Immediately after receipt of letter of acceptance of the tender the contractor shall mobilizes all his<br />

resources (Labour and material) and take upto the work in right earnestness. The minim. Progress<br />

to be achieved will be as follows :-<br />

i) Mobilization & jacketing : Time frame will be ___nil________ months from date of<br />

letter of acceptance.<br />

ii) Subsequently every __nil______ months, jacketing of at least __nil_________ spans will<br />

be done. If the contractor fails to adhere to the progress mentioned above, minimum<br />

Rs.______________ only per in complete span will be deducted from any amount payable to him<br />

.<br />

7. The quantities indicated against various items of the schedule items are for the purpose of<br />

tendering. Payment will be made for the quantities which will be actually executed & measured at<br />

site as per accepted rates.<br />

8. The rates quoted by the tenderer shall include washing stone chips screening chips, sand where<br />

necessary and nothing extra shall be paid on this account.<br />

9. The quoted rates pertaining to the labour & materials schedule of rates 1996 and for other items in<br />

the schedule of items of the tender shall be deemed to take into account the difficulties detention<br />

and delay in supply of Rly. materials encountered in occourse of works and nothing extra on these<br />

accounts shall be paid.<br />

10. No arrangement for supply of Petrol, Coal or any other fuel, consumable materials etc. required<br />

for the work shall be done by the Rly. and contractor shall have to make his own arrangement for<br />

same.<br />

11. The contractors has to make his own arrangement at his own cost to supply water suitable for the<br />

execution of different works as well as for the drinking purpose of the staff and labour at site. Rly.<br />

shall under-take no responsibility what so-ever for arranging water for any purpose for execution<br />

of work.<br />

12. All materials to be supplied by the contractor shall be subject to prior inspection & approval at<br />

site by the Engr. Or his representative. Contractor’s materials which for any reasons have be<br />

ordered by the Engineer or his representative to be removed from site must be removed by the<br />

contractor within 7 days of receipt of the order failing which the Rly. Admn. shall be at liberty to<br />

remove the materials and/or dispose of these material at their discretion in and manner as may<br />

think fit and expenses incurred in connection shall be recovered from dues of the contractor. The<br />

contractor shall in no case be entitled to any compensation for this. If necessary, Engineer or any<br />

of his representative must be freely allowed to inspect the materials in the contractor’s<br />

godown/site.<br />

12.A. The contractor will be permitted to start the work only after he has brought the requisite<br />

machineries in working condition, especially concrete placer with supporting equipments.<br />

Vibrators, weight batcher with self loading hoppers in addition to other equipments as site, his<br />

failure to mobiles these equipments within one month of the issue of acceptance latter may render<br />

him liable for termination of contract. The Railway Administration may in such an event,<br />

complete the work at his risk and cost.<br />

13. If necessary, Engineer or any of his representative must be freely allowed to inspect the materials<br />

in the contractor’s Go down/site.<br />

14. The Railway administration reserves the right that if necessary certain items of works as provided<br />

in the agreement may be deleted altogether and may be done by any other suitable means as may<br />

be decided by the Engineer for which no claim whatsoever will be entertained from the<br />

contractor.