<strong>DolWin3</strong><br />
162 kilometre grid connection<br />
for offshore wind energy<br />
The <strong>DolWin3</strong> project establishes a 900 MW grid connection<br />
for wind farms in the south-western part of the German North Sea.<br />
Facts and figures<br />
• Connection:<br />
162 km grid connection<br />
capacity 900 MW<br />
onshore: 79 km land cable<br />
offshore: 83 km sea cable<br />
Offshore AC/DC converter<br />
platform (DolWin gamma)<br />
• Grid coupling point:<br />
Dörpen West converter station<br />
• Project status:<br />
completion: 2017<br />
The <strong>DolWin3</strong> project is the third<br />
connection in the DolWin cluster.<br />
The distance from the wind farms<br />
to the coast is about 83 kilometres.<br />
Then the grid connection runs for<br />
another 79 kilometres across land<br />
to the converter station in Dörpen<br />
West, which will serve as the grid<br />
coupling point. Completion of<br />
construction in 2017.<br />
Our Offshore department<br />
On behalf of TenneT TSO, our affiliated<br />
company TenneT Offshore GmbH<br />
constructs and operates grid connections<br />
for offshore wind farms.<br />
TenneT Offshore performs the planning<br />
and construction of power connection<br />
at sea and up to the grid connection<br />
point. The projects mainly involve the<br />
following tasks for connecting offshore<br />
wind farms:<br />
• Development of technical concepts<br />
• Route planning and surveying<br />
• Carrying out the legal and nature<br />
conservation procedures<br />
• Tendering, awarding and executing<br />
grid connection projects
<strong>DolWin3</strong><br />
TenneT brings energy from sea to land<br />
Flensburg<br />
DolWin gamma<br />
12 km<br />
Brunsbüttel<br />
Büttel<br />
Borkum-<br />
Riffgrund I<br />
Norderney<br />
83 km<br />
Hagermarsch<br />
Inhausen<br />
Hamswehrum<br />
Conneforde<br />
Emden / Borßum<br />
79 km<br />
Diele<br />
converter station<br />
Dörpen West<br />
TenneT TSO GmbH<br />
Bernecker Straße 70<br />
95448 Bayreuth<br />
Telephone +49 921 50740-4094<br />
Fax +49 921 50740-4095<br />
E-mail offshore@tennet.eu<br />
Twitter@tennettso<br />
www.tennet.eu<br />
TenneT is Europe’s first cross-border grid operator. With approximately<br />
20,000 kilometres of extra-high voltage lines and 36 million<br />
end users in the Netherlands and Germany we rank among the<br />
top five grid operators in Europe. Our focus is to develop a northwest<br />
European energy market and to integrate renewable energy.<br />
Taking power further<br />
© TenneT<br />
No part of this publication may be<br />
reproduced or transmitted in any form<br />
or by any means without the explicit<br />
permission of TenneT.<br />
No rights may be derived from the contents<br />
of this document.<br />