<strong>NM</strong> <strong>532</strong> <strong>Curve</strong> <strong>Correction</strong> <strong>Project</strong> Environmental Assessment<br />

1.0 SUMMARY<br />

The <strong>New</strong> <strong>Mexico</strong> <strong>Department</strong> <strong>of</strong> Transportation (<strong>NM</strong>DOT), in cooperation with the Federal Highway<br />

Administration (FHWA), proposes to reconstruct three curves <strong>of</strong> the <strong>NM</strong> <strong>532</strong> roadway in Lincoln County,<br />

<strong>New</strong> <strong>Mexico</strong> (see Figure 1.1). <strong>NM</strong> <strong>532</strong> is a rural arterial roadway that extends from <strong>NM</strong> 48 in Alto to<br />

Ski Apache, and it provides the only roadway access to Ski Apache and nearby areas on the Lincoln<br />

National Forest. The project area is located within <strong>NM</strong>DOT District 2. The <strong>NM</strong> <strong>532</strong> <strong>Curve</strong> <strong>Correction</strong><br />

<strong>Project</strong> is listed in the Fiscal Year (FY) 2012-2015 Statewide Transportation Improvement Program<br />

(STIP) Amendment 4 as control number (CN) 2101140. The <strong>NM</strong> <strong>532</strong> <strong>Curve</strong> <strong>Correction</strong> <strong>Project</strong> EA was<br />

developed in accordance with the National Environmental Policy Act (NEPA), <strong>NM</strong>DOT Location Study<br />

Procedures (<strong>NM</strong>DOT, 2000) and Federal Highway Administration (FHWA) Technical Advisory T<br />

6640.8A, 23 Code <strong>of</strong> Federal Regulations (CFR) Parts 771 and 772, and other applicable guidelines and<br />

regulations.<br />

The purpose <strong>of</strong> the <strong>NM</strong> <strong>532</strong> <strong>Curve</strong> <strong>Correction</strong> <strong>Project</strong> is to improve traffic and safety conditions between<br />

MP 0.0 and MP 12.0 while considering the needs <strong>of</strong> local residents, forest visitors, and the Mescalero<br />

Apache Tribe. The project need is based on the following conditions: insufficient shoulder width;<br />

roadway geometry does not meet current standards resulting in several sharp curves; post-fire soil erosion<br />

undercuts the roadway, steep drop-<strong>of</strong>fs next to driving lanes; limited signage to inform drivers <strong>of</strong> roadway<br />

conditions; lack <strong>of</strong> pull-<strong>of</strong>f areas; poor pedestrian access at scenic areas; extensive maintenance needs;<br />

and economic viability <strong>of</strong> recreation-related businesses.<br />

The following three curves are proposed for extensive reconstruction: Texas Turn at MP 6.89-7.05, Axle<br />

Bend <strong>Curve</strong> at MP 8.21-8.37, and Last <strong>Curve</strong> at MP 11.86-11.95 (see Figure 1.2). These curves have<br />

been identified as priority for improvements. Work would entail increasing the curve radii and correcting<br />

the curve grades. At each curve, a retained soil system (RSS) wall would be constructed using additional<br />

native fill. The RSS would consist <strong>of</strong> a geo-grid embankment constructed at a 0.5:1 slope with rock-filled<br />

baskets for the wall face. Perforated drainpipes and subsurface drain outlets would be installed as part <strong>of</strong><br />

the RSS wall. Guardrail would be installed at the top <strong>of</strong> the embankment. Energy dissipaters or other<br />

similar slope protection measures would be installed in areas where drainage has caused severe erosion.<br />

On the upslope side <strong>of</strong> Axle Bend <strong>Curve</strong>, some rock would be excavated and removed. No blasting<br />

would occur. Rock or slope protection would be used to create a stabilized rock-cut face only if unstable<br />

rock is encountered.<br />

The current proposed typical section would consist <strong>of</strong> two 11-foot travel lanes, two 3-foot shoulders, and<br />

two 2.5 foot tapers. Existing vehicle pull-<strong>of</strong>f areas at each curve would be paved. In some areas, slopes<br />

would be excavated and additional fill would be placed. Walls, guardrails, and signs would be installed in<br />

some sections.<br />

The total estimated project cost for the Recommended Build Alternative is $1.8 million. Construction <strong>of</strong><br />

the project would begin in 2013.<br />

This EA concludes that the Recommended Build Alternative meets the purpose and need <strong>of</strong> the proposed<br />

project and is not expected to have significant adverse social, economic, or environmental impacts that<br />

will warrant an Environmental Impact Statement. Unless significant impacts are identified as a result <strong>of</strong><br />

public review, a Finding <strong>of</strong> No Significant Impact (FONSI) will be requested from FHWA. If a FONSI is<br />

issued, it will provide approval for final design and construction <strong>of</strong> <strong>NM</strong> <strong>532</strong> at Texas Turn at MP 6.89-<br />

7.05, Axle Bend <strong>Curve</strong> at MP 8.21-8.37, and Last <strong>Curve</strong> at MP 11.86-11.95.<br />

March 2013 1 CN 2101140