SPECIAL CONDITIONS AND SPECIFICATIONS OF CONTRACT<br />
Tender No.B/66/Tender/24/Open/DNR/2005-06 dt. 24.10.2005<br />
1. For work done under Eastern Railway Schedule of Labour and Materials Rates, 1996 supply of<br />
materials by the Railway to Contractor shall be under the terms and conditions specified in the<br />
preface and in the introductory remarks of the various Chapters of the said schedule with<br />
identification specified in para 3 below :-<br />
2. The Contractors shall supply all materials required for the execution of the whole work and<br />
execute the work according to the standard conditions and specifications unless otherwise<br />
expressly stated in the schedule of items or in the tender papers.<br />
3. Materials to be supplied by the Railway shall be supplied to the contractor either from the store<br />
Godown of any of the Rly. Store of IOW situated at DNR or in wagon load lead near any of the<br />
said stores, and shall have to be carried from the said Stores to the site of the works by the<br />
Contractor at his own cost. Contractors shall unload materials from wagons within the free time<br />
allowed and sharfage or demurrage charges, if accrued (as per Railway traffic rules in force form<br />
time to time) shall be debited to the Contractors. The tendered rates shall include loading,<br />
unloading carriage to the site of works, leading, lifting, stacking, rehandling etc. of all materials to<br />
be supplied either by the Railway or by the Contractor in this contract for works in the schedule of<br />
items and no separate payment will be made in this respect. (This supersedes conditions of<br />
payment for lead of materials as specified in the introductory remarks in various Chapters of E.<br />
Railway labour and materials schedule, 1996).<br />
4. Any materials issued in excess of requirement shall be returned by the contractor in good<br />
condition to IOW’s Godown at DNR and no lead/or any other charges for return of such materials<br />
shall be for. If the contractor fails to return any excess cement or steel or other materials drawn by<br />
him in good condition to the said IOW’s Stores, the cost of such excess materials shall be<br />
recovered as fell<br />
i) For the quantity not exceeding 2 ½ % over the actual requirement the cost of such excess<br />
stores at issue rate if such issued rate is fixed for this contract or at the market rate prevailing at<br />
the time of issue together with all charges such as Rly. freight handling, lead, supervision and all<br />
other incidental charges leviable according to the <strong>Indian</strong> Railway Code Rules shall be recovered<br />
from the Contract.<br />
ii) For the quantity in excess of 2 ½ % of the requirement an increase of 100% will be added<br />
to the value calculated as para 4(i) above.<br />
5. The ‘Instructions to tenderers and conditions of tender’ Special conditions and specification of<br />
Contract’ and the stipulation made in the schedule of items lay down the various conditions and<br />
specifications covering the work under this contract, in addition to in part super session of<br />
General Conditions of contract and the specification (1963 edition) with upto-date amendments<br />
thereto, In all matters not expressly provided for or allowed for in the tender papers, the execution<br />
of works shall be in accordance with General conditions of contract and standard specification<br />
1969 edition with upto-date amendments thereto. Where there is any Conflict between the<br />
between the “Instructions to tenderers and condition of tender” General conditions and<br />
specification of Contract one hand and the General conditions of contract and standard<br />
specifications (1969 edition) with upto-date amendments thereto, on the other the former shall<br />
prevail.<br />
6. PROGRAMME FOR COMPLETION OF WORK: