33. MAINTENANCE PERIOD :<br />

The maintenance period for the work shall be (7) seveen months reckoned from the date of<br />

completion of the work as per the contract to the satisfaction of the Engineer and his certification<br />

as such During the maintenance period, the contractor shall red fully liable and responsible as<br />

detailed in Clause 47 of the General conditions of contract and standard specification 1969 (with<br />

upto date amendments there to) of the Engineering Deptt. of Eastern Railway.<br />

34. Materials to be supplied by the contractor shall conforming the General conditions of contract and<br />

standard specifications (followed by Work hand Book Part I & 2 GCC Feb, 2001) of the<br />

Engineering Dtptt. Of Eastern Railway as well as to the various stipulation in these tender papers.<br />

If called upon to do so, the contractor shall state the act source of supply of any materials to be<br />

supplied by him and submit samples of sand, stone chips, bricks, boulder, ballast etc. for approved<br />

of the Engineer or his representative.<br />

35. The tenderers shall submit their own rates in the schedule of items except against the items to be<br />

covered under the Eastern Railway Engg. Deptt. schedule of Labour and materials rates, 1996<br />

(with upto date amendments thereto). For the items in the schedule of items to be covered under<br />

the Eastern Railway Engg. Deptt. schedule of Labour & materials rates 1996 (with upto date<br />

amendments thereto) the tenderers shall quote a percentage rate above or below the said schedule<br />

of labour and material rates, 1996.<br />

36. The rates quoted in the schedule of items, shall include all lead, lift, transport/carrying, loading,<br />

unloading, handling, re-handling crossing of tracks obstructions observing traffic regulations etc.<br />

for the materials to be supplied by the Railway free of cost from IOW store at _______________<br />

etc. for the items of work in the schedule of items and shall include transporting of the said<br />

materials by the contractor to the site of work at his own cost and no separate payment shall made<br />

on these accounts.<br />

37. Subject to as otherwise provided in this contract, all notices to be given on behalf of the President<br />

of India and all other action to be taken on his behalf, may be given or taken behalf by Engineer<br />

or his representative.<br />

38. The rates quoted by the contractor in the schedule of items for reinforced cement concrete and<br />

plain concrete works shall incl. Preparation and mixing of concrete in power driven concrete<br />

mixer transporting and placing the mixed concrete to the location of work placement of concrete<br />

in the arch portion of the bridge using mechanical concrete placer, compaction of concrete by<br />

needle, vibrations, cutting, bending, binding, tying and placing of steel reinforcement including<br />

straightening of bent rods, if any, prior to binding, tem plating and shall include scaffolding,<br />

shoring, centering and shuttering, erection and dismantling, curing of concrete complete, all<br />

labour and materials tools and plant, all lead and lift and nothing extra will be paid on these<br />

accounts. The shoring, centering and shuttering shall be subject to approval by the Engineer<br />

before the concrete is placed.<br />

39. The provision of contract labour (Regulation & Abolition) Act. 1970 and contract labour<br />

(Regulation & Abolition) Central Rule 1971 with all its additions, alteration and amendments as<br />

may be made from time shall be fully binding on the contractors and shall become part of this<br />

contract. The violation of any of the statutory provision of the said act and Rule shall be treated as<br />

break best essential and substantial terms and conditions of the contract and with the result the<br />

contract may abrogated forthwith at the initiated of the Rly. administration. The contractor besides<br />

his other liabilities shall also be bound and liable to the Railway Administration (Principal<br />

employer) being the parties to he contract to pay and/or compensate for the expense which the<br />

Rly. his to incur to fulfill the terms and Rule because of failure on the part of the contractor to<br />

fulfill these terms and condition and/or provision of the said Act and Rules and Rly.