PALM BEACH COUNTY<br />
TURNPIKE ASPHALT MAINTENANCE – BOYNTON BEACH BOULEVARD (MILEPOST 86)<br />
• Southbound <strong>Turnpike</strong> exit and entrance ramps at Boynton Beach Boulevard – Closed between 9 p.m. Sunday, <strong>April</strong><br />
21, and 5 a.m. Monday, <strong>April</strong> 22.<br />
o DETOUR: Southbound <strong>Turnpike</strong> traffic should exit at Lake Worth Road (Exit 93), go west to U.S. 441 and<br />
then south to Boynton Beach Boulevard. Traffic on Boynton Beach Boulevard should head west to U.S. 441,<br />
south to Atlantic Avenue and then east to the <strong>Turnpike</strong> on-ramp.<br />
o It may be necessary to close the ramps Monday night, should weather or other conditions delay the work<br />
Sunday night.<br />
TURNPIKE MILLING AND RESURFACING – 45TH STREET (MILEPOSTS 102-104)<br />
• One of two <strong>Turnpike</strong> lanes in each direction may be closed in the vicinity of 45th Street, between mileposts 102 and<br />
104, from 9 p.m. to 6 a.m. Sunday, <strong>April</strong> 21, through Thursday, <strong>April</strong> 25.<br />
PROJECT DESCRIPTION: The $1.8 million project entails milling, resurfacing and safety upgrades on the <strong>Turnpike</strong><br />
between Milepost 102.5 and Milepost 103.7. Work also includes guardrail resetting, erosion control, pipe desilting, slope<br />
repair, bridge deck spall repairs and expansion joint replacement. It is anticipated the project will be completed in the<br />
summer of 2013.<br />
TURNPIKE BRIDGE REPLACEMENT – PGA BOULEVARD (MILEPOST 109)<br />
• One of two <strong>Turnpike</strong> lanes in each direction may be closed as needed in the vicinity of PGA Boulevard between 9<br />
p.m. and 5 a.m. Sunday, <strong>April</strong> 21, through Thursday, <strong>April</strong> 25.<br />
o Traffic on the <strong>Turnpike</strong>’s northbound entrance ramp from PGA Boulevard also may be stopped for a few<br />
minutes at a time between 10 p.m. and 5 a.m.<br />
PROJECT DESCRIPTION: The <strong>Turnpike</strong>’s PGA Boulevard ramp bridge is being replaced with a higher bridge to provide<br />
additional clearance for tall vehicles. <strong>Construction</strong> began in August 2012. It is anticipated the project will be completed in<br />
the fall of 2013. Approximate cost: $6.2 million.<br />
TURNPIKE BRIDGE REPLACEMENT & INTERCHANGE IMPROVEMENTS – INDIANTOWN ROAD (MILEPOST 116)<br />
• One of two <strong>Turnpike</strong> lanes in each direction may be closed as needed in the vicinity of Indiantown Road from 9 p.m.<br />
Monday to 5 a.m. Sunday, <strong>April</strong> 21, through Thursday, <strong>April</strong> 25.<br />
o Traffic on the <strong>Turnpike</strong>’s northbound exit ramp to Indiantown Road also may be stopped for a few minutes<br />
at a time between 11 p.m. and 4 a.m.<br />
PROJECT DESCRIPTION: The <strong>Turnpike</strong>’s Indiantown Road ramp bridge is being replaced with a higher bridge to provide<br />
additional clearance for tall vehicles. It is anticipated the project will be completed in May 2013. Approximate cost: $4.7<br />
2