Step 2<br />
REQUIRED EQUIPMENT AND MATERIAL<br />
GENERAL<br />
1. Stakes, string and string level for alignment.<br />
2. Measuring tape & level.<br />
3. Torque wrench.<br />
4. Masking tape or duct tape.<br />
5. 2 to 4 lengths of rope 50' or longer.<br />
6. Hacksaw<br />
7. 1 1/8" wrench<br />
8. Ladder, movable scaffolding or platform lift.<br />
9. Optional - power wrench, transit (available from a rental store).<br />
BUILDINGS OVER 140'<br />
1. Caulking gun.<br />
SURFACE MOUNT - concrete<br />
1. Drill.<br />
2. Minimum 3/8" x 6" anchor bolts - 4 per base plate.<br />
3. Concrete drill bit sized to install anchor bolts.<br />
SURFACE MOUNT - other<br />
1. 8" X 8" base plate - 2 per arch.<br />
2. 42" stakes and or earth anchors - according to soil conditions.<br />
3. Sledge hammer<br />
POST MOUNT<br />
1. Drill.<br />
2. 11/16" wood drill bit.<br />
3. Minimum 8" x 8" x 8' treated posts<br />
4. Post hole auger - minimum 12" diameter.<br />
5. Minimum 3/8" x 5" lag bolts - 4 per base.<br />
6. Drill bit to install lag bolts<br />
7. Crushed rock or concrete to set posts.<br />
8. Two (2) pieces of 5/8" (minimum) rebar, 12" long for each post.<br />
9. Depending on mount type - dimensional lumber to span posts 2 x building length.<br />
See STEP 7 and STEP 8 on Page 9.<br />
THESE MATERIALS ARE FOR A 4 FOOT (48") POST. IF YOUR POST IS A DIFFERENT<br />
HEIGHT YOU WILL NEED TO ADJUST MATERIALS ACCORDINGLY.<br />
SEE APPENDIX B, PAGE 24 FOR MATERIALS AND CONSTRUCTION<br />
OF VENTILATED AND NON-VENTILATED SIDE WALLS.<br />
4<br />
Q205.1.1