T E S A N D H A Z A R D C H E C K L I S T<br />

4.1 PTW Certificates<br />

Certificates are attached to the <strong>Permit</strong> to <strong>Work</strong> together with the Hazard Check List and other<br />

necessary documents to obtain permission from the AS for preparation(s) required in order to carry<br />

out the work described in Box 1 of the permit e.g. Mechanical/Electrical Isolation/Confined Space<br />

Entry/Hot <strong>Work</strong> on Live Production Facility.<br />

The certificate is NOT a permit to work and cannot be used without the permit.<br />

The certificates used in the PTW system are listed in Appendix 4.<br />

The colours of certificate copies are:<br />

<strong>Work</strong>site - Yellow<br />

<strong>Permit</strong> Issue Point - Green<br />

Note: An Electrical Isolation Certificate has a white copy that is retained by the SAEP/AEP when<br />

electrical isolations are made.<br />

<strong>4.2</strong> Use of Certificates<br />

<strong>4.2</strong>.1 Multiple <strong>Work</strong> <strong>Permit</strong>s issued Under a Single Isolation Certificate<br />

It may be necessary to issue more than one permit for work on equipment that has been isolated<br />

either Electrically or Mechanically, for example to carry out separate maintenance work on a pump<br />

and motor set where an Isolation/De-isolation Certificate (Electrical) and/or an Isolation/De-isolation<br />

Certificate (Mechanical) has been issued. In these cases all permits shall be considered as part of the<br />

same work. The following procedure shall be complied with:<br />

1. The initial isolations shall be applied for, carried out and a padlock and electrical caution tag<br />

shall be applied at points of electrical isolation and chain and valve or spade isolation tags<br />

applied at the point of mechanical isolation, and the Isolation/De-isolation Certificates and<br />

<strong>Permit</strong> shall be issued as appropriate. Refer to Section 3 of this document and Sections 3.5 and<br />

8.9 of BSP-02-Standard-1629 (<strong>Mod</strong>ule 10) - Electrical Safety Rules.<br />

2. Before the issue of a second or subsequent permit, a second padlock and electrical caution tag<br />

and/or mechanical isolation tag shall be fixed at the points of isolation made for the first permit.<br />

Every permit issued under the authority of an Isolation/De-isolation Certificate shall be<br />

represented at a point of isolation by electrical isolation padlocks and caution tags and/or the<br />

mechanical isolation tags, as appropriate. Where it is not possible to apply a second padlock, a<br />

multiple hasp or other similar device shall be used.<br />

3. The second or subsequent permits are given the same number as that in the task box of the<br />

initial permit. The PIP copy of the Isolation/De-isolation Certificate(s) shall be given the numbers<br />

of all additional permits issued together with copies of all permits attached to the Isolation/Deisolation<br />

Certificate(s) and inserted together into the same slot in the PIP as the original permit.<br />

4. On completion of each individual permit in Box 9a, the electrical isolation padlock and caution<br />

tag and/or chain and mechanical isolation tag associated with the task shall be removed from the<br />

points of isolation and the related permit detached from the PIP copy of the Isolation/De-isolation<br />

Certificates.<br />

5. The physical electrical and/or mechanical isolations shall not be removed until all permits<br />

associated with the relevant Isolation/De-isolation Certificate have been returned to the PIP,<br />

cancelled in Box 9a and removed from attachment to the relevant certificates.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 42 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

<strong>4.2</strong>.2 Isolation / De-Isolation Certificate (Mechanical)<br />

The Isolation/De-Isolation Certificate (M) is used when any valve or spade isolation is required by the<br />

permit. (Refer to Appendix 4, Figure 7).<br />

BOX 1 - APPLICATION<br />

The WSS completes Box 1 of the Isolation/De-Isolation Certificate (M) entering:<br />

• their name, their contractor/dept., their signature and date of application.<br />

• the installation<br />

• worksite<br />

• equipment to be isolated.<br />

• the number of the originating work permit.<br />

• the number of the Equipment Disjointing <strong>Permit</strong> if applicable.<br />

The box marked‚ “<strong>Work</strong> continuing on permit no.” is to be used when a permit validity period has<br />

expired but work is not complete. The certificate can then be transferred to a new permit and the new<br />

permit number entered in the box.<br />

BOX 2 - REASONS FOR ISOLATION<br />

The WSS is to enter the reason for an isolation being required.<br />

The <strong>Permit</strong> and the Isolation/De-isolation Certificate (M) must then be submitted to the AS.<br />

BOX 3 - DETAILS OF ISOLATION/DE-ISOLATION<br />

The AA is to list all points of isolation, indicating whether a valve is to be opened or closed. The AS also<br />

indicates in Box 3 the location of all points of spade/blank isolation if necessary.<br />

At de-isolation, the AA is to list all points of de-isolation indicating removal of spades/blanks and reinstatement<br />

of valves is necessary.<br />

BOX 4 - ISOLATION<br />

When the permit has been approved, the AS is to authorise the certificate by signing Box 4a.<br />

The AA is responsible for ensuring that the isolations are carried out correctly, using coloured plastic<br />

chain and tie-wraps to hold the chain in place. Each isolation requires an isolation tag to be attached.<br />

These are individually numbered and the AA is to enter the tag number in the relevant column of Box 3.<br />

When the isolations are complete, the AA is to sign Box 4b confirming that the equipment has been<br />

isolated and the isolations are holding. The AA is to initial the ‘Initial checked’ column in Box 4 of the<br />

work permit to confirm isolation have been made.<br />

IF BLEEDING OFF, DRAINING DOWN, VENTING OR ANY OTHER RELEASE OF HYDROCARBON TO<br />

ATMOSPHERE IS REQUIRED THIS MUST BE COMPLETED AND VARIFIED BEFORE AN<br />

EQUIPMENT DISJOINTING PERMIT IS RAISED. ANY CONFLICTING ACTIVITY MUST BE<br />

SUSPENDED PRIOR TO BLEEDING OFF, DRAINING DOWN, VENTING OR ANY OTHER RELEASE<br />

OF HYDROCARBON TO ATMOSPHERE.<br />

The AA is responsible for ensuring that spade tags are written and secured to spade/blanked disjointed<br />

isolation points. When isolation is complete, the WSS signs Box 4c of the certificate.<br />

BOX 5 - DE-ISOLATION<br />

When the WSS has completed the work as described in Box 1 of the Hot/Cold <strong>Work</strong> <strong>Permit</strong> that<br />

originated the EDP, and the permit(s) have been cancelled by signatures in Boxes 9a and 9b, the<br />

associated EDP is to be re-accepted and re-authorised providing it remains within the validity period set<br />

by the AS in Box 5. If not, a new EDP must be applied for before disjointing commences.<br />

Box 5a of the Isolation/De-isolation Certificate (M) must be signed by the AS before the WSS can carry<br />

out spade de-isolation.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 43 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

When all spade de-isolations are complete the WSS is to sign Box 5b. The AA is responsible for<br />

ensuring that the spade isolation tags are returned to the permit issue point and match with the tag<br />

stubs and that the status of the de-isolation is as defined in Box 3, ‘Spade De-Isolated’ column. When<br />

satisfied that spade de-isolation is complete and the disturbed flanges have been pressure tested the AA<br />

is to cancel the Equipment Disjointing <strong>Permit</strong> as described in Section 3.9.1.<br />

The AA may then remove the valve isolation tags and de-isolate the valves and return the tag stubs to<br />

the permit issue point and match the stubs with the isolation tags and sign Box 5c of the Isolation/De-<br />

Isolation Certificate.<br />

BOX 6 - EXTENDED PERIOD ISOLATION (EPI)<br />

If the WSS is not able to complete the work, and the equipment is to be left isolated, the permit is to be<br />

cancelled using Box 10 and the certificate, isolations and the permit are to be placed in the EPI slot in<br />

the permit rack. The AA is to check to ensure all isolations and tags remain in place.<br />

The AS is to take the certificate to the Senior Operations Supervisor (SOS) who will use Box 6 of the<br />

certificate to confirm the EPI giving the reason and entering the number of the cancelled permit together<br />

with their name, signature, time and the date at which the EPI is implemented.<br />

The worksite and permit issue point certificate(s) are to be placed in the permit rack under EPI together<br />

with the permit to which they are linked.<br />

In order to ensure the EPI remains valid, if the isolation period exceeds 6 months and the isolation is<br />

still required a new Isolation/De-isolation Certificate (Mechanical) shall be issued after confirmation<br />

that all safety controls and notices remain in place.<br />

When the WSS wants to restart the work they are to apply for a new permit. The AS will request the<br />

SOS is to recover the two copies of the original certificate from the EPI slot of the permit rack and reauthorise<br />

the certificate by taking off the EPI by writing in the number of the new permit and giving<br />

their name, signature, time and the date that the EPI has been removed. The AS is to then attach the<br />

certificate to the new permit, and work may proceed once the permit has been approved, accepted and<br />

authorised.<br />

<strong>4.2</strong>.3 Isolation/De-Isolation Certificate (Electrical)<br />

An Isolation/De-isolation Certificate (E) shall be used as follows:<br />

• where electrical isolation is required as a preparation for work as described in the Box 1 of the<br />

permit<br />

• for long term isolation of electrical circuits.<br />

For further information, refer to BSP-02-Standard-1629 (<strong>Mod</strong>ule 10) - Electrical Safety Rules (for copy<br />

of certificate reference is made to Appendix 4, Figure 8).<br />

Note: Normally an Isolation/De-isolation certificate (E) is attached to a PTW, however where a<br />

long-term electrical isolation is required but no work controlled by a permit is necessary then<br />

the Electrical Isolation/De-isolation Certificate may be used as a stand-alone document.<br />

In order to ensure the Electrical Isolation remains valid, if the isolation period exceeds 6 months and<br />

the isolation is still required a new Isolation/De-isolation Certificate (Electrical) shall be issued after<br />

confirmation that all safety controls and notices remain in place.<br />

BOX 1 - APPLICATION<br />

<strong>To</strong> be completed by the WSS requesting the isolation.<br />

The WSS shall enter: -<br />

• Cold/Hot/EDP permit number linked to the certificate<br />

• their name, indicator or contractor and signature<br />

• a work description detailing the reason for Electrical Isolation<br />

• the type of equipment requiring isolation<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 44 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

• the mechanical equipment ID Number of the equipment requiring isolation<br />

• the location of the equipment requiring electrical isolation<br />

The box marked ‘Associated Documents’ is to be completed as necessary. When the validity period of<br />

the permit to which the certificate is attached expires but work is still continuing, the certificate is to be<br />

transferred to the new permit. The new permit number is to be entered into the ‘work continued on<br />

permit number’ box.<br />

Note: When equipment is not isolated for work on a permit and a certificate is used for an EPI then<br />

entering a new permit number is not necessary.<br />

BOX 2 - RELEASE (by Authorised Signatory)<br />

The AS is to confirm release of the equipment for electrical isolation by completing this box, thereby<br />

allowing the RPE to proceed with the isolation.<br />

BOX 3 - REQUIRED ELECTRICAL ISOLATION (by SAEP/AEP)<br />

The SAEP/AEP is to identify what electrical equipment is to be isolated, where it is located and how<br />

isolation shall be carried out before proceeding. This identification shall be performed in accordance<br />

with BSP-02-Standard-1629 (<strong>Mod</strong>ule 10) - Electrical Safety Rules.<br />

The SAEP/AEP shall enter: -<br />

• the unique identification number of the electrical equipment to be isolated<br />

• the isolation/notice point together with the location at which the caution notice/padlock will be<br />

placed<br />

• a tick in the safety padlock box as required<br />

• a tick in the fuse removal box as required<br />

• a tick in the caution notice box as required<br />

• additional/other precautions necessary for the isolation<br />

BOX 4 - ISOLATION<br />

The SAEP/AEP performing the electrical isolation as defined in Box 3 shall complete this section. The<br />

person undertaking the isolation should be the same person that identified the requirements in Box 3.<br />

The SAEP/AEP shall enter: -<br />

• the unique identification number of the safety padlock used for the isolation(s).<br />

• the lockout box number in which the key(s) for the safety padlock(s) are held.<br />

• the location of any fuses removed during isolation.<br />

Once the above information has been provided and the ISOLATION has been carried out the declaration<br />

shall be completed by the electrical person who carried out the ISOLATION.<br />

The green copy of the certificate is then attached to the green copy of the permit for display at the PIP .<br />

The yellow copy is attached to the worksite copy of the permit for display at the worksite.<br />

The white copy is retained by the SAEP/AEP.<br />

BOX 5 - DE-ISOLATION/ISOLATION FOR TEST PURPOSES ONLY<br />

If the equipment under isolation requires to be tested before cancellation of the permit then an<br />

APPLICATION shall be made to the AS by the WSS.<br />

The worksite copy of the permit and certificate is to be returned to the PIP and both copies of the permit<br />

and certificates matched up.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 45 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

The WSS applying for the de-isolation for test should be the same person or be from the same<br />

department who applied in Box 1 of the certificate. The WSS will complete the APPLICATION section of<br />

Box 5a. The AS when satisfied that it is safe to proceed will give CLEARANCE for de-isolation in Box<br />

5b. Once CLEARANCE has been confirmed by the AS in Box 5b, then the SAEP/AEP may proceed with<br />

temporary DE-ISOLATION for testing purposes only.<br />

The green copy of the certificate will be attached to the green copy of the permit for display in the PIP<br />

and the yellow copy of the certificate attached to the worksite copy of the permit at the worksite.<br />

NB: The permit remains suspended at all times during testing. (Refer Section 5.6.3).<br />

The SAEP/AEP who carried out the de-isolation for testing purposes is to remain at the work site<br />

throughout the testing period and will not leave the worksite at anytime during the testing unless<br />

isolation is required to allow work necessary for further testing.<br />

Box 5, if testing is not satisfactory no repair work conflicting with the work description in Box 1 of the<br />

permit may take place and a new permit will be required.<br />

On completion of testing the SAEP/AEP is to ISOLATE the electrical equipment in accordance with the<br />

requirements in Box 3 and complete the declaration in Box 5c.<br />

BOX 6 - EXTENDED PERIOD ISOLATION<br />

This section shall be completed in accordance with the <strong>Permit</strong> to <strong>Work</strong> Procedure in Section 5.7.<br />

Note: When equipment is not available to allow work completion and this certificate is used for an<br />

extended period isolation then this box is to be completed.<br />

BOX 7 - FINAL DE-ISOLATION<br />

On completion of the work and the completion of Box 9a of the permit and the cancellation of any other<br />

electrical safety documents if applicable or the taking off of an EPI the WSS will apply to the AS for<br />

CLEARANCE to enable the SAEP/AEP to finally DE-ISOLATE the electrical equipment thereby making<br />

it re-available for use.<br />

The SAEP/AEP performing the de-isolation is to complete the declaration in Box 7c having matched all<br />

copies of the certificate (yellow, green and white).<br />

<strong>4.2</strong>.4 Master Isolation Control Certificate<br />

Use of the Master Isolation Control certificate is described in Section 5.8.<br />

The Master Isolation Control certificate is shown in Appendix 4, Figure 9.<br />

<strong>4.2</strong>.5 Safety System Override Certificate<br />

This certificate (see Appendix 4, Figure 10) must be used when work is taking place close to or on<br />

safeguarding systems. In order to prevent activation of the safeguarding system concerned via welding<br />

flash/gas leak or work on the sensor etc., it must be overridden ONLY while the work is in progress<br />

with the permit authorised.<br />

Before a safeguarding system can be overridden, the AS must provide the details of actions required to<br />

maintain safeguarding while the system is overridden.<br />

The WSS is to complete Box 1 and 2 of the certificate. The AS after completing Box 3a and 3b will take<br />

the certificate to the SOS for authorisation of the override in Box 4 and for authorisation of its removal<br />

in Box 5.<br />

Refer to BSP-71-Procedure-08, Override Control Procedure for details (attached in <strong>Mod</strong>ule 3).<br />

NB: When a safeguarding system is overridden and a safety system isolation certificate is in use<br />

the certificate must be cancelled and the override removed at every suspension of the permit<br />

and at cancellation in Box 9a of the permit when work is complete.<br />

A separate Safety System override certificate is required for every period of authorisation of the<br />

permit.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 46 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

BOX 1 - APPLICATION<br />

The WSS completes Box 1 of the Safety System Override Certificate entering:<br />

• their name, their contractor/dept., their signature and date of application<br />

• the installation<br />

• worksite<br />

• equipment to be overridden<br />

• the number of the originating work permit<br />

The box marked‚ “<strong>Work</strong> continuing on permit no.” is to be used when a permit validity period has<br />

expired but work is not complete. The certificate can then be transferred to the new permit and the new<br />

permit number entered in the box.<br />

BOX 2 - REASONS FOR ISOLATION<br />

The WSS is to enter the reason for the Safety System Override.<br />

BOX 3a - DETAILS OF ISOLATION/OVERRIDE<br />

The AS is to give the details in Box 3a of the type and category of isolation.<br />

BOX 3b - DETAILS OF ACTION REQUIRED TO PROVIDE SAFEGUARDING DURING SYSTEM<br />

OVERRIDE<br />

The AS is to give details in Box 3b of actions required to provide adequate safeguarding during the<br />

overriding of the Safety System concerned.<br />

BOX 4 - OVERRIDING<br />

The SOS will confirm that the overriding may take place by giving authorisation in Box 4. The person<br />

doing the override will sign in Box 4 to confirm that it has been made.<br />

BOX 5 - NORMALISING<br />

When the permit to which the certificate is attached is either suspended or cancelled and no work is<br />

taking place the SOS will authorise the normalising of the Safety System in Box 5. The person putting<br />

the system back to normal will confirm that the override has been taken off.<br />

BOX 6 - EXTENDED PERIOD ISOLATION (EPI)<br />

If the WSS is not able to complete the work, and the equipment is to be left isolated, the permit is to be<br />

cancelled using Box 10 and the certificate, isolations and the permit are to be placed in the EPI slot in<br />

the permit rack. The AA is to check to ensure all isolations and tags remain in place.<br />

The AS is to take the certificate to the SOS who will use Box 6 of the certificate to confirm the EPI giving<br />

the reason for it and entering the number of the cancelled permit together with their name, signature,<br />

time and the date at which the EPI is implemented.<br />

The worksite copy and permit issue point copy of the certificate are to be placed in the permit rack<br />

under EPI together with the permit to which they are linked.<br />

In order to ensure the EPI remains valid, if the isolation period exceeds 6 months and the override is<br />

still required, a new System Override Certificate shall be issued after confirmation that all safety<br />

controls and notices remain in place.<br />

When the WSS wants to restart the work, they are to apply for a new permit. The AS will request the<br />

SOS to recover the worksite copy and permit issue point copy of the original certificate from the EPI slot<br />

of the permit rack. The AS re-authorise the certificate by taking off the EPI by writing in the number of<br />

the new permit and giving their name, signature, time and the date that the EPI has been removed. The<br />

AS is to then attach the certificate to the new permit, and work may proceed once the permit has been<br />

approved, accepted and authorised.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 47 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

<strong>4.2</strong>.6 Confined Space Entry Certificate<br />

A Confined Space Entry certificate (see Appendix 4, Figure 11 & 12) is required whenever entry is<br />

made into confined spaces. These may contain concentrations of toxic or flammable gases or<br />

vapours, or reduced oxygen content, in their atmosphere. For limits of oxygen, flammable vapour<br />

and contaminant concentrations see BSP-02-Standard-1645 (<strong>Mod</strong>ule 07) - Confined Spaces.<br />

The validity or authorisation period of a Confined Space Entry certificate shall not exceed 12 hours.<br />

The boxes of the Confined Space Entry Certificate are to be completed as follows:<br />

BOX 1 - APPLICATION<br />

<strong>To</strong> be completed by the WSS entering:<br />

• their name, contractor/dept., their signature and date of application<br />

• the location/installation<br />

• worksite<br />

• the number of the original permit for the work for which the confined space entry is required<br />

BOX 2 - SAFETY PRECAUTIONS REQUIRED<br />

All items on the checklist are to be checked by the AA before any entry to the confined space shall<br />

take place.<br />

BOX 3 - GAS TESTING<br />

Immediately before the vessel entry, an AGT is to test the atmosphere of the space to be entered for<br />

oxygen concentration, flammable gases/vapours and toxic concentration.<br />

The AGT is to enter on the certificate:<br />

• the confined space tested<br />

• the results of the gas test carried out<br />

• their name, signature, time and date of the test<br />

BOX 4 - AUTHORISATION<br />

Once satisfied that the confined space is safe to enter, the AA will define the period for which the<br />

certificate is valid/authorised and the frequency at which gas tests are to be repeated within the<br />

validity/ authorisation period as directed by AS. The entry into the confined space can then be<br />

authorised.<br />

REVERSE SIDE - RE-ACCEPTANCE AND RE-AUTHORISATION<br />

The AGT is to test the confined space for oxygen concentration, flammable gases/vapours and toxic<br />

concentration immediately before entry into the Confined Space before the Confined Space Entry<br />

certificate and the associated work permit can be re-accepted and re-authorised.<br />

Provided the result indicates that it is safe to enter the confined space, the AA will:<br />

Re-authorise the Confined Space Entry validity period by entering:<br />

• the authorised period (maximum 12 hours)<br />

• the gas test results<br />

• a tick in the safe box<br />

• their signature<br />

The AGT will sign in the column against the gas test confirming it is safe to re-enter.<br />

If the AGT is not the AA for the area in which the confined space entry is to take place the AA<br />

responsible must sign in the AA signature box.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 48 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

A record of personnel who enter and leave the confined space is to be maintained by the Confined<br />

Space Standby Person through the use of a Tally Board.<br />

<strong>4.2</strong>.7 Excavation Certificate<br />

An Excavation Certificate (see Appendix 5, Figure 13 & 14), is required before excavating is allowed<br />

in BSP operating or controlled areas to a depth greater than 0.3 m. The yellow worksite copy of the<br />

certificate must be attached to the worksite copy of the permit and displayed at the worksite.<br />

BOX 1 - APPLICATION<br />

<strong>To</strong> be completed by the WSS by entering:<br />

• their name, contractor/dept., their signature and date of application<br />

• the location/installation of the excavation<br />

• the worksite<br />

• the number of the original permit for the work for which the excavation certificate is required<br />

BOX 2 - DETAILS OF EXCAVATION REQUIRED<br />

The WSS is to provide full details of the excavation required.<br />

BOX 3 - ATTACHMENTS<br />

The WSS is required:<br />

• to acquire the underground service drawings from TSM/221 and submit them with the<br />

certificate.<br />

• to provide a sketch to assist in defining the area of excavation accurately and submit it with<br />

the certificate.<br />

• to obtain and complete a Geometrics Mappable Change form (refer to Appendix 11).<br />

• to provide any other relevant attachments.<br />

All attachments must be agreed between the AS and WSS and attached to the certificate before<br />

approval of the work is given.<br />

BOX 4 - KNOWN UNDERGROUND SERVICES<br />

When the certificate is circulated as per the distribution list, the Asset Holder departments are to<br />

indicate all known underground services that may be affected in the excavation.<br />

It is the responsibility of the WSS to ensure that an Excavation Certificate is circulated to all BSP<br />

or Government Departments that may be involved.<br />

The distribution list is provided at the bottom of page 1 of the Excavation Certificate. The Asset<br />

Holder and their responsibilities are as follows:<br />

Distribution in all cases<br />

• PPA/1: Responsible for electrical power cables underground and for domestic gas and water<br />

lines.<br />

• IMT/2: Responsible for underground telephone cables.<br />

• DOP/1: Responsible for underground oil and gas pipelines onshore.<br />

• TSM/221: Responsible for mapping in the area of the excavation.<br />

Distribution if affected<br />

• PPA/3: Responsible for domestic gas, water, sewers and drains.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 49 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Distribution if applicable<br />

In areas where Government underground facilities may exist, the clearance of the Chairman of the<br />

Location of Services Committee for the relevant district must be obtained.<br />

Copies must also be sent to:<br />

• The Assistant Controller – Telecommunications<br />

• Senior Executive Engineer – Public <strong>Work</strong>s Department<br />

• Chairman – Municipal Council<br />

• District Electrical Engineer<br />

If the excavation involves any government roads, the police must be consulted in advance via LGL.<br />

In an emergency, BSP may immediately close roads and notify the police.<br />

If the excavation involves constructing new access roads to government roads or if the drainage<br />

system of any government road may be affected, the District Senior Executive Engineer must be<br />

consulted by the Project Engineer responsible with regard to the engineering aspects, in addition to<br />

obtaining permission by signature to excavate.<br />

BOX 5 - OTHER UNDERGROUND SERVICES<br />

Asset Holder departments are to indicate here any other services, whose presence or location in the<br />

area of the proposed excavation is uncertain.<br />

BOX 6 - CONTROL<br />

Necessary controls are to be specified by the AA responsible for the area in which the excavation is to<br />

take place.<br />

BOX 7 - ACCEPTANCE<br />

<strong>To</strong> be signed by the WSS.<br />

BOX 8 - AUTHORISATION<br />

<strong>To</strong> be signed by the AA.<br />

<strong>4.2</strong>.8 Certificate History Sheet<br />

This certificate (see Appendix 4, Figure 16) is to be attached to a permit when the number of<br />

certificates in use with that permit exceeds the space provided in Box 4 of the permit.<br />

<strong>4.2</strong>.9 Hot <strong>Work</strong> on Live Production Facility<br />

This certificate (see Appendix 4, Figure 17) must be used in conjunction with a Hot <strong>Work</strong> <strong>Permit</strong> for<br />

Category 1 hot work and must be verified by the AOS. This certification can also be used for<br />

Category 2 and is at SOS discretion.<br />

The number of hot work activities should be determined by the AOS on a case-by-case basis, by<br />

using the RAM and cumulative risk assessment output, i.e. BSP-02-Guideline-022 (HAZID). For each<br />

installation, the SOS is to set a limit on the number of Hot <strong>Work</strong> <strong>Permit</strong>s that may be authorised at<br />

any one time. This limit should also take into consideration whether the installation is live (SIMOPS)<br />

or shutdown and during night time or hours of darkness and has containment. The limit should be<br />

determined by the weekly cumulative risk assessment, and must be formally recorded at all times in<br />

the PIP.<br />

<strong>Work</strong> Incompatible with Hot <strong>Work</strong><br />

Hot work tasks being undertaken, other than in pressurised non-hazardous areas (habitats), are to<br />

be stopped if any of the following activities are to take place on the same jacket as the hot work site<br />

offshore, or WITHIN 15 METERS ONSHORE.<br />

• Flammable liquids are to be transferred.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 50 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

• Spray Painting is to occur.<br />

• Hydrocarbons are to be, or may be, released by bleeding down process system, or<br />

depressurising Hydrocarbons, breaking containment, pressure testing, pig launching/receiving<br />

etc.<br />

• Any other tasks considered by the AOS to be incompatible with hot work.<br />

<strong>4.2</strong>.10 Scaffolding<br />

This certificate (see Appendix 4, Figure 18) must be used to approve the erection or dismantling of<br />

multiple scaffolds on one level of an offshore platform, or multiple scaffolds within a defined area<br />

onshore.<br />

<strong>4.2</strong>.11 Hazard Check List<br />

The electronic BSP PTW Hazard Check List is designed as a Job Hazard Analysis for most work<br />

covered by a permit. Each checklist identifies the hazards and permit controls and provides a check<br />

list for worksite controls that need to be in place. The Hazard Check Lists are provided for two<br />

reasons:<br />

• to ensure that the correct controls are identified for frequently carried out, potentially<br />

hazardous work covered by a permit.<br />

• to provide a means for the WSS/AA/AS to ensure that the correct controls are applied for the<br />

hazards identified and any necessary recovery measures are available should a control(s) failed.<br />

A Hazard Check List is not itself a permit, and cannot be used without being attached to one.<br />

<strong>4.2</strong>.12 Completing A Hazard Check List<br />

The HCL forms can be downloaded from the HSE/Fountain/Safety Check Page.<br />

• The HCL should be provided by the AS when a permit is to be approved.<br />

BOX 1<br />

In discussion with the WSS, the AS completes Box 1 by striking out those hazards not thought to be<br />

present during the work leaving a list of potential hazards identified.<br />

BOX 2<br />

The AS completes Box 2 by indicating the appropriate Risk Assessment: Low, Medium or High. In<br />

case of Medium or High Risk, the WSS has to attach a method of statement of Hazard identification,<br />

e.g. JSA, HIP, HAZID, etc.<br />

BOX 3<br />

The AS completes Box 3 and transfers appropriate controls from the check list to the attached<br />

permit. Controls not necessary are deleted.<br />

BOX 4<br />

The AS refers to Box 4 and specifies on the attached permit any additional items of PPE identified in<br />

Box 4. PPE not necessary is deleted.<br />

BOX 5<br />

The WSS completes Box 5, the Minimum Health Management Standards - First Aid requirements by<br />

indicating the type of Medical Emergency Response required for the proposed work, in terms of Tier<br />

0, Tier 1 or Tier 2.<br />

BOX 6<br />

The WSS completes Box 6 by verifying the controls indicated in Box 6 at the <strong>Work</strong>site. WSS to<br />

confirm controls by putting an initial in the boxes or delete if not applicable.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 51 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

The WSS indicates if any other hazards are present on the location of the proposed work. If<br />

additional hazards are present, the appropriate HCL has to be used and additional controls have to<br />

be added to the permit by the AS.<br />

BOX 7<br />

The AS signs Box 7 of the HCL confirming the discussion has been held with WSS and the Boxes 1,<br />

2, 3, 4, 5 and 6 are completed accordingly.<br />

BOX 8<br />

The WSS will confirm in Box 8 that a TBT will be given to those carrying out the work before it<br />

commences.<br />

BOX 9<br />

The WSS signs in Box 9 to confirm that all controls identified on the permit and in Box 6 of the HCL<br />

are in place.<br />

The AA signs in Box 9 to confirm that they have checked that all controls identified on the permit<br />

and in Box 6 of the HCL are in place.<br />

THE LINE DEPARTMENTS AND CONTRACTORS NEED TO REVIEW THE SCL FOR COMPLETENESS<br />

AND IN EVENT OF IDENTIFIED NEED FOR UPGRADE OF THE SCL, CONTACT THE ASSET / SERVICE<br />

UNIT HSE ADVISER.<br />

<strong>4.2</strong>.13 Hazard Check List Instruction Card (see Appendix 4, Figure 19)<br />

Plastic cards containing instructions are issued for the following purposes:<br />

• Duties of Fire Watcher<br />

• Duties of Overside Watcher<br />

• Duties of Confined Space Entry Standby Person.<br />

It is the responsibility of the WSS to ensure the unique number and type of the checklist is entered<br />

in Box 4 of the relevant permit under ‘Supporting Documents’.<br />

The WSS is responsible for briefing Fire Watcher, Overside Watcher or Confined Space Standby Man<br />

ensuring they fully understand the duties outlined on the card.<br />

4.3 Electrical Documentation<br />

4.3.1 Sanction for Test<br />

A Sanction for Test is used when testing is to be carried out on high voltage, (1,000 volts ac or 1,500<br />

dc and above) electrical equipment.<br />

4.3.2 Limitation of Access<br />

A Limitation of Access certificate is required when work is to be carried out in the vicinity of live Low<br />

Voltage and High Voltage electrical equipment.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 52 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

5 I S O L A T I O N S<br />

5.1 Planning Safe Isolation Boundaries<br />

5.1.1 Purpose of Isolations<br />

The purpose of an isolation is to ensure that a physical barrier is placed between a source of energy<br />

and a place of work. This applies irrespective of the type of work or the nature of the energy. It may<br />

therefore be necessary for mechanical process work to require isolation of electrical power supplies to<br />

pump motors as well as physical isolation by closing of valves and insertion of blinds. It may also be<br />

necessary for electrical work, e.g. repairs to a pump motor, to require mechanical isolation of<br />

equipment potentially hazardous to the person carrying out the work. In order to ensure that energy<br />

sources of all types are prevented from posing a hazard to the place of work, it is necessary first to<br />

plan the establishment of an ‘Isolation Boundary’ between the sources of energy and the work.<br />

It is occasionally necessary to issue more than one permit for work on equipment which has been<br />

isolated, either Electrically or Mechanically, for example to carry out separate maintenance activities<br />

on a pump and motor set where an Isolation/De-isolation Certificate (Electrical) and/or an<br />

Isolation/De-isolation Certificate (Mechanical) has been issued. In these cases the multiple permits<br />

shall be treated as separate work and the additional procedure in Section 4, para.<strong>4.2</strong>.1 shall be<br />

applied.<br />

5.1.2 Confined Space Entry<br />

Where entry to a process vessel, storage tank or similar confined space is necessary, entry shall not be<br />

authorised until the vessel has been mechanically and if necessary electrically isolated in accordance<br />

with the methods detailed in Confined Spaces i.e. BSP-02-Standard-1645 (<strong>Mod</strong>ule 07) and Electrical<br />

Safety Rules i.e. BSP-02-Standard-1629 (<strong>Mod</strong>ule 10).<br />

5.1.3 <strong>Work</strong> on Process Systems<br />

For work on process systems, isolation in preparation for the work, is to be provided by equipment<br />

disjointing and/or blanking of pipe ends, or by a double block and bleed isolation. Where isolation are<br />

by double block and bleed or by a single valve written approval must be obtained from the Asset<br />

Custodian.<br />

ISOLATION BY EQUIPMENT DISJOINTING<br />

Equipment Disjointing involves the removal of spool pieces, valves etc., the insertion of spades where<br />

possible and the blanking of open flanges if necessary so that the section of the process system to be<br />

worked on is physically separated from other parts of the system. This requires an Equipment<br />

Disjointing <strong>Permit</strong> to be raised to cover the disjointing.<br />

Blanks fitted to piping, and spades inserted into piping, must be to the same specification and<br />

pressure rating of the piping in which they are fitted.<br />

DOUBLE BLOCK AND BLEED ISOLATION<br />

This requires two separate valves with a bleed connection in between. This is less secure than<br />

isolation by equipment disjointing and spading etc. must be approved by the Asset Custodian.<br />

The block valves must be of a positive closing type such as gate or ball valves. Butterfly or control<br />

valves must not be used for this purpose.<br />

Motor or hydraulically operated valves should be immobilised by isolating their motive power supply.<br />

Check valves of any type must not be used for isolation, they should be removed and blanks fitted if<br />

isolation is required where they are installed.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 53 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

The isolation valves shall be proven against upstream pressure, with the bleed valves closed, by<br />

observing and noting the build up of pressure between the block valves for one hour using a calibrated<br />

pressure gauge of the correct range. Once the isolation has been proven, the block valves shall be<br />

completely immobilised by chain link so that they cannot be operated without the approval of the<br />

appropriate AS. Bleed lines shall be led to an appropriate location although it must still be possible to<br />

monitor the bleed for leakage.<br />

5.1.4 <strong>Work</strong> on Non Process Systems<br />

<strong>Work</strong> on utility systems, e.g. fire mains, domestic gas lines, etc., may be carried out under a single<br />

proven isolation, provided that the system conditions do not exceed 1,000 kPA or 50°C, should the<br />

system conditions exceed 1,000 kPA or 50°C, isolation either by equipment disjointing or double block<br />

and bleed is required.<br />

5.1.5 <strong>Work</strong> on Systems Involving Electrical Power<br />

<strong>Work</strong> on electrical systems requires electrical isolation in accordance with either BSP-02-Standard-<br />

1629 (<strong>Mod</strong>ule 10) - Electrical Safety Rules or BSP-02-Standard-1630 (<strong>Mod</strong>ule 13) - General Electrical<br />

Safety as appropriate.<br />

Mechanical work on systems to which an electrical supply is connected or present requires electrical<br />

isolation in accordance with the above requirements.<br />

5.2 Recording of Isolations<br />

5.2.1 Requirement for Certificates<br />

MECHANICAL<br />

Isolation/De-Isolation Certificates (M) are to be raised to cover ALL isolations with the exception of the<br />

following:<br />

An isolation certificate is not required if BOTH of the following conditions are met:<br />

• The isolation is to be carried out by a competent person nominated by an AS, for the purpose of<br />

calibration or minor repair/replacement work. Minor repair/replacement work is limited to work<br />

that can be completed without the person doing the work needing to leave the worksite while the<br />

work is being carried out.<br />

• The isolation must not be left in place at the end of the working period.<br />

ELECTRICAL<br />

An Isolation/De-Isolation Certificate (E) is required for all electrical isolation for non-electrical <strong>Work</strong>.<br />

See Section 4, para. <strong>4.2</strong>.3.<br />

Where electrical isolation and/or earthing is required for electrical work of 1,000 volts ac or 1,500 dc<br />

or above an Electrical <strong>Work</strong> <strong>Permit</strong> is to be used, see Electrical Safety Rules i.e. BSP-02-Standard-<br />

1629 (<strong>Mod</strong>ule 10).<br />

5.2.2 Recording at <strong>Permit</strong> Issue Point<br />

Whenever an Isolation Certificate (E) is used without being attached to a permit, the electrical isolation<br />

is to be identified on the <strong>Permit</strong> Location Board in the <strong>Permit</strong> Issue Point, as described in Section 4,<br />

para. <strong>4.2</strong>.3.<br />

5.3 Authorisation of Isolations<br />

5.3.1 Mechanical Isolation<br />

Mechanical isolations shall not be carried out unless they have been approved by the appropriate AS.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 54 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

5.3.2 Electrical Isolation<br />

Electrical isolations shall not be carried out unless they have been approved by an SAEP/AEP.<br />

5.4 Securing of Isolations<br />

5.4.1 Valve Isolation<br />

When a valve or similar device is used as part of an isolation boundary and does not have an internal<br />

valve lock, it is to be secured in the required position by the use of a high visibility plastic chain and<br />

padlock.<br />

5.<strong>4.2</strong> Electrical Isolation<br />

The procedure for the securing of electrical isolations is described in BSP-02-Standard-1629 (<strong>Mod</strong>ule<br />

10) - Electrical Safety Rules.<br />

5.5 Tagging of Isolation Points<br />

All points of isolation, except those that do not require Isolation Certificates (See Para 5.2.1), shall be<br />

identified by the attachment of tags. Different types of tags are used for the isolation of valves, spades<br />

and electrical equipment. Valve and Spade Tags are shown in Appendix 4 Figures 21 and 22,<br />

Electrical Tags in Figure 23. The use of tags for electrical equipment is described in the HSE Standard<br />

<strong>Mod</strong>ule 10 - Electrical Safety Rules.<br />

The stubs of the Spade and Valve Tags (i.e. the halves not attached to the points of physical isolation)<br />

are to be attached to the <strong>Permit</strong> Issue Point copy of the Isolation Certificate. When the isolation is<br />

removed, the two halves of each tag are to be compared to confirm that all isolations have been<br />

removed. The stubs are not to leave the <strong>Permit</strong> Issue Point until the isolation has been removed and<br />

the two halves of the tags checked to ensure de-isolation is complete.<br />

A valve isolation tag label is completed by the AA indicating:<br />

• the equipment isolated<br />

• the isolation certificate number to which the tag(s) are linked<br />

• the name of the AA carrying out the isolation<br />

• the indicator of the AA carrying out the isolation<br />

• the signature of the AA carrying out the isolation<br />

• the date of the isolation<br />

• the AA indicates in the Valve Open/Closed box whether the valve is open or closed by ticking the<br />

relevant box<br />

Where a single valve or other isolating device is used as an isolation for more than one isolation<br />

boundary, a tag label linked to each Isolation Certificate attached to the relevant permit is to be<br />

applied to the valve or device. In this situation it is not necessary to apply additional physical securing<br />

for each Isolation Certificate, but the securing device fitted shall not be removed until the last isolation<br />

applicable to the valve or spade is removed.<br />

A spade isolation tag label is completed by the AA indicating:<br />

• the equipment spade/isolated/blanked<br />

• the isolation certificate number to which the tag(s) are linked<br />

• the name of the AA attaching the spade isolation tag<br />

• the signature of the AA attaching the spade isolation tag<br />

• the date when the spade isolation tag is attached<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 55 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

An electrical isolation tag label is completed by the relevant electrical person (SAEP/AEP) indicating:<br />

• the equipment electrically isolated<br />

• the permit number to which the tag(s) are linked<br />

• the electrical isolation certificate to which the tag are linked<br />

• the reason for isolation<br />

• the number of the safety padlock used to make the isolation(s)<br />

• the name of the SAEP/AEP carrying out the isolation<br />

• the indicator of the SAEP/AEP carrying out the isolation<br />

• the signature of the SAEP/AEP carrying out the isolation<br />

• the date of isolation<br />

• the time of isolation<br />

• the telephone number of the SAEP/AEP who carried out the isolation<br />

5.6 De-Isolation on Completion of <strong>Work</strong><br />

5.6.1 Mechanical<br />

Where there is a requirement to remove spades or blanks or to replace spool pieces, and it is necessary<br />

to break the System Integrity, an Equipment Disjointing <strong>Permit</strong> must be used. If the validity period of<br />

the EDP used to insert the blinds has not been exceeded it may be re-accepted and re-authorised. If the<br />

validity period has been exceeded, a new Equipment Disjointing <strong>Permit</strong> must be applied for.<br />

Before de-isolation is approved, the AS must:<br />

5.6.2 Electrical<br />

• Ensure all work in connection with the Hot/Cold <strong>Work</strong> <strong>Permit</strong>, that required the insertion of<br />

spades/blanks has been completed and the worksite is in a safe condition for de-isolation to<br />

be carried out.<br />

• Agree and identify with the WSS, the spades/blanks to be removed.<br />

• Check the <strong>Permit</strong> Rack to ensure that de-isolation will not affect other work authorised.<br />

• Check the <strong>Permit</strong> Location Board for approval.<br />

• If a new EDP has been applied for approve or if the original EDP used validity period has not<br />

been exceeded approve reacceptance and reauthorisation.<br />

• When satisfied that the de-isolation can take place, after the permit has been accepted or reaccepted<br />

by the WSS, the AA is to sign Box 7 or 8b of the Equipment Disjointing <strong>Permit</strong>,<br />

authorising or re-authorising disjointing and de-isolation to proceed.<br />

• After the de-isolation has been completed, the AA is to remove the Spade Isolation Tag(s), and<br />

return them to the <strong>Permit</strong> Issue Point and ensure that all Tag stubs match. Should any tags<br />

or tag stubs not be found the AA must confirm that de-isolation has been made by signing<br />

Box 5c on the Mechanical De-isolation Certificate.<br />

Final de-isolation shall not take place until the WSS has declared all the work covered by the electrical<br />

isolation to be complete by signing Box 9a of the permit.<br />

Insert the white copy of the Electrical Isolation Certificate is requested from the SAEP/AEP and the<br />

certificate is re-assembled.<br />

Prior to de-isolation, the WSS shall request clearance to have the electrical equipment de-isolated by<br />

completing Box 7a of the Isolation/De-isolation Certificate.<br />

The AS is then to carry out the following:<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 56 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

a) Check the <strong>Permit</strong> Location Board to ensure that the removal of the isolation involved will not<br />

affect the isolation boundary for any other work.<br />

b) When satisfied that the work covered by the Electrical Isolation is complete, the AS shall sign<br />

Box 7b of the Isolation/De-isolation Certificate to authorise de-isolation to take place.<br />

The SAEP/AEP shall de-isolate the electrical equipment and complete Box 7c of the Isolation/Deisolation<br />

Certificate and return the certificate to the WSS. The WSS shall return the certificate and the<br />

permit to the permit issue point for cancellation by the AA, who will then complete Box 9b of the<br />

<strong>Permit</strong>. The white copy of the certificate retained by the SAEP/AEP at isolation will now be reattached<br />

to the worksite and PIP copies of the certificate.<br />

Note: Where de-isolation is required at a remote location, under the control of another AA, a fax copy<br />

of the isolation certificate confirming that the de-isolation is complete is to be sent.<br />

5.6.3 De-isolation for Test<br />

De-isolation of electrical equipment may take place, prior to completion of the work covered by the<br />

electrical isolation for testing purposes only, see also <strong>4.2</strong>.3..<br />

Prior to de-isolation for testing:<br />

a) The WSS shall ensure that the permit has been suspended in accordance with the procedure<br />

in Section 3.7.1.<br />

b) The WSS shall request clearance to have the electrical equipment de-isolated by completing<br />

the application in Box 5a of the Isolation/De-isolation Certificate.<br />

The AS shall:<br />

c) Check the <strong>Permit</strong> Location Board to ensure that the removal of the isolation involved will not<br />

affect the isolation boundary of any other work.<br />

d) When satisfied that the testing work may proceed, the AS shall sign the Clearance Box 5b of<br />

the Isolation/De-Isolation Certificate to approve de-isolation.<br />

The SAEP/AEP shall de-isolate the electrical equipment and remain at the worksite throughout the<br />

testing period until the testing is completed.<br />

Further isolation and de-isolation of the electrical equipment may be carried out until the testing is<br />

confirmed as complete provided that the permit remains suspended.<br />

Once testing is confirmed as complete the SAEP/AEP shall isolate the equipment and complete the<br />

declaration in Box 5c of the Isolation/De-isolation Certificate and return the certificate to the AA.<br />

The permit to which the electrical isolation certificate is attached must be reaccepted and reauthorised<br />

before any further work may commence.<br />

5.7 Extended Period Isolations (EPIs)<br />

5.7.1 Use of Extended Period Isolations<br />

Extended Period Isolations are isolations that are required to remain in place although no work is<br />

being carried out within their boundary. They may be required:<br />

a) Where work has started but is, or is likely to be, suspended for a period exceeding the<br />

Validity Period given by the AS in Box 5 (Cold <strong>Work</strong> EDP), 5a (Hot <strong>Work</strong> <strong>Permit</strong>) for example,<br />

when awaiting spares for a repair.<br />

b) Where an item of equipment becomes redundant and is to be isolated pending its removal or<br />

the provision of a more permanent means of isolation.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 57 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

5.7.2 Approval of Extended Period Isolation<br />

The procedure for authorising and documenting EPIs is as follows:<br />

a) When work cannot be restarted within the Validity Period given by the AS in Box 5 (Cold <strong>Work</strong><br />

EDP), 5a (Hot <strong>Work</strong> <strong>Permit</strong>) or when it is decided that de-isolation will be of a permanent<br />

nature the associated Hot Cold or EDP is to be cancelled by the WSS in Box 10a and the AA in<br />

Box 10b.<br />

b) The AA is to indicate in Box 10b of the permit that the work has not been completed, but the<br />

isolation(s) is being retained under the relevant isolation certificate(s) writing in their<br />

number(s).<br />

c) The AS is to confirm an EPI by completing Box 6a of the relevant isolation certificate stating:<br />

• the reason for the isolation.<br />

• the type and number of the <strong>Permit</strong> being cancelled.<br />

The AS is then to take the Isolation Certificate(s) to the SOS for signature for<br />

confirmation of the EPI.<br />

d) Both copies of the Isolation Certificate and the Isolation Tag Label stubs are to be retained in<br />

the EPI section of the <strong>Permit</strong> Rack together with the cancelled permit, HCL, tag stubs and<br />

other supporting documents if applicable for audit verification. For Electrical EPI’s, the<br />

WHITE copy of the Electrical Isolation Certificate is to be retained by the SAEP.<br />

e) The pegs on the <strong>Permit</strong> Location Board relating to the isolation that has been confirmed as an<br />

EPI, are to be changed to GREEN to distinguish them from normal isolations.<br />

f) For Electrical EPIs the keys for the padlocks used to make the isolation are to be retained by<br />

the SAEP/AEP.<br />

g) The PIP Coordinator or AA responsible for the area of the isolation will ensure the site tag(s)<br />

are regularly checked and replaced if necessary if the information on the tag(s) becomes<br />

illegible.<br />

5.7.3 Re-Starting <strong>Work</strong> within an EPI Boundary<br />

When it becomes possible for the work to restart again within the EPI boundary:<br />

a) The WSS is to apply for a new <strong>Permit</strong>, entering the number of the Isolation Certificate relevant<br />

to the EPI in Box 4 of the permit. The WSS is to enter the new <strong>Permit</strong> number in the <strong>Work</strong><br />

Continuing under permit number box in Box 1 of the certificate. The isolation certificate(s) is<br />

then attached to the new permit and submitted to the AS for approval.<br />

b) The AS on receiving the application enters the new permit number into Box 6b of the relevant<br />

isolation certificate when referring the certificate to the SOS for signature for confirmation of<br />

the removal of the EPI.<br />

5.8 Master Isolations<br />

5.8.1 Use of Master Isolations<br />

A Master Isolation may be used to establish isolation boundaries for major shutdowns so that a<br />

number of tasks can be undertaken within a single boundary. This reduces the complexity of isolation<br />

documentation, but requires careful control to ensure that isolations are not removed prematurely.<br />

The number of Master Isolations applied should be kept to a minimum to reduce the number of valves<br />

forming part of more than one boundary, and hence requiring multiple tag labels.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 58 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

5.8.2 Master Isolations for Shutdowns<br />

The process of carrying out Master Isolations for a shutdown is to be as follows:<br />

1. Plan the Isolation<br />

The required isolation boundary is to be planned and marked-up on appropriate Isolation drawings<br />

and a Spading Plan developed. Each isolation point should be given a Unique Identifying Number.<br />

2. Complete the Master Isolation Control Certificates and identify Valve Isolation Tags<br />

A separate set of Master Isolation Control Certificates (see Section 4, para <strong>4.2</strong>.4) is to be produced by<br />

the PIP Coordinator for each Platform, or isolation boundary area. The set needed to cover all<br />

isolation points for that Platform/Area are to be attached to the <strong>Work</strong> <strong>Permit</strong>. The top sheet of each set<br />

is to be given an identifying number in the number box at the top right of the Certificate.<br />

The isolations should be written on the Master Isolation Control Certificate Register in the order that<br />

the isolations are to be carried out.<br />

Valve Tags are to be written for all valve isolation points. Only the EQUIPMENT/ISOLATION<br />

CERTIFICATE NUMBER/VALVE OPEN/VALVE CLOSED Sections are to be filled in at this time, the<br />

information written on the Tag being as that detailed in Section 5.5.<br />

The numbers of the Valve Tags are to be entered in the column provided on the Master Isolation<br />

Control Certificate Register.<br />

3. Authorise Master Isolation Process to Start<br />

When satisfied that it is safe for the Master Isolation(s) to commence the AS is to approve the relevant<br />

work permit(s).<br />

NB: If there is a requirement to break the integrity of the System then an Equipment Disjointing <strong>Permit</strong><br />

is required. A separate Valve Isolation Certificate is not required for this operation.<br />

4. Carry out Master Isolations (Valves)<br />

Valve Isolation is now to be carried out in the sequence decided by the AS. As each isolation is made,<br />

the AA is to:<br />

• Sign and date the Valve Isolation Tag(s) and Tag Stub(s).<br />

• Secure the Tag to the isolation point.<br />

• Initial the ‘Area Authority Initial’ Box in the Valve Isolation column of the Master Isolation<br />

Control Certificate to verify that isolation.<br />

• On completion of Valve Isolation, return the Master Isolation Control Certificates and tag stub(s)<br />

to the <strong>Permit</strong> Issue Point.<br />

Where the isolation for a Platform or Area includes isolation points outside of that platform or area (e.g.<br />

on another platform), these are to be included on the Master Isolation Control Certificate. The ‘Area<br />

Authority Initial’ Box is to be initialled by the AA when a copy of the Isolation Certificate from the<br />

remote area has been received stating that the isolation has been carried out. This may be sent from<br />

the remote area by fax.<br />

If a change to the isolation boundary is required, this may be approved by the AS writing the reason<br />

for change in the ‘Description’ column against the appropriate isolation, and by signing it.<br />

When the AA is satisfied that the isolation of all valves involved in the Master Isolation for an<br />

individual Platform or Area is complete, the AA is to sign the ‘Valve Isolation Complete’ Box at the foot<br />

of the Master Isolation Control Certificate.<br />

The set of Master Isolation Control Certificates and tag stub(s), together with the Isolation Drawing(s),<br />

is to be retained in the EPI Section of the <strong>Permit</strong> Rack for the relevant Platform or Area.<br />

5. Plan Master Isolation (Spading)<br />

Prior to installation of spades requiring breaking of containment, the AS and AA must:<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 59 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

• Ensure all equipment has been drained down and depressurised.<br />

• Ensure all valve isolations are in place and holding.<br />

• Refer to the spading plan and decide the best method and sequence for insertion<br />

spades/blanks.<br />

• Discuss the chosen method with the WSS.<br />

• Ensure an Equipment Disjointing <strong>Permit</strong> is applied for if the containment is flammable, toxic or<br />

corrosive.<br />

6. Prepare Spade Isolation Tags<br />

Spade tags are to be written for all Spade Isolation points. Only the EQUIPMENT and ISOLATION<br />

CERTIFICATE NUMBER Sections on the tags are to be filled in at this time completing:<br />

• The Equipment Description and Unique Identifier Number for the blind/spade isolation.<br />

NB: If a blind/spade is to be inserted to a valve next to a valve that has already been isolated as part<br />

of the Master Isolation then the same unique identification number may be used.<br />

If the spade is not to be fitted at the valve already isolated then a new unique identifier should be<br />

given.<br />

• The number given to the Master Isolation Control Certificate to be inserted as the ISOLATION<br />

CERTIFICATE NUMBER.<br />

• The numbers of the spade tags are to be entered into the column provided on the Master<br />

Isolation Control Certificate.<br />

7. Authorise Spade Isolation Process to Start<br />

When satisfied that it is safe for the Spade Isolations to commence, the WSS is to accept the approved<br />

Equipment Disjointing <strong>Permit</strong> in Box 6 and blank/spade isolation may proceed after the AA has<br />

authorised the permit in Box 7.<br />

8. Carry out Master Isolation (Spades)<br />

Blank/spade Isolation is now to be carried out in the sequence decided and agreed by the AS and AA.<br />

As each blank/spade is fitted the AA is to:<br />

• Sign and date the Spade Isolation Tag and Tag Stub.<br />

• Secure the Tag to the Isolation Point.<br />

• Initial the ‘Area Authority Initial’ Box in the Spade Isolation column of the Master Isolation<br />

Control Certificate.<br />

• Sign the “Spade isolation complete”, the AA signs the “Spade Isolation complete” Box of the<br />

Master Isolation Control Certificate and brings the Master Isolation Control Certificates and<br />

Spading Tag Stub to the PIP on completion of the spade isolation.<br />

The Equipment Disjointing <strong>Permit</strong> is cancelled in Boxes 9a by the WSS and 9b by the AA.<br />

9. Spade De-Isolate after Shutdown<br />

Before de-isolation can be authorised, the AA is to carry out the following:<br />

• Check the <strong>Permit</strong> Rack with the PIP Coordinator or the person delegated to maintain the PLB<br />

for the location to ensure that all work being carried out within the isolation boundary has been<br />

completed, or is in a safe condition to allow the de-isolation to commence.<br />

• Check the <strong>Permit</strong> Rack with the PIP Coordinator or the person delegated to maintain the PLB<br />

for the location for work in other areas not within the isolation boundary to ensure that the deisolation<br />

will not affect other work being carried out.<br />

• Check that no part of the boundary to be de-isolated forms part of the boundary of an isolation<br />

for another area (refer to Section 5, para. 5.5).<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 60 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

The WSS will apply for an Equipment Disjointing <strong>Permit</strong> and enter the number of the Master Isolation<br />

Control Certificate in Box 4 of the permit. De-isolation is the reverse of the procedure outlined in Steps<br />

1 – 8 above.<br />

When satisfied that the de-isolation process can commence the AS will approve de-isolation by<br />

completing Box 5 of the Equipment Disjointing <strong>Permit</strong>.<br />

De-isolation may then be carried out in a controlled manner following the sequence decided and agreed<br />

between the AS and the AA. As each spade or blank is removed, the AA is to:<br />

• Remove the Spade Isolation Tag from the isolation point.<br />

• Initial the ‘Area Authority Initial’ Box in the Spade De-isolation column of the Master Isolation<br />

Control Certificate to verify that de-isolation.<br />

• Bring the Spade Tags and Master Isolation Control Certificates back to the <strong>Permit</strong> Issue Point<br />

and match the tag with the appropriate stubs to confirm that all blanks/spades have been<br />

removed.<br />

• Confirm that the WSS has cancelled the EDP in Box 9a and complete the cancellation by filling<br />

in the relevant details in Box 9b.<br />

• Pressure test disturbed flanges.<br />

When satisfied that the de-isolation(s) are complete, the AA is to initial the ‘Spade De-isolation’ Box of<br />

the Master Isolation Control Certificate.<br />

10. Valve De-Isolation Prior to Start Up<br />

Before valve de-isolation can commence the AS and AA must agree the sequence to de-isolate in a<br />

controlled and safe manner.<br />

When satisfied, the AA may then:<br />

• Remove the Valve Isolation Tag(s) from the Isolation point(s).<br />

• Initial the ‘Area Authority Initial’ Box of the Valve De-isolation column of the Master Isolation<br />

Control Certificate to verify de-isolation.<br />

• Bring the Valve Isolation Tags and Master Isolation Control Certificates back to the <strong>Permit</strong> Issue<br />

Point and match the tags with the appropriate stubs to confirm that all valves have been deisolated.<br />

The YELLOW, worksite copy of the Master Isolation Control Certificates is to be archived with the<br />

appropriate <strong>Permit</strong>s in the <strong>Permit</strong> Archive. The GREEN PIP copy is to be retained as a Spade Register<br />

by the PIP for future reference.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 61 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

6 P E R M I T I S S U E P O I N T S ( P I P S )<br />

BSP-02-Procedure-1622<br />

6.1 <strong>Permit</strong> Issue Point Control<br />

There are 4 main types of <strong>Permit</strong> Issue Point.<br />

Type Description / Comment Examples<br />

1 These are the most straightforward, where the AS has<br />

ready access to the AA and the <strong>Work</strong>site.<br />

2 This type requires the AS to either travel to the <strong>Work</strong>site<br />

to approve the permit and attached documents, or send<br />

the permits and attached documents after approval with<br />

the AA when the permit is to be accepted and authorised<br />

for the first time.<br />

Operational Assets<br />

Offshore (normally<br />

manned complexes),<br />

Seria Terminal, New<br />

Gas Compression<br />

Plant (NGCP).<br />

Operational Assets<br />

Offshore Field Areas<br />

and Onshore<br />

Engineering Support<br />

Because of the distance between the PIP and the<br />

<strong>Work</strong>site, and when the AA does not return directly to<br />

the PIP after acceptance and authorisation of the work<br />

for which the permit was issued, the white copy of the<br />

permit is kept in the PIP <strong>Permit</strong> Rack to maintain<br />

visibility of work underway. As the permit is accepted,<br />

authorised and suspended at the worksite, the PIP is<br />

informed and the white copy is moved to the appropriate<br />

section of the rack.<br />

3 This type delegates the responsibility for co-ordination of<br />

permit work to the AA on site. As for all permits, the<br />

approval is carried out by the AS. The permit is then<br />

taken to the PIP controlling the area where the work is to<br />

take place.<br />

The permit is accepted and authorised at the site by the<br />

WSS and AA. Further re-acceptance and reauthorisation<br />

after suspension is carried out locally by<br />

the WSS and the AA for the location at which the work is<br />

taking place.<br />

AA (xOP) on<br />

<strong>Work</strong>boats and<br />

Construction Barges<br />

(when not alongside a<br />

complex), Land field<br />

Tank Groups, Tali<br />

Field and Rasau<br />

Station.<br />

NB: For land field tank groups, Tali-field and Rassau<br />

station, the white copy is retained in a simplified <strong>Permit</strong><br />

Rack in the approved slot.<br />

4 These are at the office of the department responsible for<br />

the work. In order to coordinate a number of<br />

simultaneous tasks, it is necessary to setup a PIP at a<br />

site office to keep track of work underway at any<br />

particular location. The PIP board displays the Plot Plan<br />

of the location and the work is identified by the coloured<br />

disc of the permit being applied.<br />

All onshore Non-<br />

Hydrocarbon Sites, e.g.<br />

PPA/3.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 62 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

6.2 Display of <strong>Permit</strong>s and Isolations<br />

BSP-02-Procedure-1622<br />

A structured display showing the status of all <strong>Permit</strong>s and Isolations for the area covered by the PIP<br />

will be maintained within the PIP by the PIP Coordinator or a person delegated to do so.<br />

The purpose of the display is:<br />

a) <strong>To</strong> identify work under way clearly to AS(s) and AA(s) so that any potential conflicting work can be<br />

avoided.<br />

b) <strong>To</strong> identify to all users of the PIP what equipment is isolated and therefore not available for use.<br />

c) Notification of variation control.<br />

The Display is made up of two parts:<br />

1) The <strong>Permit</strong> Rack.<br />

2) <strong>Permit</strong> Location Board.<br />

6.2.1 The <strong>Permit</strong> Rack<br />

The permit rack has a number of sections, each one representing an area of an installation or a<br />

platform in a complex. Each section of the rack is subdivided vertically into sections representing the<br />

status of the permit. Into these sections are placed the appropriate copies of permits and supporting<br />

documents. The depth of the rack sections is arranged so that the permit number, description of task<br />

and permit type are visible without removing the complete permit from the rack.<br />

The permit status sections are:<br />

a) Planned <strong>Permit</strong>s for work applied for by the WSS but not yet approved by<br />

the AS.<br />

<strong>Permit</strong>s for work that have been approved by the AS awaiting<br />

worksite preparations to commence.<br />

b) Authorised <strong>Permit</strong>s for which work is in progress.<br />

c) Suspended <strong>Permit</strong>s for which work has started but is not currently in<br />

progress.<br />

d) Extended Period Isolation <strong>Permit</strong>s, Certificates and supporting documents for isolation(s)<br />

retained for an extended period for justifiable reasons.<br />

e) Expired <strong>Permit</strong>s for which the validity period for the work has expired but<br />

which have not yet been cancelled.<br />

The colours of the permit copies visible in the racks provide confirmation of the permit status.<br />

GREEN copy showing<br />

BLUE or RED copy showing<br />

WHITE copy showing<br />

RED or BLUE copy is at the worksite and work is underway. The<br />

permit is AUTHORISED.<br />

The worksite copy is in the rack with the PIP and white copy (if<br />

applicable) and no work is in progress. The work is either<br />

PLANNED or SUSPENDED.<br />

Both worksite and GREEN copies are at the worksite while<br />

preparation are made before the permit can be accepted and<br />

authorised. This gives an indication of possible conflicting work.<br />

NB: A white copy may be used for information purposes if the PIP and worksite copy are at a remotely<br />

located worksite (refer Section 6.1).<br />

Whenever the permit changes status, the permit and its supporting documents are moved to the<br />

appropriate section of the rack, e.g. from PLANNED to AUTHORISED to SUSPENDED, etc.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 63 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

<strong>To</strong> highlight when isolations or de-isolations are in progress, a BLUE separator labelled “ISOLATION IN<br />

PROGRESS” and “DE-ISOLATION IN PROGRESS” may be inserted in front of the permit to warn<br />

persons about to start work in the area that this activity is going on.<br />

A similar BROWN separator may be used when “TESTING IS IN PROGRESS”.<br />

6.2.2 The <strong>Permit</strong> Location Board (PLB/PIP)<br />

Indication of <strong>Work</strong> Underway<br />

Whenever a permit is authorised or re-authorised and the work is about to start, the exact location<br />

of the worksite will be indicated by a numbered 20mm diameter magnetic disc placed on the <strong>Permit</strong><br />

Location Board.<br />

RED<br />

BLUE<br />

PURPLE<br />

for Hot <strong>Work</strong><br />

for Cold <strong>Work</strong><br />

for Equipment Disjointing<br />

Each disc will have its number clearly visible on it and this number will be written in the Task No.<br />

box provided at the top of the permit by the PIP Coordinator or AS, at the first approval of the<br />

permits. At each re-acceptance/re-authorisation, the number linked to the permit will be retained<br />

until the permit is cancelled. The number then becomes re-available for use.<br />

Indication of Plant or Equipment Isolated through Pegging<br />

The Pegging System as described below is MANDATORY for all <strong>Permit</strong> Issue Points having PIP<br />

Coordinators.<br />

A hole is drilled in the symbol for each item of plant/equipment indicated in the <strong>Permit</strong> Location<br />

Board, into which is inserted by the PIP Coordinator or AA or the person delegated a coloured peg<br />

when the item is to be isolated or immobilised by an isolation in the system.<br />

A marked-up PEFD must be attached the appropriate permit to indicate valves which require<br />

isolation.<br />

BLUE PEG Valve Isolation/De-isolation. This peg is inserted when the isolation has been<br />

approved and is about to be carried out, AFTER a check has been made to confirm<br />

that the isolation does not conflict with any other isolation already in place.<br />

The blue peg remains in the board until all parts of the isolation are complete, i.e.<br />

Electrical/Instrument/Mechanical.<br />

On de-isolation the blue peg will replace a red peg when the blank/spade has been<br />

removed if appropriate and/or remain in place until the de-isolation is complete.<br />

RED PEG Spade Isolation. The peg is changed from blue to red when the blank/spade<br />

isolations are in place and confirmed in Box 4c of the Mechanical Isolation<br />

Certificate by the WSS.<br />

On de-isolation, the red peg is replaced by the blue peg when the blank/spade is<br />

removed as the first part of the de-isolation commences. Progress of the deisolation<br />

can be readily obtained by reference to the Mechanical Isolation<br />

Certificate in the appropriate section of the rack.<br />

YELLOW PEG<br />

GREEN PEG<br />

Process Override. This peg is inserted at the appropriate location for the override.<br />

Details of the override may be obtained by reference to the Safety System Override<br />

Certificate attached to the relevant permit in the appropriate section of the rack.<br />

Extended Period Isolation. The blue/red peg is changed to green when a permit is<br />

cancelled but the isolation remained in place.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 64 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Safety and Emergency System Isolations/Override/Inhibits<br />

When UV, smoke, gas or heat detectors and/or automatic fire suppression systems are isolated,<br />

overridden or inhibited, the fact will be recorded on the <strong>Permit</strong> Location Board with the appropriate<br />

pictorial marker placed at the location of the isolation/override/inhibit.<br />

Other Displays on the <strong>Permit</strong> Location Board<br />

Barriers<br />

Scaffolding<br />

Radiography/Testing<br />

/Excavation<br />

Diving<br />

Variation<br />

Wireline<br />

Services/Wellhead<br />

Maintenance<br />

The position of barriers will be indicated by red and white magnetic<br />

strips at the barrier location. This will alert those using the PIP to any<br />

restriction of access and act as a reminder to remove barriers when they<br />

are no longer required.<br />

A pictorial marker is placed at the appropriate location on the <strong>Permit</strong><br />

Location Board whenever scaffolding is being erected or dismantled.<br />

When the scaffold is complete and the attached Scafftag has its green<br />

face showing, it is then considered to be part of the facility structure and<br />

the marker may be removed from the <strong>Permit</strong> Location Board. The<br />

pictorial marker will be displayed during the dismantling of the<br />

scaffolding.<br />

When radiography is in progress, pictorial markers are placed on the<br />

location board to indicate the precise location. When testing of<br />

equipment or excavation is in progress the appropriate pictorial markers<br />

are placed on the affected areas on the location board so that no other<br />

work that could be affected by them is allowed to proceed.<br />

Whenever diving operations are authorised on an offshore platform, the<br />

fact will be highlighted by a pictorial marker on the <strong>Permit</strong> Location<br />

Board to indicate that platform systems have been isolated for diving in<br />

accordance with the requirements of ROV Operations i.e. BSP-02-<br />

Standard-1652 (<strong>Mod</strong>ule 18).<br />

Whenever there is a red anomaly highlighted in a Facility Status Report<br />

(FSR), the Asset Holder needs to repair/resolve the anomaly or put a<br />

positive containment in place within 7 days. If Variations are made to<br />

allow for continuous operation, a Variation form is completed detailing<br />

the method of operation of the equipment. A RED pictorial marker with<br />

a ‘V’ is to be displayed on the <strong>Permit</strong> Location Board to indicate a<br />

variation is in place requiring special controls to be put in place by all<br />

work parties. A copy of the Variation Form including marked-up PEFDs,<br />

Inspection Reports and all the containment measures such as isolation<br />

tags, pictures etc. is displayed in the EPI section of the permit rack.<br />

When routine Wireline or Wellhead Service work has been authorised by<br />

the Asset Holder in accordance with the requirements of <strong>Work</strong><br />

Instruction BSP-71.3.1.3.242.0, a pictorial marker is placed on the<br />

<strong>Permit</strong> Location Board at the location of the work.<br />

For Wireline Services, the pictorial marker is a YELLOW square with a<br />

“WLS” sign and for Well Head Maintenance a GREEN square marker with<br />

a “WHM” sign.<br />

The pictorial markers used on <strong>Permit</strong> Location Boards are shown below. Pictorial markers may be<br />

ordered via HRS/37.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 65 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

<strong>Permit</strong> Location Board Pictorial Markers<br />

HOT WORK<br />

15 EQUIPMENT<br />

DISJOINTING PERMIT<br />

COLD WORK<br />

TESTING IN<br />

PROGRESS<br />

SMOKE DETECTOR<br />

INHIBITED<br />

EXCAVATION<br />

IN PROGRESS<br />

GAS DETECTOR<br />

INHIBITED<br />

SCAFFOLDING<br />

IN PROGRESS<br />

UV DETECTOR<br />

INHIBITED<br />

RADIOGRAPHY<br />

IN PROGRESS<br />

DIVERS DOWN<br />

WORKBOAT/TENDER<br />

ALONGSIDE<br />

V<br />

VARIATION<br />

HEAT DETECTOR<br />

INHIBITED<br />

TO NORMAL<br />

OPERATION IN PLACE<br />

BARRIER LOCATION<br />

WHM<br />

WELLHEAD<br />

MAINTENANCE<br />

WLS<br />

WIRELINE SERVICES<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 66 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

7 H A Z A R D O U S A R E A C L A S S I F I C A T I O N<br />

7.1 Classification of Areas<br />

7.1.1 Definitions of Hazardous Area Classification<br />

All BSP operating areas have Hazardous Area Classification. The rules applying to hot work depend upon<br />

the classification of the area in which the hot work is to take place.<br />

Zone 0<br />

Zone 1<br />

Zone 0 classification applies to the internals of process vessels, storage tanks and<br />

other similar closed containers. Any source of ignition in a Zone 0 area would,<br />

have the potential to cause a fire or explosion.<br />

Zone 1 classification applies in production areas around process vessels,<br />

wellheads, open drains, vents etc. and in all areas where gas is used as the<br />

pneumatic drive for instruments.<br />

Zone 1 area is an area in which a hazardous atmosphere is likely to occur during<br />

normal operating conditions.<br />

Zone 2<br />

Zone 2 area is an area in which a hazardous atmosphere is not likely to occur<br />

during normal operations and if it does occur, will exist only for a short period.<br />

Non Hazardous Zone All areas not classified as Zone 0, 1 or 2.<br />

7.1.2 Zone 0 and Zone 1 Areas<br />

Hot work (as defined in Section 2.2) is not allowed at any time in Zone 0 or Zone 1 areas. If all alternatives<br />

to hot work as a means of carrying out work in a Zone 0 or Zone 1 area have been considered and ruled out<br />

as impracticable, the following action must be taken:<br />

a) The process system(s) which required the area being classified as Zone 0 or 1 must be shut down,<br />

isolated, depressurised, and gas freed resulting in no hydrocarbon being present. The area may then be<br />

reclassified as Zone 2 or non-hazardous as appropriate, for the duration of the work.<br />

or<br />

b) Where specifically approved in writing by the appropriate AS, a habitat may be used in order to create<br />

an environment within a Zone 1 area, in which hot work may be carried out. The habitat shall be<br />

constructed in such a way that the atmosphere maintained within it will be non-hazardous. This<br />

requires internal pressurisation or other means of preventing gas entry and provision of gas detection<br />

equipment. The entry into and exit from the habitat shall be controlled. A Hot <strong>Work</strong> <strong>Permit</strong> may then<br />

be approved and the work carried out subject to the necessary controls specified on the permit.<br />

For offshore work, the controls specified in <strong>Work</strong> Instruction BSP-71.3.1.3.205.1. Precautions during<br />

Hot <strong>Work</strong> on Hydrocarbon Production or Processing areas must be taken, including the use of a Hot<br />

<strong>Work</strong> on Live Production Facility Certificate, where appropriate for Hot <strong>Work</strong> Category One work.<br />

When re-classifying an area to allow hot work, in order to make the re-classification visible for audit<br />

purposes, the AS should complete Box 2 of the Hot <strong>Work</strong> <strong>Permit</strong> as follows:<br />

Put a line through the original classification. Indicate the re-classification by ticking in the appropriate<br />

box and initialling alongside it.<br />

1.<br />

Zone 1<br />

Zone 2<br />

(Initial)<br />

Non-Haz<br />

2. Describe in Box 3 the method of re-classification.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 67 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

3. Attach the appropriate HAC drawing to the permit and enter the number of the drawing into Box 4<br />

of the permit as a supporting document.<br />

NB: When the permit for the work is cancelled in Box 9a and 9b the temporary re-classification of<br />

the area ceases and the area reverts to its original classification.<br />

7.1.3 Zone 2 Areas<br />

Hot work may be carried out in Zone 2 areas without shutting down production facilities, subject to<br />

the approval of the Asset Custodian. The hot work shall only be approved by the AS when no<br />

alternative means of carrying out essential work are available and stringent controls must be put in<br />

place.<br />

For offshore work, the controls listed in <strong>Work</strong> Instruction BSP-72-G-007 must be in place, including a<br />

Hot <strong>Work</strong> on Live Production Facility Certificate where appropriate.<br />

7.2 Hazardous Area Classification Drawings<br />

These detailed drawings show the boundaries of the different zones in each specific operating area.<br />

The drawings are the responsibility of SEN/4 who hold the master copies and arranges periodic review<br />

and updating. Copies of appropriate Hazardous Area Classification Drawings shall be held at each<br />

<strong>Permit</strong> Issue Point.<br />

When hot work is to be carried out in an area normally classified as Zone 0 or Zone 1 the appropriate<br />

Hazardous Area Classification Drawing must be approved by the AOS. The drawing will be marked-up<br />

to indicate the temporary re-classification of the zones for the duration of the proposed work by the<br />

AS.<br />

In the event of a permanent change of the Hazardous Area Classification Drawing being necessary<br />

approval by SEN/3 is required.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 68 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

8 R U L E S & R E S T R I C T I O N S<br />

8.1 Actions Following a General Alarm<br />

8.1.1 Stoppage of <strong>Work</strong><br />

ALL PERMITS ARE SUSPENDED IMMEDIATELY IN THE EVENT OF A REPORTABLE INCIDENT<br />

All work is to cease immediately following a General Alarm in any facility. The WSS or a person<br />

delegated by the WSS must check to ensure that the worksite has been left in a safe condition, and<br />

take the worksite copy of the permit to the muster point or wherever decided by the installation. The<br />

WSS is to report to the muster checker the fact that they have stopped work and made the worksite<br />

safe.<br />

Where work is such that unplanned stoppage may cause a hazardous condition, the permit is to state<br />

what actions must be taken in the event of an alarm in Box 3.<br />

8.1.2 Re-Starting <strong>Work</strong><br />

When the all clear has been given and normal conditions have been re-established, the AOS or SOS or<br />

equivalent will confirm whether or not permits have been suspended as a result of incident. If such an<br />

announcement is made, all permits must be suspended and then re-accepted and re-authorised at the<br />

worksite before work may re-commence.<br />

8.2 Changes to <strong>Permit</strong>s to <strong>Work</strong><br />

Once a permit has been authorised, the only change that may be made by AS/AA/WSS are additions<br />

to the controls in the event of extra controls being found necessary during the course of the work.<br />

The additional controls must be written on all copies of the permit.<br />

8.3 Testing After Maintenance<br />

Where work has affected the integrity of a system containing pressurised hazardous gases or liquids, a<br />

pressure test is to be carried out to ensure that the system is safe to be put back into service. The<br />

tests shall be carried out by competent personnel to the satisfaction of the Asset Custodian.<br />

A separate Cold <strong>Work</strong> <strong>Permit</strong> is to be applied for approved, accepted and authorised to cover such<br />

pressure testing.<br />

Testing of electrical equipment is to follow the requirements laid down in Electrical Safety Rules i.e.<br />

BSP-02-Standard-1629 (<strong>Mod</strong>ule 10) and Section 5.6.3.<br />

8.4 Preparation for Equipment Disjointing<br />

If bleeding off, draining down, venting or any other release of hydrocarbon to atmosphere is required<br />

this must be completed and verified before an equipment disjointing permit is raised. Any conflicting<br />

activity must be suspended prior to bleeding off, draining down, venting or any other release of<br />

hydrocarbon to atmosphere. This preparation must be completed before AA approves an EDP.<br />

8.5 Interfaces between Drilling Rigs and Tenders and Fixed Offshore Installations<br />

(Reference is made to the TMS 0004 – Policy and Procedures for Concurrent and Rig Activities,<br />

Sections 6.1 and 6.2)<br />

8.5.1 Manned Platforms<br />

When drilling work is taking place on a manned platform, the well being worked on is handed over to<br />

TSW. TSW must apply to the AS responsible for the Drilling Platform for all work, other than that<br />

related directly to the well.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 69 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

If any other work is planned on the same Drilling Platform as the handed over well, those intending to<br />

do it must also apply to the AS responsible for the Drilling Platform.<br />

The AS responsible for the Drilling Platform must advise the BSP Drilling Supervisor in writing of any<br />

proposed work on the Drilling Platform. <strong>Work</strong> must not commence without prior discussion with and<br />

agreement of the DSV. This condition applies to all proposed work.<br />

8.5.2 Satellite Drilling Platforms<br />

For Satellite Drilling Platforms, the Drilling Platform and platforms linked to it by bridge are handed<br />

over to TSW for the duration of the drilling work (CPRA). The DSV becomes the AS and the xOP rep<br />

the AA.<br />

TSW is responsible for the <strong>Permit</strong> to <strong>Work</strong> system on Drilling Platforms other than parts of it attached<br />

to the rig or tender (DES) which have been handed over, and all work requests must be directed to the<br />

DSV. <strong>Permit</strong>s for authorisation of work other than on the Drilling Platform shall be handled as follows:<br />

i) For work on attached bridge linked platforms the DSV is the AS and the xOP representative the<br />

AA.<br />

ii)<br />

For work on the jack-ups or tenders or those parts of the jack-up or tender attached to the<br />

Drilling Platform the <strong>To</strong>ol pusher shall be the AS and a delegated person from the tender or jackup<br />

the AA.<br />

All workers visiting the Drilling Platform, whether bridge linked or not, must report to the DSV at the<br />

drilling tender or jack-up.<br />

All application for permits on the Drilling Platform and attached bridge linked platforms must be made<br />

to the DSV.<br />

All application for permits on the Jack-up or Tender or those part of it attached to the Drilling Platform<br />

must be made to the <strong>To</strong>ol Pusher.<br />

8.5.3 Hot <strong>Work</strong> <strong>Permit</strong> Authorisation – CPPA/CPEMA<br />

CPPA/CPEMA Procedures apply for all hot work on Drilling Platforms, whether or not the platform has<br />

been handed over to TSW. When a platform is handed over to TSW, the procedure must be discussed<br />

and approval obtained from the relevant DSV or <strong>To</strong>ol Pusher before commencement.<br />

8.5.4 Drilling Rig PTW Systems<br />

Where a contractor owned Drilling Rig operates its own PTW system, a boundary is to be established<br />

between the area in which that system will operate and the area in which the BSP PTW system is to be<br />

operated. Agreement on this boundary should be reached between the relevant AOS and the Drilling<br />

Rig management. The area in which the BSP PTW system applies must include all areas of the fixed<br />

installation and those parts of the Drilling Rig which project into the installation boundary.<br />

It is recommended that all Drilling Rigs and Tenders should use the BSP PTW system when involved in<br />

CPRA operation.<br />

8.6 Non Compliance With <strong>Permit</strong> to <strong>Work</strong> Requirements<br />

8.6.1 Guideline on Mandatory Time Out – Relating to Non-Compliance In <strong>Permit</strong> <strong>To</strong> <strong>Work</strong> (PTW)<br />

Requirements<br />

Non-compliance with PTW system requirements is recognised as an issue. A Mandatory Time-Out,<br />

when non-compliance is encountered, is available to effectively deal with non-compliances and to<br />

improve the effectiveness of the system as a management tool for the prevention of incidents.<br />

The duration of forced Time-outs should be long enough for those involved to understand why the job<br />

has been stopped.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 70 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

A PTW is a vital control barrier in day-to-day management of hazards that have the potential to cause<br />

harm. Breaching of this barrier can result in undesirable incident that can cause harm to People,<br />

Asset, Environment, and Reputation (PAER).<br />

The guideline for the Mandatory Time out is as follows:<br />

1. On identification of any significant or serious non compliance in the work permit system<br />

requirement or application, all work under the control of the PTW concerned must be<br />

suspended immediately and the worksite made safe.<br />

2. All involved in the work must be made fully aware of the reason for the stoppage of the work<br />

before any recommencement is allowed.<br />

3. The length of the Time-Out will depend on how soon all relevant parties directly involved with<br />

the work can be brought together and briefed and made aware of the reason for the Time-Out.<br />

The Time-Out must be conducted in a suitable environment for effective discussion, and should<br />

be away from immediate vicinity of the worksite.<br />

The Mandatory Time-Out is a continuous process to monitor the effectiveness of PTW implementation.<br />

The following are required for review and monitoring purposes:<br />

1. All Mandatory Time-outs are to be highlighted in the respective location or facility daily report.<br />

2. The details of Mandatory Time-Outs will be included in all toolbox talks.<br />

3. The Training Service Provider will brief course participants on the reasons for the Mandatory<br />

Time-Outs.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 71 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

9 W O R K N O T N O R M A L L Y R E Q U I R I N G A P E R M I T<br />

<strong>Permit</strong>s to <strong>Work</strong> are MANDATORY for the control of all work that may be potentially hazardous in ALL<br />

Hydrocarbon Processing Assets, which involves breach of containment e.g. routine pigging, and ALL<br />

other Areas or Services where the Asset Holder has decided upon the use of the <strong>Permit</strong> to <strong>Work</strong> system<br />

in the Area for which they are the Post Holder. Exceptions to this rule are to be STRICTLY LIMITED.<br />

Examples of work that may normally be carried out without a <strong>Permit</strong> to <strong>Work</strong> are:<br />

• Production watch keeping and plant operations including standard checks or sampling of<br />

hydrocarbons, where these tasks are covered by Operating Procedures or Job Instructions.<br />

• Visual Inspection unless that inspection is within a confined space. (Reference HSE Standard 07<br />

Confined Spaces TMSD 1645 page 4 of 15 for examples)<br />

• Helideck operations confined to the landing and take off of helicopters.<br />

• <strong>Work</strong> carried out on Drilling Tenders, Jack-up Rigs Construction Barges or <strong>Work</strong> Boats unless<br />

the vessel is located within a 500 metres exclusion zone in which case the BSP PTW System<br />

shall be used.<br />

• Fault finding work required to bring a system back into normal operation following an<br />

unplanned shut down provided that:<br />

• The work is directly supervised by the AA for the area concerned.<br />

• The AS has advised the AA and Control Room personnel, if applicable of any hazards, or<br />

effects on other parts of the process, associated with the work.<br />

• The work does not include fault finding of a non-routine nature that may produce an unsafe<br />

situation.<br />

NB: A permit will be required if the containment of a system is to be breached or work is<br />

required on live electrical equipment.<br />

Once the fault has been identified, a <strong>Permit</strong> must be applied for in order to carry out any<br />

necessary repair or rectification.<br />

• For ‘Standard’ Wireline and Wellhead maintenance activities. A well handover form may be used<br />

(refer to Appendix 6) and <strong>Work</strong> Instruction BSP-17.3.1.3.242.0.<br />

The TSW/4 Team Leader who accepted the well on temporary handover from the Asset Holder must be<br />

an appointed WSS. The Asset Unit Supervisor handing over the well to TSW/4 Team Leader must be<br />

an appointed AS with responsibility for the area in which the well is located.<br />

<strong>Permit</strong>s to <strong>Work</strong> are not normally required for activities carried out by third parties on land, which is<br />

not a BSP operating or controlled area. However, before such work commences, BSP Legal Dept and<br />

the BSP Asset Holder concerned may wish to impose any relevant controls to ensure the safety and<br />

integrity of any BSP Assets that may be affected.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 72 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

1 0 M O N I T O R I N G , A U D I T I N G A N D R E V I E W O F T H E P T W S Y S T E M<br />

10.1 Definitions<br />

Monitoring of the PTW system consists of regular audits carried out by those responsible for ensuring<br />

the effectiveness of the <strong>Permit</strong> to <strong>Work</strong> System.<br />

Auditing is a systematic examination of the operation and effectiveness of the PTW System. Auditing is<br />

performed in accordance with written procedures and checklists, and should concentrate on an<br />

objective evaluation of evidence provided.<br />

A System <strong>Rev</strong>iew (Level 1 Audit) is an annual examination of the system, carried out after completion<br />

of an annual audit of the PTW System. The review takes into account audit findings, proposals for<br />

change and other relevant information, to assess what changes are necessary to the system to optimise<br />

its effectiveness in meeting its objectives.<br />

10.2 Objectives<br />

The objectives of Monitoring and Audit of the PTW system are:<br />

• <strong>To</strong> establish that the PTW system is being used as an effective hazard management tool.<br />

• <strong>To</strong> check that the PTW system is meeting it's stated objectives.<br />

• <strong>To</strong> provide an opportunity for identifying improvements required to the PTW system and to the<br />

system used for auditing of it.<br />

• <strong>To</strong> check that compliance with system requirements and controls is being followed.<br />

The objectives of the System <strong>Rev</strong>iew are:<br />

• <strong>To</strong> review proposals for change to the PTW system and decide on their implementation.<br />

• <strong>To</strong> review audit findings, incident reports and other relevant data to identify what improvements<br />

are required in the system.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 73 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

10.3 Auditing of the <strong>Permit</strong> to <strong>Work</strong> System<br />

Structure of the PTW Audit System<br />

ANNUAL<br />

PTW AUDIT<br />

LEAD BY HSE/4<br />

Level 1<br />

QUARTERLY PTW AUDIT,<br />

LEAD BY AREA OPERATIONS<br />

SUPERVISOR,<br />

(AOS OR EQUIVALENT)<br />

AS PART OF DEPARTMENTAL<br />

Level 2<br />

MONTHLY PTW VERIFICATION,<br />

LEAD BY OPERATIONAL STAFF,<br />

(SOS OR EQUIVALENT)<br />

AS PART OF DEPARTMENTAL ANNUAL<br />

HSE PLAN<br />

Level 3<br />

WEEKLY MONITORING OF PTW<br />

SYSTEM<br />

BY PTW AUTHORISED SIGNATORIES AND PIP<br />

COORDINATOR,<br />

(COS, FOS OR EQUIVALENT)<br />

Level 4<br />

A schematic representation of the <strong>Permit</strong> to <strong>Work</strong> audit system structure is shown above.<br />

10.3.1 Level 1 Audit<br />

Level 1 audit are to be carried out annually, and provide a formal independent check on the operation<br />

and effectiveness of the complete <strong>Permit</strong> to <strong>Work</strong> System within BSP. The audit will require a team with<br />

a Lead Auditor and is likely to last for several days, plus extra time for preparation and report<br />

production. The audit should examine the PTW system both onshore and offshore to determine its<br />

effectiveness in meeting its stated objectives of hazard identification and management. A formal set of<br />

Terms of Reference in accordance with Activity BSP-02.63, shall be developed and agreed. Before the<br />

start of the audit, the Audit Authority (AD) is to issue a memorandum concerning the audit,<br />

emphasising its importance and stating when it will take place.<br />

The Level 1 audit is to include:<br />

• A check on the frequency, standard and results of Level 2 and Level 3 Audits at those locations<br />

under audit.<br />

• Checks of the PTW system including individual permits at those locations under audit to identify<br />

whether the requirements of the PTW system are being properly applied.<br />

• An examination of PTW training arrangements and their efficiency with reference to the training<br />

master file.<br />

• A review of PTW documentation in place at the location under audit to check for accuracy and<br />

adequacy.<br />

• A review of understanding of the system, and the attitude towards it, by those personnel involved<br />

in its application at the location under audit.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 74 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

• Examination of arrangements for the appointment of Signatories, Supervisors, PIP Coordinators<br />

and authorised gas Testers to confirm satisfactory appointment controls are in place.<br />

• Examination of the arrangements for system review.<br />

• Any other checks on the system considered necessary by the auditors involved that falls within<br />

the scope of the Terms of Reference of the Level 1 audit.<br />

Any of the standard audit forms may be used to assist in the audit.<br />

The Audit Team should include representatives from HSE and other departments within BSP and from<br />

the Training Service Provider. The majority of the team members shall be experienced in operation and<br />

management of PTW systems and should have completed the PTW Auditors course.<br />

The Audit Authority is to ensure that all corrective actions required by audit reports have been properly<br />

actioned and are subject to regular monitoring.<br />

After each audit, the Audit Authority (AD) is to consider the findings and decide on those actions that<br />

should be entered into FOUNTAIN.<br />

10.3.2 Level 2 - Quarterly Audit<br />

Level 2 audits are to be carried out at intervals not exceeding 3 months using the PTW Level 2 audit<br />

form (refer Appendix 5 – Form B). Results of Level 3 audits should be entered into the Summary Sheet<br />

for Level 2 and 3 audit (refer Appendix 5 – Form A). Any findings or actions can be discussed during<br />

the daily morning meeting for the location concerned and entered into the Fountain Database Action<br />

Item Tracking System for further follow-up and action.<br />

Level 2 audits should examine the operation of the complete PTW system in the area under audit and<br />

will last for at least one working day. Level 2 audits may be carried out by auditor(s) from within the<br />

area, or by auditor(s) from other areas. The HSE Advisor for the area under audit should be invited to<br />

participate in the audit to ensure consistency.<br />

Individual auditors should have knowledge and understanding of hazard management principles and of<br />

PTW system management, gained by having:<br />

• <strong>Work</strong>ed with an established PTW system for a period not less than 1 year,<br />

• Successfully completed the BSP PTW Signatories and Auditors courses.<br />

The Level 2 Audit is to include:<br />

• Checks on the frequency, standard and results of Level 3 Audits.<br />

• Checks on the operation of the PTW System required by the Level 2 Audit Forms (refer Appendix<br />

5 – Form B).<br />

• Any other checks on the system considered necessary by the auditor after reference to previous<br />

Level 2 audits for the area under audit.<br />

The Audit Authority is to ensure that all corrective actions required by audit reports are entered into the<br />

FOUNTAIN database and are properly actioned and subject to regular monitoring.<br />

10.3.3 Level 3 - Monthly Verification<br />

Level 3 verification is to be carried out at intervals not exceeding 4 weeks. They are required to be<br />

carried out in all areas where the PTW System is implemented to verify that the system is working as<br />

intended. These audits provide regular checks on the application of the system and early notification<br />

of any emerging problem areas. They are likely to take no more than an hour to complete and will<br />

normally involve only one auditor.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 75 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Level 3 audits are to be carried out using the standard PTW Audit Forms (refer to Appendix 5, Form C).<br />

The Level 3 verification process is particularly valuable as it not only provides a verification of PTW<br />

system performance and application but also, by requiring users to audit the management of the PTW<br />

system for which they are themselves responsible, develops supervisory responsibilities. Findings or<br />

actions can be entered into the FOUNTAIN tracking system and all actions are to be checked and<br />

verified for implementation and close-out during the next Level 3 verification.<br />

10.3.4 Level 4 - Weekly Monitoring<br />

As part of their normal duties, the AS and/or the PIP Coordinator should carry out routine weekly<br />

monitoring of permits on a spot check basis. The PTW Level 4 weekly monitoring checklist is used (refer<br />

to Appendix 5, PTW Level 4 Weekly Monitoring – Form D).<br />

All findings from or actions necessary as a result of the Weekly monitoring are to be discussed during<br />

the daily morning meeting for the location concerned and entered into the PAKAT tracking system.<br />

The Level 4 weekly monitoring is audited as part of Level 3 verification.<br />

10.3.5 Responsibilities of Personnel Involved in the Audit Process<br />

The key persons involved in the audit process are the Auditor and the Audit Authority.<br />

The Auditor is the person responsible for carrying out the audit.<br />

The Audit Authority is the person to whom the audit report is presented and who is responsible for<br />

ensuring that any corrective actions required are made. The role of the Audit Authority is vital in<br />

ensuring that corrective actions are delegated and completed.<br />

Key responsibilities are:<br />

The Auditor<br />

Auditors must prepare properly for and carry out audits effectively and provide an audit report, where<br />

applicable, that sets out the findings of the audit in a concise manner. Auditors are to be aware that<br />

corrective action for non-compliances found during audits is the responsibility of the location being<br />

audited. The carrying out of an Audit does not transfer any responsibility for correcting defects from<br />

the line to the Auditor.<br />

The specific responsibilities of Auditors are:<br />

• <strong>To</strong> carry out the audit on the time and date agreed with the location being audited.<br />

• <strong>To</strong> make sufficient time available in order for the audit to be properly conducted.<br />

• <strong>To</strong> brief those involved in the audit prior to its commencement.<br />

• <strong>To</strong> concentrate on the objectives of the audit.<br />

• <strong>To</strong> conduct the audit in an alert, courteous and conscientious manner, carrying out all the checks<br />

required of the audit documentation.<br />

• <strong>To</strong> submit the report to the Audit Authority within 3 days (Level 3 audit) or 7 days (Level 2 audit).<br />

The Audit Authority<br />

The Audit Authority is to ensure that audits take place in accordance with the audit plan, and is to<br />

ensure sufficient time is made available to analyse and action audit results.<br />

Specific responsibilities of the Audit Authority are:<br />

• <strong>To</strong> have a clear definition of the Audit Level for the area for which they are the Audit Authority.<br />

• <strong>To</strong> ensure an audit programme is published.<br />

• <strong>To</strong> ensure there are sufficient trained and appointed auditors for the area of responsibility.<br />

• <strong>To</strong> ensure that audit results are analysed and actioned.<br />

• <strong>To</strong> ensure actions are properly tracked and reviewed.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 76 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

10.3.6 Audit Numbering<br />

Each Level 2 and Level 3 Audit is to be given a reference number, which is to be written in the space<br />

provided on the Audit forms. Level 1 (annual) audits are referred to simply by the year in which they<br />

were carried out.<br />

The reference number consists of 4 parts:<br />

a) A site or department identifier, e.g. AMPA9.<br />

b) The Audit Level - 2 or 3.<br />

c) The last two digits of the year in which the audit was carried out.<br />

d) The month in which the audit was carried out.<br />

These parts are to be combined into a single identifier of the format shown in the following examples:<br />

AMPA9/3/95/Aug - The Level 3 audit Ampa 9 August 1995<br />

CP7/2/01/Mar - The Level 2 audit Champion 7 March 2001<br />

10.3.7 Organisation for Audits<br />

The table below defines the Audit Authority, Auditor and audit programming and training requirements<br />

for Level 1/2/3 audits:<br />

Level 3<br />

Every month<br />

TYPE OF AUDIT<br />

Level 2<br />

Every 3 months<br />

Level 1<br />

Annual<br />

Audit Authority SOS or equivalent AOS or equivalent AD<br />

Boundary within<br />

which Audit is conducted<br />

Auditor<br />

Audit Programme<br />

Report of Findings to<br />

Audit Authority<br />

<strong>Rev</strong>iew of Corrective<br />

Actions<br />

Individual installations,<br />

locations or services<br />

Asset units, Service units<br />

Corporate<br />

Auditors should have successfully completed the appropriate PTW courses (PTW-2,<br />

3, (5) and 4).<br />

Produced as part of the AU/SU for Level 2,3 Audit<br />

annual HSE Plan<br />

Corporate HSE Plan for<br />

Level 1<br />

Within 3 days Within 7 days Within 4 weeks<br />

Area HSE Meeting<br />

Asset Holder<br />

Department HSE Meeting<br />

BSP-LT<br />

Archivist<br />

All actions held in FOUNTAIN for follow-up<br />

Reports Held in the location at which the audit was carried out Held by HSE/4<br />

10.3.8 Conduct and Level of Audits<br />

<strong>To</strong> provide a proper assessment of the operation of the PTW system, the audit must be recognised as<br />

important by both Auditors and Auditees. Auditees should show active participation through cooperating<br />

with the Auditors in giving sufficient time for the audit, when required. Auditees should<br />

provide the auditor with sound and reasoned responses to audit questions. The importance of auditing<br />

should be emphasised during HSE Meetings, particularly those where corrective actions are being<br />

reviewed.<br />

Where auditors find isolated minor errors, which are not repeated either by the individual involved or<br />

elsewhere in the area audited, they should be addressed to the individual involved, but should not<br />

constitute non-compliance.<br />

Examples of non-compliance are listed below:<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 77 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

• Repeated errors by an individual.<br />

• Errors found to be repeated elsewhere in the audit area by individuals.<br />

• A single error that could have led to an unsafe condition.<br />

• Any deliberate failure to comply with the requirements of the PTW system.<br />

In assessing whether an audit finding is a non-compliance requiring corrective action to be taken,<br />

auditors should bear in mind the definition of a non-compliance, which is:<br />

A deviation of unacceptable magnitude from the defined standard which, unless corrected, may<br />

lead to a break down of the system.<br />

10.3.9 Audit Result Categories<br />

Findings for Level 2 audits are categorised using a Risk Assessment Matrix (RAM) (refer Attachment 5,<br />

Appendix 5).<br />

The rating of the audit is given as Good, Fair, Unsatisfactory or Unacceptable.<br />

10.3.10 Audit Programme<br />

An audit programme for Level 2 & 3 audits is to be established as part of each Asst Unit/Service Unit<br />

annual HSE plan and is to form part of the departmental HSE verification matrix. The Level 1 audit is<br />

part of the annual Corporate FAU plan.<br />

Auditors may be from the Asset Holder Department or from other departments working in the area.<br />

Auditors from areas other than the area being audited may be used to provide an independent check.<br />

Level 3 verification should be scheduled on a monthly basis by location and non-compliances presented<br />

at monthly Divisional HSE meetings.<br />

Level 2 audits should be scheduled on a quarterly basis by area, and non-compliances presented as<br />

part of the Departmental HSE meeting quarterly HSE plan verification review.<br />

Level 1 audits will be scheduled by HSE Department as part of the annual corporate HSE Plan. In<br />

order to ensure that all aspects of the PTW system are examined, the Level 1 audit programme should<br />

identify specific issues and/or areas to be examined in the audit.<br />

The programme must ensure that all types of documentation are covered, and that there is a rotation of<br />

types of audit.<br />

10.4 Audit Reports<br />

Reports on Level 2 and Level 3 audits are to be submitted to the Audit Authority (refer Appendix 5 –<br />

Form A).<br />

Audit reports should:<br />

• Be brief concentrating on significant findings from the audit.<br />

• Separate non-compliances from observations.<br />

• Recommend corrective actions and delegate action parties.<br />

• Be presented to the Audit Authority for approval of the recommended actions and delegated action<br />

parties.<br />

• Be accepted and signed by the Audit Authority. The audit report then becomes a formal statement<br />

of actions required.<br />

• Be distributed to all delegated action parties and those involved in the audit.<br />

Distribution of Level 2 Audit and Level 3 Verification Reports is indicated at the foot of the Audit Form<br />

A. The report should be distributed to:<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 78 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

• Audit Authority<br />

• Delegated Action Parties<br />

• Those involved in the Audit<br />

• The Audit Archive<br />

A copy of all Level 2 audits is to be sent to HSE/4.<br />

10.5 Audit Archiving<br />

Audits for each area audited are to be kept in an archive to ensure that:<br />

• A record of required corrective actions is available.<br />

• Examination of audit records is possible to ensure the audit was correctly carried out and that<br />

the corrective actions have been taken can be made by subsequent auditors.<br />

The archives are to be maintained as follows:<br />

• The maintenance of the audit archive is to be delegated to a person responsible (PIP<br />

Coordinator or equivalent).<br />

• The archive is to contain the master copy of all audits carried out for the audit area.<br />

• The documents held in the archive are to be the Audit Report, together with all supporting audit<br />

forms and documents collected during the audit.<br />

• The archive file should include a list of all audits it contains.<br />

• The archive is to be kept in a secure location.<br />

• No information is to be removed from the Archive. If copies of audit results are required, the<br />

master must be returned immediately to the archive.<br />

• Audit reports should be held in the archive file for a period of at least12 months after the audit.<br />

10.6 System Management <strong>Rev</strong>iew<br />

10.6.1 Frequency and Objectives<br />

The PTW System Custodian (HSE/4) is to arrange for the system to be reviewed on an annual basis.<br />

The objectives of the System Management <strong>Rev</strong>iew (Level 1 Audit) are stated in para. 10.3.1.<br />

10.6.2 <strong>Rev</strong>iew Mechanism<br />

The PTW System Custodian is to conduct the review in conjunction with appropriate personnel from<br />

those areas operating the PTW system, and may involve amongst others the Training Service Provider.<br />

The review is to deliver recommendations for changes to the system, based on consideration of the<br />

following:<br />

• Audit Reports<br />

• Incident Reports<br />

• Proposals for Change<br />

• Changes to appropriate industry guidance documents<br />

• Changes to company organisation<br />

Copies of the recommendations from the review are to be circulated for agreement prior to being<br />

implemented. All resulting changes to the procedure or other documentation are to be carried out in<br />

accordance with appropriate document control procedures.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 79 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

1 1 R E F E R E N C E S<br />

Industry<br />

E&P Forum Guidelines on <strong>Permit</strong> to <strong>Work</strong> Procedures Report No. 6.29/189, January 1993<br />

<strong>Shell</strong> International Exploration and Production (SIEP)<br />

EP 95 - <strong>03</strong>15 Guidelines on <strong>Permit</strong> to <strong>Work</strong> (PTW) Systems, October 1995<br />

BSP Documents<br />

TMS 0004: Policy and Procedures for Concurrent Production and Rig Activities (CPRA)<br />

TMS 0569: Policy and Procedures for Concurrent Production and Painting Activities (CPPA)<br />

TMS 0577: Policy and Procedures for Concurrent Production and Engineering Maintenance Activities<br />

(CPEMA)<br />

BSP-02.63 Procedure for Audits and <strong>Rev</strong>iews Follow-up<br />

Offshore Diving Operations<br />

Executing Hot <strong>Work</strong> on an Offshore Production Facility<br />

HSE Standard <strong>Mod</strong>ules: BSP-02-Standard-1645 - Confined Spaces (<strong>Mod</strong>ule 07)<br />

BSP-02-Standard-1629 - Electrical Safety Rules (<strong>Mod</strong>ule 10)<br />

BSP-02-Standard-1652 - Diving and ROV Operations (<strong>Mod</strong>ule 18)<br />

BSP-02-Procedure-1645 - Incident Reporting & Follow-Up (<strong>Mod</strong>ule 30)<br />

BSP-02-Procedure-1620 - Incident Investigation Procedure (<strong>Mod</strong>ule 31)<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 80 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

1 2 L I S T O F A P P E N D I C E S<br />

APPENDIX 1:<br />

APPENDIX 2:<br />

APPENDIX 3:<br />

APPENDIX 4:<br />

APPENDIX 5:<br />

APPENDIX 6:<br />

APPENDIX 7:<br />

APPENDIX 8:<br />

APPENDIX 9:<br />

TRAINING AND APPOINTMENT OF SIGNATORIES<br />

PERMIT TO WORK DOCUMENTS<br />

PERMIT TO WORK FORMS<br />

CERTIFICATES, SAFETY CHECK LISTS & TAGS<br />

PTW AUDIT FORMS<br />

WELL SERVICES / WELL HEAD MAINTENANCE HANDOVER FORM<br />

PTW APPOINTMENT RECORD<br />

PTW APPOINTMENT FLOW CHART<br />

LIST OF APPOINTED AREAS & PTW AUTHORITY CARD<br />

APPENDIX 10: TEMPORARY ASSET HOLDER HANDOVER LETTER<br />

APPENDIX 11: MAPPABLE CHANGES FORM<br />

APPENDIX 12 : ‘3 WHATS’ RISK ASSESSMENT<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 81 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

A P P E N D I X 1 : T R A I N I N G A N D A P P O I N T M E N T O F<br />

S I G N A T O R I E S A N D S U P E R V I S O R S<br />

BSP-02-Procedure-1622<br />

SIGNATORIES (AS/AA) MAY NEITHER APPROVE OR AUTHORISE AND SUPERVISORS (WSS) MAY NOT<br />

APPLY FOR OR ACCEPT WORK COVERED BY A PERMIT WITHOUT HAVING SUCCESSFULLY COMPLETED<br />

THE APPROPRIATE PERMIT TO WORK COURSE AND BEEN APPOINTED BY AN APPOINTING AUTHORITY.<br />

In exceptional circumstances, contractor supervisors may be required as Authorised Signatories and should<br />

take the appropriate course(s).<br />

a) Training Aim<br />

<strong>To</strong> develop awareness of and competence in the responsibilities and accountabilities of roles within the<br />

<strong>Permit</strong> to <strong>Work</strong> System.<br />

b) <strong>Permit</strong> to <strong>Work</strong> Courses<br />

PTW Managing Hazards<br />

(PTW-2)<br />

PTW Supervisors<br />

(PTW-1)<br />

PTW Signatories<br />

(PTW-3)<br />

PTW Refresher<br />

(PTW-5)<br />

PTW Auditor<br />

(PTW-4)<br />

Competence levels for all PTW courses are set to ensure that persons involved in the PTW process have<br />

sufficient knowledge and understanding of the PTW system to apply it correctly.<br />

b.1 <strong>Work</strong>site Supervisor (PTW-1) – Competence level 70% (average over 3 written assessments + permit<br />

check).<br />

For <strong>Work</strong>site Supervisors and Authorised Gas Testers. Valid for 3 years.<br />

b.2 Managing Hazards at the <strong>Work</strong>place (PTW-2) – Competence level Mark 80% (average over 2 written<br />

assessments).<br />

Pre-requisite for ALL PTW Signatories AND <strong>Work</strong>site Supervisors.<br />

discretion.<br />

Validity as per Management<br />

b.3 <strong>Permit</strong> Signatories (PTW-3) – Competence level 75%. (average over 3 written assessments + permit<br />

check).<br />

For Authorised Signatories and Area Authorities and Authorised Gas Testers. Valid for 3 years.<br />

b.4 PTW Auditors (PTW-4) – Competence level 80% (1 written assessment + permit check).<br />

For proposed Level 3 and Level 2 auditors of the PTW system. It is a pre-requisite for potential<br />

Auditors to have completed PTW courses (PTW-2 and 3(5)) before taking this course. Validity as per<br />

Management discretion.<br />

b.5 PTW Refresher (PTW-5) – Competence level WSS 70% (1 written assessment + 1 permit check),<br />

AS/AA/PIP Coordinator 75% - (1 written assessment + 1 permit check). <strong>To</strong> be taken no later than<br />

3 years after attending the appropriate PTW course. Valid for 3 years.<br />

b.6 Gas Tester (FGV-4) – Competence level 75% (1 written assessment).<br />

For Gas Testers authorised to take gas tests required for hot work and prior to entry into a confined<br />

space. Valid for 3 years.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 82 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

c) Expiry of validity period<br />

When the validity period for PTW-1/3/5/FVG-4 has expired, a 3 month grace period is allowed for the<br />

AS/AA/WSS/AGT concerned to attend PTW-5/FVG/4. If the grace period has expired and PTW-5 has<br />

not been attended the AS/AA/WSS concerned must retake PTW-1/2/3 course as appropriate.<br />

Nominations<br />

Line departments wishing to nominate either BSP or contractor employees under their control for permit to<br />

work courses, should in the first instance apply through HLD/311 using the ‘Request for Local Training PTW<br />

Courses’ form. Contractors may apply directly to the Training Service Provider.<br />

Assessment<br />

All PTW Courses include a formal assessment to ensure that those attending the courses have achieved the<br />

required level of competency of the system, as defined in the relevant PTW Course Design Manuals.<br />

The re-appointment process (refer Appendix 8) requires all AS/AA/WSS to attend and demonstrate<br />

competence in a 1-day Refresher (PTW-5) no later than 3 years after attending PTW-1/3/5.<br />

If the required competence level for PTW-5 is not demonstrated by a candidate, the candidate is required to<br />

undergo coaching at the location at which they will be involved with the PTW system to be followed by<br />

attending PTW-2 followed by PTW-1/3 as appropriate. If the candidate cannot demonstrate competence level<br />

required by PTW-2/1/3, it is necessary for them to undergo a further 6 months coaching period at the<br />

location at which they will be involved with the PTW system before re-attending PTW-2/1/3 as appropriate.<br />

If the candidate is still unable to achieve the competence level required they will be subject to deployment to<br />

another position at the same job group or deployment to a position in a lower job group.<br />

Certification<br />

After having demonstrated their competence for the appropriate PTW training course, the successful<br />

candidates will receive individually numbered PTW training certificates. Separate certificates are issued for<br />

each of the six courses. The certificate contains the candidate’s name, I/C or passport number and date of<br />

course attended and expiry date of certificate (where applicable). These details will be entered into a central<br />

record held by HLD (PRISMA) and the Training Service Provider.<br />

Demonstration of Competence<br />

Before appointing a candidate to perform the role for which they have demonstrated competence at the<br />

appropriate course, the AU/SU (Appointing Authority) shall be satisfied that the candidate demonstrates the<br />

sufficient level of competence, knowledge and understanding of the following by:<br />

i. Having sufficient familiarity with the plant within their own area (AS/AA/PIP Coordinator).<br />

ii.<br />

iii.<br />

iv.<br />

Having sufficient knowledge and understanding of other areas of the Installation which may affect<br />

<strong>Permit</strong>s which they will sign (AS/AA/PIP Coordinator).<br />

Having sufficient knowledge and understanding of local <strong>Work</strong> Instructions, HSE Standards and their<br />

interface with the PTW system, or other appropriate instructions affecting controls to be taken for<br />

particular work (AS/AA/WSS/PIP Coordinator).<br />

Demonstrating competence in the application of HEMP by identifying assessing and controlling<br />

potential hazards on the Installation involved paying particular attention to whose which are<br />

Installation specific (AS/AA/WSS/PIP Coordinator).<br />

v. Having successfully completed the appropriate training courses (AA/AS/WSS/PIP Coordinator).<br />

The candidate for appointment must also demonstrate an adequate understanding of the local environment<br />

in which they are to perform a PTW role.<br />

Recognition of competence can only be decided by the Appointing Authority, who must formally appoint<br />

candidates before they begin to carry out their role within the PTW System (refer Appendix 7).<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 83 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Appointment<br />

The following personnel require formal endorsement from an Appointing Authority in recognition of their<br />

competency for their proposed PTW System role:<br />

• Authorised Signatories - SS or Senior SSS having achieved the required competency level in PTW-2 +<br />

PTW-3 (PTW-5)<br />

• Area Authorities – SSS or TAS having achieved the required competency level in PTW-2 + PTW-3 (PTW-5)<br />

• <strong>Work</strong>site Supervisors – having achieved the required competency level in PTW-1 + PTW-2 (PTW-5)<br />

• Authorised Gas Testers – having achieved the required competency level in PTW-1 or 3 + PTW-2 (PTW-5)<br />

+ FVG-4<br />

• System Auditors – having achieved the required competency level in PTW-2 + PTW-3 (PTW-5) + PTW-4<br />

• PIP Coordinator – having achieved the required competency level in PTW-2 + PTW-3 (PTW-5)<br />

Senior Authorised Electrical Persons and Authorised Electrical Persons who will work with<br />

Electrical <strong>Permit</strong>s are appointed under the procedure described in Electrical Safety Rules i.e. BSP-<br />

02-Standard-1629 (<strong>Mod</strong>ule 10).<br />

Appointment Authorities<br />

The table below shows the minimum training requirement for each of the roles. For clarity, the minimum<br />

PTW Training requirement for candidate for in each role is also shown.<br />

ROLE MINIMUM PTW TRAINING APPOINTING AUTHORITY<br />

<strong>Work</strong>site Supervisor PTW-2 + PTW-1 (PTW-5) SOS and/or HSE Adviser<br />

Area Authority PTW-2 + PTW-3 (PTW-5) + PTW-4 SOS and/or HSE Adviser<br />

Authorised Signatory PTW-2 + PTW-3 (PTW-5) + PTW-4 Department Head<br />

Gas Tester PTW-1 or 3 + PTW-2 (PTW-5) + FVG-4 SOS<br />

PIP Coordinator PTW-2 + PTW-3 (PTW-5) + PTW-4 Division Head and/or HSE Adviser<br />

LEVEL 3 Auditor PTW-2 + PTW-3 (PTW-5) + PTW-4 Department Head<br />

LEVEL 2 Auditor PTW-2 + PTW-3 (PTW-5) + PTW-4 Department Head<br />

LEVEL 1 Auditor PTW-2 + PTW-3 (PTW-5) + PTW-4 HSE Department Head<br />

Method of Appointment/Re-appointment<br />

The appointee will demonstrate that they have attended the appropriate course for their intended role using<br />

their Personal Safety Logbook (PSL). Appointment/re-appointment is for no longer than the validity<br />

period of the appropriate course(s) attended. The Appointing Authority will confirm the candidate into the<br />

proposed PTW role and in which area/facility this authority can be exercised. The Appointing Authority<br />

MUST specifies:<br />

• The <strong>Permit</strong> Authority<br />

• In which area(s) this authority is permissible<br />

For BSP and Contractor staffs who work within a specific AU/SU, that AU/SU’s Appointing Authority should<br />

carry out the appointment.<br />

If the asset is under a new Project (where the Project Manager has the ownership of the asset), then the<br />

Project Manager will be the Appointing Authority.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 84 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

PTW Appointment/Re-appointment Record<br />

The AU/SU Line Management or PTW PIP Coordinator must keep all appointment records for audit<br />

verification (refer to Appendix 7).<br />

A PTW Authority Card will be issued by the Appointment Authority (refer to Appendix 9) to a candidate<br />

successfully completing the appointment/re-appointment interview.<br />

NB: The candidate(s) PSL is the document used for verification of appointment/re-appointment and<br />

must be stamped accordingly after the appointment interview.<br />

Administration<br />

The Appointing Authority, normally the AU/SU’s Line Management, should maintain an accurate record of<br />

appointed PTW staff in their area.<br />

Contractors should be appointed by the AU/SU’s Line Management for the location in which they will carry<br />

out their proposed role.<br />

The Appointing Authority concerned will maintain an accurate database of all contractor employees<br />

appointed.<br />

Re-Qualification<br />

a) Any person occupying a role within the PTW system may be nominated for re-training in the appropriate<br />

course for that role should their line management decide.<br />

b) Any person who has not taken PTW-1 or 3 for more than 3 years must take PTW-5 refresher course<br />

irrespective of whether or not a validity period or ‘at company discretion’ was stamped on their<br />

certificates or PSL.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 85 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

A P P E N D I X 2 - P T W D O C U M E N T S<br />

BSP-02-Procedure-1622<br />

a) List of Documents<br />

Title Reference Number Last <strong>Rev</strong>ision<br />

Equipment Disjointing <strong>Permit</strong> <strong>03</strong>/HSE 06.01<br />

Hot <strong>Work</strong> <strong>Permit</strong> 04/HSE 04.96<br />

Cold <strong>Work</strong> <strong>Permit</strong> 05/HSE 12.95<br />

Electrical <strong>Permit</strong> to <strong>Work</strong> 01/EDE 11.95<br />

Diving Operations <strong>Permit</strong> 06/HSE 12.04<br />

Isolation/De-Isolation Certificate (M) 09/HSE 12.95<br />

Isolation/De-Isolation Certificate (E) 02/EDE 11.95<br />

Safety System Isolation Override Certificate 11/HSE 12.95<br />

Master Isolation Control Certificate 12/HSE 12.95<br />

Confined Space Entry Certificate 14/HSE 01.04<br />

Excavation Certificate 15/HSE 01.04<br />

Scaffolding Certificate 18/HSE 12.95<br />

Hot <strong>Work</strong> on Live Production Facility Certificate 19/HSE 01.04<br />

Certificate History Sheet 20/HSE 12.95<br />

Instruction to Fire Watcher (Card) 21/HSE 07.94<br />

Instruction to Overside Watcher (Card) 22/HSE 07.94<br />

Instruction to Standby Person (Confined Space<br />

Entry Card)<br />

23/HSE 07.94<br />

Diving Checklist for Vessel 07/HSE <strong>03</strong>.96<br />

Isolation Tag - Valve 35/HSE 11.94<br />

Isolation Tag - Spade 36/HSE 08.94<br />

Caution Notice Tag <strong>03</strong>/EDE 11.95<br />

Danger Notice Tag 06/EDE 11.95<br />

Circuit Earthed Notice Tag 07/EDE 11.95<br />

Sanction for Test 04/EDE 11.95<br />

Limitation of Access 05/EDE 11.95<br />

Switching Programme (Page 1) 09.1/EDE 11.95<br />

Switching Programme (Page 2) 09.2/EDE 11.95<br />

Authorisation Certificate - Electrical* 08/EDE 11.95<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 86 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

b) Document Numbering System<br />

All documents used within the BSP <strong>Permit</strong> to <strong>Work</strong> system have a unique number which identifies the<br />

individual document, its owner and the date on which the document was last revised. The number is printed<br />

on the bottom right-hand corner.<br />

04/HSE/1195<br />

Document Number<br />

Document Owner<br />

Date of Last<br />

<strong>Rev</strong>ision<br />

The date of revision in the number is for internal HSE reference purposes and does not normally have to be<br />

used. The dates listed in this module refer to the last revision dates at the time this module was printed.<br />

c) Ordering PTW Documents<br />

PIP Coordinators or persons nominated for management of PIP of respective AU/SU should maintain<br />

adequate copies of all relevant PTW documents used within their own respective locations.<br />

<strong>To</strong> order copies of PTW documents, a STATIONERY ORDER FORM is raised and sent to HRS/37 together<br />

with a sample of the hard copies of the PTW documents required (to avoid errors and hence delay in delivery).<br />

HRS/37 will raise SAP for ordering as requested.<br />

Attention is drawn to the following points:<br />

1) Training service providers and contractors who require PTW documentation must order through their<br />

Contract Holder.<br />

2) A delivery point must be identified.<br />

3) Queries with regard to difficulties or delays in delivery of any documents should be addressed to HSE<br />

Advisor/Contract Holder.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 87 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

A P P E N D I X 3 P T W F O R M S<br />

BSP-02-Procedure-1622<br />

Fig 1: Cold <strong>Work</strong> <strong>Permit</strong><br />

Fig 2: Hot <strong>Work</strong> <strong>Permit</strong><br />

Fig 3: Equipment Disjointing <strong>Permit</strong><br />

Fig 4: Electrical <strong>Work</strong> <strong>Permit</strong><br />

Fig 5: Diving Operation <strong>Permit</strong><br />

Fig 6: Diving Operation <strong>Permit</strong> - continued<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 88 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 1: Cold <strong>Work</strong> <strong>Permit</strong><br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 89 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 2: Hot <strong>Work</strong> <strong>Permit</strong><br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 90 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 3: Equipment Disjointing <strong>Permit</strong><br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 91 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 4: Electrical <strong>Permit</strong> to <strong>Work</strong><br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 92 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 5: Diving Operations <strong>Permit</strong> Page 1<br />

DIVING OPERATIONS PERMIT<br />

Certificate No.<br />

Page 1 of 2<br />

DIST: Yellow – <strong>Work</strong>site, Green – <strong>Permit</strong> Issue Point<br />

D<br />

1. APPLICATION by Performing Authority (Diving Supervisor<br />

or CSR)<br />

FOR THE ATTENTION OF:<br />

LOCATION<br />

Planned Time Date<br />

Continued from Fax<br />

<strong>Work</strong><br />

Schedule<br />

Start<br />

Finish<br />

<strong>Permit</strong> No: ________________<br />

_________________<br />

DSV Tel No: ________________________ DSV Fax No: ______________________<br />

Supv/CSR Name:____________________Signature: _________________Date: ____________Time: ____________Ind: _________<br />

2. DESCRIPTION OF WORK ROUTINE NON-ROUTINE<br />

3. SAFETY PRECAUTIONS DURING DIVING ACTIVITIES (BSP-71.3.1.3.206.1)<br />

Is Electrical <strong>Work</strong> Required Yes No<br />

ACTIONS PRIOR TO DIVING OPERATIONS:<br />

1. Confirm requirements of BSP-71.3.1.3.206.1 are fully complied with.<br />

2. Sump to be cleared of all chemical waste prior to the start of operations and then<br />

6. The following isolations will be required:<br />

SUPPORTING DOCUMENTS ATTACHED<br />

cleared daily prior to re-validation of this permit.<br />

3. DIVERS DOWN boards to be placed at all access points to the platform (Main<br />

manned Complex only).<br />

4. No additional permit to be issued on the diving complex during diving operations,<br />

without discussion between C.S.R and Authorised Signatory.<br />

5. STL to be informed that no. boats are to approach within 500 metres of the diving<br />

operations without requesting permission from the diving C.S.R on VHF Ch. 15.<br />

Certificates √ Number<br />

Isolation Mechanical<br />

Isolation Electrical<br />

EDP<br />

Area<br />

Authority,<br />

initial<br />

checked<br />

SCL<br />

4. HAZARD IDENTIFICATION AND SPECIAL PRECAUTIONS<br />

5. APPROVAL by Asset Holder Authorised Signatory<br />

I have examined the <strong>Work</strong> Description, Preparations and Precautions stated above, I agree they are correct. This <strong>Permit</strong>, when properly<br />

authorised and accepted at Boxes 6 and 7 below, will be valid for a MAXIMUM of 5 DAYS. <strong>Work</strong>site Preparations and Isolations may<br />

now proceed.<br />

Name: ___________________________ Signature: ________________<br />

RPE IF ELECTRICAL WORK REQUIRED<br />

From Time: _________________________ on Date: _________________<br />

<strong>To</strong> Time: ___________________________ on Date: _________________<br />

Name: ________________________ Ind: _____________ Signature: _______________Time: ___________ Date: __________<br />

TO BE REAUTHORISED EVERY<br />

HOURS (DELETE AS APPLICABLE)<br />

6. AUTHORISATION BY Area Authority<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 93 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

I certify that all isolations and depressurisation and actions necessary for Diving Operations to commence have been carried out. I<br />

authorise the work as described to be carried out subject to the above safety precautions. I will inform the diving vessel C.S.R<br />

immediately should it be necessary to deviate from or it becomes impossible to comply with, any of the safety precautions listed on this<br />

permit.<br />

Name: ________________________ Ind: _____________ Signature: _______________Time: ___________ Date: __________<br />

7. DECLARATIONS AND ACCEPTANCE by Diving Supervisor/ C.S.R<br />

I understand and declare that work will only take place when all of the above safety precautions are complied with. I understand that<br />

this <strong>Permit</strong> only applies for underwater work and must then be re-authorised as indicated in box 5.<br />

Name: ________________________ Ind: _____________ Signature: _______________Time: ___________ Date: __________<br />

06/HSE/12.04<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 94 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 6: Diving Operations <strong>Permit</strong> Page 2<br />

DIVING OPERATIONS PERMIT<br />

Certificate No.<br />

Page 2 of 2<br />

DIST: Yellow – <strong>Work</strong>site, Green – <strong>Permit</strong> Issue Point<br />

D<br />

8. RE-AUTHORISATION<br />

a. ACCEPTANCE BY DIVING SUPV/C.S.R b. RE-AUTHORISATION BY ASSET HOLDER<br />

c. RE-AUTHORISATION BY<br />

CSR<br />

<strong>To</strong> be signed by the oncoming Diving Supv<br />

or CSR whenever the permit is reauthorised<br />

and whenever responsibility<br />

passes from one to another.<br />

ADDITIONAL DIVING SUPV/ C.S.R<br />

Specimen Signature<br />

1) Name____________Signature________<br />

2) Name____________Signature________<br />

I have inspected the worksite and am satisfied<br />

that it is safe to continue work. I will ensure that<br />

the <strong>Permit</strong> conditions and precautions are<br />

adhered to.<br />

Re-authorisation by CSR (on behalf of the AA) is<br />

permitted subject to logged verbal communication with<br />

the asset that operations may proceed.<br />

ADDITIONAL AREA AUTHORITY<br />

Specimen Signature<br />

1) Name: ______________ Signature: ________<br />

2) Name: ______________ Signature: ________<br />

3) Name: ______________ Signature: ________<br />

4) Name: ______________ Signature: ________<br />

I am satisfied that it is safe for the work specified.<br />

I re-authorise the permit for the period stated,<br />

provided the conditions established by the <strong>Permit</strong><br />

are maintained.<br />

Record of logged verbal<br />

communication with the asset<br />

control room. Record name of<br />

person spoken to on asset.<br />

Name<br />

(AS/AA)<br />

Date/Ti<br />

me<br />

CSR<br />

Initial<br />

WORK SUPERVISION<br />

<strong>To</strong> be signed below by the off<br />

going Diving C.S.R whenever<br />

work stops for more than 4<br />

hours, or when supervisory<br />

responsibility changes<br />

I have inspected the worksite.<br />

It has been left in a clear and<br />

safe condition.<br />

NAME<br />

DEPT<br />

RESPONSIBLE<br />

FROM<br />

TIME DATE<br />

SIGNA<br />

TURE<br />

VALID FROM<br />

VALID UNTIL<br />

TIME DATE TIME DATE<br />

SIGNA<br />

TURE<br />

TIME<br />

DATE<br />

SIGNA<br />

TURE<br />

9. PERMIT CANCELLATION – WORK COMPLETE 10. PERMIT CANCELLATION – WORK NOT COMPLETE<br />

a) PERMIT RETURN BY DIVING SUPERVISOR/ C.S.R a) PERMIT RETURN BY DIVING SUPERVISOR/ C.S.R<br />

I declare that the underwater work described above has<br />

been completed. All underwater equipment/rigging has<br />

been recovered and the site has been left in a safe and<br />

undamaged condition. This has been verified by<br />

I declare that the underwater work described above has not<br />

been completed. All underwater equipment/rigging has<br />

been recovered and the site has been left in a safe and<br />

undamaged condition. This has been verified by<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 95 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

ROV/Diver inspection.<br />

ROV/Diver inspection.<br />

Name: _______________________ Time: ________________<br />

Signature: ____________________ Time: ________________<br />

Name: _______________________ Time: ________________<br />

Signature: ____________________ Time: ________________<br />

b) PERMIT CANCELLATION BY AREA AUTHORITY b) PERMIT CANCELLATION BY AREA AUTHORITY<br />

* Delete as appropriate.<br />

* Delete as appropriate.<br />

<strong>Work</strong> complete. <strong>Work</strong>site Clear and Safe.<br />

* Re-instatements/De-isolation Complex.<br />

* Isolations retained under Cert. No.(s) _____________________<br />

<strong>Work</strong> complete. <strong>Work</strong>site Clear and Safe.<br />

* Re-instatements/De-isolation Complex.<br />

* Isolations retained under Cert. No.(s) _____________________<br />

Name: _________________ ind: __________ Time: __________<br />

Signature: __________________ Date: ____________________<br />

Name: _________________ ind: __________ Time: __________<br />

Signature: __________________ Date: ____________________<br />

06/HSE/12.04<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 96 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

A P P E N D I X 4 C E R T I F I C A T E S , S A F E T Y C H E C K L I S T S & T A G S<br />

Certificates:<br />

Fig 7:<br />

Fig 8:<br />

Fig 9:<br />

Fig. 10<br />

Fig.11<br />

Fig 12<br />

Isolation / De-Isolation Certificate (Mechanical)<br />

Isolation /De-isolation Certificate (Electrical)<br />

Master Isolation Control Certificate / Spade Register<br />

Safety System Isolation / Override Certificate<br />

Confined Space Entry Certificate<br />

Confined Space Entry – <strong>Rev</strong>erse side<br />

Fig. 13 Excavation Certificate - Page 1 of 2<br />

Fig. 14 Excavation Certificate - Page 2 of 2<br />

Fig. 15<br />

Fig. 16<br />

Fig 17<br />

Fig. 18<br />

Hazard Identification Plan<br />

Certificate History Sheet<br />

Hot <strong>Work</strong> on Live Production Facility Certificate<br />

Scaffolding Certificate<br />

Briefing Cards for Personnel involved in Standby Duties:<br />

Fig. 19<br />

Fig. 20<br />

Fire Watcher Duty (English/Malay)/Confined Space Standby Person<br />

Diving Vessel Safety Checklist<br />

Tags:<br />

Fig. 21<br />

Fig. 22<br />

Fig. 23<br />

Valve Isolation Tag<br />

Spade Isolation Tag<br />

Caution Notice Tag<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 97 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 7: Isolation/De-Isolation Certificate ( Mechanical)<br />

1. APPLICATION by Performing Authority<br />

THIS IS NOT A PERMIT TO WORK<br />

ISOLATION/DE-ISOLATION<br />

CERTIFICATE (MECHANICAL)<br />

DIST: Yellow – <strong>Work</strong>site, Green – <strong>Permit</strong> Issue Point<br />

Certificate No:<br />

ISO – M<br />

Name: _______________________________ Installation: ___________________________ Equipment Disjointing<br />

<strong>Permit</strong> No: ____________<br />

Contractor/Dept: _______________________ <strong>Work</strong>site: _____________________________ Initiating <strong>Work</strong><br />

<strong>Permit</strong> No: ____________<br />

Signature: ____________________________ Equipment: ___________________________ <strong>Work</strong> Continuing<br />

on <strong>Permit</strong> No: 1<br />

Date: ________________________________<br />

2<br />

2. REASON FOR ISOLATION by <strong>Work</strong>site Supervisor<br />

3<br />

3. DETAILS OF ISOLATION/DE-ISOLATION by Authorised Signatories (Initial and date)<br />

VALVE/LINE No:<br />

VALVE<br />

ISOLATION<br />

TAG No:<br />

VALVE<br />

OPEN<br />

VALVE<br />

CLOSED<br />

SPADE<br />

ISOLATION<br />

TAG No:<br />

SPADE<br />

ISOLATED<br />

SPADE DE-<br />

ISOLATED<br />

4. ISOLATION 5. DE-ISOLATION<br />

4a. Approved By Authorised Signatory<br />

Name: ___________________________ Signature: ______________<br />

Time: _____________ Date: _______________ Ind: ______________<br />

5a. Approved By Authorised Signatory<br />

Name: ___________________________ Signature: ______________<br />

Time: _____________ Date: _______________ Ind: ______________<br />

4b. Valve Isolation By Area Authority<br />

Name: ___________________________ Signature: ______________<br />

Time: _____________ Date: _______________ Ind: ______________<br />

5b. De-Spaded By Performing Authority<br />

Name: ___________________________ Signature: ______________<br />

Time: _____________ Date: _______________ Ind: ______________<br />

4c. Spade Isolated by <strong>Work</strong>site Supervisor<br />

Name: ___________________________ Signature: ______________<br />

Time: _____________ Date: _______________ Ind: ______________<br />

5c. Valve De-Isolation by Area Authority<br />

Name: ___________________________ Signature: ______________<br />

Time: _____________ Date: _______________ Ind: ______________<br />

6. EXTENDED PERIOD ISOLATION This section to be completed when this Certificate<br />

remains in force without an associated <strong>Permit</strong><br />

Reason for EPI<br />

No. of Cancelled <strong>Permit</strong>:<br />

EPI Authorised by<br />

(Senior Operation<br />

Supervisor)<br />

EPI ON<br />

_____________________<br />

_____________________ Name<br />

_____________________ Signature<br />

_____________________ Time<br />

_____________________ Date<br />

No. of New <strong>Permit</strong>:<br />

Removal of EPI<br />

Authorised by<br />

(Senior Operation<br />

Supervisor)<br />

EPI OFF<br />

_____________________<br />

_____________________ Name<br />

_____________________ Signature<br />

_____________________ Time<br />

_____________________ Date<br />

09/HSE/1295<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 98 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 8: Isolation/De-Isolation Certificate (Electrical)<br />

(Authorised by Senior Operation Supervisor)<br />

(Authorised by Senior Operation Supervisor)<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 99 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 9: Master Isolation Control Certificate<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 100 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 10: Safety System Override<br />

1. APPLICATION by <strong>Work</strong>site Supervisor<br />

THIS IS NOT A PERMIT TO WORK<br />

SAFETY SYSTEM ISOLATION/<br />

OVERRIDE CERTIFICATE<br />

DIST: Yellow – <strong>Work</strong>site, Green – <strong>Permit</strong> Issue Point<br />

Certificate No:<br />

SSI<br />

Name: _______________________________ Location/ Original Associated <strong>Work</strong><br />

Installation: ___________________________ <strong>Permit</strong> No: ____________________<br />

Contractor/Dept: _______________________<br />

<strong>Work</strong>site: _____________________________<br />

1<br />

Signature: ____________________________<br />

<strong>Work</strong> Continuing 2<br />

Contractor: ____________________________ on <strong>Permit</strong> No:<br />

3<br />

Date: ________________________________<br />

2. REASON FOR ISOLATION by <strong>Work</strong>site Supervisor<br />

3a. DETAILS OF ISOLATION/OVERRIDE by Authorised Signatory/SOS<br />

TYPE:<br />

(tick)<br />

ISOLATION<br />

OVERRIDE<br />

MECHANICAL ELECTRICAL INSTRUMENT<br />

3b. DETAILS OF ACTIONS REQUIRED TO PROVIDE SAFEGUARDS WHILE SYSTEM IS ISOLATED/OVERRIDDEN<br />

4. ISOLATION 5. DE-ISOLATION<br />

Authorised By (Name): ________________________________________<br />

SENIOR OPERATION SUPERVISOR<br />

Signature: __________________________________________________<br />

Time: ___________________ Date: _____________________________<br />

Carried out By: _________________________ Ind: _________________<br />

Signature: __________________________________________________<br />

Time: ___________________ Date: _____________________________<br />

Authorised By (Name): ________________________________________<br />

SENIOR OPERATION SUPERVISOR<br />

Signature: __________________________________________________<br />

Time: ___________________ Date: _____________________________<br />

Carried out By: _________________________ Ind: _________________<br />

Signature: __________________________________________________<br />

Time: ___________________ Date: _____________________________<br />

6. EXTENDED PERIOD ISOLATION This section to be completed when this Certificate<br />

Remains in force without an associated <strong>Permit</strong><br />

Reason for EPI<br />

No. of Cancelled <strong>Permit</strong>:<br />

EPI Authorised by<br />

(Senior Operation<br />

Supervisor<br />

EPI ON<br />

_____________________<br />

_____________________ Name<br />

_____________________ Signature<br />

_____________________ Time<br />

_____________________ Date<br />

No. of New <strong>Permit</strong>:<br />

Removal of EPI<br />

Authorised by<br />

(Senior Operation<br />

Supervisor)<br />

EPI OFF<br />

_____________________<br />

_____________________ Name<br />

_____________________ Signature<br />

_____________________ Time<br />

_____________________ Date<br />

11/HSE/1295<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 101 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 11: Confined Space Entry<br />

1. APPLICATION by <strong>Work</strong>site Supervisor<br />

THIS IS NOT A PERMIT TO WORK<br />

CONFINED SPACE ENTRY CERTIFICATE<br />

DIST: Yellow – <strong>Work</strong>site, Green – <strong>Permit</strong> Issue Point<br />

Certificate No:<br />

CS<br />

Name: _______________________________ Location/ Original Associated <strong>Work</strong><br />

Installation: ___________________________ <strong>Permit</strong> No: ____________________<br />

Contractor/Dept: _______________________<br />

<strong>Work</strong>site: _____________________________<br />

1<br />

Signature: ____________________________<br />

<strong>Work</strong> Continuing 2<br />

Contractor: ____________________________ on <strong>Permit</strong> No:<br />

3<br />

Date: ________________________________<br />

2. SAFETY PRECAUTIONS REQUIRED (Area Authority to check)<br />

Items to be Checked by Area Authority before Confined Space Entry can proceed:<br />

1. Plant/equipment has been removed from service and all persons concerned have been notified. …………………<br />

Checked and<br />

Complete (Initial)<br />

2. a. The above plant has been isolated from all sources of dangerous liquids, gases and fumes by insertion of<br />

spades or by removing a section of pipework and blanking open ends closest to the vessel. ……………….....<br />

b. Plant/equipment has been isolated from all sources of electrical and mechanical power. ………………………<br />

c. Isolation Certificate Nos. ………………………………………………………………………………………………..<br />

3. All flushing/inert gas purging completed and inert gas connection disconnected ……………………………………. .<br />

4. Plant/equipment in the surrounding area checked safe from hazards arising from concurrent work/operations……<br />

5. Life lines, breathing apparatus and resuscitation equipment available. …………………………………………………<br />

6. Adequate access and exits is provided. …………………………………………………………………………………….<br />

7. Air moving equipment installed and operational. Vessel is cool. ………………………………………………………..<br />

8. Procedures and rescue plans made and discussed with the <strong>Work</strong>site Supervisor and personnel entering vessel<br />

and standby personnel. ……………………………………………………………………………………………………….<br />

9. Standby person appointed and briefed on their duties by the <strong>Work</strong>site Supervisor using Confined Space Standby<br />

Person briefing card. ………………………………………………………………………………………………………….<br />

3. GAS TESTING<br />

Confined Space Tested ________________________________________________________________________________________________________<br />

OXYGEN<br />

HYDROCARBON<br />

% LEL<br />

TOXIC ppm OTHER COMMENTS<br />

Name _____________________________________ Signature _______________________________ Time ___________________ Date _____________<br />

4. AUTHORISATION TO ENTER CONFINED SPACE BY AREA AUTHORITY<br />

I certify that the above results indicate that the confined space covered by this certificate is<br />

SAFE UNSAFE to enter<br />

Gas tests to be repeated at intervals of _____________________ hours<br />

Gas tests to be continuous YES NO<br />

The Certificate is valid until:<br />

hours ____________________ date _____________________<br />

Name _____________________________________ Signature _______________________________ Time ___________________ Date _____________<br />

14/HSE/1295<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 102 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 12: Confined Space Entry (continued)<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 1<strong>03</strong> of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 13: Excavation<br />

THIS IS NOT A PERMIT TO WORK<br />

EXCAVATION CERTIFICATE<br />

Page 1 of 2<br />

Certificate No.<br />

EX<br />

DIST: Yellow – <strong>Work</strong>site, Green – <strong>Permit</strong> Issue Point<br />

1. APPLICATION by <strong>Work</strong>site Supervisor<br />

Name: ____________________<br />

Location/<br />

Installation: ___________________<br />

Original Associated <strong>Work</strong><br />

<strong>Permit</strong> No: _______________<br />

Contractor/Dept:________________<br />

<strong>Work</strong>site: ____________________<br />

Signature:____________________<br />

Contractor: _________________<br />

Date:_________________________<br />

2. DETAILS OF EXCAVATION (<strong>Work</strong>site Supervisor)<br />

<strong>Work</strong> continuing on <strong>Permit</strong> No:<br />

1<br />

2<br />

3<br />

3. ATTACHMENTS (<strong>Work</strong>site Supervisor)<br />

- 1 scale (1:500) drawing provided by TSM/221 required:<br />

Yes<br />

No<br />

- Drawings :<br />

(Specify)<br />

- Sketch :<br />

(Specify)<br />

- Other :<br />

(Specify)<br />

4. KNOWN UNDERGROUND SERVICES by appropriate Asset Holder<br />

Detail of known buried service(s): i.e. cable & pipe diameters, voltages, gas & liquid pressures, method of marking etc.<br />

3.1 Electrical : _____________________________________________ REF IND SIGNATURE<br />

3.2 Gas : _____________________________________________<br />

3.3 Flammable Liquid : _____________________________________________<br />

3.5 Sewer : ______________________________________________<br />

3.5 Water Main : ______________________________________________<br />

3.6 Instrument : ______________________________________________<br />

3.7 Telecom : ______________________________________________<br />

3.8 Others : ______________________________________________<br />

5. OTHER UNDERGROUND SERVICES THAT MAY BE PRESENT (ASSET HOLDER DEPARTMENT)<br />

Distribution:<br />

1. IN ALL CASES : TSM IMT PPA/1 DOP/1<br />

2. IF AFFECTED : PPA/3 LGL<br />

3. FOR GOVERNMENT : Chairman, Location of Services Committee, KB<br />

INSTALLATIONS IF Assistant Controller of Telecoms, KB<br />

AFFECTED<br />

District Senior Executive Engineer, Public <strong>Work</strong>s Dept, KB<br />

Chairman, Municipal Council, KB<br />

District Electrical Engineer, KB<br />

15/HSE/01.04<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 104 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 14: Excavation (continued)<br />

EXCAVATION CERTIFICATE<br />

Page 2 of 2<br />

DIST: Yellow – <strong>Work</strong>site, Green – <strong>Permit</strong> Issue Point<br />

6. PRECAUTIONS (Area Authority)<br />

Certificate No.<br />

EX<br />

YES<br />

NO<br />

6.0 All excavations and digging to comply with BSP-02-Standard-1643, <strong>Mod</strong>ule No. 5<br />

6.1 Contact has been made with Government Departments<br />

6.2 All known and identified services shall be located and marked in the field using wooden pegs<br />

6.3 Pilot trenches to be hand dug to a maximum depth of 1.2 meters per step<br />

6.4 Excavation may be carried out by mechanical means after pilot trenches are completed<br />

6.5 Service tracing equipment is to be used before/during* excavation<br />

6.6 Personnel carrying out excavation operations to wear insulating rubber boots/gloves*<br />

6.7 Shoring/battering/benching* to be applied<br />

6.8 Standby person to be provided<br />

6.9 Adequate barriers and sign boards to be provided<br />

(*Delete word that do not apply)<br />

Required action if service is damaged (specify) _____________________________________________________________________<br />

___________________________________________________________________________________________________________<br />

______________________________________________________________________________<br />

___________________________________________________________________________________________________________<br />

___________________________________________________________________________________________________________<br />

6.11 Further precautions to be taken (specify): _____________________________________________________________________<br />

___________________________________________________________________________________________________________<br />

______________________________________________________________________________<br />

______________________________________________________________________________<br />

______________________________________________________________________________<br />

7. ACCEPTANCE by <strong>Work</strong>site Supervisor<br />

I understand all the above safety precautions. I will ensure that work only takes place when all these safety<br />

precautions are compiled with.<br />

Name: __________________ Signature:___________ Indicator/Contractor: ________________ Date: __________<br />

8. AUTHORISATION by Area Authority<br />

I have examined the description of the work proposed in the application portion of the <strong>Work</strong> <strong>Permit</strong> referred to in<br />

Box 1, and the additional information on this certificate. I am satisfied that the controls required by the <strong>Work</strong><br />

<strong>Permit</strong> and the Supporting Documents are appropriate. I agree to the Excavation work being carried out, subject<br />

to the controls and conditions specified being complied with during the validity period specified on the <strong>Work</strong><br />

<strong>Permit</strong>.<br />

Name: _____________________ Signature: ________________ Indicator:________________ Date: ___________<br />

15/HSE/01.04<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 105 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 15: Hazard Identification Plan<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 106 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 16: Certificate History Sheet<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 107 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 17: Hot <strong>Work</strong> On Live Production Facility<br />

HOT WORK ON LIVE PRODUCTION<br />

FACILITY<br />

DIST: Yellow – <strong>Work</strong>site, Green – <strong>Permit</strong> Issue Point<br />

1. APPLICATION by <strong>Work</strong>site Supervisor<br />

Certificate No.<br />

LIV<br />

Name: ____________________<br />

Location/<br />

Installation:___________________<br />

Original Associated <strong>Work</strong><br />

<strong>Permit</strong> No: _______________<br />

Contractor/Dept:________________<br />

<strong>Work</strong>site :____________________<br />

Signature:_____________________<br />

Date:_________________________<br />

2. INFORMATION (<strong>Work</strong>site Supervisor and Area Authority)<br />

<strong>Work</strong> continuing on Hot <strong>Work</strong> <strong>Permit</strong><br />

No:<br />

1<br />

2<br />

3<br />

Open Flame Yes No Welding Yes No Grinding/Blasting Yes No<br />

CPRA Yes No CPEMA Yes No CPPA Yes No<br />

Hot Tap Yes No Hot tap requirements Yes No Hazardous Area Yes No<br />

Complied with and attached<br />

Drawings available on site<br />

HAZARD Distance (Metres) Pressure (kPa) HAZARD Distance (Metres) Pressure (kPa)<br />

Process lines<br />

Vents<br />

Pressure Control<br />

Valves<br />

Level Control<br />

Valves<br />

Sump<br />

Vessels<br />

Relief Valves<br />

‘P’ Pilots<br />

Instrument gas<br />

Tell tales<br />

3. SPECIFIC PRECAUTIONS (<strong>Work</strong>site Supervisor and Area Authority)<br />

4. DECLARATION by <strong>Work</strong>site Supervisor and Area Authority<br />

We have personally checked the worksite and confirm that the hazards associated with the proposed work have been properly identified and that the<br />

operational requirements for Hot <strong>Work</strong> on a Live Production Facility are in place and can be complied with throughout the duration of the proposed work.<br />

We are satisfied that the controls are suitable for the proposed Hot <strong>Work</strong> on a Live Production Facility to be undertaken, subject to the approval of the work<br />

permit by the Authorised Signatory responsible for the area in which the proposed work is to take place.<br />

Name: _______________________ Ind: __________ Name: _____________________ Ind: _______________ Time: ____________ Date: __________<br />

WORKSITE SUPERVISOR<br />

AREA AUTHORITY<br />

Signature: ___________________________________ Signature: _____________________________________ Time: ____________ Date: __________<br />

5. APPROVAL by Authorised Signatory<br />

I have examined the description of the work proposed in the application portion of the Hot <strong>Work</strong> <strong>Permit</strong> referred to in Box 1, and the additional information<br />

provided by the certificate. I am satisfied that the controls specified on the permit and the supporting documents are appropriate. I approve the issue of the<br />

Hot <strong>Work</strong> <strong>Permit</strong> for this work, subject to the controls and conditions specified being complied with during the validity period specified on the permit.<br />

Offshore: On or below Spider Deck/<br />

Complex or Field Operation Supervisor<br />

Name: _________________________ Ind: _____________<br />

Boat Landings:<br />

Above Spider Deck/Landing:<br />

Senior Offshore Supervisor<br />

Signature: ______________________ Date: ____________ Onshore: Tali Field, Land Fields,<br />

Time: ____________ Tank Groups, Seria Terminal Operation Senior Supervisor<br />

19/HSE/01.04<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 108 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 18: Scaffolding<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 109 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 19: Safety Checklist Instruction Cards<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 110 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 20: Diving Safety Checklist for Vessel<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 111 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 21: Valve Isolation Tag<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 112 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 22: Spade Isolation Tag<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 113 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Figure 23: Caution Notice Tag<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 114 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

A P P E N D I X 5 - P T W A U D I T F O R M S<br />

BSP-02-Procedure-1622<br />

Attachment 1 : Form A: Summary Sheet Level 2 and 3 Audits<br />

Attachment 2 : Form B: Level 2 Audit Verification Form<br />

Attachment 3 : Form C: Level 3 Audit Verification Form<br />

Attachment 4 : Form D: Level 4 Monitoring Form<br />

Attachment 5 : Guide to classifications Matrix and Ratings<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 115 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

SUMMARY SHEET - LEVEL 2 and 3 AUDITS<br />

Form A<br />

Audit Reference No:<br />

FORM A<br />

BSP PTW AUDIT REPORT LEVEL 2 AUDIT & LEVEL 3 VERIFICATION<br />

Auditor Name(s):<br />

<strong>Permit</strong> Type (Level 3 Verification only):<br />

BSP Ref. Ind.:<br />

<strong>Permit</strong> No (Level 3 Verification only):<br />

FINDINGS<br />

Overall Rating:<br />

Signature of Auditor(s):<br />

Signature of Audit Authority:<br />

Date:<br />

Date:<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 116 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

<strong>Permit</strong> to <strong>Work</strong> Level 2 Audit<br />

BSP-02-Procedure-1622<br />

Form B<br />

PERMIT AUDIT FORM B LEVEL 2 Page 1 of 1<br />

Audit Area: Audit Reference No.: Audit Date:<br />

Auditor Name:<br />

QUESTIONS ANSWER REMARKS<br />

Are Level 3 & 4 Verifications carried out? (Evidence provided)<br />

Are Level 3 & 4 Verifications findings discussed?<br />

Are Verifications findings rectified/actioned?<br />

Is HEMP applied in PTW application?<br />

Does PTW use the health hazards identified in the HRA studies?<br />

Are PTWs issued used correctly to manage hazards?<br />

Is lateral learning from PTW related incidents discussed?<br />

Is a Job Hazard Analysis used? What type? Who produces it? Is there a link to<br />

HRA?<br />

Is the definition of Hazardous Area for the location under audit clear to all<br />

personnel involved in the PTW system?<br />

Are completed permits properly cancelled?<br />

Are cancelled permits properly archived?<br />

Are related certificates properly cancelled?<br />

Are related forms, certificates, tags and HCL included in the archive?<br />

Is the plot plan (PIP) used to identify conflicting work?<br />

Is the current revision of HSE Standard <strong>Mod</strong>ule 3 available at the PIP?<br />

Have the PTW users attended all relevant courses?<br />

Are the EPI documents correct?<br />

Has the correct information been entered on certificates in EPI?<br />

Is the EDP being used as designed for disjointing work?<br />

Are controls identified on the Hazard Check List being transferred to the PTW?<br />

Are Safety System Override Certificates used correctly and overrides removed<br />

when they are suspended or cancelled?<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

Yes/No<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 117 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

<strong>Permit</strong> to <strong>Work</strong> Level 3 Verification<br />

BSP-02-Procedure-1622<br />

Form C<br />

PERMIT AUDIT FORM C LEVEL 3 VERIFICATION Page 1 of 2<br />

Audit Area:<br />

Audit Reference No.:<br />

Auditor Name:<br />

Audit Date:<br />

<strong>Permit</strong> Type:<br />

<strong>Work</strong> Description:<br />

QUESTIONS ANSWER REMARKS<br />

BOX 1 – APPLICATION AND WORK DESCRIPTION<br />

1 Is the location and worksite description correct/clear? yes/no<br />

2 Is the type of permit used correct for the work described? yes/no<br />

3 Is a single permit reasonable for the work described? yes/no<br />

BOX 2 – PROTECTIVE EQUIPMENT AND WORKSITE SUPERVISION<br />

4 Is the protective equipment specified adequate for the work? yes/no<br />

5 Is Area Authority continuous presence required at worksite? yes/no<br />

6 Is <strong>Work</strong>site Supervisor continuous presence required at worksite? yes/no<br />

7 Is the Hazardous Area classification correct? yes/no<br />

BOX 3 – HAZARD IDENTIFICATION AND SPECIAL PRECAUTIONS<br />

8 Have the controls been transferred from the HCL to the permit? yes/no<br />

9 For Hot <strong>Work</strong> permits – Have the special precautions been identified? yes/no<br />

10 For Hot <strong>Work</strong> permits – Have the gas test requirements been identified? yes/no<br />

11 For EDP – Has the containment, temperature and pressure been<br />

identified?<br />

yes/no<br />

BOX 4 – SUPPORTING DOCUMENTS<br />

12 Are the supporting document(s) correct/adequate for the work? yes/no<br />

13 Are they attached to the permit? yes/no<br />

14 Are the permit/certificate cross-references correct? yes/no<br />

15 What Hazard Management Plan has been used for the work? yes/no<br />

16 Has the Hazard Management Plan been correctly completed? yes/no<br />

17 Have any linked documents been identified? yes/no<br />

BOX 5, 5a (HWP) – PERMIT APPROVAL<br />

18 Is the approval time given for the permit before the start of the validity yes/no<br />

period?<br />

19 Is the validity period given for the work correct? yes/no<br />

20 Is the name and signature of the RPE provided (if applicable)? yes/no<br />

BOX 5b HOT WORK PERMIT ONLY INITIAL GAS TEST/RECORD OF ADDITIONAL GAS TESTS<br />

21 Was the gas test taken before the permit was accepted? yes/no<br />

22 Are the Safe/Unsafe and Result boxes completed correctly? yes/no<br />

23 Are additional gas tests properly recorded? yes/no<br />

BOX 6 – ACCEPTANCE<br />

24 Has the permit being accepted within the validity period? yes/no<br />

BOX 7 – AUTHORISATION<br />

25 Is authorisation after acceptance and within the validity period? yes/no<br />

26 Is the 1 st period of authorisation given correct? yes/no<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 118 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

BOX 8 – RE-AUTHORISATION<br />

27 Are there additional <strong>Work</strong>site Supervisors involved in re-accepting the yes/no<br />

work?<br />

28 Are their specimen signature(s) provided above Box 8a? yes/no<br />

29 Are there additional Area Authorities involved in re-authorising the work? yes/no<br />

30 Are their specimen signature(s) provided above Box 8b? yes/no<br />

31 Has the permit been suspended properly in Box 8c? yes/no<br />

BOX 9/10 – PERMIT CANCELLATION WORK COMPLETE/NOT COMPLETE<br />

32 Has the <strong>Work</strong>site Supervisor cancelled the permit correctly in Box<br />

9a/10a?<br />

33 Has the permit been correctly cancelled by the Area Authority in Box<br />

9b/10b?<br />

34 Have the correct statements been deleted by the Area Authority in Box<br />

9b/10b?<br />

yes/no<br />

yes/no<br />

yes/no<br />

PERMIT ISSUE POINT<br />

35 Are all permits displayed in the correct section of the permit rack(s)? yes/no<br />

36 Is the permit location board being correctly maintained with magnetic and yes/no<br />

pictorial markers?<br />

37 Are Variations to operations identified pictorially on the permit location yes/no<br />

board?<br />

38 Are EPI’s correctly located in the permit rack and identified on the PLB? yes/no<br />

39 Are records of overrides displayed on the permit location board? yes/no<br />

40 Is a list of appointed WSS/AS/AA/AGT’s maintained in the PIP yes/no<br />

Conclusion & Recommendation:<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 119 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

<strong>Permit</strong> to <strong>Work</strong> Level 4 Weekly Monitoring<br />

BSP-02-Procedure-1622<br />

Form D<br />

PERMIT AUDIT LEVEL 4 Page 1 of<br />

Audit Area:___________________ Audit Reference:__________________ Audit Date:_______________<br />

Auditor Name: ________________ Reference Ind.:____________________________________________<br />

<strong>Permit</strong> Type:__________________ <strong>Permit</strong> Number: ___________________________________________<br />

<strong>Work</strong> Covered by <strong>Permit</strong>:<br />

REFERENCE QUESTIONS FOR FINDINGS<br />

1. Are the relevant hazards correctly identified on the permit? Are there no conflicts between checklist and permit?<br />

2. Are the permits and other associated documents displayed at the worksite?<br />

3. Has the documentation been completed and authorised correctly?<br />

4. Is the specified safety equipment in place, in good condition and being used correctly?<br />

5. are the specified precautions adequate and being implemented?<br />

6. Has the work party been briefed on the work and the requirements of the permit and have they understood the briefing?<br />

7. Are the required isolations in place and does the work party understand the isolation?<br />

8. Do the work party know the hazards at the worksite (Safety hazards, Health hazards, Environmental Hazards), the escape routes,<br />

GPA and Shutdown switches and telephones?<br />

WHY WAS PERMIT SELECTED FOR A REVIEW?<br />

a. High risk, such as hot work on live facilities or heavy lifting.<br />

b. <strong>Work</strong> party not familiar with local conditions or new personnel included in work party.<br />

c. New or not yet completely competent Area Authority or <strong>Work</strong>site Supervisor.<br />

d. <strong>Work</strong> by several work parties in the same worksite or in the same location.<br />

e. <strong>Work</strong> involving breaking into pressurised systems.<br />

f. <strong>Work</strong> involving safety systems overrides.<br />

g. <strong>Work</strong> guided by lengthy procedures or complex communication requirements.<br />

h. Other reason: Specify:<br />

PERMIT LEVEL 4 REVIEW<br />

Date: PTW Number Location: Audit by: Verified by SOS:<br />

A B C D E F G H<br />

<strong>Permit</strong> Description:<br />

REMARKS:<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 120 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Attachment-5<br />

Guide to setting of Risk level of Action Items of Level 1, 2, & 3 Audits (As per Yellow Guide Risk<br />

Assessment Matrix March 2006)<br />

Severity<br />

0<br />

1<br />

2<br />

3<br />

4<br />

5<br />

People<br />

No injury or<br />

health<br />

effect<br />

Slight injury<br />

or health<br />

effect<br />

Minor injury<br />

or health<br />

effect<br />

Major injury<br />

or health<br />

effect<br />

PTD or up<br />

to 3<br />

fatalities<br />

More than<br />

3 fatalities<br />

Consequences<br />

Assets<br />

No<br />

damage<br />

Slight<br />

damage<br />

Minor<br />

damage<br />

<strong>Mod</strong>erate<br />

damage<br />

Major<br />

damage<br />

Massive<br />

damage<br />

Environment<br />

No effect<br />

Slight<br />

effect<br />

Minor<br />

effect<br />

<strong>Mod</strong>erate<br />

effect<br />

Major<br />

effect<br />

Massive<br />

effect<br />

Reputation<br />

No<br />

impact<br />

Slight<br />

impact<br />

Minor<br />

impact<br />

<strong>Mod</strong>erate<br />

impact<br />

Major<br />

impact<br />

Massive<br />

impact<br />

A<br />

Never<br />

heard of in<br />

the Industry<br />

Increasing likelihood<br />

B<br />

Heard of in<br />

the Industry<br />

C<br />

Has<br />

happened in<br />

the<br />

Organisation<br />

or more than<br />

once per<br />

year in the<br />

Industry<br />

D<br />

Has<br />

happened at<br />

the Location<br />

or more than<br />

once per<br />

year in the<br />

Organisation<br />

E<br />

Has<br />

happened<br />

more than<br />

once per<br />

year at the<br />

Location<br />

Guide to setting of Risk level of Action Items<br />

<strong>To</strong>lerability Criteria<br />

BLUE<br />

YELLOW<br />

RED<br />

Definition<br />

Manage for continuous improvement.<br />

Incorporate risk reduction measures. Control to ALARP.<br />

Incorporate risk reduction measures. Control to ALARP. <strong>To</strong>lerability of<br />

risk to be endorsed by the line manager directly accountable for the<br />

Location or Organisation.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 121 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Findings Assessment and Evaluation Criteria (as per EP2005-0180-SP-02)<br />

IMPLICATIONS SCOPE OF CONCERN EVIDENCE<br />

GOOD<br />

There is no desire/need to take more<br />

or less risk, therefore no additional<br />

actions or resources they are needed to<br />

alter the framework. No follow-up is<br />

required by the next level of<br />

management.<br />

Confined to very few<br />

specific areas. A fit-forpurpose<br />

risk based<br />

control framework is in<br />

place.<br />

The framework is designed to<br />

provide reasonable assurance of<br />

achieving business objectives.<br />

The framework is resourced<br />

appropriately and is operating as<br />

expected/intended.<br />

FAIR<br />

Actions are needed to enhance the<br />

design and/or operation of the control<br />

framework, in order to adjust the level<br />

of risk exposure. The next level of<br />

management should be advised of and<br />

review the actions being taken to<br />

enhance the framework.<br />

Room for overall<br />

enhancement.<br />

A risk-based control framework is<br />

in place. There is scope for<br />

enhancement in the design<br />

and/or operation of the<br />

framework. The expectation is<br />

that on balance the entity will<br />

substantially meet its business<br />

objectives.<br />

UNSATISFACTORY<br />

Actions are needed to improve key<br />

elements of the design and/or<br />

operation of the control framework.<br />

There is a significant gap between the<br />

current level of risk exposure and the<br />

‘target’ level. The next level of<br />

management should monitor the<br />

implementation of agreed actions/<br />

improvements.<br />

Overall cause for<br />

concern from the<br />

standpoint of the<br />

entity.<br />

The risk-based control framework<br />

is in need of improvement. There<br />

are structural weaknesses in the<br />

framework. The exception is that<br />

on balance the entity will<br />

substantially fail to meet its<br />

objectives.<br />

UNACCEPTABLE<br />

The next level of management should<br />

take urgent action to confront the<br />

situation and commit appropriate<br />

resources to immediate resolution of<br />

the weaknesses. Business or Group<br />

senior management should monitor<br />

the implementation of agreed actions/<br />

improvements.<br />

Wide-ranging, may<br />

affect or expose other<br />

parts of <strong>Shell</strong>.<br />

The risk-based control framework<br />

is not designed and/or not<br />

operating properly. Processes and<br />

systems are seriously deficient of<br />

failing. Drastic and urgent action<br />

is needed to alter the level of<br />

exposure. The exception is that<br />

the entity will not meet its<br />

objectives.<br />

Determination of Overall Audit Finding Ratings of Level 1, 2, & 3 Audits and Audit Opinion<br />

Finding Rating<br />

Most favourable possible audit opinion<br />

SERIOUS HIGH MEDIUM HIGH +<br />

MEDIUM<br />

GOOD FAIR UNSATISF<br />

ACTORY<br />

UNACCEP<br />

TABLE<br />

NIL NIL FEW X<br />

NIL NIL MANY X<br />

NIL FEW FEW X<br />

NIL FEW MANY X<br />

1 or 2 ANY ANY X<br />

NIL MANY ANY X<br />

> 2 ANY ANY X<br />

The basic definitions to be used for “Few ≤ 20 findings” and “Many ≥ 40 findings”<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 122 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

A P P E N D I X 6 - W E L L H A N D O V E R F O R M F O R S T A N D A R D<br />

W I R E L I N E A N D W E L L H E A D M A I N T E N A N C E<br />

Well Number:<br />

WELL HAND OVER FORM<br />

FOR STANDARD WIRELINE AND WELLHEAD MAINTENANCE ONLY<br />

Location:<br />

Start Date:<br />

Job Request Number:<br />

Description of <strong>Work</strong>:<br />

Well Status<br />

HAND OVER TO WELL SERVICES<br />

Well Status<br />

HAND BACK TO ASSET HOLDER<br />

Closed Yes/No Time: Closed Yes/No Time:<br />

Opened Yes/No Time: Opened Yes/No Time:<br />

Surrounding area clear? Yes/No Surrounding area clear? Yes/No<br />

Waste disposal facility in place? Yes/No Waster properly disposed? Yes/No<br />

Description of well condition:<br />

Description of well condition:<br />

PERSONAL PROTECTIVE EQUIPMENT<br />

Helmets and boots Yes/No Hearing protection Yes/No Additional PPE required (specify)<br />

Eye protection Yes/No Wireline sign and barriers Yes/No<br />

Gloves<br />

(specify<br />

Yes/No Well head maintenance<br />

Yes/No<br />

type)<br />

sign and barrier<br />

FACILITY STATUS REPORT (PLATFORM INTEGRITY)<br />

CONCURRENT ACTIVITIES/OTHER REMARKS<br />

HEMP FOR WORK (IDENTIFICATION OF HAZARDS, ASSESSMENT OF HARM, CONTROLS AND RECOVERY MEASURES<br />

<strong>Work</strong> Hazard Potential Control Recovery Measure(s)<br />

L/M/H<br />

L/M/H<br />

L/M/H<br />

L/M/H<br />

L/M/H<br />

WIRELINE/WHM CREW INTERNAL HANDOVER – The Hazard Check Lists has been discussed, agreed and accepted<br />

Outgoing TSW/4x Team-Leader Incoming TSW/4x Team-Leader Outgoing TSW/4x Team-Leader Incoming TSW/4x Team-Leader<br />

Name: Name: Name: Name:<br />

Date/Time: Date/Time: Date/Time: Date/Time:<br />

Signature: Signature: Signature: Signature:<br />

HANDOVER: The well is handed over to the TSW/4x team leader in a safe<br />

condition. <strong>Work</strong> may now commence.<br />

HANDBACK: The well is returned to the Asset Unit in a safe condition.<br />

All wireline / well head maintenance equipment has been removed.<br />

The worksite is clean/clear.<br />

AU Supervisor TSW/4x Team Leader TSW/4x Team Leader AU Supervisor<br />

Name<br />

Date/Time<br />

Name<br />

Date/Time<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 123 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

Signature<br />

Signature<br />

Use: This form can only be used to carry out the following standard Wireline Wellhead Maintenance work – a) SCSSSV replacement b) Zone change c) Gas<br />

Lift Change d) Plugging or Unplugging e) BHP Surveys f) HUD/Status Check g) Pressure Testing and Greasing X-Mas Tree Valves h) Fishing<br />

Operations<br />

NB: This form CANNOT be used for the following non-standard Wireline Wellhead Maintenance work – a) Replacing or Repairing X-Mas Tree Valves b)<br />

CTU Activities c) Perforation Activities d) Production Logging/RPM Logging Activities<br />

NO WORK OTHER THAN THE STANDARD WIRELINE WELLHEAD MAINTENANCE WORK MENTIONED ABOVE MAY BE CARRIED OUT ON THE<br />

WELL HANDED OVER WHEN THIS FORM IS BEING USED.<br />

Retention: Original copy at worksite, carbon copy at Operation PIP<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 124 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

A P P E N D I X 7 - P T W A P P O I N T M E N T R E C O R D<br />

PTW APPOINTMENT RECORD – Interview Sheet<br />

Appointments Interview<br />

Satisfactory<br />

Assessor’s Remarks<br />

Applicable for ALL PTW’s Role(s) Yes No<br />

1 Candidate to provide evidence of PTW training<br />

appropriate for role requiring appointment (Mandatory):<br />

• Certificate(s) and/or PSL<br />

2 Candidate to demonstrate knowledge on PTW<br />

Procedure, HSE <strong>Mod</strong>ule <strong>03</strong> (BSP-02-Procedure-1622).<br />

Identifying the current revision and stating what<br />

changes have been made by the latest revision.<br />

3 Candidate to identify to what role(s) they wish to be<br />

appointed.<br />

Assessor to Tick Box(es)<br />

<br />

<strong>Work</strong>site Supervisor<br />

<br />

<br />

<br />

<br />

Area Authority<br />

Authorised Gas Tester<br />

Authorised Signatory<br />

Level 2/3 Auditor<br />

4 Candidate to confirm having had HSE briefing and to<br />

explain facility emergency response procedure.<br />

Candidate to be given a brief facility description with an<br />

explanation of hazards and control measures in place<br />

for the facility.<br />

Candidate to be given a brief description of any<br />

variation of application of the work permit system<br />

applicable at the facility.<br />

5 NB: Only for use when appointing Authorised Gas Tester<br />

Candidate to give brief explanation of requirements for<br />

gas testing for oxygen level/flammable gases/toxic<br />

gases.<br />

Candidate to give explanation of the results required<br />

before hot work/entry into confined spaces would be<br />

approved.<br />

6 Candidate to give an example of HEMP application for<br />

work that they will carry out at the location.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 125 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

7 Candidate to demonstrate knowledge of lifting hazards<br />

applicable to work that they will be involved in, both<br />

manual and mechanical.<br />

8 Candidate to demonstrate knowledge of compliance<br />

required for MHMS Tier 1 Medical Response and<br />

explain their responsibilities in providing a First Aider if<br />

applicable.<br />

9 Candidate to demonstrate knowledge of items<br />

necessary for inclusion in an effective <strong>To</strong>ol Box Talk.<br />

Candidate to supply completed <strong>To</strong>ol Box Talk form for<br />

work they would be involved in at the facility.<br />

As a result of the appointment interview conducted with the candidate identified below Tick Box(es):<br />

The candidate is assessed as COMPETENT, and appointed in the role identified at the Site(s) and Location(s)<br />

indicated below:<br />

<br />

<br />

<br />

<br />

<br />

<strong>Work</strong>site Supervisor<br />

Area Authority<br />

Authorised Gas Tester<br />

Authorised Signatory<br />

Level 3/2 Auditor<br />

Site(s) and Location(s) of Appointment:<br />

The candidate is assessed as NOT YET COMPETENT. The following items require re-assessment. List as<br />

appropriate.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 126 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

CONFIRMATION OF APPOINTMENT<br />

I, _______________________________________ will comply with the PTW requirements and controls. I will<br />

(Candidate’s name)<br />

intervene to stop any unsafe act or correct unsafe condition and raise a PAKAT detailing the unsafe act or condition<br />

after discussing it with the person(s) involved and coming to an agreement of future actions to be taken. I will report to<br />

Senior Line Supervisor any non-compliance I see committed. I will apply HSE Non-Compliance Guideline at all times.<br />

Appointee:<br />

Assessed & Appointed by AU/SU’s Appointing Authority:<br />

Name<br />

: ______________________________<br />

Name<br />

: ______________________________<br />

Company<br />

: ______________________________<br />

Company<br />

: ______________________________<br />

Ref. Indicator : _______________<br />

Ref. Indicator : _______________<br />

Signature<br />

: _______________<br />

Signature<br />

: _______________<br />

Date<br />

: _______________<br />

Date<br />

: _______________<br />

The PTW appointment for the appointed roles specified above is valid for 3 years from the date of the<br />

appropriate PTW course attended.<br />

PTW Appointment VALID From<br />

PTW Appointment VALID until<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 127 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

A P P E N D I X 8 - P T W A P P O I N T M E N T F L O W C H A R T<br />

BSP-02-Procedure-1622<br />

Due for Competency Assessment<br />

After 3 Years of Course Attended<br />

i.e. PTW-1 and PTW-3<br />

Send to 1 day PTW Refresher<br />

Course (PTW-5)<br />

YES<br />

Pass ?<br />

NO<br />

Suspend Current PTW Role (s)<br />

Coaching by Line Supervisor<br />

Send to 3 days PTW Course<br />

PTW-1/2, PTW-2/3<br />

Pass ?<br />

NO<br />

Coaching by Line Supervisor<br />

For 6 Months<br />

NO<br />

Pass ?<br />

YES<br />

YES<br />

Abandon Assessment Process<br />

• Redeployment to another position<br />

at same job group<br />

OR<br />

• Redeployment to another position<br />

at lower job group<br />

Competence Assessment Procedure<br />

BSP-20-02-10-Procedure-002<br />

AU/SU’s Line Management or<br />

Project Manager to do Appointment<br />

Use Appointment<br />

Interview Sheet<br />

Coaching by<br />

Line Supervisor<br />

NO<br />

Pass<br />

Appointment<br />

Interview<br />

Stamp PSL<br />

Issue PTW Authority Card<br />

YES<br />

Competent to perform PTW Role.<br />

Staff can works in a<br />

Specific AU/SU’s<br />

Facility<br />

END<br />

No Further Assessment<br />

NO<br />

PTW-5<br />

Validity of<br />

3 Years<br />

YES<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 128 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

A P P E N D I X 9 - L I S T O F A P P O I N T E D A R E A S & P T W A U T H O R I T Y<br />

C A R D<br />

List of Appointed Areas for PTW Roles:<br />

1. AMPA Complex<br />

2. AMPA Fields<br />

3. Fairley Complex<br />

4. Fairley Fields<br />

5. Champion Complex<br />

6. Champion Fields<br />

7. Ensco-51<br />

8. Hoist-JO-1<br />

9. Land Rig T-41<br />

10. West Pelaut<br />

11. Rasau Stations<br />

12. Tali Fields<br />

13. NGCP<br />

14. Tank Group 27<br />

15. Tank Group 28<br />

16. Tank Group 29<br />

17. Tank Group 30<br />

18. Tank Group 31<br />

19. SCOT<br />

20. Bandar Gas Operations (BGO)<br />

21. Water Treatment Plant – PPA/4<br />

22. Water & Gas Utilities – PPA/4<br />

23. Electrical Utilities – PPA-1<br />

24. Building – PPA/3<br />

25.Civil & Infrastructure – PPA/5<br />

26. SCO Yard<br />

27. Others – Specify.<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 129 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

8.8 cm<br />

5.4 cm<br />

S/No:<br />

(Or I/C No)<br />

Expire by:<br />

PTW Authority Card<br />

Name:<br />

Dept:<br />

Company:<br />

Assessed & Appointed by:<br />

Name:<br />

Dept:<br />

Date:<br />

Signature:<br />

Validity Period: 3 Years as of PTW-1/3/5)<br />

The person named on this card is appointed as a PTW role(s)<br />

TICKED in the YES Box for the area(s) listed on the back of this card.<br />

PTW Roles YES AREAS (See Appendix 9) YES<br />

Authorised Signatory<br />

Area Authority<br />

<strong>Work</strong>site Supervisor<br />

Authorised Gas Tester<br />

PIP Coordinator<br />

PTW Level 2/3 Auditor<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 130 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

A P P E N D I X 1 0 - T E M P O R A R Y A S S E T H O L D E R H A N D O V E R L E T T E R<br />

Temporary Asset Holder Handover Letter<br />

I as the Asset Holder have examined Box 1, 2, 3 and 4 of PTW No: ,<br />

and agree they have been completed correctly for the intended work. This permit,<br />

when properly approved, accepted and authorised in Boxes 5, 6 and 7 will be<br />

valid for a MAXIMUM duration as outlined in Section 3.1.5 of PTW Procedure<br />

<strong>Mod</strong>ule <strong>03</strong> (depending upon permit type). Additional hazard identification and<br />

controls transferred from Box 2 of the Hazard Check Lists have been entered in<br />

Box 3.<br />

I temporarily release all or part of the Asset to the Temporary Asset Holder<br />

identified below who will accept responsibility for all or part of the Asset in order<br />

to carry out the work described in Box 1 of the permit and who will give approval<br />

for the work in Box 5 (5a) for HWP of the permit.<br />

RELEASE BY ASSET HOLDER<br />

I agree to release the all or part of the Asset for the work described in Box 1 of the<br />

permit.<br />

Asset or part of Asset:<br />

Area:<br />

Equipment:<br />

Name:<br />

Signature:<br />

Ind: Time: Date:<br />

ACCEPTANCE BY TEMPORARY ASSET HOLDER (Must be a BSP Authorised Signatory)<br />

I agree to temporary accept the Asset or part of the Asset on behalf of the BSP<br />

Performing Authority.<br />

Asset or part of Asset:<br />

Area:<br />

Equipment:<br />

Name:<br />

Signature:<br />

Ind: Time: Date:<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 131 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

A P P E N D I X 1 1 - M A P P A B L E C H A N G E S F O R M<br />

BSP-02-Procedure-1622<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 132 of 133


<strong>Mod</strong>ule <strong>03</strong> - BSP <strong>Permit</strong> to <strong>Work</strong> Procedure<br />

BSP-02-Procedure-1622<br />

A P P E N D I X 1 2 – ‘ 3 W H A T S ’ R I S K A S S E S S M E N T<br />

3 Whats<br />

The 3 whats is the simplest form of risk assessment and is meant to be carried out before starting any job. It<br />

is designed so that the workers who are carrying out the job are the people considering the inherent hazards<br />

and risks of that job you're about to do. All you have to do is think about the activities in the task you are<br />

about to undertake and ask yourself these three simple questions;<br />

What can go Wrong ?<br />

Think about what could happen<br />

to you or your colleague in<br />

relation to what you are about to<br />

do at the worksite you are about<br />

to work in<br />

What can cause it to go Wrong ?<br />

Think about the situation, condition,<br />

object or activity that could be the<br />

cause of what could happen to you<br />

or your colleague<br />

What can be done to prevent it ?<br />

Think about what you or your<br />

team could do to prevent an<br />

incident or accident in relation<br />

to what you have identified<br />

could be a problem<br />

<strong>Permit</strong> to <strong>Work</strong> Procedure – <strong>Rev</strong>. <strong>4.2</strong> Page 133 of 133

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!