METRO GOLD LINE FOOTHILL EXTENSION CONSTRUCTION AUTHORITY Request for Proposals (RFP) Intermodal Parking Facilities and Enhancements Design-Build Project RFP C1150 VOLUME 3- TECHNICAL PROVISIONS DOCUMENT 1- GENERAL REQUIREMENTS
- Page 2 and 3: METRO GOLD LINE FOOTHILL EXTENSION
- Page 4 and 5: 7.0 DOCUMENTATION .................
- Page 6 and 7: 1.0 PROJECT MANAGEMENT 1.1 Manageme
- Page 8 and 9: B. Creation of the Schedule of Valu
- Page 10 and 11: B. Recognized business groups and a
- Page 12 and 13: communications). The protocol shall
- Page 14 and 15: I. Create and maintain a log of all
- Page 16 and 17: design packages shall consist of di
- Page 18 and 19: D. Architectural; METRO GOLD LINE F
- Page 20 and 21: E. Cost effectiveness; F. Schedule
- Page 22 and 23: Reports of design reviews, includin
- Page 24 and 25: 2.1.11 Final Design Certification W
- Page 26 and 27: 2.3 Design Support during Construct
- Page 28 and 29: Design-Builder shall safeguard, mai
- Page 30 and 31: METRO GOLD LINE FOOTHILL EXTENSION
- Page 32 and 33: 3.6.1 Application of Standards A. P
- Page 34 and 35: other operations. Hazardous or cont
- Page 36 and 37: Design-Builder shall not discharge
- Page 38 and 39: permit fees, notification, and comp
- Page 40 and 41: 3.13 Seismic Safety Design-Builder
- Page 42 and 43: A. Authority shall have provided al
- Page 44 and 45: 3.21 Work Restrictions At all times
- Page 46 and 47: B. Calendar shall incorporate each
- Page 48 and 49: logic ties. Designate these activit
- Page 50 and 51: activity durations, and activity da
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
Request for Proposals (RFP)<br />
Intermodal Parking Facilities<br />
and Enhancements<br />
Design-Build Project<br />
RFP C1150<br />
VOLUME 3- TECHNICAL PROVISIONS<br />
DOCUMENT 1- GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
TABLE OF CONTENTS<br />
INTERMODAL PARKING FACILITIES AND ENHANCEMENTS<br />
GENERAL REQUIREMENTS<br />
1.0 PROJECT MANAGEMENT ..................................................................................................... 1<br />
1.1 Management Program and Organization ....................................................................... 1<br />
1.2 Project Management Plan ............................................................................................. 1<br />
1.3 Project Management and Administration ....................................................................... 2<br />
1.4 Coordination and Interface with Other Contractors ........................................................ 4<br />
1.5 Community Impact and Communications Program ........................................................ 4<br />
1.6 Environmental Sustainability .......................................................................................... 7<br />
2.0 DESIGN MANAGEMENT ........................................................................................................ 8<br />
2.1 Design Responsibility .................................................................................................... 8<br />
2.2 Design Changes .......................................................................................................... 20<br />
2.3 Design Support during Construction ............................................................................ 21<br />
3.0 CONSTRUCTION CRITERIA ................................................................................................ 22<br />
3.1 Access and Protection of Property ............................................................................... 22<br />
3.2 Pre/Post Construction Surveys .................................................................................... 23<br />
3.3 Dewatering .................................................................................................................. 24<br />
3.4 Temporary Facilities and Utility Services ..................................................................... 24<br />
3.5 Construction Sequence Factors ................................................................................... 26<br />
3.6 Maintenance of Traffic during Performance of the Work .............................................. 26<br />
3.7 Temporary Erosion and Sediment Control during Performance of the Work ................ 30<br />
3.8 Water Pollution Controls during Performance of the Work ........................................... 30<br />
3.9 Air Pollution Controls during Performance of the Work ................................................ 31<br />
3.10 Construction Noise and Vibration Control .................................................................... 33<br />
3.11 Fire Prevention ............................................................................................................ 33<br />
3.12 Jobsite Cleanliness ...................................................................................................... 34<br />
3.13 Seismic Safety ............................................................................................................. 35<br />
3.14 Historical and Scientific Specimens Encountered During Construction ........................ 35<br />
3.15 Salvage of Materials .................................................................................................... 35<br />
3.16 Removal, Treatment and Disposal of Materials ........................................................... 35<br />
3.17 Hazardous Substances Handling and Disposal ........................................................... 36<br />
i INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
3.18 Tree Removal .............................................................................................................. 36<br />
3.19 Temporary Lighting ...................................................................................................... 36<br />
3.20 Construction Start-up ................................................................................................... 36<br />
3.21 Work Restrictions ........................................................................................................ 39<br />
3.22 Site Preservation/Environmentally Restricted Sites ..................................................... 39<br />
4.0 COST/SCHEDULE MANAGEMENT ..................................................................................... 40<br />
4.1 Schedule Terminology ................................................................................................. 40<br />
4.2 Personnel .................................................................................................................... 41<br />
4.3 Scheduling Software .................................................................................................... 41<br />
4.4 Tabular and Graphic Reports....................................................................................... 42<br />
4.5 Schedule Format and Content ..................................................................................... 42<br />
4.6 Baseline Schedule ....................................................................................................... 47<br />
4.7 Project Schedule Updates ........................................................................................... 50<br />
4.8 Written Narrative.......................................................................................................... 52<br />
4.9 Review and Evaluation ................................................................................................ 54<br />
4.10 Schedule Control Procedures ...................................................................................... 55<br />
4.11 Effect of Schedule Reviews ......................................................................................... 55<br />
4.12 Progress Photographs ................................................................................................. 55<br />
4.13 Rain Days and Weather ............................................................................................... 56<br />
5.0 QUALITY MANAGEMENT .................................................................................................... 57<br />
5.1 Quality Control/Quality Assurance Plan ....................................................................... 57<br />
5.2 Quality Control/Quality Assurance Plan – Part One ..................................................... 59<br />
5.3 Quality Control/Quality Assurance Plan – Part Two ..................................................... 62<br />
5.4 Quality Control/Quality Assurance Plan – Part Three .................................................. 67<br />
5.5 Documentation Quality Control and Quality Assurance................................................ 74<br />
6.0 CONTRACT MEETINGS ....................................................................................................... 76<br />
6.1 Project Kick-Off Meeting .............................................................................................. 76<br />
6.2 Weekly Project Coordination and Progress Meeting .................................................... 77<br />
6.3 Baseline Schedule and Current Project Schedule Meetings ........................................ 78<br />
6.4 Utility Owner Meetings ................................................................................................. 78<br />
6.5 Third Party Coordination Meetings .............................................................................. 79<br />
6.6 Additional Meetings ..................................................................................................... 79<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
ii INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
7.0 DOCUMENTATION ............................................................................................................... 80<br />
7.1 Format of Documents .................................................................................................. 80<br />
7.2 Submission of Documents ........................................................................................... 83<br />
7.3 Management of Documents ......................................................................................... 84<br />
7.4 Record Documents ...................................................................................................... 84<br />
7.5 Record Drawings ......................................................................................................... 85<br />
7.6 Record Specifications .................................................................................................. 87<br />
8.0 SITE SAFETY REQUIREMENTS .......................................................................................... 89<br />
8.1 <strong>General</strong> ....................................................................................................................... 89<br />
8.2 Products ...................................................................................................................... 93<br />
8.3 Execution .................................................................................................................... 95<br />
8.4 Design-Builder Responsibility .................................................................................... 100<br />
9.0 REVIEW, VERIFICATION AND ACCEPTANCE ................................................................. 101<br />
9.1 Facilities Tests and Inspection ................................................................................... 102<br />
9.2 Verification and Acceptance ...................................................................................... 104<br />
9.3 Punch Lists ................................................................................................................ 109<br />
9.4 Verification, Notifications, Briefings, and Documentation ........................................... 109<br />
10.0 CONTRACT DATA REQUIREMENTS LIST (CDRL) .......................................................... 111<br />
10.1 Definitions and Use ................................................................................................... 111<br />
10.2 Master List of Submittals ........................................................................................... 111<br />
10.3 Format <strong>Requirements</strong> for Submittals ......................................................................... 111<br />
10.4 Identification <strong>Requirements</strong> ....................................................................................... 112<br />
10.5 Submittals.................................................................................................................. 113<br />
10.6 Supplemental Submittals ........................................................................................... 116<br />
10.7 Design-Builder Responsibilities ................................................................................. 116<br />
10.8 Authority’s Review ..................................................................................................... 117<br />
11.0 ADDITIONAL DESIGN-BUILDER REQUIREMENTS .......................................................... 120<br />
11.1 Mitigation Monitoring Program ................................................................................... 120<br />
11.2 Coordination and Conformity with Agreements .......................................................... 120<br />
11.3 Operations and Maintenance Manuals ...................................................................... 120<br />
11.4 Spare Parts and Materials ......................................................................................... 125<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
iii INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
APPENDICES<br />
Appendix A Environmental Sustainability Guidelines and Checklist<br />
Appendix B Contract Data Requirement List<br />
Appendix C Tree Removal Policy<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
iv INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
1.0 PROJECT MANAGEMENT<br />
1.1 Management Program and Organization<br />
For the duration of the Contract, Design-Builder shall be responsible for the total management of<br />
the design and construction (including all permits), installation, inspection, testing, and acceptance<br />
of the Work as described in the Contract Documents, pursuant to the terms and conditions thereof.<br />
Design-Builder shall be responsible for establishing the required organization and procedures and<br />
providing the personnel and supporting equipment/facilities to ensure that the Project is completed<br />
within the applicable Completion Deadline.<br />
Design production work shall be completed in Los Angeles County or immediately adjacent<br />
Counties for the duration of the design.<br />
Key Personnel of Design-Builder’s Project management team shall each be experienced in the<br />
activities of their assigned role and shall have a record of past performance sufficient to ensure that<br />
they have the experience, competence, and integrity to successfully complete a contract of this<br />
magnitude.<br />
All of Design-Builder’s activities shall be under the direction of the Project Manager who shall be the<br />
principal contact between Design-Builder and the Authority.<br />
1.2 Project Management Plan<br />
Design-Builder shall submit to the Authority for review and approval, and comply with the Project<br />
Management Plan. The Project Management Plan shall include, at a minimum, the following items:<br />
A. An organizational chart of all management personnel from Project Manager down to<br />
discipline leads and superintendent level, together with the qualifications,<br />
responsibilities, and involvement of Key Personnel on the Project;<br />
B. Complete work breakdown structure (WBS), indicating the source/responsibility for<br />
completing each aspect of the Work. The WBS shall be the basis for organizing all Work<br />
under the Contract, and shall be reflected in the organization of the Baseline Schedule<br />
and Current Project Schedules;<br />
C. A submittal schedule for all deliverables and design review data, as required by Section<br />
4.0;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
D. The approach to manage and oversee the design and construction, including interface<br />
management and integration with the Alignment Contractor’s work, including:<br />
1. Permits;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
2. Establishment of horizontal and vertical control and design;<br />
3. Structures;<br />
4. Drainage;<br />
5. Water quality/SUSMP;<br />
6. Signing and graphics;<br />
7. Utilities;<br />
8. Stairs;<br />
9. Elevators;<br />
10. Mechanical, ventilation, and sprinkler systems;<br />
11. Electrical;<br />
12. Landscaping/irrigation;<br />
13. Duct banks and conduits;<br />
14. Roadway improvements;<br />
15. Maintenance of pedestrian, bicycle, and vehicular;<br />
16. Power and infrastructure for the communications systems that are provided<br />
by others; and<br />
17. Coordination with Alignment Contractor; and<br />
E. A comprehensive description of how the community and stakeholder outreach will be<br />
conducted, and how it will relate to the key design and construction milestones.<br />
1.3 Project Management and Administration<br />
Design-Builder’s responsibilities include the following:<br />
A. Project management and administration, including scheduling, cost control, reporting,<br />
material procurement, and inspection;<br />
2 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
B. Creation of the Schedule of Values in accordance with Contract Section 7.2;<br />
C. Design, engineering, and analysis;<br />
D. Obtaining all required permits;<br />
E. Construction and installation, including management and supervision;<br />
F. Quality control;<br />
G. Quality assurance;<br />
H. Interface management;<br />
I. Equipment testing and commissioning;<br />
J. Preparation, management, and execution of the plans and other elements required to<br />
satisfy the safety and security provisions as specified in Section 8.0 of this document;<br />
K. Quality testing and verification; performance of all required reviews, inspections, tests,<br />
and demonstrations required for verification and acceptance of the Project;<br />
L. Project documentation, including preparation, delivery and correction, as necessary, of<br />
all deliverable data as specified in the Contract Documents;<br />
M. Provision of all bonds, insurance, permits/licenses, guarantees, and warranties as<br />
required by the Contract Documents;<br />
N. All Work required under the guarantees and warranties as required by the Contract;<br />
O. A communications program to proactively interface with stakeholders regarding the<br />
design and construction of the Project;<br />
P. Design, fabrication, installation, and maintenance of all Project identification signs;<br />
Q. Maintenance, servicing, and repairs of all Design-Builder provided facilities and<br />
equipment until Substantial Completion. Design-Builder shall maintain records of all<br />
preventive and corrective maintenance performed and make this information available to<br />
the Authority for review upon request;<br />
R. Coordination with Authority, Cities, Utility Owners, County, and other applicable<br />
Governmental Persons;<br />
S. Coordination with <strong>Metro</strong>, which will be coordinated via Authority; and<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
3 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
T. Other Project management activities/tasks required to satisfy all of the provisions of this<br />
Contract.<br />
1.4 Coordination and Interface with Other Contractors<br />
Design-Builder shall provide all equipment, improvements, and other elements necessary to<br />
complete the Project. Design-Builder shall check and be fully familiar with applicable Alignment<br />
Project’s design and construction and other documents as provided by the Authority from time-to-<br />
time. Specifically, Design-Builder is responsible for verifying the interfaces and compatibility of the<br />
Alignment Project with the Project and alerting the Authority within three weeks of each transmittal<br />
of any discrepancies, errors, or other problems affecting Design-Builder or where Alignment<br />
Contractor’s design would affect the Project.<br />
In addition, Design-Builder shall coordinate its operations with all non-Authority contractors along<br />
and adjacent to the Project.<br />
1.4.1 Alignment Contractor<br />
Design-Builder shall fully coordinate and cooperate with the Authority and the Alignment Contractor<br />
to achieve a fully coordinated, integrated, complete, and functional design in accordance with the<br />
Contract Documents.<br />
1.5 Community Impact and Communications Program<br />
Under the direction of the Authority, Design-Builder shall have primary responsibility for developing<br />
and implementing a communications program that keeps stakeholders (i.e., public, businesses,<br />
Cities, local agencies, elected officials, community based organizations, etc.) informed regarding<br />
activities on the Project and mitigates construction impacts as much as possible. The program shall<br />
be outlined in a detailed Community Outreach and Communications Plan that explains the<br />
communication activities planned, and how they relate to the different design and construction<br />
phases of the Project.<br />
The plan shall include a narrative explaining Design-Builder’s understanding and approach to<br />
effectively and proactively communicate with affected stakeholders, and what actions will be taken<br />
to mitigate potential impacts as a result of the Project and construction activities. At minimum, the<br />
plan shall discuss specific issues relating to each of the following major impacted stakeholder and<br />
how those issues will be proactively addressed:<br />
A. Recognized community groups and affected residents;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
4 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
B. Recognized business groups and affected businesses;<br />
C. Cities;<br />
D. County;<br />
E. <strong>Metro</strong>;<br />
F. Utility Owners;<br />
G. First responders; and<br />
H. Schools and Unified School Districts within close proximity of the Project.<br />
The following is a partial list of potential impacts that shall be addressed (this list is not<br />
comprehensive and should be expanded as necessary to mitigate anticipated impacts):<br />
A. Traffic control, dust control, and noise/vibration control during performance of the Work;<br />
B. Maintenance of pedestrian, bicycle, and vehicular traffic and access during performance<br />
of the Work (including safe routes to schools and emergency response);<br />
C. Business access and other impacts during performance of the Work;<br />
D. Property impacts during performance of the Work;<br />
E. Emergency and Safety situations during performance of the Work;<br />
F. Utility disruption, interruption, and Relocation impacts;<br />
G. Facility design; and<br />
H. Landscaping and fencing design.<br />
The program shall make it easy for interested and affected stakeholders to stay abreast of the latest<br />
updates, and include:<br />
A. Development and maintenance of a Project database that includes affected and<br />
interested stakeholders (residents, businesses, community-based organizations, first<br />
responders, city officials, etc.). Design-Builder shall provide a copy of the database<br />
upon request to the Authority for inclusion in the Authority’s master database, but<br />
minimally shall provide monthly updates as part of the status updates to the Authority<br />
and a final database at the completion of the Project;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
5 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
B. Use of traditional and new media tools to inform the community about upcoming impacts<br />
and Project milestones (e.g., preparation of press releases and media advisories; blog<br />
posts, e-notices, and Twitter and Facebook updates);<br />
C. Coordination and participation at stakeholder meetings, presentations, and briefings at<br />
appropriate milestones throughout the design and construction process (different<br />
formats shall be used to reach different stakeholder audiences and can include online<br />
and traditional formats);<br />
D. Development of public information materials (fact sheets, web content, display boards,<br />
slide show presentations, other relevant materials) for use at meetings, presentations,<br />
and briefings throughout the design and construction process (all materials shall<br />
recognize that the Project is funded by Measure R through <strong>Metro</strong>);<br />
E. Creation of construction-related status signage and distribution of public notices to<br />
provide affected stakeholders advanced notice of closures and impacts (see Section 3.0<br />
for additional details). Notices and signage shall recognize that the Project, Construction<br />
Authority, and Measure R funding and must be distributed and posted at least five days<br />
before an impacting activity (city officials should receive the notice ahead of the public<br />
and be given enough time to review and provide comments). Notices may need to be<br />
developed in Chinese and Spanish, depending on the community;<br />
F. Early and regular communication with affected neighbors through email, direct mail,<br />
residential/business neighborhood walks (or other approaches) to identify, address,<br />
and/or mitigate any design and construction concerns; and<br />
G. Staff support for the Authority’s overall community relations program related to the<br />
Project, including development of monthly e-newsletter updates, web content,<br />
participation at stakeholder meetings and briefings, etc.<br />
As with all aspects of Design-Builder program, the communications program shall meet the highest<br />
standards of quality and excellence. A component of the communications plan shall outline<br />
Design-Builder’s quality control process for the communications materials and activities, including<br />
providing adequate time for Authority and city (when appropriate) review and approval of all public<br />
materials and activities.<br />
1.5.1 Contact with News Media/Media Protocol<br />
As part of the communications program, Design-Builder shall develop a protocol for all media<br />
activities (proactive media outreach, responding to media requests, and emergency/crisis<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
6 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
communications). The protocol shall assume the following: (1) the Authority’s media spokesperson<br />
and/or his/her designee shall be notified of all media-related issues and Design-Builder shall comply<br />
with the direction of Authority for all media related activities, and (2) Design-Builder shall also<br />
identify a spokesperson and/or his/her designee, so that a representative is available at all times to<br />
assist with communicating with the media.<br />
1.5.2 Specific Information<br />
Should an event, incident, or other Project circumstance develop which is likely to generate<br />
community or media interest, Design-Builder shall inform the Authority immediately and cooperate<br />
with Authority direction with regard to content and distribution of information. Design-Builder shall<br />
ensure that all field supervisors and other management personnel are aware of and follow the<br />
Authority’s emergency communication action plan in the event of an emergency.<br />
1.5.3 Authority Consent<br />
Notwithstanding anything to the contrary set forth herein, Design-Builder shall not have any<br />
communications with the public or the media or otherwise communicate or distribute any<br />
information regarding the Project without obtaining Authority’s prior written consent.<br />
1.6 Environmental Sustainability<br />
Design-Builder shall incorporate environmentally sustainable options and “green building” measures<br />
whenever they are technically feasible and cost-effective in accordance with the Authority’s<br />
Environmental Sustainability Guidelines and Checklist located in Appendix A.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
END OF SECTION<br />
7 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
2.0 DESIGN MANAGEMENT<br />
This Section 2.0 specifies Design-Builder’s design management requirements relating to the<br />
development of design products during the course of the Project.<br />
The designer may perform production design work in Los Angeles County or immediately adjacent<br />
Counties.<br />
2.1 Design Responsibility<br />
Design-Builder shall:<br />
A. Produce the complete design of the Project as described in the Contract Documents;<br />
B. Develop Design Documents that shall be in conformity with the requirements set forth in<br />
the Contract Documents and signed and sealed by a State of California registered<br />
architect or engineer in the appropriate discipline when the design is ready for<br />
construction;<br />
C. Manage all interfaces and shall develop an interface management plan that identifies all<br />
interfaces associated with the Project and documents how each interface will be<br />
accomplished during the Contract;<br />
D. Conduct meetings and coordinate with all third parties and applicable Governmental<br />
Persons whose approval is required. Refer to Section 6.0 of these <strong>General</strong><br />
<strong>Requirements</strong> for additional meeting requirements;<br />
E. Comply with all design requirements pertaining to Persons having jurisdiction over the<br />
Work and obtain all necessary approvals from said Persons and other third parties for all<br />
design and construction;<br />
F. Transmit a copy of all correspondence to and from Design-Builder or its representatives<br />
and any Person or third party to the Authority;<br />
G. Notify the Authority of any problems in the written narrative discussed in Section 4.8.<br />
Design-Builder shall be liable for any delays caused by a Person responsible for issuing<br />
permits or approvals except as set forth in Contract Section 12.3.1(c);<br />
H. Use the Authority’s document upload interface system (DUI) to electronically submit<br />
Design Documents (and any other contract-related documents) for review and obtain<br />
comments from reviewers throughout the Project;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
8 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
I. Create and maintain a log of all submittals in a format agreed to by the Authority and<br />
provide the log to the Authority on a weekly basis; and<br />
J. Include submittal review times in the Baseline Schedule and Current Project Schedules<br />
in accordance with the following: 30 days for Authority and <strong>Metro</strong>; and 30 days for all<br />
other third parties unless otherwise stated in Volume 5- Agreements.<br />
2.1.1 Design Organization<br />
Design-Builder’s design organization may comprise consultant staff or an in-house design team, but<br />
shall be qualified and experienced in the design of parking facilities and the requirements of this<br />
Project. Design-Builder shall maintain a sufficient quality and quantity of professional staff<br />
throughout the duration of the Contract to ensure Design-Builder meets the requirements set forth<br />
in the Contract Documents.<br />
2.1.2 Design-Builder’s Design Manager<br />
Design-Builder shall designate and assign a Design Manager who reports to Design-Builder’s<br />
Project Manager and who is responsible for managing all Work performed by Design-Builder’s<br />
design organization, including the designers, engineers, schedule and production of each design<br />
package. The Design Manager shall be a California-licensed professional engineer and have<br />
sufficient experience and background necessary to lead the design effort for the Project. Design-<br />
Builder must obtain Authority’s written approval of the final selection of the Design Manager prior to<br />
such Design Manager beginning work. The Design Manager shall plan and manage the design<br />
activities using a Critical Path method (CPM) of scheduling together with a work breakdown<br />
structure detailing the actual Design Documents to be produced.<br />
When the design packages are finalized for each submittal, the Design Manager shall conduct an<br />
assessment and evaluation of the design and shall certify to Design-Builder’s Project Manager that<br />
the design satisfies the requirements set forth in the Contract Documents, including those for:<br />
A. Accuracy;<br />
B. Adequacy;<br />
C. Conformity to standards of practice;<br />
D. Compliance with applicable Governmental Rules and third party requirements;<br />
E. Reliability;<br />
F. Maintainability;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
9 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
G. Constructability;<br />
H. Cost effectiveness;<br />
I. Interfaces and systems integration;<br />
J. Quality; and<br />
K. Suitability for purpose and/or function as specified in the Contract Documents.<br />
To make such certification to Design-Builder’s Project Manager, the Design Manager shall assess<br />
and evaluate all aspects of design, including:<br />
A. Design and Construction Documents;<br />
B. Analytical approach;<br />
C. Project design package coordination, including third party designs;<br />
D. Major temporary works’ effect on permanent works;<br />
E. Field design changes;<br />
F. Design approvals for materials and procedures; and<br />
G. As-built records.<br />
2.1.3 Responsible Land Surveyor<br />
Design-Builder shall be responsible for providing a licensed land surveyor who shall be responsible<br />
for the setting of permanent survey monuments for the Project. These monuments shall include<br />
control monuments, property and Right of Way monuments, and monuments required by the State<br />
Standard Specifications. They shall also include the replacement of property monuments, bench<br />
marks, and control monuments damaged or destroyed during performance of the Work. The<br />
responsible land surveyor will assure that survey monuments that might be destroyed during the<br />
Work are protected with reference points that allow for their replacement in the same location. The<br />
responsible land surveyor shall perform field surveys to support design and construction activities.<br />
2.1.4 Design Packages<br />
Within 30 days from Notice to Proceed, Design-Builder shall develop and submit to Authority for<br />
review and approval, a plan and schedule for packaging the Design Documents for the Work into a<br />
series of groupings or design packages. At a minimum, the Work shall be divided into separate<br />
design packages for each Parking Facility and separate Enhancement packages for each City. The<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
10 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
design packages shall consist of discrete elements of the Work that provide a logical and efficient<br />
method for completing the Project within the approved Baseline Schedule or Current Project<br />
Schedule, and in conformity with Contract Documents, providing the best coordination and interface<br />
of design elements between the design disciplines involved. Each design drawing package shall<br />
have a cover sheet, index sheet, and abbreviation/legend sheet(s), which shall be maintained and<br />
updated for each design package submittal.<br />
Design-Builder shall separately submit each design package at each design development stage<br />
(refer to Sections 2.1.5.2 through 2.1.5.4 for requirements at each design development stage) to the<br />
Authority and applicable third parties for review and approval of the design of all Work for which<br />
their approval is required. Authority and third party design reviews shall not commence until all<br />
required Design-Builder internal design reviews have been accomplished in accordance with<br />
Section 2.1.7.<br />
The design package plan and submittal schedule shall consist of a description and scope of design<br />
Work for each design package, including limits and interface points; schedule of design review<br />
stages and dates; and responsible engineer. The design package plan and submittal schedule<br />
shall be incorporated into the Baseline Schedule and Current Project Schedule, as applicable, and<br />
be reviewed monthly in accordance with Section 4.6 of these <strong>General</strong> <strong>Requirements</strong> until design is<br />
complete. Based on an estimated total number of packages and the content of the packages, the<br />
Authority (with applicable third party participation) and Design-Builder will agree to a maximum<br />
number of design packages that shall be scheduled for review and approval by the Authority and<br />
third parties, as applicable, at one time. Design-Builder shall obtain the Authority’s written<br />
concurrence prior to deviating from the approved maximum number of design packages that can be<br />
scheduled at one time for review and approval.<br />
2.1.5 Design Development<br />
Design-Builder shall develop the design of the Project utilizing the process outlined in Sections<br />
2.1.5.1 through 2.1.5.4 of these <strong>General</strong> <strong>Requirements</strong>.<br />
2.1.5.1 Design Workshop<br />
Within 60 days of Notice to Proceed, Design-Builder shall conduct a design workshop to present its<br />
design understanding/approach and provide detailed information regarding design concepts,<br />
design quality requirements, issues, status, communication review procedures, and discuss the<br />
following subjects:<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
11 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
A. <strong>General</strong>:<br />
B. Civil:<br />
C. Utilities:<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Status report listing data or information from others that affect completion of<br />
Project scope definition and Design-Builder’s approach to acquire the data<br />
and/or information specifically excluded or missing from the documents;<br />
2. Identify the means and methods intended to acquire all third party approvals;<br />
3. Identification and reasons for any variations from Volume 3- Technical<br />
Provisions;<br />
4. Identification of any modifications to the design approach and documents<br />
presented by Design-Builder as part of their Proposal;<br />
5. Approach to constructability reviews; and<br />
6. Approach to overall Project coordination and interface;<br />
1. Preliminary grades at the Parking Facilities, Enhancements, and interface<br />
locations;<br />
2. Preliminary construction phasing for the preparation of maintenance of traffic<br />
plans;<br />
3. Preliminary traffic signal, traffic sign, and pavement marking design;<br />
4. Preliminary drainage and water quality design identifying both on and off site<br />
systems;<br />
5. Preliminary geotechnical analysis/results;<br />
6. Preliminary foundation and structural design;<br />
7. Preliminary type, size, and location of all retaining walls and the preliminary<br />
means and methods on construction/installation;<br />
8. Other elements of the Project definition advanced to the degree that satisfies<br />
the above stated purpose of the workshop; and<br />
9. Provide a preliminary definition of permanent and temporary needs for the<br />
facilities, Utilities, roadway rearrangements, and access; and temporary<br />
needs for construction and for Design-Builder staging and storage;<br />
12 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
D. Architectural;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Solutions, coordinated with Utility Owners, for Utility Work;<br />
2. Identification of any early Relocations shall be as so deemed by Design-<br />
Builder;<br />
3. Preliminary design of New Utilities and extension of existing Utilities;<br />
4. Preliminary conduit and sleeve provisions, as required by the Project and<br />
<strong>Metro</strong>; and<br />
5. Utility and structure conflicts shall be identified;<br />
E. Mechanical, electrical, and plumbing (MEP):<br />
1. Approach to the MEP requirements at Parking Facilities, including ventilation;<br />
2. Preliminary conduit routing plan for parking structures, along with interface to<br />
the Alignment Contractor’s duct bank and conduit system (DBCS);<br />
3. Approach to equipment rooms; and<br />
4. Preliminary facility equipment sizes and locations; and<br />
F. Communications Systems infrastructure:<br />
1. Approach to communications equipment housings at Parking Facilities; and<br />
2. Identification of infrastructure and interfaces for the Communications systems<br />
provided by others.<br />
Design-Builder shall develop the agenda of the workshop and how it will be organized (i.e., by<br />
design package, engineering discipline, sub-tier design organizations, internal and Authority design<br />
reviews). At this meeting, Design-Builder will present its submittal schedule and describe how this<br />
schedule will be updated once it is approved by the Authority. The intent of the workshop is to make<br />
all design reviews effective and efficient for all parties.<br />
2.1.5.2 Interim Design (60%) Over-The-Shoulder Review<br />
During the design process, Design-Builder shall develop Project-specific specifications in<br />
Construction Specification Institute (CSI) format, or Authority-approved alternative, and drawings<br />
based on the specific materials, products, equipment, procedures, and methods that Design-Builder<br />
intends to use, and shall comply with all applicable Authority and third party requirements.<br />
13 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Following the completion of the design workshop described in Section 2.1.5.1, each Parking Facility<br />
and Enhancement design package, as defined in Section 2.1.4, shall be presented to the Authority<br />
and applicable third parties, for an over-the-shoulder review, and shall include general<br />
configuration, grades, sections, plan and elevation views, preliminary equipment layouts,<br />
preliminary structure layouts and foundation design, preliminary design reports, drainage and water<br />
quality, utilities, MEP, roadway improvements, retaining walls, and similar level of design for the<br />
features included in the design package. Progress design drawings (grading, structural,<br />
architectural, MEP, cross sections, drainage, water quality, roadway, and pavement details)<br />
structural calculations, geotechnical and hydrology reports, and specifications, and various product<br />
data and samples shall be submitted to the Authority and applicable third parties for review, as part<br />
of the interim design review. All documentation required to request deviations from the Authority or<br />
third party design criteria or standards shall also be submitted at this stage.<br />
In addition, construction sequencing, street closure requests, and the tree removal list shall be<br />
complete at this stage. The interim design stage shall include all completed preliminary design<br />
items.<br />
Design-Builder shall submit progress drawings to the Authority and applicable third parties for<br />
review. All interim design review items shall be at approximately 60% level of design completion.<br />
The interim design submittals shall include all necessary design, plans, reports, and information in<br />
sufficient detail for the reviewer to fully comprehend the intent of the proposed design.<br />
2.1.5.3 Pre-Final Design (85%)<br />
Design-Builder shall submit to the Authority and applicable third parties for review and approval all<br />
pre-final design submittals at approximately the 85% level of design completion. The pre-final<br />
design shall address all aspects of the design shown on Design-Builder’s drawings and<br />
specifications, include all the details necessary for construction, and shall have been coordinated<br />
among the various disciplines. All design review and lessons learned comments received from<br />
prior reviews shall have been reviewed, resolved, and incorporated, as applicable. The following<br />
items shall be checked during the pre-final design review:<br />
A. Applicable Governmental Rules and third party requirements;<br />
B. Interface requirements with other elements;<br />
C. Comments and action items from earlier design reviews;<br />
D. Comments and concerns from the external and constructability reviews;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
14 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
E. Cost effectiveness;<br />
F. Schedule compliance;<br />
G. Clarity of intent;<br />
H. Standard and directive drawings; and<br />
I. Adherence to direction provided by the Authority and commitments made to third parties.<br />
The pre-final design shall demonstrate that the design detail satisfies design requirements and the<br />
exact interface relationships between the system and other items of equipment and facilities.<br />
Design-Builder’s pre-final design submittals shall include the following:<br />
A. Complete Design Documents identifying all proposed construction;<br />
B. Permit applications;<br />
C. Identification that the numerous interfaces between disciplines has been addressed;<br />
D. List of pre-construction activities to be done by others;<br />
E. Construction schedule;<br />
F. Geotechnical design summary report (GDSR);<br />
G. Environmental design summary report (EDSR), containing a description, list of<br />
regulatory requirements, list of necessary permits, and other regulations; description of<br />
mitigation requirements; and bibliography of all relevant documents which describe the<br />
environmental conditions on the project;<br />
H. MEP documents required in the 60% interim design submittal shall be updated and<br />
augmented as necessary to the 85% design level and included in the pre-final design<br />
submittal; and<br />
I. Civil and architecture:<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Advance the components developed in the previous stages of design to an<br />
85% level of completion. Each aspect shall be of sufficient detail for the<br />
reviewer to fully evaluate the completeness of the proposed design;<br />
2. Updated paint chips and in-field samples on actual materials such as<br />
canopies, handrails, etc., for each of the color selections specified in Volume<br />
3, Document 2- Performance Specifications, Section 8.0, and additional color<br />
15 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
selections as requested by the Authority, if different than information<br />
submitted at the 60% design level; and<br />
3. Updated architectural components for each project component such as bus<br />
shelters, seating elements, light poles and fixtures, trash receptacles, bike<br />
lockers and racks, and finish surface materials, if different than information<br />
submitted at the 60% design level. Design-Builder shall provide cut sheets<br />
and supporting material along with an actual sample in Authority-approved<br />
color. This includes a submission of materials and appropriate<br />
documentation for all aesthetic features proposed for the Project.<br />
2.1.5.4 Final Design Development (100%)<br />
Following the review of the 85% submittals and receipt of comments, Design-Builder shall revise<br />
the drawings and documents to reflect the necessary corrections to comply with applicable<br />
Governmental Rules, third party requirements, and other requirements of the Contract Documents<br />
and conduct joint comment resolution meeting(s) for each design package submittal in accordance<br />
with Section 2.1.9. Design-Builder shall then revise, supplement if necessary, and resubmit 100%<br />
or final design plans to the Authority and applicable third parties for review and approval.<br />
The final design package shall include Design Documents necessary for final Authority and third<br />
party approval and for construction of the Work that are detailed, 100% complete, and checked in<br />
accordance with Design-Builder’s QCQAP. All documentation including written approval of design<br />
deviations from Authority, <strong>Metro</strong>, or third party requirements shall have been provided to Authority<br />
prior to the final design package submittal.<br />
2.1.6 Design Review Documentation<br />
Design-Builder shall maintain a written record of all formal internal design reviews. The written<br />
record shall:<br />
A. List the participants of each review;<br />
B. Cover the items discussed;<br />
C. Identify items being designed, developed, or reviewed;<br />
D. Identify discrepancies noted and report on corrective action taken or planned;<br />
E. Identify follow-up items, due dates, and party responsible for future action; and<br />
F. Identify items needing resolution and time constraints for resolution.<br />
16 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Reports of design reviews, including oversight visits, shall be submitted to the Authority within<br />
seven days of completion of the review or visit.<br />
Items found during reviews, surveillances, or audits by Design-Builder or his design organization<br />
requiring correction shall be documented on comment sheets and tracked for resolution by the<br />
design organization.<br />
The Authority may require Design-Builder to re-submit additional Design Documents for review<br />
where the information submitted is considered insufficient to conduct a proper review or actions<br />
arising from the design review require significant revisions.<br />
Design-Builder shall bear the time and cost of impacts for resubmissions or revisions arising from<br />
the design reviews and caused by Design-Builder’s non-compliance with the requirements set forth<br />
in the Contract Documents or inadequacy or incompleteness of the submittal.<br />
Detailed requirements for the submission of Design Documents are included in Section 7.0 and<br />
Section 10.0 of these <strong>General</strong> <strong>Requirements</strong>. Design-Builder shall copy the Authority on all<br />
submittal correspondence between Design-Builder and applicable third parties and/or<br />
Governmental Persons, and include copies of any and all review comments pertaining to submittals<br />
within seven days of transmission or receipt.<br />
2.1.7 Design-Builder’s Internal Design Checks and Certifications<br />
Design-Builder shall perform an internal design review process at all design levels for all Design<br />
Documents produced by the design organization including its Subcontractors. Design-Builder shall<br />
certify that the documents have been reviewed and checked per the quality control/quality<br />
assurance plan (QCQAP) and that previous review comments have been incorporated or resolved.<br />
In addition to the internal design reviews, Design-Builder shall form a constructability team and such<br />
team shall perform internal constructability reviews at 60% and 85% completion of each design<br />
package to ensure that construction considerations have been taken into account during the design<br />
process. Design-Builder’s constructability team shall be formed of members that are independent<br />
of the design team. Reports of the constructability review shall be submitted to the Authority within<br />
seven days of completion of the review indicating the parameters and interfaces verified during the<br />
review and including comments and how they are being addressed. All internal review comments<br />
shall be addressed by Design-Builder prior to submittal to the Authority.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
17 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
2.1.8 Submittal Review Comments<br />
Authority comments will be provided to Design-Builder using a comment review matrix. Third party<br />
comments will be provided to Design-Builder by the third party in their (third party’s) format.<br />
Design-Builder may receive separate comment packages from each organization and group within<br />
an organization that reviews a design submittal. Design-Builder shall input review comments<br />
(internal and external) into an electronic database, track each comment to resolution, and address<br />
and/or incorporate all comments. Design-Builder shall respond to all Authority and third party<br />
comments within 15 days of receipt. Design-Builder shall show the exact timing of reviews and<br />
resolution of comments through the weekly progress meetings and in the three-week rolling<br />
schedule and shall provide the Authority a copy of all comments that are made and a copy of how<br />
each comment has been addressed within seven days following the joint comment resolution<br />
meetings discussed in Section 2.1.9.<br />
Any comments received by Design-Builder beyond the timeline specified in the Contract Data<br />
<strong>Requirements</strong> List (CDRL) in Appendix B, shall be responded to by Design-Builder and Design-<br />
Builder’s responses shall be submitted to the Authority within seven days after receipt by Design-<br />
Builder of the review comments.<br />
2.1.9 Joint Comment Resolution Meetings<br />
A joint comment resolution meeting shall be scheduled by Design-Builder to discuss responses to<br />
the Authority and third party review comments and to determine the review comments to be<br />
incorporated into the Design Documents. More than one joint comment resolution meeting per<br />
design submittal may be necessary in order to discuss all design review submittal review<br />
comments. Design-Builder shall prepare meeting minutes of the joint comment resolution meetings<br />
in accordance with Section 6.0.<br />
2.1.10 Third Party Coordination Plan<br />
Design-Builder shall provide a third party coordination plan that includes the names of all applicable<br />
Governmental Persons, Utility Owners, and any other relevant third parties as well as the contact<br />
Persons at each agency or entity. The plan shall describe all interfaces, including the types of<br />
permits, approvals, coordination, and/or inspections anticipated for the Project. The third party<br />
coordination plan shall be submitted to the Authority for approval at least 10 days prior to the design<br />
workshop required in Section 2.1.5.1.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
18 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
2.1.11 Final Design Certification<br />
When the final 100% design for a design package has been completed, Design-Builder’s Design<br />
Manager shall submit verification and certification to Authority that:<br />
A. The design has been checked in accordance with Design-Builder’s Authority-approved<br />
QCQAP;<br />
B. Design-Builder has obtained all required third party approvals and permits;<br />
C. The Design Documents meet the requirements set forth in Section 2.1.2;<br />
D. The Design Documents comply with the requirements of the Contract Documents; and<br />
E. The Work shown on the Design Documents is ready for construction.<br />
2.1.12 Approval of Final Design Documents<br />
When all comments to the final design submittal for each design package have been addressed by<br />
Design-Builder to the Authority’s satisfaction and Design-Builder has obtained all applicable third<br />
party approvals, Authority shall sign and indicate on the final Design Documents “Approved for<br />
Construction”.<br />
Once a document has been Approved for Construction and items need to be clarified, such<br />
information shall be issued to Design-Builder’s field construction staff only after a copy has been<br />
provided to the Authority. In order to ensure that the Authority has received such information, no<br />
construction documentation shall be allowed to be used for construction unless it has an Authority<br />
Approved for Construction stamp. Work constructed from a document that does not have an<br />
Authority stamp shall be considered nonconforming. Any changes to Approved for Construction<br />
drawings and Specifications shall be issued as controlled documents to all plan-holders on the<br />
Project. Changes shall be marked as delta drawings with a unique delta number (starting with 1),<br />
clouded changes, and date. Specifications shall show modified text as highlighted or sidebar. All<br />
Approved for Construction Design Documents with changes shall be issued as superseding<br />
replacements with a clear definition of the changes to be implemented on the transmittal. If the<br />
changes are a result of a Change Order or Request for Information (RFI), the corresponding<br />
Change Order or RFI number shall be noted on the plan deltas and on the transmittal.<br />
2.1.13 Design Review of Major Temporary Works<br />
Design-Builder shall conduct a design review with the Authority and applicable third parties of major<br />
temporary works, including falsework and shoring, that represent complex structures and that<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
19 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
potentially may affect the Safety, quality, and durability of the permanent construction. The design<br />
of major temporary works shall be submitted to the Authority for information a minimum of 15 days<br />
prior to commencement of the work.<br />
Design-Builder shall produce the major temporary works designs after the design package<br />
documents have been approved and distributed. Major temporary works designs must undergo a<br />
separate formal review with the Authority and applicable Governmental Persons. All falsework and<br />
shoring plans must be stamped by a registered professional engineer currently licensed in the State<br />
of California, unless more stringent requirements are stated in Volume 5- Agreements.<br />
All necessary permits, clearances, and closures from applicable Governmental Persons shall be<br />
secured prior to construction.<br />
2.1.14 Additional Reviews<br />
The Authority (with <strong>Metro</strong>, Cities, Utility Owner, and other third party participation) may conduct<br />
additional “over-the-shoulder” reviews as considered necessary to ensure a continuous and uniform<br />
consistency in the quality, and effective incorporation of the requirements set forth in the Contract<br />
Documents and revisions to designs.<br />
2.2 Design Changes<br />
Design changes may occur prior to construction or may occur after Final Design, and may be<br />
initiated by Design-Builder or the Authority. Design-Builder shall address satisfactorily any changes<br />
to approved design initiated by Design-Builder or Authority for portions of the design already<br />
checked by the design organization and certified by Design-Builder’s Design Manager. Design-<br />
Builder shall not be entitled to any increase in the Contract Price or extension of time for changes<br />
initiated by the design organization or Design-Builder.<br />
All design changes shall undergo the same design review process as the original design.<br />
Design changes to final Design Documents shall be approved in writing by the responsible engineer<br />
of the original design or by a California-licensed professional engineer of appropriate experience if<br />
the original responsible engineer(s) is no longer available. All changes to designs, drawings,<br />
Specifications, calculations, and reports shall be signed and dated by a California-licensed<br />
professional engineer (signed and sealed for design changes to final Design Documents). Design-<br />
Builder's Design Manager shall submit verification and certification to the Authority in accordance<br />
with Section 2.1.11.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
20 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
2.3 Design Support during Construction<br />
Design-Builder is responsible for ensuring the technical integrity of the design. This responsibility<br />
includes the review and approval of construction submittals. Therefore, Design-Builder shall review<br />
and approve construction submittals. The Design-Builder’s Design Manager and responsible<br />
architect or engineer (Designer of Record) shall also review and approve all construction submittals<br />
for technical adequacy before they are submitted to the Authority and prior to construction.<br />
Design-Builder’s design organization and Design-Builder’s Design Manager shall verify during<br />
performance of the Work that the conditions actually encountered are consistent with the Approved<br />
for Construction Design Documents and Construction Documents. Design-Builder’s design<br />
organization shall prepare as-builts of the Approved for Construction Design Documents as the<br />
Work progresses in accordance with Section 6.0. Design-Builder shall conduct the necessary<br />
inspections and reviews to assure the accuracy and correctness of as-built documents.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
END OF SECTION<br />
21 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
3.0 CONSTRUCTION CRITERIA<br />
This Section 3.0 provides minimum construction criteria that must be complied with for this<br />
Contract. Design-Builder shall be solely responsible for, and have control over, construction<br />
means, methods, techniques, sequences, procedures, quality, Safety, and for coordinating all<br />
portions of the Work, subject to and in compliance with all requirements contained in the Contract<br />
Documents. Design-Builder shall take all reasonable precautions and shall provide protection to<br />
prevent damage, injury or loss due to its operations to property adjacent to the Site. Design-Builder<br />
shall ensure that all of its activities, and the activities of its employees, agents, officers, and<br />
Subcontractors, and all other Persons for whom Design-Builder may be legally or contractually<br />
responsible are undertaken in a manner that will minimize the effect on surrounding property and<br />
the public to the maximum extent practicable.<br />
As a precondition to commencing construction and procurement activities, Design-Builder shall<br />
furnish final Design Documents and Construction Documents for that portion of the Work, which<br />
shall be advanced to the 100% level and have been stamped Approved for Construction by the<br />
Authority. Any Work initiated by Design-Builder prior to approval by the Authority therefor will be at<br />
Design-Builder’s sole risk.<br />
During performance of the Work at the Site, Design-Builder shall clean and protect Work in<br />
progress on the basis of continuous daily maintenance. Design-Builder shall protect installed Work<br />
and materials from damage or deterioration.<br />
Design-Builder shall clean and maintain installed Work in good condition at all times prior to<br />
Substantial Completion. Design-Builder shall restore any infrastructure, street, road, facility,<br />
landscaping, Utility, etc., disturbed during performance of the Work. The Work will include<br />
removing all debris and cleaning the Site.<br />
3.1 Access and Protection of Property<br />
Design-Builder shall conduct construction operations in such a manner as to minimize<br />
inconvenience to owners of adjacent or affected properties. Convenient access to all property from<br />
streets along the Site shall be maintained.<br />
Whenever and wherever Work is performed, free access must be given to each fire hydrant, fire<br />
alarm box and standpipe. When required, fire hydrants shall be extended by suitable piping to an<br />
accessible point approved by the local fire department.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
22 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Design-Builder shall safeguard, maintain and protect all Utilities, wires, ducts, pipes, posts and<br />
poles, signals and other public and private property.<br />
Whenever necessary, Design-Builder shall erect and maintain signs, fences, barricades and<br />
pedestrian walkways and provide watchman and/or police officers for the protection of the public,<br />
the Site, adjoining property, and adjoining public places.<br />
Design-Builder shall maintain, protect and be responsible for the Safety, stability, and integrity of all<br />
buildings, Utilities, structures and property affected by the Work. Design-Builder shall provide for<br />
the protection, and support of existing buildings, Utilities, structures and property as needed. Any<br />
damage done to adjacent properties by Design-Builder or its Subcontractor’s shall be repaired to<br />
their original state at the sole expense of Design-Builder.<br />
Design-Builder shall restore all easement areas used for construction staging, storage or access to<br />
the condition existing prior to entry upon the property except for any Alterations specifically required<br />
by the Project. Restoration of the property shall include replacing in kind sidewalks, driveways,<br />
plantings, lawns, signs, drainage systems, walls, ramps, and other features.<br />
3.2 Pre/Post Construction Surveys<br />
Design-Builder shall perform a pre and post construction survey of the adjacent properties, Utilities,<br />
streets, and all other structures and facilities that may be impacted as part of the construction<br />
process. Design-Builder shall produce a detailed continuous high-definition digital video of the Site<br />
as well as use surveys, photographs, and other means necessary to accurately determine the<br />
existing street and Site conditions. Design-Builder shall photograph the entire Site, including<br />
adjacent structures, foliage, roadway surfaces, and any other features that will capture the<br />
undisturbed Site. If existing damage to adjacent structures, facilities, etc., is identified, these areas<br />
shall be carefully documented prior to the Work starting. Design-Builder shall submit to the<br />
Authority for review and approval copies of all photos, video, other survey records, and documented<br />
existing damaged conditions.<br />
Pre-construction surveys (PCS) of properties shall record existing conditions at the time of the<br />
examination prior to commencement of construction. Post-construction surveys shall be required to<br />
document that construction activities has not damaged adjacent properties. PCS of storm drains<br />
and sewer lines shall provide the existing conditions and document any existing cracks and breaks.<br />
Post construction surveys shall be required to document that construction activities have not<br />
damaged the system and shall document the same length of pipe that the PCS documented. The<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
23 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
PCS shall record the physical condition of existing structures and other facilities, etc., in the relevant<br />
area adjacent to the construction areas. This survey shall be performed in such a way as to form<br />
the basis for evaluating actual or alleged damage to these structures that may be caused by the<br />
construction. The post-construction survey shall be an identical examination performed in order to<br />
record the post-construction condition of the structures and other facilities, etc., adjacent to rail<br />
construction areas. The post-construction survey shall be performed in such a way as to document<br />
any changes or damages which have occurred during construction.<br />
In order to detect any movement of existing bridges and other structures that may be affected by<br />
the Work, Design-Builder, prior to the start of excavation, shall establish a system of vertical and<br />
horizontal control points on or about such structures. The points shall be tied to benchmarks and<br />
indices sufficiently remote so as not to be disturbed by Design-Builder’s operations. Such points<br />
shall be checked on a regular schedule, at least weekly, by a qualified person under the direction of<br />
a professional engineer or registered land surveyor.<br />
Design-Builder shall be responsible for handling all claims for damages and for repairing or<br />
replacing damaged facilities, structures, etc., at no cost to the Authority. In addition, any damage<br />
discovered after construction and not documented as part of the pre-construction survey shall be<br />
Design-Builder’s responsibility to fix at Design-Builder’s cost.<br />
3.3 Dewatering<br />
If needed, Design-Builder shall provide a dewatering system that effectively reduces hydrostatic<br />
pressures and lowers groundwater levels below excavation levels, as necessary for the safe and<br />
proper execution of work.<br />
Design-Builder shall take measures to ensure that soil particles are not removed by the system, that<br />
no movement is caused in adjacent areas by dewatering operations, and that no damage is caused<br />
to property, buildings, structures, facilities, sewers, other Utilities, pavements, etc.<br />
3.4 Temporary Facilities and Utility Services<br />
Design-Builder shall design, install, operate, maintain, remove and bear all costs for all temporary<br />
facilities, including offices, field offices, electrical power, telephone, water, fire protection, sanitary<br />
sewer and other Utilities needed for the construction and installation of the Project.<br />
A. Temporary electrical service includes:<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
24 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Providing lighting, power, and costs thereof for field offices, storage facilities<br />
and other construction facilities and areas;<br />
2. Providing power centers for electrically operated and controlled construction<br />
facilities including tools, equipment, interior construction lighting, and heating,<br />
cooling and ventilation equipment;<br />
3. Providing night security lighting at secured areas within the Site at offices,<br />
storage facilities, and excavated areas. Providing battery-operated or<br />
equivalent emergency lighting facilities at construction areas where normal<br />
light failures would cause employees to be subjected to hazardous<br />
conditions. Testing such facilities monthly; and<br />
4. Bearing all costs of temporary electrical service, including permits, fees, and<br />
deposits required by the governing authority or Utility Owner, connection<br />
charges, and temporary easements, including installation, maintenance and<br />
removal of equipment;<br />
B. Temporary telephone services include furnishing, installing, maintaining and removing all<br />
telephone service needed to effectively manage the construction, installation, and testing<br />
operations;<br />
C. Temporary water services include furnishing, installing, maintaining and removing a<br />
temporary water system during performance of the Work for drinking, construction,<br />
sanitation, first aid, fire protection and cleaning. Design-Builder shall be responsible for<br />
obtaining permits and approvals from regulating authorities and paying fees, deposits,<br />
and connection costs including installation, usage, maintenance, and removal<br />
associated with temporary water systems;<br />
D. Temporary fire protection includes furnishing, installing, maintaining and removing<br />
temporary fire protection equipment during performance of the Work as required by the<br />
local and National Fire Protection Association (NFPA) fire regulations;<br />
E. Temporary sanitation service includes:<br />
1. Furnishing, installing, maintaining and removing temporary sanitary facilities<br />
during performance of the Work;<br />
2. Providing separate or single-user toilets to ensure privacy between the sexes<br />
during performance of the Work; and<br />
25 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
3. Submitting Shop Drawings with details and layout of temporary installations<br />
to applicable third parties for approval prior to installing temporary facilities.<br />
Temporary facilities shall meet all applicable Governmental Rules; and<br />
F. Temporary heating, ventilation and air conditioning includes furnishing, installing,<br />
maintaining and removing a temporary HVAC system to allow the Work to be performed<br />
within the requirements of applicable Governmental Rules, and to prevent damage to<br />
materials being stored by Design-Builder.<br />
3.5 Construction Sequence Factors<br />
Design-Builder shall provide a detailed schedule of all the Work to be performed in a logical<br />
sequence in accordance with the design and construction requirements, maintenance of traffic, and<br />
protection of Utility services.<br />
Design-Builder must maintain both vehicular and pedestrian traffic within and adjacent to the Site,<br />
including local businesses, at all times throughout the duration of the Project.<br />
Design-Builder shall coordinate and schedule the construction activities to minimize impacts to<br />
freeway and local roadway traffic, and Utility disruptions.<br />
3.6 Maintenance of Traffic during Performance of the Work<br />
These criteria set forth basic principles and prescribe standards for the design, application, and<br />
maintenance of the various types of traffic control devices required for street construction and<br />
maintenance operations Work with which Design-Builder shall adhere and comply. These<br />
principles and standards are intended to ensure the safe and expeditious movement of traffic<br />
through construction and maintenance zones and the Safety of the work force performing these<br />
operations. Minimum standards of application are prescribed for typical situations and for<br />
controlling traffic through Work areas, including traffic devices, markings, barricades, signing, and<br />
channeling devices.<br />
Design-Builder’s design and construction of traffic control for maintenance of traffic shall comply<br />
with all applicable Governmental Rules and Governmental Approvals.<br />
26 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
3.6.1 Application of Standards<br />
A. Principles and Procedures: Design-Builder shall have the primary responsibility for<br />
maintaining the Safety of motorists, pedestrians, bicyclists, and workers in the vicinity of<br />
the construction and maintenance areas including the following:<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Traffic Safety in construction zones shall be an integral and high-priority<br />
element of the Project from Project initiation through final design and<br />
construction. Similarly, maintenance work shall be planned and conducted<br />
with the Safety of motorists, pedestrians, and workers kept in mind at all<br />
times;<br />
2. The basic Safety principles governing the design of permanent streets shall<br />
also govern the design of construction and maintenance sites. The goal shall<br />
be to route traffic through such areas with geometric and traffic control<br />
devices comparable to those for normal situations;<br />
3. Design-Builder shall submit a Maintenance of Traffic Plan (MTP) in detail<br />
appropriate to the complexity of the situation for approval to both the<br />
Authority and applicable third party;<br />
4. Design-Builder shall protect the public from the hazards resulting from open<br />
excavations, falling construction materials, impaired sight distances, and<br />
reduced vertical or horizontal distances;<br />
5. Design-Builder shall coordinate with Local Schools to ensure students are<br />
walking at a safe distance from construction zones; and<br />
6. Design-Builder shall coordinate with County Sheriff, City Police, and First<br />
Responders, as necessary;<br />
B. Inhibited traffic movement shall be minimized;<br />
C. Construction time shall be minimized to reduce exposure to potential hazards;<br />
D. Motorists shall be guided in a clear and positive manner while approaching and<br />
traversing construction and maintenance areas.<br />
1. Adequate warning, delineation and channeling by means of proper pavement<br />
markings, signing, and use of other devices that are effective under varying<br />
conditions of light and weather shall be provided to ensure the motorist of<br />
positive guidance in advance of and through the Work area. Design-Builder<br />
27 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
shall maintain such temporary markings and signage to all applicable<br />
Governmental Rules;<br />
2. Inappropriate markings and signs shall be removed or covered to eliminate<br />
any misleading cues to drivers under all conditions of light and weather; and<br />
3. Use of flaggers and/or police officers shall be employed when required to<br />
control traffic or when all other methods of traffic control are inadequate to<br />
warn and direct drivers;<br />
E. Design-Builder shall provide individuals trained in the principles of safe maintenance of<br />
traffic at Work areas to ensure that all maintenance of traffic elements of the Project are<br />
in conformity with the approved MTP and are effective in providing safe conditions for<br />
motorists, pedestrians, and workers;<br />
F. All traffic control devices shall be installed only when needed, covered when not needed,<br />
and removed immediately when no longer required in accordance with the approved<br />
MTP; and<br />
G. Temporary traffic measures described in the CA-MUTCD shall be utilized.<br />
3.6.2 Convenience of Public<br />
Design-Builder shall conduct its Work with the least possible obstruction of traffic. The convenience<br />
of the public and of the residents adjacent to the Project, and the protection of Persons and<br />
property, are of primary importance and shall be provided for by Design-Builder in an adequate and<br />
satisfactory manner. Adequate temporary crossings shall be constructed and maintained where<br />
necessary to provide access to adjacent property, and fire hydrants shall be kept accessible.<br />
3.6.3 Truck Loads<br />
Trucks hauling wet or loose materials shall have tight tailgates and shall be loaded and secured<br />
with adequate freeboard of not less than three inches, without precarious cones or piles of material.<br />
Dry material shall be covered or wet to assist with dust control. Falling debris, roadway clean-ups<br />
and any damage repair to vehicles, Persons or property on nearby roadways shall be the sole<br />
responsibility of Design-Builder.<br />
3.6.4 Spills<br />
Design-Builder shall provide for prompt removal from existing roadways of all dirt and other<br />
materials that have been spilled, washed, tracked or otherwise deposited thereon by its hauling or<br />
28 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
other operations. Hazardous or contaminant spills shall be treated and cleaned up immediately.<br />
Spill kits shall be kept on-Site and available for use by trained personnel.<br />
3.6.5 Dust<br />
Design-Builder shall employ construction methods and means that will keep fugitive dust to the<br />
minimum. Design-Builder shall provide and adhere to a “Dust Control Plan” which shall provide for<br />
the containment of dust on the Project, and on roads, streets and other areas immediately adjacent<br />
to the Project limits, wherever traffic or buildings that are occupied or in use are affected by such<br />
dust, as indicated in the approved Storm Water Pollution Prevention Plan. The Dust Control Plan<br />
including the materials and methods used for dust control shall be subject to the approval of<br />
Authority.<br />
Design-Builder shall design, plan and incorporate/implement in construction, dust control mitigation<br />
measures, to ensure compliance with mitigation measures as specified in Volume 4- Environmental<br />
<strong>Requirements</strong>.<br />
3.6.6 Barricades<br />
Design-Builder shall, as necessary, erect or place, and maintain in good condition, appropriate and<br />
adequate barricades, warning signs, lights, flares, red or orange flashing electric flasher units,<br />
rubber cones, and other warning and danger signals and devices at working sites, closed roads,<br />
intersections, open excavations, locations of material storage, standing equipment and other<br />
obstructions; at points where the usable traffic width of the road is reduced; at points where traffic is<br />
deflected from its normal course of lanes; and at other places of danger to vehicular or pedestrian<br />
traffic or to completed Work. The various traffic control and warning devices shall be in accordance<br />
with all applicable Governmental Rules.<br />
3.6.7 Protection from Falling Materials<br />
Design-Builder shall not perform Work above vehicular or pedestrian traffic until it obtains explicit<br />
written permission from all applicable Governmental Persons. Subject to such permission, Design-<br />
Builder shall provide the necessary devices and means to protect such traffic from falling<br />
construction materials and other objects and from painting operations, during the time that the Work<br />
is carried on above traffic. When a detour will be established, Design-Builder shall make<br />
arrangements for establishing, maintaining, and signing for it, providing Safety measures as are<br />
necessary to provide traffic guidance and protection, and assume the cost thereof. All traffic control<br />
shall adhere to all applicable Governmental Rules.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
29 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
3.6.8 Materials<br />
Traffic controls and signs required for the duration of this Project shall conform to the California<br />
Manual of Uniform Traffic Control Devices or applicable Governmental Rules.<br />
3.7 Temporary Erosion and Sediment Control during Performance of the Work<br />
Temporary erosion control includes grassing, mulching, applying netting, watering and reseeding<br />
sloped surfaces, providing berms at top of slopes, and providing interceptor ditches at ends of<br />
berms and at locations which will eliminate or minimize erosion during performance of the Work.<br />
Temporary sediment control includes silt ponds, silt dams, traps, barriers and appurtenances at the<br />
toe of excavation, embankment, spoil and borrow area slopes. Temporary erosion and sediment<br />
control measures deployed shall meet the codes and requirements of the applicable Governmental<br />
Persons and comply with the requirements of the environmental mitigation monitoring program.<br />
Specific criteria for storm drain discharge are provided in the “National Pollutant Discharge<br />
Elimination System” (NPDES) permit. The Authority has filed a Notice of Intent with the State<br />
Water Resources Control Board under the Construction <strong>General</strong> NPDES Permit (Order 2009-0009-<br />
DWQ). The Authority shall serve as the legally responsible party to file the Project related<br />
documents. Design-Builder shall be responsible for compliance with all permit conditions as agents<br />
for the Authority.<br />
Design-Builder shall submit a “Storm Water Pollution Prevention Plan” (SWPPP) per the<br />
Construction <strong>General</strong> NPDES Permit and applicable Governmental Rules. The SWPPP shall<br />
include all best management practices (BMPs) details and requirements and shall be<br />
adjusted/updated as the Work changes or progresses.<br />
3.8 Water Pollution Controls during Performance of the Work<br />
Design-Builder shall handle all wastewater from storm runoff, equipment washing, drilling, or any<br />
other action of their operations to remove contaminants (e.g., suspended particles, hydrocarbons,<br />
etc.) in accordance with the SWPPP. Design-Builder shall monitor all wastewater discharges to<br />
ensure that it meets all criteria specified in the permit. Design-Builder shall retain records of<br />
measurements for inspection by the permit issuer and Authority. Design-Builder shall perform<br />
monitoring of all wastewater discharges in accordance with the permit and the BMPs indicated in<br />
the SWPPP. Design-Builder shall submit monthly monitoring reports to the Authority no later than<br />
10 days after the end of each monthly monitoring period.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
30 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Design-Builder shall not discharge pollutants, such as chemicals, fuels, lubricants, bitumen’s, raw<br />
sewage or other harmful wastes into sanitary or storm systems or the ground.<br />
Design-Builder shall control the use of lubricating oils, hydraulic fluids, greases, and other such<br />
products. Design-Builder shall promptly clean up and properly dispose of materials contaminated<br />
by spillage or leaking of these products.<br />
No waste or erosion materials shall be allowed to enter any sanitary/storm removal systems.<br />
Erosion materials from excavation areas, or stockpiled fill shall be contained within the Site.<br />
Design-Builder shall develop methods to control waste and erosion, including such means as<br />
filtration, settlement, and manual removal.<br />
Design-Builder shall sample and test groundwater, and provide results to the Authority, prior to<br />
discharge off-site. Design-Builder shall obtain appropriate permits for groundwater discharge in<br />
accordance with applicable Governmental Rules.<br />
Design-Builder shall prepare and implement a program to control water pollution for all construction,<br />
a water pollution control plan (WPCP). The WPCP must specify how Design-Builder will handle<br />
stormwater, groundwater, and construction wastewater in accordance with permits, and pertinent<br />
laws and regulations. The WPCP shall be submitted to the Authority for approval prior to the start of<br />
construction.<br />
Design-Builder shall design, plan and incorporate/implement in construction, water quality mitigation<br />
measures, to ensure compliance with mitigation measures as specified in Volume 4- Environmental<br />
<strong>Requirements</strong>.<br />
3.9 Air Pollution Controls during Performance of the Work<br />
Design-Builder shall comply with all applicable Governmental Rules and mitigation measures<br />
summarized in the Authority’s Final Environmental Impact Report (FEIR) to limit adverse effects on<br />
air quality as a result of any construction activity, vehicle or equipment.<br />
Detailed descriptions and explanations of specific impact mitigation measures are contained in the<br />
South Coast Air Quality Management Authority (SCAQMD) rules and regulations (Rule 403,<br />
Limitation of Fugitive Dust Emissions) and the FEIR.<br />
Examples of procedures and techniques Design-Builder may employ include:<br />
A. Cover or adequately water loads of materials, debris, and soil transported to or from the<br />
Site. Trim or remove loose material from all loads before leaving the loading Site;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
31 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
B. Daily water down and sweep streets and sidewalks, which have heavy volumes of<br />
construction vehicles carrying debris and excavated materials; and<br />
C. Vehicles leaving the Site and entering paved public streets shall be cleaned of mud and<br />
dirt. Trucks arriving and leaving the Site with materials or debris shall be loaded and<br />
covered so that they do not drop materials or debris on the streets. Design-Builder shall<br />
maintain a suitable vehicle cleaning and inspection installation with a permanent crew for<br />
this purpose. Spills of materials or debris in public areas shall be removed immediately.<br />
Design-Builder shall remove scrap and waste material and dispose of it in accordance with<br />
applicable Governmental Rules.<br />
Design-Builder shall use construction equipment designed and equipped to prevent or control air<br />
pollution in conformity with applicable Governmental Rules. Evidence of such design and<br />
equipment shall be maintained and made available for inspection by the Authority.<br />
Design-Builder shall establish and maintain records of the routine maintenance program for internal<br />
combustion engine powered vehicles and equipment used on the Project. These records shall be<br />
available for inspection by the Authority.<br />
During excavation, gases may be released from the soil or from underground reservoirs. These<br />
gases may contain methane, other more complex hydrocarbons or hydrogen sulfide and may<br />
present hazards due to their flammability or toxicity. Design-Builder shall ensure Safety in<br />
accordance with the regulations of OSHA and CAL/OSHA and all applicable Governmental Rules.<br />
Although the composition, quantity and concentration of the gases that might be released are<br />
unknown, the release of these gases into the atmosphere may be subject to control by the<br />
SCAQMD and the California Air Resources Board (CARB). Design-Builder will immediately notify<br />
the Authority of any such issues and coordinate with the SCAQMD and the CARB. Furthermore,<br />
Design-Builder will inform the Authority of further required actions. Any and all excavations<br />
involving soil containing Volatile Organic Compounds (VOCs) shall comply with SCAQMD Rule<br />
1166. Design-Builder shall be responsible for SCAQMD Rule 1166 permitting, permit fees,<br />
notification, and compliance. When a Rule 1166 permit is required, Design-Builder shall obtain the<br />
permit prior to start of construction involving soil containing VOCs.<br />
During the Work involving demolitions and some excavations, asbestos-containing materials (ACM)<br />
may be present. Any and all Work involving more than 100 square feet of ACM shall comply with<br />
SCAQMD Rule 1403. Design-Builder shall be responsible for SCAQMD Rule 1403 permitting,<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
32 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
permit fees, notification, and compliance. When a Rule 1403 permit is required, Design-Builder<br />
shall hold the permit prior to start of construction activities involving ACM.<br />
Design-Builder shall design, plan and incorporate/implement in construction, air quality mitigation<br />
measures, to ensure compliance with mitigation measures as specified in Volume 4- Environmental<br />
<strong>Requirements</strong>.<br />
3.10 Construction Noise and Vibration Control<br />
Design-Builder shall perform construction operations in a manner to minimize noise and vibration,<br />
and in accordance with codes and requirements of the applicable jurisdictional Governmental<br />
Persons and as required in the environmental mitigation monitoring program. Design-Builder shall<br />
provide working machinery and equipment with efficient noise suppression devices, and employ<br />
other noise and vibration abatement measures necessary for protection of both employees and the<br />
public. Design-Builder shall protect employees and the public against noise exposure in<br />
accordance with the requirements of the Occupational Safety and Health Act of 1970 and the<br />
current statutory noise limits set by the Occupational Safety and Health Administration.<br />
Design-Builder shall comply with all applicable Governmental Rules relating to noise and vibration.<br />
Monitoring: Design-Builder shall promptly inform the Authority of any complaints received from the<br />
public regarding noise or vibration. In the event of complaints, Design-Builder shall monitor noise<br />
and vibration levels of the Work operations to ensure compliance with the applicable Governmental<br />
Rules and retain records of noise and vibration measurements for inspection by the Authority. If the<br />
Work operations exceed the noise and vibration limitations, Design-Builder shall describe the action<br />
proposed and the schedule for implementation, and subsequently inform the Authority of the results<br />
of the action.<br />
3.11 Fire Prevention<br />
3.11.1 Code Compliance<br />
Design-Builder shall perform the Work in a careful manner with full consideration to fire prevention<br />
as required by the State Fire Marshal, and the more stringent of: the CA Uniform Construction<br />
Code, Design-Builder’s underwriter’s requirements, National Fire Protection Association Building<br />
Codes, National Board of Fire Underwriters, and applicable Governmental Persons having<br />
jurisdiction. Fire resistant materials shall be used for temporary enclosures.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
33 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
3.11.2 Extinguishers<br />
Chemical extinguishers shall be provided by Design-Builder during the progress of the Work where<br />
and as required by the State Fire Marshal, the local fire department and the National Board of Fire<br />
Underwriters. In storage sheds, warehouses, Design-Builder’s offices, and workmen’s temporary<br />
buildings Design-Builder shall be responsible for furnishing and maintaining its own extinguisher<br />
equipment.<br />
3.11.3 Prevention Program<br />
Design-Builder shall maintain an active program of fire prevention to keep workers fire conscious<br />
during the entire Contract duration. It shall designate one member of its organization to execute<br />
and coordinate the fire control measures of its own organization, those of all Subcontractors and<br />
those of all other personnel at the Site. Design-Builder shall report to the Authority any lack of<br />
cooperation or refusal to participate on the part of any worker or Subcontractor with regard to the<br />
fire prevention program. Failure of any worker or Subcontractor to cooperate with Design-Builder in<br />
carrying out the above program shall be grounds for barring that individual or firm from the Project.<br />
3.11.4 Flammable Materials<br />
Design-Builder shall ensure that any storage of flammable materials on the Site complies with all<br />
requirements of applicable Governmental Rules as well as any applicable insurance requirements.<br />
3.11.5 Burning<br />
On-Site open burning of rubbish, garbage, trade waste, leaves or plant life is strictly prohibited by<br />
California law. Design-Builder shall comply with all Governmental Rules regarding burning.<br />
3.12 Jobsite Cleanliness<br />
Design-Builder shall be responsible for daily cleaning up of the Site to eliminate fire hazards,<br />
removal of all of its refuse from the Site, weed abatement, and graffiti removal. Design-Builder shall<br />
be responsible for daily cleaning up of the site to comply with Storm Water Pollution Prevention<br />
Plans (SWPPP), discharge permits and mitigation measure requirements, specified in Volume 4-<br />
Environmental <strong>Requirements</strong>. If Design-Builder fails to clean up the Site accordingly within one day<br />
after it has been given written notice to do so by Authority, Authority shall have the right to have the<br />
Site cleaned up by others and the cost of such work shall be charged to Design-Builder. If an<br />
applicable Governmental Person fines the Project for non-compliance with jobsite cleanliness<br />
requirements as part of any permit, Design-Builder shall be liable for payment of the fine.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
34 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
3.13 Seismic Safety<br />
Design-Builder shall comply with all applicable Governmental Rules regarding seismic safety.<br />
Due to the proximity of a nearby earthquake fault, Design-Builder shall also maintain an active<br />
program for earthquake safety awareness and procedures as part of Design-Builder’s injury and<br />
illness prevention program submittal as required in Section 8.0.<br />
3.14 Historical and Scientific Specimens Encountered During Construction<br />
Articles of historic or scientific value such as coins, fossils, bones, or articles of antiquity that may<br />
be uncovered during the progress of the Work shall become the property of the Authority. Such<br />
finds shall be reported immediately to the Authority, who shall determine appropriate next steps,<br />
which may include stoppage of Work or direction regarding the removal or disposition of the article.<br />
Design-Builder’s operations or activities shall not adversely impact existing historical and<br />
archeological resources, and particular care shall be taken with regard to historically significant<br />
facilities as identified in Volume 4- Environmental <strong>Requirements</strong>.<br />
3.15 Salvage of Materials<br />
All materials such as signs, fencing, traffic control signals and equipment, street lights and<br />
guardrails belonging to Governmental Persons or Utility Owners shall be salvaged by Design-<br />
Builder and delivered to the applicable Governmental Persons or Utility Owners, respectively, as<br />
directed by the Authority or disposed of by Design-Builder if directed by the Authority.<br />
3.16 Removal, Treatment and Disposal of Materials<br />
Design-Builder shall prepare and maintain a “Material Disposal Plan” for the responsible<br />
identification, removal, treatment and disposal of all excavated materials including paving material,<br />
common excavation, rock excavation, debris, removed Utility materials, and other materials<br />
encountered during the construction, including any Hazardous Substances. The removal, treatment<br />
and disposal of all such materials shall conform to all applicable Governmental Rules.<br />
In the event that Hazardous Substances are encountered during performance of the Work, Design-<br />
Builder shall follow the process identified in the Contract Section 8.2.<br />
Design-Builder shall track the actual disposition of all disposed material, recording the time of the<br />
disposal, nature of the materials and the location of the disposal.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
35 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
3.17 Hazardous Substances Handling and Disposal<br />
Design-Builder shall prepare and submit to the Authority for review and approval, a “Hazardous<br />
Waste Operations Safety and Health Plan” to be implemented on the Project. The plan shall follow<br />
the requirements under California Code of Regulations (CCR) Title 8, 5192 and shall include<br />
detailed personal protective equipment (PPE) level definition and contamination level limits on<br />
anticipated Hazardous Substances for PPE designation. Design-Builder shall employ trained<br />
personnel to perform contaminated soil removal operations. Design-Builder shall examine<br />
referenced environmental documentation in preparation of the “Hazardous Waste Operations<br />
Safety and Health Plan” requirements.<br />
The Authority has not identified material within the Site that would be defined as a hazardous waste<br />
under the Federal Resource Conservation and Recovery Act (RCRA) of 1976, 42 U.S.C. Section<br />
6901 et seq. If encountered, Design-Builder shall load RCRA-hazardous wastes onto vehicles of<br />
certified licensed hazardous waste transporter. Design-Builder shall not commingle Hazardous<br />
Substances with non-Hazardous Substances or RCRA waste with non-RCRA waste.<br />
Design-Builder shall be responsible for environmental operations and contaminated soils created by<br />
Design-Builder activities.<br />
3.18 Tree Removal<br />
Trees shall be removed and replaced in accordance with the Authority’s Tree Removal Policy<br />
located in Appendix C and as outlined in Volume 3, Document 2- Performance Specifications.<br />
3.19 Temporary Lighting<br />
Temporary lighting and lighting of temporary public walkways immediately adjacent to the Project<br />
sites shall be provided by Design-Builder as necessary for public safety, and in accordance with<br />
codes and requirements of the applicable Governmental Persons.<br />
3.20 Construction Start-up<br />
Design-Builder shall not commence construction of any portion of the Project prior to occurrence of<br />
all the following events except with the prior written statement of no objection of Authority which<br />
may be granted or withheld in its sole discretion and Design-Builder shall commence such<br />
construction promptly following such events upon release for construction:<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
36 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
A. Authority shall have provided all required approvals including approval of (a) the project<br />
management plan, (b) the health and safety plan (HASP), (c) the quality<br />
assurance/quality control plan, (d) the material disposal plan, (e) the wastewater<br />
management plan, (f) the water pollution control plan, (g) the soils management plan,<br />
and (h) all applicable permits, including encroachment permits, described in Section<br />
3.20.1, for the individual Work elements;<br />
B. Design-Builder and any third party (where applicable) shall have approved all applicable<br />
Design Documents and Construction Documents relating to such portion of the Project;<br />
C. All required community notifications have occurred in accordance with Section 1.5;<br />
D. All Governmental Approvals necessary for construction of the applicable portion of the<br />
Project shall have been obtained and all conditions of such Governmental Approvals,<br />
which are a prerequisite to commencement of such construction, shall have been<br />
performed;<br />
E. All required insurance and bonds shall remain in full force and effect;<br />
F. All necessary rights of access for such portion of the Project shall have been obtained;<br />
G. Design-Builder shall have completed all required investigations to establish and confirm<br />
the existence and location of Utilities in such portion of the Project;<br />
H. All maintenance of traffic and access to property requirements, including maintenance of<br />
traffic plans (MOT), and public notices are in place and in conformity with Contract<br />
Documents;<br />
I. All quality assurance personnel and equipment necessary for the Work to be constructed<br />
are on Site;<br />
J. Design-Builder shall have an approved Construction Work Plan, per Section 3.20.1<br />
relating to such portion of the Project; and<br />
K. A readiness review shall have been conducted in accordance with Section 3.20.2.<br />
3.20.1 Construction Work Plans (CWPs)<br />
Design-Builder shall have an approved Construction Work Plan (CWP) in place prior to the start of<br />
construction for individual Work elements or as specified by the Authority. The CWPs shall be<br />
presented and discussed at the readiness review meetings described in Section 3.20.2. The<br />
subject Work may not proceed until the CWP is approved by Design-Builder’s quality manager,<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
37 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Safety representative, Designer of Record, and the Authority. For all Work impacting or interfacing<br />
with existing <strong>Metro</strong> and Railroad Operator facilities, structures, etc., Design-Builder shall submit a<br />
CWP at least 30 days prior to planned commencement of Work. As a minimum, CWPs shall<br />
address:<br />
A. Description of the Work and applicable Contract section;<br />
B. Staging plans;<br />
C. Include actions that are defined as “special events” in that the Work may constitute<br />
exposing the general public to danger, inconvenience or risk;<br />
D. List of required submittals to complete the Work activity;<br />
E. Individual(s) and position(s) responsible for supervision of the Work;<br />
F. Planned start date of the Work, progress rate expected and extended work hours<br />
required;<br />
G. Prerequisite activities required;<br />
H. Include a Job Hazard Analysis for the scope of work;<br />
I. Site specific Safety issues, including Safety equipment, access to location,<br />
environmental considerations, etc;<br />
J. Emergency response information;<br />
K. Inspection and/or tests to be accomplished; and<br />
L. Inspection hold points.<br />
3.20.2 Readiness Reviews<br />
Design-Builder shall conduct readiness reviews with the Authority. Readiness reviews shall be<br />
conducted prior to the start of specific Work activities to conduct prerequisite planning of activities,<br />
review required submittals and discuss specific Work to be accomplished. Design-Builder shall<br />
authorize the Work to proceed based on results of the readiness review. Work may not proceed<br />
without the approval of Design-Builder’s quality manager, Safety representative, Designer of<br />
Record, and the Authority. Design-Builder shall notify Authority a minimum of 48 business hours<br />
before each readiness review.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
38 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
3.21 Work Restrictions<br />
At all times during performance of the Work, Design-Builder shall comply with the requirements of<br />
the Cities, Utility Owner and all other applicable Governmental Persons regarding areas and times<br />
of work restrictions; failure to comply shall not be the basis for any Request for Change Order.<br />
Design-Builder shall obtain written approval from the applicable City, Utility Owner and/or<br />
Governmental Person to deviate from their respective requirements regarding areas and times of<br />
work restrictions.<br />
3.22 Site Preservation/Environmentally Restricted Sites<br />
Sites identified in Volume 4- Environmental <strong>Requirements</strong> as Environmentally Sensitive Areas<br />
(ESAs) shall be protected and maintained during performance of the Work, including the historic<br />
depots located at Monrovia and Azusa-Alameda stations. If any of these Sites are damaged during<br />
performance of the Work, they shall be restored to its pre-existing condition or replaced, as<br />
necessary at Design-Builder’s expense.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
END OF SECTION<br />
39 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
4.0 COST/SCHEDULE MANAGEMENT<br />
Design-Builder shall develop and maintain a cost integrated scheduling system for this Contract.<br />
Planning, scheduling, management, and execution of the Work in accordance with Contract<br />
Documents is the sole responsibility of Design-Builder.<br />
The Baseline Schedule and Current Project Schedule shall be resource-loaded and will be utilized<br />
to evaluate progress of the Work and the progress payment application. The Baseline Schedule<br />
and Current Project Schedule shall reflect Design-Builder’s plan to complete the Work within the<br />
applicable Completion Deadlines and Contract Price. The Baseline Schedule and Current Project<br />
Schedule shall contain sufficient detail and shall include Contract Data <strong>Requirements</strong> List (CDRL)<br />
submittals, Completion Deadlines, real estate availability, procurement/delivery of materials, Utility<br />
coordination, demolition, construction, and testing.<br />
Design-Builder is required to involve all major Subcontractors in developing and implementing the<br />
Baseline Schedule and updating the Current Project Schedule. Design-Builder shall provide the<br />
Authority with written confirmation of concurrence of major (5% or more of Contract Price) trade<br />
Subcontractors and Suppliers with the Baseline Schedule and Current Project Schedule.<br />
Design-Builder’s failure to include any element of Work in its schedules shall not excuse Design-<br />
Builder from completing all the Work required within any applicable Completion Deadline. If<br />
activities are found to be missing from the Baseline Schedule after the Authority’s initial review,<br />
Design-Builder shall submit a revised schedule to include these items. No extension of time will be<br />
granted because of errors or omissions on the Baseline Schedule or Current Project Schedule. It is<br />
Design-Builder’s responsibility to incorporate all necessary activities to construct the Project within<br />
the applicable Completion Deadlines.<br />
Early completion schedule – If Design-Builder proposes an early completion schedule (or any<br />
subsequent update) and Authority approves of such early completion schedule, Design-Builder<br />
shall not be eligible to receive a Change Order for a failure to complete Work in accordance with<br />
such early completion schedule.<br />
4.1 Schedule Terminology<br />
The following terms as used in this Section 4.0 shall have the following meanings:<br />
A. Baseline Schedule shall mean Computer-generated project network schedule in<br />
precedence diagram method (PDM) format detailing design, procurement, construction,<br />
testing, and other Contract requirements for the entire Project;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
40 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
B. Calendar shall incorporate each of the days that fall within the period during which the<br />
Work is to be performed and shall indicate whether each such day is a Working Day or<br />
non-Working Day. The base time unit used in the calendar shall be one calendar day.<br />
The Contract duration is measured in calendar days and shall include all non-Working<br />
Days such as holidays and weekends;<br />
C. Critical path shall mean the activities which are on the longest path;<br />
D. Current Project Schedule shall mean the most recent copy of the Baseline Schedule that<br />
is updated monthly to reflect actual progress logic, duration, and other as-built<br />
conditions, as well as remaining Work to complete and has been approved by the<br />
Authority; and<br />
E. Negative Float shall mean a negative amount of time between the early finish date and<br />
4.2 Personnel<br />
late finish date of an activity. An activity with Negative Float must be completed ahead<br />
of schedule if the Work is to be completed on time as indicated in the Baseline Schedule<br />
and Current Project Schedule. Negative Float usually indicates the need for corrective<br />
and/or preventive action to complete the Work on schedule and will not be approved by<br />
the Authority;<br />
A part time scheduler shall be employed by Design-Builder who shall have a minimum of 5 years of<br />
experience as a scheduler on projects of similar scope using Primavera scheduling software. The<br />
scheduler shall cooperate with the Authority and shall be available for the purpose of continuously<br />
monitoring and maintaining Design-Builder's detailed construction scheduling program. Design-<br />
Builder’s scheduler shall be identified in Design-Builder’s Project Management Plan. The Authority,<br />
at its sole discretion, has the right to refuse to accept construction scheduler based upon lack of<br />
experience as required in this specification. If Authority refuses to accept scheduler proposed by<br />
Design-Builder, Design-Builder shall provide another scheduler who meets experience<br />
requirements stated herein within 20 Working Days from the time of notification of rejection by the<br />
Authority.<br />
4.3 Scheduling Software<br />
Design-Builder's cost/schedule management system shall be a computer-generated, time scaled,<br />
Critical Path method (CPM) network utilizing the precedence diagram method of representation.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
41 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Unless otherwise approved in writing by the Authority prior to use, the scheduling software shall be<br />
Primavera Project Planner (P3) Version 3.0 or Primavera P6 Professional Project Management.<br />
4.4 Tabular and Graphic Reports<br />
The following reports shall be submitted on A-size (8½” x 11”) paper with the Baseline Schedule<br />
and monthly thereafter with the Current Project Schedule submittal:<br />
A. Critical Path bar chart depicting longest path;<br />
B. Summary schedule depicting rolled up activities by work breakdown structure (WBS);<br />
C. Bar chart depicting all activities sorted WBS, early start, and Float;<br />
D. Critical Float report listing all activities with 20 work days or less Float;<br />
E. Cost report listing activity ID, budgeted cost, percentage complete, cost this period, cost<br />
to date, cost to complete, and cost at completion;<br />
F. Progress curve depicting actual progress based on cost performance relative to early<br />
and late start curves;<br />
G. Predecessor and successor report sorted by WBS, early start, and Float; and<br />
H. Activity report identifying changes between the Current Project Schedule and latest<br />
working schedule. Activity changes to report shall include “new activities”, “deleted<br />
activities”, “original durations”, “relationships or logic”, and “descriptions”.<br />
The following reports shall be submitted on D-size (22 inches by 34 inches) or E-size (34 inches by<br />
44 inches) medium suitable for reproduction with the Baseline Schedule and monthly updates<br />
thereafter with the Current Project Schedule submittal:<br />
A. Time scaled diagram depicting all activities sorted WBS, early start, and Float; and<br />
B. Summary schedule depicting rolled up activities by WBS.<br />
Submittals shall include one original and five copies of original bar charts, time-scaled networks,<br />
narratives, and tabular reports unless specified otherwise. All submittals shall be accompanied by<br />
the source data on DVD/CD.<br />
4.5 Schedule Format and Content<br />
Completion Deadlines and equipment availability dates, real estate availability dates, as described<br />
in the Contract Documents, are unique zero duration activities containing corresponding dates and<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
42 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
logic ties. Designate these activities as a “start” or “finish” milestone. Each milestone activity will<br />
constrain its dependent work. Assume Notice to Proceed is given at day zero for calculation of<br />
constraint dates for milestones.<br />
The Baseline Schedule must include dates for availability of Site (refer to Volume 3, Document 2,<br />
Appendix 3- Property Acquisition Matrix) and Completion Deadlines.<br />
4.5.1 Activity Data<br />
Design-Builder shall include the following activity data in its Baseline Schedule and Current Project<br />
Schedules:<br />
A. Activity identification (ID): Activity ID’s shall be left justified and not contain space<br />
between characters;<br />
B. Activity description: Each activity shall have a description that is unique and that<br />
unambiguously identifies the scope of the activity;<br />
C. Activity duration: Construction and testing activities shall have durations no greater than<br />
15 days. Procurement, permitting, third party coordination, submittals, and milestones<br />
activities may use the duration required, as stated in the Contract Documents;<br />
D. Activity dates: Calculation of early and late start and finish dates of activities shall be<br />
based upon the application of retained logic and contiguous durations. When the use of<br />
multiple calendars results in incorrect activity dates, at the request of the Authority,<br />
Design-Builder shall provide correct activity dates;<br />
E. Activity constraints: Date constraints shall be limited to start-no-earlier-than, start-no-<br />
later-than, finish-no-earlier-than, and finish-no-later-than and shall only be applied to<br />
Availability of Site date and Completion Deadlines. Float constraints shall not be used;<br />
and<br />
F. Activity type: Completion Deadlines shall have the type “Finish Milestone”. All other<br />
activities shall have the type “Task” or “Task Dependent”, unless otherwise approved by<br />
the Authority. Design-Builder shall not define additional milestones.<br />
4.5.2 Activity Codes<br />
Design-Builder shall develop an activity code dictionary which identifies bid items, responsibility,<br />
stage or phase, area, work type, and Change Order. The activity code dictionary shall be submitted<br />
to the Authority for approval within 14 days after Notice to Proceed. If Design-Builder is utilizing<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
43 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Primavera P6 Professional Project Management software, then activity coding must be “Project<br />
specific” only. The use of global activity codes is not allowed.<br />
4.5.3 Activity Calendars<br />
The minimum planning unit for the Project shall be days. A minimum of two calendars shall be<br />
used.<br />
A. CALENDAR 1 - Five-day, Monday through Friday with Holidays; and<br />
B. CALENDAR 2 - Seven-day, Monday through Sunday without Holidays.<br />
If P6 software is utilized for scheduling the work, hours of work (for purposes of the software) for<br />
standard day shall be from 7:00 am to 4:00 pm (0700h – 1600h) for all calendars. Actual work<br />
hours shall comply with applicable Governmental Rules. In addition, all calendars shall be Project-<br />
specific. Global calendars shall not be utilized.<br />
4.5.4 Cost Loading<br />
Design-Builder shall define cost resources. The resources shall be applied to all relevant activities.<br />
A. Schedule of Values: Design-Builder shall develop a detailed Schedule of Values in<br />
accordance with Contract Section 7.2.1;<br />
B. The budgeted cost of each Schedule Activity shall represent all labor, material,<br />
equipment, other direct costs, overhead, profit, and all other costs or amounts necessary<br />
to complete that Schedule Activity. Front-end or unbalanced loading of costs is not<br />
permitted and shall result in rejection of the schedule;<br />
C. No costs shall be applied to Schedule Activities for Shop Drawing preparation,<br />
manufacturing, or delivery of equipment or materials without having been previously<br />
approved by the Authority;<br />
D. Resource calendars: The use of resource calendars is not required; and<br />
E. Driving resources: The designation of a resource as driving is not required.<br />
4.5.5 Logic<br />
A. Activity relationships: The schedule logic for each activity shall be constructed by<br />
determining which activities must be complete before the activity can start, which<br />
activities can occur simultaneously with the activity, which activities cannot start until the<br />
activity is complete, and the impact of all resource limitations on activity sequencing,<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
44 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
activity durations, and activity dates. All paths through the Current Project Schedule<br />
shall proceed in the direction representing the progression of time. Activity lag durations<br />
shall not have a negative value. Activity lags shall not be used in lieu of logic<br />
relationships. Redundant ties to preceding activities in a sequential series of activities<br />
will not be permitted.<br />
B. Float: Float (F) shall be defined as the number of days from the late finish date (LF) to<br />
the early finish date (EF) of an activity. When the LF is later than the EF, the Float shall<br />
be positive. Free Float shall be defined as the maximum number of days that the early<br />
finish of an activity can slip without delaying the early start of any of that activity’s<br />
successor.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. The controlling path to a Completion Deadline shall be that path to the<br />
milestone possessing the least Float. A Completion Deadline may have<br />
multiple controlling paths. The longest path leading to a Completion Deadline<br />
shall be defined as a Critical Path or as possessing critical Float.<br />
2. Float shall not be for exclusive use of either the Authority or Design-Builder.<br />
Float shall be jointly owned, an increasing or decreasing resource available to<br />
both the Authority and Design-Builder. The use of Float suppression<br />
techniques by Design-Builder, including preferential sequencing, special<br />
lead/lag logic restraints, extended activity durations, or imposed dates will not<br />
be permitted and shall be grounds for rejection of the Baseline Schedule or<br />
Current Project Schedule. Except as otherwise specified, all paths through<br />
the Current Project Schedule shall terminate at the same milestone,<br />
construction complete, and the Float of this milestone shall be the Float of the<br />
Project controlling path.<br />
3. Timely completion: In the Baseline Schedule, timely completion shall mean<br />
that all Completion Deadlines have Float greater than or equal to zero. In<br />
monthly updates, representation of Completion Deadlines with Negative Float<br />
shall not relieve Design-Builder of its obligation to complete each Completion<br />
Deadline by its specified completion date. Unless otherwise specified, timely<br />
completion shall refer to completion before the specified deadline.<br />
4. Settings: Optional software settings may impact activity Float calculations,<br />
resource calculations, and cost calculations. Design-Builder shall be<br />
45 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
responsible to verify that all data calculated by the software accurately<br />
represent the progress of the Work to date and Design-Builder’s current plan<br />
for timely completion. The following settings are required:<br />
a. When scheduling activities, apply retained logic;<br />
b. Calculate the start-to-start lag from early start;<br />
c. Schedule durations as contiguous;<br />
d. Show open ends as non-critical;<br />
e. Calculate total Float as finish Float (late finish – early finish);<br />
f. Summary calculations shall use calendar no.1 and the weighting<br />
factor for determining percent complete shall be duration;<br />
g. Display progress on activity bars based on remaining duration;<br />
h. Show critical color, red, on activity bar; and<br />
i. Define critical activities as longest path.<br />
C. Level of Detail: Representation of the Work in greater detail than specified shall only be<br />
permitted at the Authority’s discretion.<br />
D. Submittals: Submittals shall be represented in the Baseline Schedule and Current<br />
Project Schedule by the following types of activities:<br />
1. Prepare and submit (P/S);<br />
2. Review and approve (R/A); and<br />
3. Revise and resubmit (R/R).<br />
Design-Builder shall define additional submittal activities when necessary to accurately<br />
represent required CDRL submittals. Each re-submittal and the corresponding Authority<br />
review period shall be represented by separate activities in the Current Project<br />
Schedule. Unless otherwise determined by the Authority, every submittal required by<br />
the Contract shall be included in the Baseline Schedule and Current Project Schedule.<br />
E. Detailed Schedules: A detailed schedule shall be submitted to define each scope of<br />
work that cannot be adequately represented in the Current Project Schedule using a<br />
time scale of days; to define the Work activities associated with each impact to existing<br />
operations; to further define scopes of work that are represented in the Current Project<br />
46 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Schedule in accordance with the specified level of detail, but which require further<br />
definition to permit the effective administration of the Contract. Each detailed schedule<br />
shall consist of a narrative and a bar chart submitted in accordance with this Section 4.0.<br />
Detailed schedule shall be submitted within 48 hours of the Authority’s request and no<br />
later than five Working Days prior to the commencement of the corresponding scope of<br />
work. The corresponding scope of work shall not commence prior to receipt of Authority<br />
approval of the detailed schedule associated therewith.<br />
4.6 Baseline Schedule<br />
Within 30 days after Notice to Proceed, Design-Builder shall submit to Authority for review and<br />
approval a detailed proposed Baseline Schedule presenting an orderly and realistic plan for<br />
completion of the Work, in conformity with requirements as specified herein. The Baseline<br />
Schedule shall begin design and construction activities no earlier than the date of Notice to Proceed<br />
unless Authority issues a limited Notice to Proceed.<br />
The Baseline Schedule shall consist of a computerized systematic network by Primavera Project<br />
Planner (P3) or Primavera P6 Professional Management, using the CPM technique.<br />
Design-Builder shall provide the Authority with a means to monitor and follow progress of all phases<br />
of the Work and comply with limits imposed by the scope of work, with Completion Deadlines, and<br />
with constraints, restraints or sequences included in the Contract. The Baseline Schedule shall<br />
clearly identify the Critical Path through the Project and the Float on all other activities. Schedule<br />
detail required shall include factors to the satisfaction of the Authority including the following:<br />
A. Master list of submittals and all other requirements as referenced in Contract Data<br />
Requirement List (CDRL);<br />
B. Contract interim milestones and Completion Deadlines, constraints, restraints,<br />
sequences of Work indicated;<br />
C. No activity shall have a duration longer than 15 days, with the exception of submittal,<br />
Approval, fabrication, procurement, and summary activities;<br />
D. Type of work to be performed, sequences, and labor trades involved;<br />
E. Purchases, manufacture, tests, delivery, and installation activities for major materials<br />
and equipment, and a separate list of major material items equipment for which Design-<br />
Builder intends to seek payment before installation;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
47 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
F. Preparation, submittal, review and Approval of Contract Data Requirement List (CDRL)<br />
items showing minimum time specified for the Authority and/or other third party reviews<br />
of submittals. The same time frame shall be allowed for at least one re-submittal or<br />
submittals so identified in the Contract Documents;<br />
G. Traffic control routing/phasing to support Design-Builder operations;<br />
H. Approvals and permits required by applicable Governmental Persons or other third<br />
parties;<br />
I. Schedules for Subcontract work;<br />
J. Assignment of responsibility for performing specific activities;<br />
K. Access and availability to the Site;<br />
L. Identification of interfaces and dependencies with preceding, concurrent and follow-on<br />
third party contractors;<br />
M. Resource loading for cost and equipment;<br />
N. Actual tests, submission of test reports, and acceptance of test results;<br />
O. Identification of interfaces and dependencies with preceding, concurrent, and follow-on<br />
contractors and Utility Owners;<br />
P. Indicate Utilities being Relocated by Design-Builder or by a Utility Owner;<br />
Q. Indicate work relating to satisfaction of environmental mitigation measures;<br />
R. All start-up, testing, training, and assistance required under the Contract;<br />
S. Preparation and submittal of operation and maintenance manuals;<br />
T. Design and construction interfaces with the Alignment Contractor’s work;<br />
U. Punch List work and final cleanup;<br />
V. Identification of manpower, material, or equipment restrictions as well as any activity<br />
requiring unusual shift work, such as two shifts, six day weeks, specified overtime, or<br />
work at times other than a standard work day (eight hours per day, Monday through<br />
Friday); and<br />
W. All activities shall be coded to a level necessary to allow for multiple sorting.<br />
Provide a stand-alone narrative report for the Baseline Schedule, which describes the schedule<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
48 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
phasing, assumptions, and approach to complete the Work within the interim milestones and<br />
Completion Deadlines.<br />
Within seven days after the submittal of the Baseline Schedule, Design-Builder shall schedule a<br />
meeting to discuss the submittal with the Authority. Design-Builder shall have its Project Manager,<br />
superintendent, scheduler, and major Subcontractor representatives, in attendance.<br />
Within 14 days after the Authority’s review of the Baseline Schedule submittal, Design-Builder shall<br />
have revised and incorporated the review comments and shall resubmit for review and approval by<br />
the Authority.<br />
Within 14 days after Design-Builder re-submits the Baseline Schedule, the Authority will either:<br />
A. Approve the Baseline Schedule and resource loaded activities as submitted; or<br />
B. Advise Design-Builder in writing to review any part or parts of the Baseline Schedule<br />
which either do not meet the requirements set forth in the Contract Documents or are<br />
unsatisfactory for the Authority to monitor the progress, resources, or status of the<br />
Contract.<br />
The Authority may approve the Baseline Schedule on the condition that the first Current Project<br />
Schedule is revised to correct deficiencies identified, or with other conditions as may be determined<br />
by the Authority.<br />
When the Baseline Schedule is approved by the Authority, it shall be considered the official Project<br />
schedule until a Current Project Schedule has been submitted to and approved by the Authority.<br />
The Authority reserves the right to require Design-Builder to adjust, add to, remove from, or clarify<br />
any portion of the Baseline Schedule which may later be discovered to be insufficient for monitoring<br />
of the Work or other reason. No additional compensation will be provided for such adjustments,<br />
additions, removals, or clarifications.<br />
The Authority’s approval of Design-Builder’s Baseline Schedule represents a determination that the<br />
schedule appears to comply with the requirements set forth in the Contract Documents and appears<br />
adequate to permit the Authority to perform management functions during the course of<br />
construction. It shall not be considered a representation by the Authority that the Work can be<br />
constructed within the time durations specified, or with the resources allocated to the various<br />
activities. Notwithstanding Authority’s approval of the Baseline Schedule, Design-Builder bears<br />
sole and exclusive responsibility for the accuracy of all aspects of the Baseline Schedule and for<br />
completion of the Project within the time limits and other requirements established in the Contract<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
49 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Documents and for the Contract Price.<br />
Submittal of the Baseline Schedule shall be understood to be Design-Builder’s representation that:<br />
A. The Baseline Schedule meets the requirements of the Contract Documents and that<br />
Work shall be executed in sequence indicated on the schedule; and<br />
B. Design-Builder has distributed the Baseline Schedule to Subcontractors for review and<br />
has received the Subcontractors’ acceptance, which shall be noted on Subcontractors’<br />
letterhead to Design-Builder and transmitted to the Authority for the record. Letters from<br />
applicable Subcontractors, indicating such Subcontractors’ review and approval shall<br />
accompany Current Project Schedule submittal updates.<br />
4.7 Project Schedule Updates<br />
4.7.1 Current Project Schedule Monthly Updates<br />
Following Authority approval of the Baseline Schedule, Design-Builder shall submit to the Authority<br />
for approval on a monthly basis, a Current Project Schedule for the purpose of accurately<br />
documenting the progress of the Work to date and correcting the schedule to accurately reflect<br />
Design-Builder’s current plan for the timely completion of the Work.<br />
The Current Project Schedule progress shall be updated as of the date designated by the Authority<br />
(“data date”). Design-Builder shall obtain the Authority’s approval prior to making deviations in logic<br />
and activity durations in the Current Project Schedule.<br />
Design-Builder shall convene regularly scheduled meetings at least seven days prior to the data<br />
date for the purpose of reviewing changes to the schedule logic and Project status. At any such<br />
meeting, Design-Builder shall provide a preliminary updated Current Project Schedule that<br />
forecasts the Project status on the data date and contains actual start and actual finish dates for<br />
activities in progress or completed, remaining durations of activities in progress, percent complete<br />
of Schedule Activities, logic changes, new or deleted activities, and new Change Order activities.<br />
If current progress reflects Float of minus 14 days or more for Substantial Completion, as indicated<br />
by most recent Current Project Schedule, Design-Builder shall submit a stand-alone portion of the<br />
network (fragnet) evaluating the delay. Each fragnet shall show activities affected, date delay or<br />
disruption occurred or how productivity rates were impacted and unmitigated impacts to the<br />
schedule caused by delay or disruption. Design-Builder shall submit similar fragnet showing<br />
Design-Builder’s plan to mitigate delay or disruption and subsequent impacts to the Current Project<br />
Schedule at the Authority’s request. Design-Builder shall provide written narrative describing<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
50 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
circumstances that caused delay or disruption and methodology used to determine extent of delay<br />
or disruption. Submission of such fragnets does not constitute permission to proceed with plan.<br />
Design-Builder shall execute some or all of the following remedial actions, and submit a Recovery<br />
Schedule that may include:<br />
A. Increasing manpower in such quantities and crafts as necessary to eliminate the backlog<br />
of work;<br />
B. Increasing the number of working hours per shift, shifts per Working Day, Working Days<br />
per week, the amount of equipment, or combination of the foregoing to eliminate the<br />
backlog of work; and<br />
C. Rescheduling the Work in conformity with the Contract Documents.<br />
Before implementing any of the above actions, Design-Builder shall notify and obtain approval from<br />
the Authority. If such actions are approved by Authority, Design-Builder shall incorporate revisions<br />
into the Current Project Schedule.<br />
The addition of equipment or labor; increasing the working hours; or otherwise adjusting other work<br />
methods, manners, or procedures to return to contractually required completion dates will not be<br />
considered justification for a Change Order, nor be treated as acceleration where the need for a<br />
Recovery Schedule has been caused by Design-Builder and/or its Subcontractors or Suppliers, at<br />
any tier.<br />
4.7.2 As-Built Schedule Submittal<br />
Design-Builder shall submit prior to Final Acceptance, and as a prerequisite of Final Acceptance, an<br />
as-built schedule for the Project. The as-built schedule shall include correct actual dates for<br />
activities based upon the latest Current Project Schedule.<br />
4.7.3 Time Impact Analysis<br />
When Design-Builder receives a Potential Change Order (PCO), Change Order (CO) or submits a<br />
Request for Change Order seeking to extend a Completion Deadline, Design-Builder shall submit to<br />
the Authority a written time impact analysis illustrating the influence of each change or delay to the<br />
Baseline Schedule or Current Project Schedule. Design-Builder shall utilize the approved Current<br />
Project Schedule in effect one month prior to the start of the delay. Include in each time impact<br />
analysis a fragnet demonstrating how Design-Builder proposes to incorporate the PCO, CO or<br />
delay into the Current Project Schedule. The fragnet shall contain a sequence of new and/or<br />
activity revisions that are proposed to be added to the Current Project Schedule.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
51 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Each time impact analysis shall demonstrate estimated time impact based on events of delay, date<br />
of PCO or CO given to Design-Builder, status of design or construction at that point in time, and<br />
event time computation of activities affected by the PCO, CO or delay.<br />
Design-Builder shall submit each time impact analysis in accordance with the requirements set forth<br />
in Contract Section 12.0. If Design-Builder does not submit a time impact analysis within the period<br />
of time specified in Contract Section 12.0, Design-Builder will be deemed to have irrevocably<br />
waived rights to additional time and cost.<br />
Because Float within Current Project Schedule is jointly owned, it is acknowledged and agreed by<br />
Design-Builder that the Authority-Caused Delays on the Project may be offset by Authority-caused<br />
time savings (including: Critical Path submittals returned in less time than allowed for in the<br />
Contract, acceptance of substitution requests which result in a savings of time along the Critical<br />
Path for Design-Builder, etc.). In such an event, Design-Builder will not be entitled to receive an<br />
extension of time or delay damages until the Authority-caused time savings are exceeded by non-<br />
concurrent Authority-Caused Delays to Contract completion.<br />
A. The Authority will approve or reject each time impact analysis. Upon approval, a copy of<br />
a time impact analysis signed by the Authority will be returned to Design-Builder for<br />
incorporation into the Current Project Schedule;<br />
B. Upon mutual agreement by both parties, Design-Builder shall incorporate fragnets<br />
illustrating the influence of Potential Change Orders, Change Orders and delays into the<br />
Current Project Schedule during the first update after agreement is reached; and<br />
C. In the event Design-Builder does not agree with the decision of the Authority regarding<br />
impact of a change or delay, it will be resolved in accordance with Section 16.0 Dispute<br />
Resolution of the Contract.<br />
4.8 Written Narrative<br />
4.8.1 Baseline Schedule<br />
Design-Builder shall explain determination of activity durations and describe Design-Builder’s<br />
approach for meeting required interim milestone dates and Completion Deadlines, as specified in<br />
the Contract. Design-Builder shall include as a minimum: Basis and assumptions used in<br />
preparing submittal, including crew sizes, equipment requirements, and anticipated delivery dates;<br />
restraints, Critical Path activities, production rates; activities requiring overtime or additional shifts;<br />
activities that contain time contingencies for impacts to be expected from normal rainfall; holidays<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
52 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
and other non-work days; potential problem areas; permits; coordination required with the Authority,<br />
railroads, Utilities and other parties; and long lead delivery items requiring more than 30 days from<br />
order to delivery. Design-Builder shall identify Work items that may be expedited by use of<br />
overtime and additional shifts. Design-Builder shall identify and explain sequencing and other<br />
constraints such as manpower, material, and equipment. Design-Builder shall include a listing of<br />
holidays and special non-work days.<br />
4.8.2 Current Project Schedule<br />
Design-Builder shall submit a Current Project Schedule narrative on a monthly basis, containing the<br />
following information in detail:<br />
A. A description of the planned flow of the Work, identifying all driving resources, key<br />
constraints, and potential problems (including solutions), influencing Design-Builder’s<br />
approach to the Work;<br />
B. A description of all construction interfaces with Railroad Operators;<br />
C. A description of all construction interfaces with the Alignment Project and with third<br />
parties at the Site;<br />
D. A written status report on the communications program, including activities conducted in<br />
the last period, community concerns/issues log (including actions taken to respond and<br />
resolve concerns), updates to the stakeholder database, and a list of activities to be<br />
conducted in the coming month.<br />
E. A summary of planned labor utilization for the Project; identifying the maximum number<br />
of workers on Site each month based on the resource loaded Current Project Schedule.<br />
Identification of actual and potential labor resource limitations;<br />
F. A summary of planned equipment utilization for the Project. Identify actual and potential<br />
equipment resource limitations;<br />
G. Identification of the updated period, the data date, and the Current Project Schedule file<br />
name;<br />
H. Identification of activities with critical or near critical Float that were planned to occur<br />
during the update period by which did not occur or occurred later than the scheduled late<br />
start or late finish date, and a detailed explanation of these delays;<br />
I. Identification of delays occurring to activities taking place off the Site, such as submittal<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
53 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
preparation, fabrication, and delivery activities;<br />
J. A listing of all activities with critical or near critical Float for which the Authority is<br />
responsible; identification of the activity ID, activity description, remaining duration, Float,<br />
and activity dates;<br />
K. Plans for the forthcoming report period, including Design Document submittals;<br />
L. Description of all actual and potential delays and problems affecting the Project’s Critical<br />
Path;<br />
M. An explanation of actions taken, or proposed, to minimize delays, and how they will<br />
affect the overall Project;<br />
N. Analysis of milestones;<br />
O. Explanations to changed logic relationships, lags, previously approved original durations,<br />
calendars, activity codes including WBS, additions/deletions to the log, any imposed<br />
suspend or resume dates, additions/deletions to constraint dates, altered previously<br />
approved actual starts or finishes;<br />
P. Explanations of added activities for Change Orders;<br />
Q. New schedule activities requested to be added shall have explanations as to why they<br />
are required, new predecessor and successor logic ties and what impact they have on<br />
Completion Deadlines. If the new activities refine previously approved activities, these<br />
shall be noted and the old activities removed; and<br />
R. A 60-day look ahead narrative report on all CDRL approvals required.<br />
4.9 Review and Evaluation<br />
The Authority’s review and approval of any Contract schedule or report under this Section 4.0, or<br />
any other submittal by Design-Builder, shall not relieve Design-Builder from its obligation to perform<br />
according to the Contract Documents and complete the Work by the Completion Deadlines, even if<br />
the Current Project Schedules, reports or other submittals are inconsistent with the Completion<br />
Deadlines. The submittals and other actions by Design-Builder under this Section 4.0 shall not be<br />
construed as a Request for Change Order, Change Order, or Claim. Such notices, requests and<br />
Claims shall comply with the requirements set forth in the Contract Documents.<br />
After the approval of any Contract schedule or report required by this Section 4.0, no changes shall<br />
be made without the prior written approval of the Authority.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
54 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
4.10 Schedule Control Procedures<br />
Procedures for schedule control shall be included in Design-Builder’s Project Management Plan as<br />
part of the internal plan of implementation and reporting requirements. Following are three key<br />
elements that must be part of Design-Builder’s schedule control system:<br />
A. Monitoring/reporting system;<br />
B. Performance measurement system; and<br />
C. Schedule review/forecast.<br />
After the approval of any Project schedule, no changes shall be made without the explicit prior<br />
concurrence of the Authority.<br />
4.11 Effect of Schedule Reviews<br />
Any review or approval by the Authority of the Baseline Schedule or Current Project Schedules<br />
submitted by Design-Builder shall only mean that in the opinion of the Authority, the Baseline<br />
Schedule or Current Project Schedule is an accurate record of progress to date and an indication of<br />
Design-Builder’s intent.<br />
If the format and/or content of the Baseline Schedule or any Current Project Schedule submitted by<br />
Design-Builder is unacceptable to the Authority, Design-Builder shall revise the Baseline Schedule<br />
or Current Project Schedule, respectively, and resubmit as necessary until approved by the<br />
Authority.<br />
4.12 Progress Photographs<br />
Within 30 days after Notice to Proceed, and monthly thereafter, ending with the date of Substantial<br />
Completion of the Work, Design-Builder shall have approximately 10 digital color photographs taken<br />
of Project facilities at each future light rail station area depicting Project construction progress.<br />
Design-Builder shall submit the photographs until the work presented on the photographs is<br />
complete for the Authority’s review and approval along with the number of photographs and written<br />
description of each photograph location. Unless otherwise agreed by the Authority, the same<br />
number of photographs of the same views must be taken for each subsequent set of photographs.<br />
Design-Builder shall submit a DVD containing the photographs, and a PDF file cataloging the<br />
photographs included on the DVD, with each payment request. This catalog file shall be printable in<br />
color on 8½” x 11” paper with each page containing two photographs with written description. Two<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
55 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
hardcopies of the catalog file shall be submitted monthly with each DVD. The DVD shall be marked<br />
with the month the pictures were taken.<br />
4.13 Rain Days and Weather<br />
There shall be no adjustment to a Completion Deadline or Contract Price as a result of rain or other<br />
inclement weather.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
END OF SECTION<br />
56 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
5.0 QUALITY MANAGEMENT<br />
This Section 5.0 defines the Project quality control/quality assurance plan (QCQAP) requirements<br />
intended to ensure compliance with the Contract Documents, applicable regulatory requirements<br />
and industry standards. The QCQAP, supported by specific and detailed procedures, describes the<br />
processes and responsibilities intended to ensure the design, construction, procured equipment and<br />
materials, installation and testing will comply with all Contract Documents. Design-Builder shall<br />
provide a design QC/QA manager and a construction QC/QA manager responsible for<br />
implementing the QCQAP.<br />
5.1 Quality Control/Quality Assurance Plan<br />
Design-Builder shall develop a quality control/quality assurance plan (QCQAP) for the Work and<br />
implement the QCQAP within its organization and within Subcontractor organizations of all tiers.<br />
The QCQAP shall ensure that the design, construction and manufacturing of all facilities and<br />
equipment to be provided under this Contract will comply with the requirements of the Contract<br />
Documents and that all materials incorporated in the Work, as well as all elements of the Work will<br />
meet or exceed the standards in the Contract Documents and perform their intended purpose.<br />
Quality control (QC) comprises the actions related to the physical characteristics of a material,<br />
system, piece of equipment, or element of the Work and provides a means to control the quality of<br />
the materials, equipment and elements of the Work to ensure conformity in all respects to the<br />
requirements of the Contract Documents. Quality assurance (QA) comprises the actions related to<br />
oversight and documentation of quality of material, system, piece of equipment, or element of the<br />
Work, and provides the quality control elements to ensure conformity in all respects to the<br />
requirements of the Contract Documents.<br />
Design-Builder is responsible for quality control and first tier quality assurance and will provide<br />
office and field staff necessary to perform such oversight. The Authority is responsible for second<br />
tier quality assurance, which consists mainly of verifying that Design-Builder is performing effective<br />
quality control and assurance activities, and that Design-Builder is properly documenting the quality<br />
of the Project in accordance with Design-Builder’s approved QCQAP.<br />
5.1.1 Quality Control/Assurance Plan<br />
Design-Builder’s QCQA procedures shall be set forth in the QCQAP. In preparing the QCQAP<br />
Design-Builder shall utilize ISO 9001, and other applicable sections of ISO 9001-9004, as a<br />
guideline. The approved QCQAP shall be a “living” document and supplemented as required with<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
57 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
new aspects of the Work. The plan shall include written descriptions of QC and QA policies,<br />
procedures, methods and instructions and shall discuss the interface with the Authority’s quality<br />
program. Each Subcontractor shall agree, in writing, to fully comply with the applicable section or<br />
sections of the approved QCQAP.<br />
5.1.1.1 QCQAP Submittal <strong>Requirements</strong><br />
Design-Builder shall submit to the Authority for approval, within 30 days after the issuance of Notice<br />
to Proceed, Part One of the QCQAP. Part One of the QCQAP shall address topics pertaining to<br />
how the quality control system and standards will be set for the Work to be performed on-Site and<br />
off-Site; identify key quality control activities, deliverables and milestones keyed to the proposed<br />
Baseline Schedule; provide a complete list of all references and/or procedures to be developed for<br />
QC/QA of the Work for inclusion in Part Two and Part Three of the QCQAP; and address Design-<br />
Builder and/or Subcontractors’ planned approach to perform any additional activities/functions<br />
unique to the Work. Design-Builder shall also include in Part One of the QCQAP, the use of<br />
internal standards on quality, which it shall use to develop quality programs for specific Work<br />
activities such as software, design dependability, services and processed materials.<br />
Design-Builder shall submit to the Authority for approval, within 60 days after Notice to Proceed, a<br />
proposed Part Two of the QCQAP. Part Two shall include detailed procedures for the design and<br />
construction phases of the Work including management responsibility; quality system; contract<br />
review; design control including configuration management; document and data control; purchasing;<br />
control of customer-supplied product; product identification and trace-ability; process control,<br />
inspection and testing; control of inspection, measuring and test equipment; inspection and test<br />
status; control of nonconforming products; corrective and preventive action; handling, storage,<br />
packaging, preservation and delivery; control of quality records; training, servicing, and statistical<br />
techniques sections.<br />
Design-Builder shall submit to the Authority for review and approval, within 90 days after Notice to<br />
Proceed, a proposed Part Three of the QCQAP. Part Three shall include detailed procedures for<br />
the material, equipment and all other elements of the Work, including management responsibility;<br />
quality control system; contract review; design control including configuration management;<br />
document and data control; purchasing; control of customer-supplied product; product identification<br />
and traceability; process control, inspection and testing; control of inspection, measuring and test<br />
equipment; inspection and test status; control of nonconforming product; corrective and preventive<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
58 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
action; handling, storage, packaging, preservation and delivery; control of quality records; training,<br />
servicing, and statistical techniques sections.<br />
5.1.1.2 Supplements to QCQAP<br />
After approval by the Authority of the QCQAP, Design-Builder shall not revise the QCQAP without<br />
the prior written approval of the Authority. Design-Builder shall submit to the Authority, at least 60<br />
days prior to start of any new activities, supplements to Part Two or Part Three of the QCQAP,<br />
defining exact details of new activities.<br />
5.1.2 Meetings<br />
Prior to submitting each part of the QCQAP, Design-Builder shall meet with the Authority to discuss<br />
the QCQAP requirements and to develop a mutual understanding of the requirements of the<br />
QCQAP. After submitting each part of the QCQAP, Design-Builder shall meet with the Authority to<br />
develop a mutual understanding of the details of the QCQAP, including forms to be used for<br />
documentation, administration for on-Site and off-Site Work, and the coordination of Design-<br />
Builder’s Project management, design, construction and QC and QA staff with the Authority. At a<br />
minimum, Design-Builder’s staff required to attend each meeting shall include Design-Builder’s<br />
senior management (i.e., a higher level than Design-Builder’s Project Manager), Project Manager,<br />
and design and construction QC/QA managers.<br />
5.2 Quality Control/Quality Assurance Plan – Part One<br />
Part One of the QCQAP shall include, at a minimum, the following:<br />
A. A description of the QC/QA organization, including the number of full-time equivalent<br />
employees with specific QC/QA responsibilities and including a chart showing lines of<br />
authority and reporting responsibilities and relationships to the Authority’s organization,<br />
Design-Builder’s design staff and construction staff. This description shall also include a<br />
responsibility matrix showing who will review and approve Shop Drawings, material<br />
submittals, design and construction phases, and who will perform and document the<br />
testing;<br />
B. The Persons and organizations performing QC/QA functions shall have authority and<br />
organizational freedom to identify quality problems, and to initiate, recommend, provide<br />
and verify implementation of solutions. Persons performing QC/QA functions shall be<br />
separate and independent from any other functions, and shall be at an organizational<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
59 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
level that ensures that they are not subjected to conflicting influences, as their activities<br />
may impact the Current Project Schedule or costs resulting from implementation of<br />
QC/QA measures. In this regard, the respective quality manager shall have direct<br />
access to Design-Builder’s senior management (i.e., a higher level than Design-Builder’s<br />
Project Manager) and shall provide periodic reports directly to senior management.<br />
Furthermore, the compensation paid to quality control personnel shall not include any<br />
bonuses or other financial incentives tied to Project’s financial performance;<br />
C. The duties, responsibilities and authority of each Person proposed to be assigned a<br />
QC/QA function, as well as the individual to which he/she reports, shall be identified by<br />
Design-Builder. All Persons proposed to be assigned to QC or QA duties shall be<br />
qualified, experienced and proficient in QC and QA activities. All personnel performing<br />
QC/QA functions, as well as those Persons assigned to construction QC/QA duties, shall<br />
be exclusively designated to such duties and shall not be assigned to perform any other<br />
work. Persons in the Design QC/QA function shall have a minimum of five years<br />
experience, shall be qualified in the disciplines being reviewed, and shall certify that the<br />
documents reviewed meet the requirements set forth in the Contract Documents. These<br />
individuals shall be professional engineers registered in the State of California, report to<br />
the design QC/QA manager, and maintain contact with the Authority for the purpose of<br />
providing up to date, accurate design status with emphasis given to deviations from the<br />
Contract Documents. Construction inspectors shall be independent third party<br />
inspectors (i.e. a Subcontractor) with a minimum of five years of experience and shall be<br />
qualified in the disciplines being inspected. These individuals shall report to the<br />
construction QC/QA manager and maintain contact with the Authority for the purpose of<br />
providing up to date, accurate construction status with emphasis given to deviations from<br />
the Contract Documents and corrective actions taken. There shall be a sufficient<br />
number of field inspectors to monitor all work occurring on the Site. At a minimum, field<br />
inspectors in the following construction disciplines shall be identified: Civil, structural,<br />
geotechnical, electrical and mechanical.<br />
The Authority reserves the right to require changes in the QC/QA organization and how<br />
it functions as necessary to ensure the specified quality of the Work. The Authority<br />
reserves the right to interview any member of Design-Builder’s QC/QA organization at<br />
any time in order to verify qualifications. The Authority reserves the right to reject any<br />
member of Design-Builder’s QC/QA organization at any time during the Project should<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
60 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
that Person’s performance and qualifications not be compatible with the role of that<br />
Person in the QCQAP, and require a qualified replacement within seven days;<br />
D. Design-Builder shall provide the Authority with a letter signed by senior management of<br />
Design-Builder appointing design and construction QC/QA managers and stating that<br />
they are responsible for managing and implementing the QCQAP; include in this letter<br />
the design and construction QC/QA managers’ authority to interpret and manage the<br />
QCQAP to identify and evaluate the required correction of any and all quality control<br />
related problems, verify implementation and its effect, to control further processing or<br />
shipment of nonconforming material, products or work, and to hire, assign and remove<br />
staff members. The design and construction QC/QA managers shall report directly to<br />
senior management of Design-Builder, and the Authority. The design and construction<br />
QC/QA managers shall certify that all interfaces of the various disciplines have been<br />
reviewed and approved as required, and that all levels of production and fabrication<br />
integration have been reviewed and found to produce a final product which is in<br />
compliance with the requirements set forth in the Contract Documents. The design and<br />
construction QC/QA managers shall have the authority of all staff changes, both<br />
increases and decreases, measuring the effectiveness of the program, stopping the<br />
Work, and evaluating the number of positions to adequately perform the duties of the<br />
organization. The design and construction QC/QA managers shall each have a<br />
minimum of 10 years relevant experience as a QC/QA manager, or a project manager,<br />
or a project resident engineer on similar size and type of construction contracts which<br />
include the major trades that are part of this Contract;<br />
E. Procedures for the presentation, preparation and checking of submittals, including those<br />
of Subcontractors, off-Site fabricators, suppliers and purchasing agents;<br />
F. A description of QC/QA actions such as checking, inspection and testing, including<br />
frequencies and procedures for each type of action that verify activities affecting the<br />
quality of the Work have been correctly performed and meet all requirements set forth in<br />
the Contract Documents;<br />
G. Procedures to be followed by Subcontractors to ensure the quality of the Work provided<br />
by them and that all such Work shall be in compliance with the QCQAP; and<br />
H. Reporting and documentation procedures, including proposed reporting formats.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
61 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
5.3 Quality Control/Quality Assurance Plan – Part Two<br />
5.3.1 Minimum <strong>Requirements</strong><br />
Part Two of the QCQAP shall be developed to ensure that all Design Documents and Construction<br />
Documents shall be prepared in accordance with good, prudent and generally approved design and<br />
engineering practice, and shall meet all requirements of the Contract Documents. Additionally, Part<br />
Two of the QCQAP shall include:<br />
A. The QC/QA procedures for each type of Design Document and Construction Document<br />
specified by the requirements set forth in the Contract Documents, all of which shall be<br />
organized by engineering discipline. These procedures shall specify measures to be<br />
taken by Design-Builder to: (1) ensure that appropriate quality standards are specified<br />
and included in the Design Documents and Construction Documents and to control<br />
deviations from such standards so that no deviations from such standards shall be made<br />
unless they have been previously approved by the Authority in writing at the Authority’s<br />
sole discretion; and, (2) for the selection and review for suitability of all materials,<br />
equipment and elements that are included in the Project;<br />
B. Specific QC procedures for preparing and checking all plans, calculations, drawings and<br />
other items submitted, to ensure that they are independently checked and back-checked<br />
in accordance with generally accepted engineering practices, by experienced engineers.<br />
The originator, checker, and back-checker shall be clearly identified on the cover sheet<br />
of all submittals. Specific procedures for verifying computer programs used shall also be<br />
included. Plans, reports, and other documents shall be stamped, signed, and dated by<br />
the responsible California registered engineer where required by the Contract<br />
Documents, generally accepted engineering practices, or applicable Governmental<br />
Rules.<br />
As a part of the submittal for the final plans, Specifications and estimate approval,<br />
Design-Builder shall submit multiple copies of final design calculations and multiple<br />
copies of final design checked calculations independently checked and compliant with<br />
the latest version of the Office of Special Funded Projects, EFPB Information and<br />
Procedures Guide;<br />
C. The level, frequency and methods of review of the adequacy of the design of the Project,<br />
including the methods by which all final Design Documents and Construction Documents<br />
shall be independently reviewed, verified for adequacy of design and back-checked in<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
62 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
accordance with generally accepted design and engineering practice by experienced<br />
engineers not involved with the preparation of such documents;<br />
D. Procedures for coordinating the Work performed by different Persons in the same area,<br />
or in adjacent areas or in related tasks to ensure that conflicts, omissions or<br />
misalignments do not occur between drawings or between the drawings and the<br />
Specifications, and to coordinate the review, approval, release, distribution, and revision<br />
of documents involving such Persons;<br />
E. Procedures to (1) ensure that all personnel performing the Work are familiar with all<br />
requirements of the Contract Documents pertaining to their responsibilities, including all<br />
referenced standards; (2) for the education, training, and certification as appropriate, of<br />
personnel performing activities affecting or measuring quality of the Work to ensure that<br />
they achieve and maintain reasonable proficiency; and (3) ensure that all the Work is<br />
performed according to the QCQAP;<br />
F. Those elements of the requirements set forth in the Contract Documents, Design<br />
Documents or Construction Documents, if any, requiring special QC attention or<br />
emphasis, including applicable standards of quality or practice to be met, level of<br />
completeness and/or extent of detailing required;<br />
G. By discipline, the name, qualifications, duties, responsibilities, and authorities for all<br />
Persons proposed to be responsible for design and construction QC and QA;<br />
H. Any requirement for, and the name, qualifications, duties, responsibilities, and authorities<br />
of, external technical experts necessary to ensure the quality of the design of the<br />
Project, and the anticipated timing of use of, the expected availability of, and any<br />
coordination required with respect to, any such experts;<br />
I. The resources required for the design QC functions, including proposed specific timing,<br />
manpower and resource requirements, including scheduled QC activities, identifying all<br />
submittals to be delivered to the Authority for its review at each stage of the design of<br />
the Project;<br />
J. The requirements for documentation; for the filing of design criteria, daily inspection<br />
reports and notes, calculations, drawings, schematics, supporting materials, etc; and for<br />
the specific responsibilities of personnel to satisfy these requirements. All such Design<br />
Documents shall be maintained by Design-Builder for the duration of the Contract, and<br />
shall be organized, indexed and delivered to the Authority upon Final Acceptance unless<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
63 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
equired to be delivered earlier pursuant to the requirements set forth in the Contract<br />
Documents, or even if incomplete, within seven days of receipt of request by the<br />
Authority; and<br />
K. Identification of the QA personnel, audit procedures, and documentation designed to<br />
verify compliance with quality assurance provisions of the QCQAP.<br />
5.3.2 Review of Design Work<br />
Submissions of drawings, Specifications and computations shall be accompanied by documentation<br />
confirming that Design-Builder has fully applied and followed the approved QCQAP. This<br />
documentation shall include all appropriate reports, drawings, schematics, calculations, tables, plan<br />
sheets, etc., and evidence that all checking, revising, back-checking and other QC and QA reviews<br />
were properly performed. Design-Builder’s design QC/QA manager shall provide with each design<br />
review submittal a written certification that the submittal complies with the QCQAP in all respects,<br />
unless exempted by prior written authorization from the Authority. Documentation of conformity to<br />
the QCQAP is a requisite element of each submittal, and design review submittals not accompanied<br />
by sufficient verification of the application of QCQA procedures will be returned to Design-Builder.<br />
5.3.3 Design Quality Review<br />
Prior to the submittal of final Design Documents to the Authority and prior to finalization of<br />
Construction Documents, Design-Builder shall complete a review with engineers experienced in the<br />
appropriate discipline(s) to verify that the Design Documents and Construction Documents were<br />
prepared in such a manner as to ensure that they will be acceptable to the Authority, as well as<br />
Design-Builder. The criteria used in such review shall include (1) conformity of the final Design<br />
Documents and Construction Documents with the requirements set forth in the Contract<br />
Documents; (2) confirmation that all materials, equipment and elements of the Work provided for in<br />
such documents which shall be incorporated into the Project have been provided for and designed<br />
to perform satisfactorily for the intended purpose; (3) the appearance, organization, technical and<br />
grammatical accuracy of such documents; (4) verification that such documents have been checked<br />
and signed by the drafter, designer, checker and reviewers; (5) where required under the Contract<br />
Documents, generally accepted architectural or engineering practices or applicable Governmental<br />
Rules, verification that such documents have been stamped, signed and dated by the responsible<br />
California registered engineer; and (6) certification that such documents fully provide for<br />
constructability, compatibility of materials and conformity to acceptance criteria for inspections and<br />
tests as provided in the Contract Documents.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
64 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
The Authority shall have the right to review the Design Documents at any time to determine that the<br />
requirements of the QCQAP are being met. Design Documents that do not conform to the<br />
approved QCQAP shall be brought into conformity by Design-Builder before being sent to the<br />
Authority for further review.<br />
5.3.4 Design Changes<br />
Changes, including shop or field changes, in the design of the Project or any portion thereof as<br />
shown on the final Design Documents shall require an approved Change Order as a condition<br />
precedent to the effectiveness thereof, and shall be subject to design QC and QA measures and<br />
procedures commensurate with those applied to the original design of that portion of the Project<br />
being changed. Furthermore, all changes described in this Section 5.3.4 shall be approved in<br />
writing by the organization that performed the original design unless the Authority allows, in writing,<br />
another responsible organization to approve such changes.<br />
5.3.5 Organization and Indexing of Design and Construction Documents<br />
Within 30 days of approval by the Authority of the complete final design of the Project, Design-<br />
Builder shall provide the Design Documents organized and indexed in accordance with the<br />
document and data control system, consistent with the approved QCQAP.<br />
5.3.5.1 Preparation and Delivery of Construction Documents<br />
Design-Builder shall be responsible for preparation of all Construction Documents which shall show<br />
the general arrangement, and such details as are necessary to provide a comprehensive<br />
description, of the Work to be performed. Design-Builder shall ensure that the Construction<br />
Documents are consistent with the Design Documents, the requirements of the QCQAP and other<br />
requirements set forth in the Contract Documents. Design-Builder shall deliver Construction<br />
Documents to the Authority as provided herein.<br />
5.3.5.2 Representation by Design-Builder<br />
By approving Construction Documents, Design-Builder thereby represents that it has determined<br />
and verified field measurements, field construction criteria, materials, catalog numbers, and similar<br />
data, or will do so, and that it has checked and coordinated each Construction Document with the<br />
requirements of the Contract Documents.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
65 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
5.3.5.3 Construction Document <strong>Requirements</strong><br />
Design-Builder shall prepare all Construction Documents required for the completion of the Work in<br />
accordance with the Contract Documents.<br />
Shop Drawings for steel structures shall consist of shop, erection, and other drawings, showing<br />
details, dimensions, sizes, and other information necessary for the complete fabrication and<br />
erection of the metalwork. Shop Drawings for concrete structures shall consist of such additional<br />
detailed drawings as may be required for the prosecution of the Work and must include drawings of<br />
falsework, bracing, centering, form work, concrete reinforcement and masonry layout diagrams.<br />
Design-Builder shall check completely the bar lists and details of reinforcement steel shown on the<br />
plans and shall submit complete Shop Drawings for the reinforcement steel to the Authority for<br />
information. Material specification designations for the various components of the structures shall<br />
be noted on the drawings. Shop Drawings shall include fabrication and erection drawings, schedule<br />
drawings, manufacturer’s scale drawings, wiring and control diagrams, cuts of entire catalogs,<br />
pamphlets, descriptive literature, performance and test data.<br />
Working Drawings shall include plans for temporary structures such as decking, temporary<br />
bulkheads, support of excavation, support of Utilities, groundwater control systems, and forming<br />
and false-work for underpinning and for such other work as may be required for construction but<br />
which does not become an integral part of the completed Project. They shall be accompanied by<br />
calculations or other sufficient information to completely explain the structure or system described<br />
and its intended manner of use.<br />
Design-Builder shall prepare all Working Drawings and Shop Drawings on sheets measuring 22<br />
inches by 34 inches unless otherwise approved by the Authority. In all cases, the Shop Drawings<br />
and Working Drawings shall be to a scale sufficiently large to show all pertinent aspects of the item<br />
and its method of connection to the Work. Design-Builder shall provide each drawing with a blank<br />
area five inches by five inches, located adjacent to the title block. The title block shall display the<br />
following:<br />
A. Contract number and name;<br />
B. Number and title of the drawings;<br />
C. Date of drawing and revision number;<br />
D. Name of Design-Builder and Subcontractor submitting drawing;<br />
E. Clear identification of contents and location of the Work;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
66 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
F. Specification reference number;<br />
G. Name, California State registration number and seal of professional engineer certifying<br />
the drawings, if engineering computations are involved or if original design work is<br />
depicted; and<br />
H. Submittal number.<br />
Design-Builder shall coordinate drawings for the Work on Utilities, streets and other facilities,<br />
structures, etc., that are constructed for others so that the information required by these other<br />
entities is included on the Working Drawings.<br />
5.4 Quality Control/Quality Assurance Plan – Part Three<br />
Part Three of the QCQAP shall identify all materials, equipment and all elements of the Work, as<br />
well as the individuals and organizations performing any functions under the QCQAP, and shall<br />
provide control over all activities affecting the quality of all such materials, equipment and elements<br />
of the Work.<br />
5.4.1 Contents of Plan<br />
Part Three of the QCQAP shall:<br />
A. Specify procedures to ensure that all activities affecting the quality of the Work will be<br />
accomplished under suitably controlled conditions, using appropriate equipment, with<br />
confirmation that all prerequisites to the proper accomplishment of a given task have<br />
been satisfied;<br />
B. Specify procedures that ensure that (1) all Design-Builder personnel are familiar with all<br />
requirements of the Contract Documents pertaining to their responsibilities, including the<br />
standards referenced in the Contract Documents, (2) the education, training and<br />
certification, as appropriate, of personnel performing activities affecting or verifying<br />
quality of the Work are of reasonable proficiency, and (3) all Work is performed<br />
according to the QCQAP;<br />
C. Describe specific procedures to be followed by Design-Builder to ensure that all the<br />
Work conforms to all the requirements of the Contract Documents (including the final<br />
Design Documents) and the Construction Documents; and, that all materials, equipment<br />
and elements of the Work to be incorporated in the Project will perform satisfactorily for<br />
the intended purpose. The QCQAP shall specifically include Design-Builder’s<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
67 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
procedures for inspecting, sampling, testing and checking the Work (including initial and<br />
source testing, and work performed by Subcontractors) in accordance with the<br />
requirements of the Contract Documents;<br />
D. Specify that all activities undertaken by or on behalf of Design-Builder affecting quality of<br />
the Work shall be prescribed by documented instructions, procedures and/or drawings of<br />
a type appropriate to the circumstances and shall be accomplished in accordance with<br />
these instructions, procedures or drawings. Such instructions, procedures and drawings<br />
shall include quantitative and/or qualitative criteria as appropriate to be used to<br />
determine that all activities have been satisfactorily accomplished;<br />
E. Specify measures to control the issuance of and changes to documents, which prescribe<br />
activities affecting quality, such as instructions, procedures and drawings. These<br />
measures shall confirm that approved documents, including all authorized changes<br />
thereto, are reviewed for adequacy and approved for release by authorized personnel<br />
and are distributed to and used at the location where the prescribed Activity is<br />
performed. Changes to documents shall be reviewed and approved by the same<br />
organizations that performed the original review and approval unless the Authority<br />
allows, in writing, another responsible organization to perform such reviews and<br />
approvals;<br />
F. Specify measures to verify that purchased materials, equipment and services conform to<br />
the requirements set forth in the Contract Documents, including the final Design<br />
Documents and the Construction Documents. These measures shall include provisions,<br />
as appropriate, for evaluation and selection, objective evidence of quality furnished by<br />
Subcontractors, inspection at the manufacturer or vendor source, and examination of<br />
products upon delivery. Documentary evidence that material and equipment conform to<br />
the procurement requirements shall be available at the jobsite no less than 24 hours<br />
prior to installation or use of such material and equipment. This documentary evidence<br />
shall be retained at the jobsite and shall be sufficient to identify the specific<br />
requirements, such as the requirements set forth in the Contract Documents, applicable<br />
Governmental Rules, standards or Specifications, met by the purchased material and<br />
equipment. The effectiveness of the control of quality by Design-Builder’s own forces<br />
and Subcontractors shall be assessed by Design-Builder at intervals consistent with the<br />
importance, complexity and quantity of the product or services;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
68 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
G. Specify procedures to provide for adequate notice and opportunity for prior inspection by<br />
the Authority and applicable third parties for any Work done or materials used;<br />
H. Specify procedures for identification and control of materials, equipment and elements of<br />
the Work. These procedures shall ensure that identification of the item is maintained by<br />
appropriate means, either on the item or on records traceable to the item, as necessary,<br />
throughout fabrication, assembly, erection, installation and use of the item. These<br />
identification and control procedures shall be designed to prevent the use of incorrect or<br />
defective materials and equipment;<br />
I. Specify procedures to ensure that materials, equipment or elements of the Work that do<br />
not conform to requirements are not used or installed. These procedures shall include,<br />
as appropriate, procedures for identification, documentation, segregation, disposition<br />
and notification to the Authority and all other affected Persons, as well as procedures for<br />
the Authority to review Non-Conforming Work, review proposed resolutions for Non-<br />
Conforming Work, and accept, reject or require repair and/or reworking of Non-<br />
Conforming Work;<br />
J. Include a program for inspection and documentation of all the Work to be executed by or<br />
for the organization performing the activity to verify conformity with the documented<br />
instructions, procedures and requirements of Contract Documents applicable to such<br />
Work. Such inspection shall be performed by individuals other than those who<br />
performed the activity being inspected. Examinations, measurement and tests of<br />
materials or elements of the Work shall be performed for each Work operation, where<br />
appropriate, to confirm required quality has been achieved. Inspections shall be<br />
performed at a frequency and timing which will prevent the placement or installation of<br />
the work prior to covering or obscuring the work product requiring inspection;<br />
K. Specify procedures for establishing construction hold points for the Work which require<br />
witnessing and/or inspecting by Design-Builder’s designated representative, the<br />
Authority, or applicable third party. Design-Builder’s construction quality manager shall<br />
conduct meetings prior to new Work activities and new fabrication to establish hold<br />
points and discuss approach with QC personnel, Subcontractors, and the Authority. The<br />
approved Construction Work Plan, as discussed in Section 3.20.1, for a given activity<br />
shall include the inspection hold point(s). At all hold points, Design-Builder shall not<br />
proceed beyond that point until Design-Builder, Authority, and/or third party, as<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
69 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
applicable, has completed such witnessing and/or inspecting or waived its right, in<br />
writing, to witness and/or inspect the applicable Work;<br />
L. Include a program to confirm execution of all testing required in the Contract Documents<br />
to demonstrate that all materials, equipment and elements of the Work will perform<br />
satisfactorily for the intended purpose and meet the standards specified in the Contract<br />
Documents, including the final Design Documents. The program shall specify written<br />
test procedures for all tests which incorporate the requirements and acceptance limits<br />
contained in applicable final Design Documents and Construction Documents and which<br />
include provisions for verifying that all prerequisites for the given test have been met and<br />
that adequate test instrumentation is available and used. The program shall require test<br />
results to be documented and evaluated to confirm that test requirements have been<br />
satisfied. The test program shall be supplemental to any acceptance and assurance<br />
testing as initiated, coordinated and directed by the Authority.<br />
Provide a listing of independent testing laboratories to be used to perform sampling and<br />
testing required by the Contract Documents. The proposed laboratory must possess<br />
acceptable accreditation programs such as the National Institute of Standards and<br />
Technology (NIST), National Voluntary Laboratory Accreditation Program (NVLAP), or<br />
the American Association of State Highway and Transportation Offices (AASHTO)<br />
program. All materials inspectors and testing personnel shall have current certifications<br />
such as ACI, ICC, NISIT, AWS, etc. Specify procedures to ensure verification of<br />
certificate of accreditation, scope of accreditation and testing methods, inspection of<br />
testing laboratories, capability check and test results. The Authority reserves the right to<br />
check laboratory equipment in the proposed laboratory and laboratory technician’s<br />
testing procedures, techniques, and other items pertinent to testing, for compliance with<br />
the standards set in the Contract Documents. Calibration and testing devices shall<br />
maintain traceability to the National Institute of Standards (NIST). Design-Builder shall<br />
furnish the signed reports, certifications, and other documentation to the Authority upon<br />
request and furnish a summary report of field tests at the end of each month;<br />
M. Specify measures to ensure that tools, gauges, instruments and other measuring and<br />
testing devices used in activities affecting quality are properly maintained, controlled,<br />
calibrated and adjusted at specified periods to maintain accuracy within necessary limits;<br />
N. Specify procedures to control the handling, storage, shipping, cleaning and preservation<br />
of materials and equipment to prevent damage or deterioration;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
70 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
O. Specify procedures to indicate, by the use of markings such as stamps, tags, labels,<br />
routing cards or other suitable means, the status of inspections and tests performed<br />
upon individual items of the Work. These procedures shall provide for the identification<br />
of items, which have satisfactorily passed required inspections and tests, where<br />
necessary to preclude inadvertent bypassing or duplication of such inspections and<br />
tests;<br />
P. Specify procedures to ensure that conditions adverse to quality, such as failures,<br />
malfunctions, deficiencies, defective material and equipment, deviations and other Non-<br />
Conforming Work are promptly identified and corrected. In case of significant conditions<br />
adverse to quality, the procedures shall ensure that the cause of the condition is<br />
determined and corrective action taken to preclude repetition. The identification of the<br />
significant condition adverse to quality, the cause of the condition, and the corrective<br />
action taken shall be documented and reported to appropriate levels of Design-Builder’s<br />
management to ensure corrective action is promptly taken, and to the Authority;<br />
Q. Provide for measures ensuring compliance with all QC procedures recommended by the<br />
testing manufacturer, and providing that any other QC procedures in addition to or which<br />
serve as a substitute for the manufacturer’s procedures; and<br />
R. Provide a documented procedure for establishing and maintaining facilities and<br />
equipment.<br />
5.4.2 Review of Construction Work<br />
Submissions of drawings, Specifications, reports, certifications and computations shall be<br />
accompanied by documentation confirming that Design-Builder has fully applied and carried out the<br />
approved QCQAP. This documentation shall include Shop Drawings and Working Drawings, test<br />
reports, approvals and permits for the use of land, Site, premises, and Utilities etc., and evidence<br />
that all checking, revising, back-checking and other QC/QA reviews were properly performed.<br />
Documentation of conformity to the QCQAP is a requisite element of each submittal, and<br />
construction review submittals not accompanied by sufficient verification of the application of<br />
QC/QA procedures will be returned to Design-Builder. Design-Builder’s construction QC/QA<br />
manager shall provide with each submittal a written certification that the submittal complies with the<br />
QCQAP in all respects, unless exempted by prior written authorization by the Authority. Design-<br />
Builder shall retain a separate construction management (CM) firm (Subcontractor) to perform<br />
quality assurance and quality control during construction and quality assurance during Final Design.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
71 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
The CM firm shall have at least 10 years experience performing constructability reviews, inspection,<br />
and oversight on similar parking facilities projects.<br />
5.4.2.1 Construction Inspection and Quality Assurance<br />
Design-Builder’s construction QC/QA manager shall notify the Authority at least one week in<br />
advance of the construction preparation phase and start-up phase of each Work element. The<br />
construction QC/QA manager shall meet with appropriate key inspection staff and the construction<br />
staff for the disciplines affected to perform and document the following:<br />
A. Review applicable requirements set forth in the Contract Documents and Design-<br />
Builder’s Specifications;<br />
B. Review applicable Contract Documents and Shop Drawings and Working Drawings;<br />
C. Verify that appropriate drawings and submittals for materials and equipment have been<br />
submitted, and approved factory test results are received and on file;<br />
D. Review the testing plan and ensure that provisions have been made to provide required<br />
QC testing;<br />
E. Examine the Work area to ensure that the required preliminary Work has been<br />
completed;<br />
F. Examine the required materials, equipment and samples to ensure that they are on hand<br />
and conform to the approved drawings and submittals;<br />
G. Review the Safety plan and appropriate activity hazard analysis to ensure that applicable<br />
Safety requirements are met;<br />
H. Discuss construction methods;<br />
I. Establish the quality of workmanship required; and<br />
J. Perform a constructability review of the final design.<br />
During on-going construction Work, construction QC/QA manager shall require each inspector to<br />
document the following minimum activities on a daily inspection report, or more frequently, as<br />
necessary until the completion of each Work element:<br />
K. Document the Work, Work progress, personnel and equipment on a daily basis using<br />
forms agreed to by the Authority;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
72 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
L. Document specific inspections performed utilizing a discipline specific checklist and<br />
include the results of such inspections;<br />
M. Inspection criteria and design/construction documents used to perform inspections; and<br />
N. Documentation that non-conforming items are resolved and rework items are corrected<br />
in accordance with approved methods.<br />
The Authority shall have the right to review or audit the Work, processes and procedures at any<br />
time to determine that the requirements of the QCQAP are being met. The Work, processes and<br />
procedures that do not conform to the QCQAP will be issued a Non-Conformance Report (NCR)<br />
and shall be corrected by Design-Builder.<br />
5.4.3 Non-Conforming Work<br />
A. Non-Conforming Work is the Work that does not conform to the requirements of the<br />
Contract Documents. Upon discovery of Non-Conforming Work, Design-Builder’s<br />
inspection staff and the Authority has the right to direct Design-Builder to immediately<br />
cease performance of the Non-Conforming Work. In the event finished work quality is in<br />
doubt or believed to be non-conforming, the Authority may require Design-Builder to<br />
expose, remove or uncover such portions of the finished construction Work to verify<br />
conformity or necessary corrective actions. After examination by the Authority, Design-<br />
Builder shall restore the Work to the standard required by the Contract Documents;<br />
B. If the Work exposed or examined is not in conformity with the requirements of the<br />
Contract Documents, then the cost of uncovering, removing, and restoring the Work, and<br />
the cost of recovery of any delay to any Critical Path occasioned thereby shall be at<br />
Design-Builder’s expense. Furthermore, any Work done or materials used without<br />
adequate notice and opportunity for prior inspection by the Authority, Utility Owner, or<br />
Persons having jurisdiction, as required per the approved QAQCP, may be ordered<br />
uncovered, removed, or restored at Design-Builder’s expense, even if the Work proves<br />
acceptable after uncovering;<br />
C. Except with respect to the Work done or materials used as described in Section 5.4.3.B,<br />
if the Work exposed or examined is in conformity with the requirements of the Contract<br />
Documents, as determined by the Authority, then any delay in any Critical Path from<br />
uncovering, removing, and restoring the Work shall be considered an Authority-Caused<br />
Delay, and Design-Builder shall be entitled to a Change Order, if applicable, for the cost<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
73 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
of such efforts and recovery of any delay to any Critical Path occasioned thereby,<br />
subject to the provisions of Volume 2- Contract. Design-Builder shall promptly take all<br />
action necessary to prevent similar deficiencies from occurring in the future;<br />
D. The fact that the Authority may not have discovered the Non-Conforming Work shall not<br />
constitute an acceptance of such Non-Conforming Work. If Design-Builder fails to<br />
correct (or to substantially begin correction of) any Non-Conforming Work within 10 days<br />
of receipt of notice from the Authority requesting correction or if Design-Builder fails to<br />
diligently prosecute the correction of any Non-Conforming Work, then the Authority may<br />
cause the Non-Conforming Work to be remedied, or removed, and replaced, and may<br />
deduct the cost of doing so from any moneys due, or to become due, to Design-Builder<br />
and/or obtain reimbursement from Design-Builder for such cost; and<br />
E. It is imperative that Design-Builder understand that they must provide both Quality<br />
Control and first tier Quality Assurance on the Project and all non-conforming issues<br />
shall be addressed at Design-Builder’s QA level. Repeated non-conformance issues<br />
discovered by the Authority points to a systemic failure with Design-Builder’s QCQA<br />
procedures or staff performance and the Authority reserves the right to make necessary<br />
and immediate corrections, therefore, at Design-Builder’s expense. The procedures for<br />
correction of Non-Conforming Work shall be set forth in the QCQAP.<br />
5.4.4 Construction Changes<br />
Changes, including shop or field change, in the construction of the Project or any portion thereof as<br />
shown on the final Construction Documents, shall require an approved Change Order as a<br />
condition precedent to the effectiveness thereof, and shall be subject to construction QC/QA<br />
measures and procedures commensurate with those applied to the original construction of that<br />
portion of the Project being changed.<br />
5.5 Documentation Quality Control and Quality Assurance<br />
Design-Builder shall implement an electronic database program documenting QC and QA activities<br />
on the Project. The database program shall categorize inspections by Work type (for example CSI<br />
codes) and provide for a trending analysis of Non-Conforming Work by Work type. The program<br />
shall include all data required for the Work, as well as all communications among Design-Builder’s<br />
QCQA organization, design organization, construction organization, all Subcontractors regardless<br />
of the tier, and the Authority. Design-Builder shall maintain complete and detailed records of QC<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
74 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
and QA activities and accountability including all QCQA operations, inspections, activities and tests<br />
performed. The records shall require a formal, logical numbering system, and a continuously<br />
updated index. The records and program maintenance shall be subject to the Authority’s inspection<br />
and audit at any time. These records shall remain complete and available to the Authority at all<br />
times during the performance of the Contract and until expiration of the Warranty. Such records<br />
shall include any delays encountered and the Work noted that does not conform to the<br />
requirements of the Contract Documents (including the final Design Documents) and/or the<br />
Construction Documents, together with the corrective actions taken regarding such Work. Such<br />
records shall include a monthly written certification by the construction QC/QA manager, delivered<br />
to the Authority by the fifteenth day of the following month; that the QCQAP and all of the measures<br />
and procedures provided therein are functioning properly and are being fully complied with. In<br />
addition, such records shall include factual evidence that required activities or tests have been<br />
performed and shall describe:<br />
A. Type, number and results of QC and QA activities, including reviews, inspections,<br />
factory acceptance and field verification tests, audits, monitoring of work performance<br />
and materials analysis;<br />
B. Closely-related data such as qualifications of personnel, procedures and equipment<br />
used;<br />
C. The identity of the inspector or data recorder, the type of test or observation employed,<br />
the results and the acceptability of the Work and action taken in connection with any<br />
deficiencies noted;<br />
D. Nature of Non-Conforming Work, causes for rejection, etc;<br />
E. Proposed corrective action;<br />
F. Corrective actions taken;<br />
G. Results of corrective actions; and<br />
H. Current Project Schedule impact.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
END OF SECTION<br />
75 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
6.0 CONTRACT MEETINGS<br />
Design-Builder shall have in attendance, staff with the appropriate technical skills and decision-<br />
making authority at Project meetings. Subcontractors, materials suppliers, and others may be<br />
invited to attend Project meetings when warranted, but Design-Builder shall remain wholly<br />
responsible for proper procedure and representation regarding Project meetings.<br />
Design-Builder shall prepare and update a master meeting calendar that clearly identifies all<br />
scheduled Project-related meetings, including community and third party meetings (such as with<br />
municipal agencies). The calendar shall be updated at least weekly, and shall show all meetings<br />
scheduled for the next four weeks, as a minimum. Per agreement with the Authority, the calendar<br />
shall be made available via electronic mail, hard copy distribution, and/or on a website. Design-<br />
Builder shall provide the Authority with a minimum of 48 hour notice (to the maximum extent<br />
practicable) of invitation to meetings.<br />
Design-Builder shall prepare an agenda for each meeting and distribute it to each of the<br />
participants. To the maximum extent practicable, the Authority will advise Design-Builder at least<br />
24 hours in advance of a scheduled meeting regarding items the Authority wishes to have placed<br />
on the agenda.<br />
Unless otherwise specified in the Contract Documents, Design-Builder shall prepare minutes of all<br />
meetings and submit them to the Authority within two Working Days after the meeting, and the<br />
Authority shall have two Working Days to review the minutes and request revision to the minutes.<br />
Within two Working Days following comment thereon by the Authority, Design-Builder shall deliver<br />
copies of the meeting minutes with the Authority’s comments to each meeting attendee and others<br />
designated by the Authority.<br />
6.1 Project Kick-Off Meeting<br />
The Project kick-off meeting shall be held within seven Working Days after receipt of the Notice to<br />
Proceed at a location and time mutually agreed to by Design-Builder and the Authority. The<br />
agenda for this meeting shall include initial discussions regarding Safety, quality, design,<br />
communications, and the Baseline Schedule.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
76 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
6.2 Weekly Project Coordination and Progress Meeting<br />
Weekly Project coordination and progress meetings shall be held starting on a date and time<br />
mutually agreed by the Authority and Design-Builder. Design-Builder shall keep a running log of<br />
action items. The agenda of the meeting shall include the following:<br />
A. Project Management<br />
1. Safety<br />
2. Quality<br />
3. Schedule<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
4. Overall status of the Project<br />
5. Critical items to be resolved<br />
B. Communications Program<br />
1. Activities conducted in the last period<br />
2. Community concerns/issues log (including actions taken to respond and<br />
resolve concerns)<br />
3. Updates to the stakeholder database<br />
4. List of activities to be conducted in the coming weeks<br />
C. Third Party Management<br />
1. Status of interface coordination with Alignment Contractor<br />
2. Status of utility work including abandonments and relocations<br />
3. Schedule of meetings with third parties during the next three-week period<br />
D. Design Management<br />
1. Design submittal status and log, with emphasis on those submittals required<br />
over the next 30 day period<br />
2. Design Request for Information (RFI) status and log<br />
3. Design status<br />
4. Critical design issues to be resolved<br />
E. Construction Management<br />
77 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Construction submittal status and log;<br />
2. Construction Request for Information (RFI) status and log<br />
3. Work completed during the previous period (refer to the three week rolling bar<br />
chart schedule discussed below)<br />
4. Work scheduled during the next three-week period (refer to the three week<br />
F. Change Order Status<br />
rolling bar chart schedule discussed below)<br />
1. Change Order status and log<br />
2. Potential Claim status and log<br />
The design management portion of the meeting shall be conducted by Design-Builder’s Design<br />
Manager and attended by the appropriate members of Design-Builder’s staff, including required<br />
Subcontractors and Design-Builder’s Construction Manager.<br />
The construction management portion of the meeting shall be conducted by Design-Builder’s<br />
Construction Manager and attended by the appropriate members of Design-Builder’s staff, including<br />
required subcontractors and Design-Builder’s Design Manager. Prior to the weekly meeting,<br />
Design-Builder shall prepare for presentation at the meeting a three week rolling bar chart<br />
schedule. The three week rolling bar chart schedule shall be based on the Current Project<br />
Schedule, and include activities that are planned in this ‘window’ of time, i.e., the previous week<br />
plus three weeks ahead. The three-week rolling schedule shall include activities that are recently<br />
completed, in-work, planned to start, and planned to complete. The bar chart schedule shall show<br />
at a minimum the activity ID as defined on the Baseline Schedule or Current Project Schedule, as<br />
applicable, description, early/actual starts and finishes, original and remaining duration and Float<br />
sorted by the approved work breakdown structure (WBS).<br />
6.3 Baseline Schedule and Current Project Schedule Meetings<br />
Baseline Schedule and Current Project Schedule meetings shall be held in accordance with Section<br />
4.0.<br />
6.4 Utility Owner Meetings<br />
Design-Builder shall hold coordination meetings with each Utility Owner as required in order to<br />
expeditiously perform the Utility Work, and shall determine, in conjunction with each Utility Owner,<br />
78 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
the schedule for design and construction of all Utility Work affecting their facilities. Design-Builder<br />
shall invite Authority to all meetings with Utility Owners and indicate on the meeting notice whether<br />
or not Authority’s participation is requested; however, Authority may participate in such meetings as<br />
Authority may elect. Design-Builder shall be responsible for providing meeting facilities unless<br />
otherwise agreed.<br />
6.5 Third Party Coordination Meetings<br />
Design-Builder shall hold coordination meetings with each applicable Governmental Person and<br />
applicable third party as required in order to expeditiously perform the Work. Design-Builder shall<br />
invite Authority to all meetings with third parties and indicate on the meeting notice whether or not<br />
Authority’s participation is requested; however, Authority may participate in such meetings as<br />
Authority may elect.<br />
6.6 Additional Meetings<br />
Design-Builder shall participate in fire/life safety and security committee (FLSSC) meetings, safety<br />
and security certification review team (SSCRT) meetings and various other essential meetings that<br />
are occasionally scheduled.<br />
Further, Design-Builder shall be responsible for holding any other meeting(s) required to facilitate<br />
completion of the Project, unless specified otherwise in the Contract Documents. Authority may<br />
participate in such meetings as Authority may elect.<br />
Conversely, the Authority reserves the right to call impromptu meetings and schedule meetings, as<br />
warranted based on Design-Builder’s performance, occurrence of unforeseen issues, and progress<br />
of the Work.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
END OF SECTION<br />
79 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
7.0 DOCUMENTATION<br />
This Section 7.0 includes the requirements for preparation, maintenance, completion and<br />
submission of drawings, Specifications, and other Project-related documents (“Record<br />
Documents”).<br />
7.1 Format of Documents<br />
7.1.1 Electronic Formatting:<br />
A. File names and titles shall not contain any special characters (e.g., %, &, /);<br />
B. Submitted design documents shall be grouped into one of four categories: (1) drawings,<br />
(2) specifications, (3) calculations, or (4) reports;<br />
C. Design-Builder’s digital signature policy shall be approved by the Authority (Adobe<br />
Digital Certificate, etc.);<br />
D. Throughout the Project, documents submitted by Design-Builder shall be in PDF format<br />
in which the text is recognizable (OCR converted). Whenever possible, documents shall<br />
be direct-printed to PDF, such that the document is converted from the original program<br />
(e.g., Microsoft Office, Microstation, etc.), opposed to printing and scanning;<br />
E. Whenever possible, file sizes should be kept under 30 MB for ease of transfer;<br />
F. Submittals shall reference the CDRL number, which is composed of the Contract<br />
volume, document and section number. To develop the submittal number, Design-<br />
Builder shall reference the Contract Document as described in the table below:<br />
Volume Document Section<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
Submittal Numbering System<br />
Subsection<br />
Item<br />
Unique<br />
# Submittal #<br />
Example 1 3 1 08 01 03 01 3.1.08.01.03.01<br />
Example 2 3 1 01 02 N/A 01 3.1.01.02.00.01<br />
1. Within the submittal number, Contract Volume and Document numbers shall<br />
Submittal<br />
Description<br />
Site Safety -<br />
IIPP<br />
Project<br />
Management<br />
Plan<br />
contain one digit; and Contract Section, Subsection, Item and unique number<br />
shall contain two digits.<br />
G. Design-Builder shall submit to the Authority for review and approval a file naming<br />
convention for other documents such as RFIs and Change Orders. Design-Builder shall<br />
80 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
account for revisions within the naming convention (e.g., RFI-010.01, where 0.01 is<br />
revision 1);<br />
H. Image files such as JPEG, video/audio clips, etc., do not need to be converted into PDF<br />
format. Where applicable, image resolution should be 150-dpi , video resolution<br />
680x480 (standard PAL or NTSC), and audio resolution of 128-kbps;<br />
I. Files with multiple sections (such as manuals) should be bookmarked. A table of<br />
contents or index page should also be created that can link to the various PDF sections;<br />
J. Other than standard digital signature protection, security features should not be enabled.<br />
The Authority should be able to read, write to, save, etc., a submitted document;<br />
K. Standard TrueType TM fonts should be enabled (Arial, Times Roman, etc.);<br />
L. Where applicable, Design-Builder shall submit the schedules (Primavera) in the methods<br />
and formats discussed in <strong>General</strong> <strong>Requirements</strong> Section 4.0;<br />
M. Upon request of the Authority, Design-Builder shall submit electronic files in the original<br />
software format (DOC, XLS, DGN);<br />
N. To reduce document control labor and to properly track documents, Design-Builder shall<br />
support the Authority’s contract management software system by:<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Electronically transferring documents such as submittals, Change Orders,<br />
Requests for Information (RFIs), cost proposals, correspondence, etc., to the<br />
Authority;<br />
2. Unless otherwise directed by the Authority, Design-Builder shall submit,<br />
receive, and respond to Project documents in a standard electronic form<br />
(such as Adobe Acrobat PDF) using the web interface (DUI) with the<br />
Authority’s “Oracle Primavera Contract Management” system. Design-<br />
Builder shall purchase the software license(s) for “Oracle Primavera Contract<br />
Management” and annual maintenance fees to support their personnel<br />
responsible for submitting documents to the Authority. The license(s) will be<br />
assigned to the web interface system, and will only be available for use by<br />
Design-Builder on the Authority’s system through completion of the Project;<br />
3. The Authority will provide instructions for accessing and submitting<br />
documents through the web interface;<br />
81 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
4. Specific Project documents, including Requests for Information (RFIs),<br />
submittals, and Change Orders may be prepared by Design-Builder in a<br />
document control system of their choice and submitted to the Authority in a<br />
searchable Adobe PDF format through the web interface system; and<br />
5. Including basic information such as title and number of each document,<br />
description, person submitting, contact information, etc. This basic<br />
information shall accompany the document(s) via submittal form sheet, email<br />
(template), web-base software, or other Authority-approved method;<br />
O. Design-Builder shall be responsible for ensuring all employees are familiar with the<br />
electronic submission requirements;<br />
P. Design-Builder is responsible for ensuring the Authority receives the electronic<br />
document. This can be performed by read-receipts, hand or certified delivery of DVD,<br />
etc; and<br />
Q. Unless otherwise approved by the Authority, contractual documents submitted after<br />
12:00 pm on Friday will not include the Saturday, Sunday, and Authority observed<br />
Monday Holidays in the calculation of days required for the Authority contractual replies.<br />
7.1.2 Paper-Copy Formatting:<br />
In an effort to reduce costs and conserve the environment, paper copies are not required for all<br />
document transmissions. Paper copies shall be submitted for necessary contractual documents as<br />
indicated in Appendix B- Contract Data Requirement List (CDRL). After Project award, the<br />
Authority and Design-Builder shall develop a policy for required paper copy submissions in<br />
accordance with the following:<br />
A. Paper documents shall be submitted in the documents original scale-size (letter, legal,<br />
etc.);<br />
B. Paper documents shall be readable;<br />
C. Paper documents shall be provided in color when necessary (photos, diagrams);<br />
D. Paper documents shall be properly packaged (stapled, binded, etc.); and<br />
E. Design-Builder shall provide paper copies when requested.<br />
82 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
7.1.3 Document Content Formatting<br />
A. Submittals shall be in the American English language, with correct grammar/spelling and<br />
technically written (instead of legally written, etc.);<br />
B. All dimensions and measurements shall be in the American system (lb/ft/sec), unless<br />
metric is requested in a <strong>Metro</strong> technical document or metric is industry standard or<br />
required by applicable Governmental Persons;<br />
C. All costs shall be identified in U.S. Dollars; and<br />
D. Information shall be clearly itemized for each item contained in the bid to allow a<br />
thorough examination.<br />
7.2 Submission of Documents<br />
A. Prior to delivering the application for Final Acceptance, Design-Builder shall deliver<br />
Record Documents to the Authority;<br />
B. For final Construction Documents, include the reproducible transparency set along with<br />
one black-line print;<br />
C. Deliver Record Documents neatly and efficiently packaged; and<br />
D. Accompany submission of Record Documents with a transmittal letter containing the<br />
following information:<br />
1. Date of submission;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
2. Project title and number;<br />
3. Design-Builder’s name and address;<br />
4. Title and number of each record document (Shop Drawings may be grouped<br />
in basic categories or divisions of work and by box identification);<br />
5. Design-Builder’s certification that each document, as submitted, is complete<br />
and accurate; and<br />
6. Signature of the Project Manager.<br />
83 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
7.3 Management of Documents<br />
Design-Builder shall carefully manage all submitted, revised, Approved for Construction documents<br />
and Specifications to ensure the latest approved versions are being implemented in the field and in<br />
fabrication.<br />
Design-Builder shall provide revised documents via a transmittal to all plan holders with a clear<br />
direction to substitute specific Approved for Construction drawings and Contract Specifications with<br />
the revised documents. When applicable, the Change Order(s) and/or Request for Information(s)<br />
authorizing the revision shall also be noted on the transmittal.<br />
Design-Builder’s quality manager shall be responsible to ensure that the latest Approved for<br />
Construction drawings and Specifications are being referenced during performance of the Work and<br />
fabrication and that all construction foremen and fabricators have the latest documents for<br />
construction.<br />
Design-Builder shall maintain all records and documents relating to the Work and the Project,<br />
including copies of all submitted documents delivered to the Authority, until five (5) years after the<br />
Final Acceptance Date or the termination of this Contract, whichever is applicable. Design-Builder<br />
shall notify Authority where such records and documents are kept. Notwithstanding the foregoing,<br />
in the event of litigation or Claims arising from the performance of the Contract, all records shall be<br />
retained and made available until such litigation, and other actions, and Claims have been finally<br />
resolved.<br />
7.3.1 Documents Relating to Operations Security<br />
All Project documents that relate to the security of the operation of the Project as a part of <strong>Metro</strong>’s<br />
system shall be considered security sensitive documents and are subject to <strong>Metro</strong>’s policy set forth<br />
in Volume 3, Document 4.5 (Design-Builder’s attention is drawn notably to Sections 1.1, 1.4.1, and<br />
1.4.5). Design-Builder shall comply with applicable portions of said policy and obtain written<br />
agreement from each DB-Related Entity to comply with applicable portions of said policy.<br />
7.4 Record Documents<br />
Design-Builder shall provide Record Documentation for all work:<br />
A. Maintain one up-to-date copy of the following documents for record purposes:<br />
1. Change Orders;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
84 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
2. Working Drawings;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
3. Design drawing packages and books of plans;<br />
4. Approved Shop Drawings;<br />
5. Clarifications or explanatory details and Specifications;<br />
6. Requests for Information (RFI) and their responses;<br />
7. Inspection reports;<br />
8. Laboratory test records (as applicable);<br />
9. Field test records (as applicable);<br />
10. List of Non-Conforming Work identified by the QCQAP and/or Authority’s<br />
compliance audit program; and<br />
11. As-built record drawings;<br />
B. Store documents used for record purposes in the field job office or other approved<br />
location, apart from documents used for construction;<br />
C. Provide files and racks for storage of documents;<br />
D. File documents in accordance with the work breakdown structure (WBS);<br />
E. Maintain documents in clean, dry, legible condition;<br />
F. Label each document “Project Record”; and<br />
G. Make documents available at all times for inspection by the Authority.<br />
7.5 Record Drawings<br />
A. Construction drawings:<br />
1. Design-Builder shall maintain “as-built” or record drawings of all Work<br />
continuously as the job progresses. A separate set of ‘red-lined’ prints or<br />
Working Drawings, for this purpose only, shall be maintained at the jobsite at<br />
all times;<br />
2. Design-Builder shall keep these drawings up-to-date and submit a print<br />
showing all changes to the Approved for Construction drawings to the<br />
Authority when the relevant work is completed;<br />
85 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
3. Design-Builder shall incorporate deviations from the ‘red-lined’ drawings,<br />
Utility services, mechanical and electrical lines, details, and other Work onto<br />
the MicroStation electronic drawing files upon completion of the respective<br />
Work;<br />
4. Shop Drawings for reinforcing steel, structural steel, embedded and mounted<br />
mechanical and electrical conduits shall also reflect “as-built” conditions, in<br />
which case the appropriate final Design Documents or Construction<br />
Documents shall be stamped to refer to such Shop Drawings as part of the<br />
“as-built” configuration;<br />
5. No Work shall be permanently concealed until the required information and/or<br />
portion of the Work has been properly inspected, accepted, and recorded by<br />
Design-Builder;<br />
6. Where the construction drawings are not of sufficient size, scale, or detail,<br />
Design-Builder shall furnish its own Shop Drawings for incorporation of<br />
details and dimensions;<br />
7. Design-Builder shall stamp each sheet in this final and record set with “as-<br />
built” in red ink, signed and dated by the Designer of Record, and deliver the<br />
following to the Authority by Final Acceptance:<br />
a. Electronic full-size PDF;<br />
b. Electronic 11” x 17” PDF;<br />
c. CADD files with reference files (where local jurisdictions require<br />
format different than <strong>Metro</strong>, provide both); and<br />
d. Hardcopies as required by local jurisdictions; and<br />
8. “As-built” information shall be transferred onto DVD media that conforms to<br />
B. Change Orders:<br />
existing <strong>Metro</strong> standards, prior to Final Acceptance;<br />
1. Incorporate changes to the final Design Documents affected by Change<br />
Orders on the CADD drawings, and identify these changes by Change Order<br />
number and effective date;<br />
86 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
2. Drawing sheets that are modified shall clearly delineate changes with a<br />
‘cloud’ around the changed detail and a call-out number in ‘delta’ adjacent to<br />
the cloud. A system of deltas shall be used to indicate changes and their<br />
date of issuance and shall be listed at the bottom left-hand corner of each<br />
plan sheet. Deltas associated with Change Orders shall indicate the Change<br />
Order number on the plan sheet. Design-Builder is responsible to assure that<br />
every plan-holder has been issued the latest changed plan and specification<br />
sheets with instructions to replace the changed sheets in their plan and/or<br />
specification sets; and<br />
3. When revised drawings are issued as the basis of, or along with, Change<br />
Orders, incorporate these revised drawings into the record set with<br />
appropriate annotation. Drawings deleted by Change Orders shall not be<br />
incorporated as part of the record set; and<br />
C. Final submittal of record drawings:<br />
7.6 Record Specifications<br />
1. All record drawings shall be transferred onto DVD media. Design-Builder<br />
A. Project Specifications:<br />
shall deliver the following to the Authority prior to Final Acceptance:<br />
a. Electronic full-size PDF;<br />
b. Electronic 11” x 17” PDF;<br />
c. CADD files with reference files (where local jurisdictions require<br />
format different than <strong>Metro</strong>, provide both); and<br />
d. Hardcopies as required by local jurisdictions.<br />
1. File the Specifications book for record purposes in a large-ring, three-ring<br />
binder or binders;<br />
2. Record information, changes, and notes in the Specifications in blank areas,<br />
such as page margins or the backs of opposite pages, or on separate sheets<br />
inserted in the binder. Record all such information, changes, and notes with<br />
red pen or red type;<br />
87 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
3. In each section, in an appropriate location, record the manufacturer, trade<br />
name, catalog number, and supplier of each product and item of equipment<br />
actually installed;<br />
4. The record Specifications book shall be complete and shall include all<br />
applicable Construction Documents other than drawings; and<br />
5. Stamp this final and record set of “as-built” Specifications “as-built”, sign and<br />
B. Change Orders:<br />
date, and deliver to the Authority, on DVD media that conforms to existing<br />
<strong>Metro</strong> standards, prior to requesting final inspection; and<br />
1. Incorporate Change Orders into the front of the Specifications book in reverse<br />
chronological order. Use appropriate page dividers to identify Change Orders<br />
and to separate Change Orders from the Specifications; and<br />
2. Changes to the Specifications affected by Change Order annotated on the<br />
affected page or pages of the Specifications or adjacent thereto.<br />
END OF SECTION<br />
88 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
8.0 SITE SAFETY REQUIREMENTS<br />
8.1 <strong>General</strong><br />
8.1.1 Description<br />
A. Design-Builder shall establish, implement and maintain an effective injury and illness<br />
prevention program (IIPP) in accordance with Section 8.3.8 of these <strong>General</strong><br />
<strong>Requirements</strong>.<br />
Design-Builder shall comply the California Code of Regulations (CCR) Title 8, as well as<br />
all other Governmental Rules applicable to its operations. Strict compliance with all<br />
applicable Governmental Rules shall be considered within the original scope of this<br />
Contract and shall not justify schedule delay for performance of Work by Design-Builder,<br />
nor shall it be relied upon to form the basis of a Claim for delay. Compliance with<br />
determinations by the Authority shall not relieve Design-Builder from other obligations<br />
imposed by Governmental Rules nor serve as the basis of a Change Order;<br />
B. Design-Builder shall enforce an alcohol and drug-free construction workplace for its<br />
employees and Subcontractors. Design-Builder shall establish a drug-free awareness<br />
program to inform employees about the alcohol and drug-free workplace policy, danger of<br />
alcohol and drug abuse, available counseling, and penalties for violating the policy; and<br />
C. Compliance with all parts of this Section 8.0 and including all effects of such compliance<br />
including related work stoppages shall be considered within the original scope of this<br />
Contract and shall not be grounds for a Change Order or a Claim for cost or delay.<br />
8.1.2 <strong>Requirements</strong><br />
A. Design-Builder shall comply with both the CCR Title 8, and the Code of Federal<br />
Regulations (CFR) Title 29. Where the State and Federal regulations have differing<br />
requirements, Design-Builder shall comply with that which is more stringent. Design-<br />
Builder shall have full responsibility for maintaining conditions which are free from<br />
recognized hazards that are likely to cause physical harm to its employees;<br />
B. Air quality testing – Design-Builder shall perform air quality testing by qualified individuals.<br />
Design-Builder shall maintain a record of the date, time and location of tests and levels of<br />
contaminants. Design-Builder shall make all records, including printouts, and independent<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
89 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
testing laboratory analyses of jobsite samples, available for review by the Authority upon<br />
request;<br />
C. Design-Builder shall conform to the requirements of the authority having jurisdiction for the<br />
establishment of a fire watch in areas where welding operations and flame cutting are<br />
performed; and<br />
D. Design-Builder shall comply with the requirements of CCR Title 8, Section 5192,<br />
8.1.3 Submittals<br />
Hazardous Waste Operations and Emergency Response, with respect to the handling of<br />
Hazardous Substances and mandated specialty training and health screening.<br />
All submittals and re-submittals, when required, shall be considered within the original scope of this<br />
Contract and shall be submitted in accordance with the approved Baseline Schedule or Current<br />
Project Schedule, as appropriate, so as to not delay the performance of Work by Design-Builder.<br />
Design-Builder shall prepare and submit to the Authority for review and approval the submittals<br />
listed below. Design-Builder shall obtain approval from the Authority prior to the earlier of: (1) the<br />
start of construction, or (2) 90 days after Notice to Proceed or as approved by the Authority in<br />
writing.<br />
At a minimum, the following items shall be submitted by Design-Builder for review and approval by<br />
the Authority:<br />
A. Site specific injury and illness prevention program (IIPP) plan described in Section 8.3.8;<br />
B. Qualifications and certifications of designated lead and other Safety representatives, and<br />
other first aid providers;<br />
C. Qualifications and/or certifications of individuals who will serve as qualified or competent<br />
Persons. These supervisory individuals are designated by Design-Builder to supervise<br />
special high risk/high hazard Safety programs such as fall protection, excavation,<br />
Hazardous Substances operations and confined space entry;<br />
D. Fall Protection Program – Design-Builder shall include details of procedures, equipment<br />
and training in accordance with Cal OSHA requirements. This program shall be<br />
established and implemented to ensure that Design-Builder's and sub-contractor's<br />
workers, exposed to a vertical fall of six feet or more to another level, are properly<br />
protected. This protection shall provide protection from hazards such as: Skylights (at<br />
any angle), floor and wall openings, leading edges, and steel erection. Methods of<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
90 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
protection shall include: Fixed systems (guardrails, covers, nets, etc.), personal fall arrest<br />
systems and job specific fall protection plans. The “Fall Protection Program” shall be<br />
submitted and accepted prior to performing any Work covered by the plan;<br />
E. Regarding the training required by CCR Title 8, Section 5192, Hazardous Waste<br />
Operations and Emergency Response, with respect to the handling of Hazardous<br />
Substances and mandated specialty training and health screening – Design-Builder shall<br />
submit a list of qualified personnel at least 30 days before commencing any excavation.<br />
Design-Builder shall update such list at monthly intervals during ongoing excavation<br />
operations. Design-Builder shall include, for each individual, the date of certification and<br />
sufficient evidence of training and medical screening to conform to appropriate laws,<br />
regulations and the requirements of this Contract. Design-Builder shall revise and<br />
resubmit list of qualified personnel as conditions warrant;<br />
F. Design-Builder shall provide excavation action plans for all excavation activities for which<br />
a protective system is required by CCR Title 8 Article 6. Design-Builder shall include on<br />
such plans all drawings for any ground support system to be used during the excavation<br />
activity and the slopes and configurations of sloping or benching systems. All excavation<br />
submittals shall be submitted at least 15 days prior to the planned Work;<br />
G. Design-Builder shall provide current certifications for all cranes operated on the Site by<br />
Design-Builder and or sub-contractors of any tier. Re-certification is required for any crane<br />
subjected to any upset, overloading, side pulling, shock loading or support failure, prior to<br />
any further use of the equipment on the Site; and<br />
H. At the start of construction, Design-Builder shall submit monthly project safety<br />
performance reports compiling the monthly and year-to-date statistics of work hours,<br />
safety inspections, safety deficiencies, OSHA recordable incidents, physician treated<br />
incidents, restricted duty/lost time cases, safety training, etc. The safety reports shall<br />
included Subcontractor statistics.<br />
8.1.4 Site Conditions<br />
A. Design-Builder personnel shall only access areas at or near active light rail tracks or<br />
traction power/electrification systems, including the rail right of way, in accordance with<br />
applicable Governmental Rules. Persons desiring access to these currently-operating<br />
<strong>Metro</strong>-Rail facilities shall attend light rail Safety training classes conducted by <strong>Metro</strong>.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
91 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Conform to a work permit program for clearance to work on or adjacent to active tracks<br />
and to provide for the de-energization of the traction electrification system.<br />
Safety training classes are held by <strong>Metro</strong> as time(s) and location(s) to be established.<br />
Design-Builder personnel without Safety training will not be permitted onto areas which<br />
require such training as set forth in applicable Governmental Rules. Trained personnel<br />
found on the Site without a valid Safety identification badge shall be expelled from the Site<br />
and may be subject to prosecution for trespassing.<br />
Details of the work permit and track allocation procedures will be discusses at the pre-<br />
construction meeting. Design-Builder shall be trained and comply with <strong>Metro</strong>’s Wayside<br />
Worker Protection procedures for active track.<br />
Design-Builder’s personnel doing Work within the rail right of way shall attend a class on<br />
hi-rail equipment operation, Safety, and <strong>Metro</strong>’s Book of Rules and Procedures;<br />
B. Design-Builder personnel who will encroach or conduct work in the Azusa Industrial Lead<br />
(rail right of way west of Irwindale Avenue) shall attend the appropriate rail Safety training<br />
classes as required by the Federal Railroad Administration and other applicable<br />
Governmental Persons. Design-Builder personnel without rail Safety training will not be<br />
permitted to be present in the rail right of way. Design-Builder is responsible for obtaining<br />
track access rights. Design-Builder is also responsible for employing a certified flagger or<br />
other personnel required to work within the rail right of way;<br />
C. Design-Builder personnel who will encroach or conduct work in the rail right of way east of<br />
San Gabriel River Bridge shall attend the appropriate rail Safety training classes as<br />
required by the Federal Railroad Administration and other applicable Governmental<br />
Persons. Design-Builder personnel without rail Safety training will not be permitted to be<br />
present in this portion of the rail right of way. Design-Builder is responsible for obtaining<br />
track access rights. Design-Builder is also responsible for employing a certified flagger or<br />
other personnel required to work within the rail right of way;<br />
D. Design-Builder shall develop a hazard communication program, which contains a list of<br />
material safety data sheets (MSDS) for Hazardous Substances to be present at the Site.<br />
Design-Builder shall maintain a current list of all Hazardous Substances that will be used<br />
in the Site operations. Unless Design-Builder provides, in writing, an alternate method to<br />
be used to provide Authority employees’ access to material safety data sheets, copies of<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
92 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
all material safety data sheets for substances appearing on the Hazardous Substance<br />
list shall be readily available at the Site;<br />
E. If an accident/incident were to occur, resulting in injury, damage to equipment or facility, or<br />
a transit incident that is potentially FRA or CPUC GO 164 reportable, Design-Builder shall<br />
immediately notify the Authority of the incident. Design-Builder shall investigate the<br />
incident and prepare an incident report including summary, photos, interviews, drug and<br />
alcohol testing (if applicable) and recommendations/corrections shall be supplied for<br />
Authority review; and<br />
F. Design-Builder shall be solely responsible for Site security and safety, including protection<br />
8.2 Products<br />
of Design-Builder, Authority, and <strong>Metro</strong> property and personnel as well as the general<br />
public. Design-Builder shall take necessary precautions to prevent theft, vandalism, or<br />
other destructive activities.<br />
8.2.1 Construction Equipment and Tools<br />
A. Design-Builder shall select and operate construction and personal protective equipment<br />
and tools in conformity with Sections 8.1.1 and 8.1.2.A and in accordance with the<br />
manufacturer’s Specifications for the equipment or tools' intended use;<br />
B. Equipment - All equipment, tools and or other items used to complete the Work shall be<br />
inspected by Design-Builder to ensure compliance with applicable regulatory standards.<br />
Equipment, tools and or other items are subject to periodic inspection by the Authority.<br />
Design-Builder shall promptly remove equipment rejected by the Authority as not<br />
conforming to Sections 8.1.1 and 8.1.2. This removal shall be considered within the<br />
original scope of this Contract and shall not be grounds for a Change Order or cost or<br />
delay Claim. Such removal shall be completed in such a manner so as to not delay the<br />
schedule for performance of Work by Design-Builder.<br />
The Authority has established a program by which equipment, tools and other items used<br />
to complete the Work shall be removed from service when it has been determined that the<br />
equipment, tools and other items present a potential for injury when used as directed by<br />
the manufacturer. A tag with a prominent red and black message including the word<br />
"DANGER" may be utilized by the Authority. This tag shall be known as a "red tag." The<br />
tag will be signed by the Authority, dated and note the specific reasons for the rejection.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
93 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Any equipment, tool and or other item so tagged shall not be used to complete the Work<br />
until the condition noted on the tag has been corrected and the tag has been removed by<br />
the Authority.<br />
Any Person who ignores, removes, damages, or otherwise tampers with an Authority red<br />
tag shall be immediately removed from the Work by Design-Builder and shall not return to<br />
the Project without the written permission of the Authority;<br />
C. Special Safety equipment - Where necessary for conformity with Section 8.1.2, Design-<br />
Builder shall provide special Safety equipment and Persons qualified to operate same to<br />
ensure the Safety of the Site. Such special Safety equipment may include air quality<br />
measuring and monitoring equipment, noise measuring and monitoring equipment and<br />
other measuring devices related to industrial hygiene. Equipment shall be used in<br />
accordance with the respective manufacturer’s design, directions, and intended use;<br />
D. Electrical installations for construction activities shall conform to the National Electrical<br />
Code ANSI/NFPA latest edition, for electrical installations and be acceptable by the State<br />
of California, Division of Occupational Safety and Health; and<br />
E. Electrical equipment and tools to be used on the Site shall be listed by at least one of the<br />
following USA testing facilities: Underwriters Laboratories, Factory Mutual, or other<br />
approved electrical testing laboratories. Any electrical tool or equipment which is not listed<br />
by at least one of the above testing facilities shall be removed from the Site.<br />
8.2.2 Safety Equipment<br />
A. All personal protective and other Safety equipment placed into use at the Site shall<br />
conform to Section 8.1.2.A and shall include markings to show appropriate ANSI<br />
approval codes or other indications of approved usage. Equipment shall not be altered<br />
in any way without written approval by the respective manufacturer;<br />
B. Persons entering the Site shall, at minimum, be equipped with the following personal<br />
protective equipment: Hardhat, safety vest, eye protection, and work boots. ANSI<br />
accepted protective footwear shall be worn by all personnel exposed to foot hazards or<br />
working below grade (steel toed recreational shoes shall not be permitted);<br />
C. All Persons who will be entering below ground areas shall be equipped with a permissible<br />
rated hand or cap light and retro-reflective vest; and<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
94 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
D. No Person shall be allowed to wear recreational pants (shorts) or sleeveless shirts onto<br />
the Site. Refer to applicable Governmental Rules for additional requirements, including<br />
colors.<br />
8.2.3 Testing Equipment<br />
Air monitoring equipment and air flow testing equipment used in underground or other locations<br />
where there is the potential for an explosive atmosphere, shall be “permissible” as defined, tested<br />
and certified by the Mine Safety and Health Administration Laboratory of the U.S. Department of<br />
Labor.<br />
8.2.4 Diesel Powered Equipment<br />
All diesel-powered equipment used in underground covered areas shall be acceptable to the State<br />
of California Division of Occupational Safety and Health and listed on Design-Builder’s diesel<br />
permit. A copy of Design-Builder's diesel permit application and issued permit shall be available for<br />
review and inspection by the Authority without prior notice.<br />
8.3 Execution<br />
8.3.1 Safety Personnel<br />
A. To ensure the Safety of the Site, Design-Builder Safety personnel shall not work more<br />
than 11 hours in any 24-hour period or more than 55 hours in any seven consecutive<br />
day period. Included in the definition of Design-Builder Safety personnel is the lead<br />
Safety representative and any other Safety representatives;<br />
B. Design-Builder shall ensure that only those Safety representative(s) approved by the<br />
Authority for employment on the Site is/are present at the Site whenever work is in<br />
progress at the Site. The absence of the required Safety representative shall result in<br />
the immediate stoppage of all work at the Site. Design-Builder is responsible for<br />
maintaining an adequate staff of Safety personnel, whose qualifications have been<br />
submitted to and approved by the Authority, in order to avoid Work stoppages in the<br />
event of an expected or unexpected absence due to vacation, illness, personal<br />
emergency, resignation, or termination of the assigned Safety representative(s).<br />
Design-Builder's Safety representative(s) shall have the authority to direct immediate<br />
correction of any unsafe or unhealthful condition and, as necessary, to stop Work until<br />
appropriate corrective measures have been completed;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
95 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
C. Design-Builder shall have a designated lead Safety representative who is approved by<br />
the Authority for employment on the Site. The lead Safety representative shall meet the<br />
following qualifications: A full-time supervisory employee of Design-Builder responsible<br />
for the implementation of Design-Builder’s safety and health program at the Site. The<br />
Safety representative shall be currently certified in first-aid and CPR by the American<br />
Red Cross or its equivalent. The Safety representative must be assigned full time to the<br />
jobsite whenever the Work is in progress. The lead Safety representative shall regularly<br />
work the day shift, attend required meetings and be fully cognizant of all Project-specific<br />
Safety practices, processes, rules and procedures, and maintain regular contact with<br />
Authority-designated Safety personnel; and<br />
D. Design-Builder shall assign Safety representatives for second and third shift who meet<br />
the following qualifications: A full-time supervisory employee of Design-Builder<br />
responsible for the implementation of Design-Builder’s Safety and health program at the<br />
Site. The Safety representative shall be currently certified in first-aid and CPR by the<br />
American Red Cross or its equivalent. The Safety representative must be assigned full<br />
time to the jobsite whenever the Work is in progress. The Safety representatives utilized<br />
by Design-Builder shall be approved by the Authority for employment on the Site.<br />
8.3.2 Air Monitoring<br />
Design-Builder shall comply with the following:<br />
A. All air monitoring activities shall conform to Sections 8.1.1, 8.1.2.A, and 8.1.2.B;<br />
B. Select and use equipment capable of providing printed logs of gas tests;<br />
C. Operate and maintain a gas monitoring system as required by Section 8.2.3. Perform air<br />
monitoring and sample analyses as required by Sections 8.1.1, 8.1.2.A, and 8.1.2.B;<br />
D. Begin testing for toxic and explosive gases as soon as the excavation or drilled hole has<br />
progressed to a level of five feet below surface level; and<br />
E. Test air quality in the most stagnant portions of excavation to ensure there is no<br />
accumulation of explosive or other dangerous gases.<br />
8.3.3 Confined Spaces<br />
A. Work in confined spaces shall be completed in conformity with Sections 8.1.1 and<br />
8.1.2.A;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
96 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
B. Design-Builder shall perform confined space operations under the immediate<br />
supervision of a competent Person as defined in CCR Title 8 who is fully familiar with the<br />
requirements for safe entry, egress, ventilation, and air monitoring procedures and<br />
capable of enforcing strict compliance;<br />
C. Design-Builder shall include confined space permitting system in Design-Builder’s IIPP<br />
as specified in Section 8.3.8; and<br />
D. Air samples shall be taken before any entry into the confined space and continuously<br />
throughout the Work period.<br />
8.3.4 Crane Operations<br />
A. All crane operators shall be licensed by the authority having jurisdiction for the<br />
equipment type to be operated and copies of said licenses shall be submitted to the<br />
Authority;<br />
B. All crane operations where the load is beyond the direct view of the operator shall be<br />
observed by a signal Person who can directly observe the load and be observed by the<br />
operator. Design-Builder shall stop load movement in the event the signal Person is<br />
unable to observe the load or fails to continuously observe the load and signal the<br />
operator;<br />
C. Prior to operating cranes on the Site, all crane operators shall have successfully<br />
completed testing that verifies the crane operator's ability to read and understand the<br />
load chart for the equipment to be operated. This testing may be performed by an<br />
independent certifying agency or a qualified member of Design-Builder’s supervisory<br />
staff who is acceptable to the Authority, has a minimum of five years heavy civil<br />
construction experience, and can satisfactorily demonstrate the ability to read and<br />
understand load charts and rigging tables to the Authority when requested, without prior<br />
notice. Written records of this testing shall be maintained on the Site and made<br />
available to the Authority for review without prior notice.<br />
Re-certification is required for any crane involved in an incident involving upset,<br />
overloading, side pulling, shock loading, or support failure. Re-certification and written<br />
acceptance by the manufacturer is also required for any modification to a crane. Crane<br />
acceptance and certification records shall be made available for review by the Authority<br />
without prior notice.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
97 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Any re-certification of a crane required for compliance with this Section 8.3.4 shall be<br />
considered within the original scope of this Contract and shall not form the basis of a<br />
Change Order or Claim for cost or delay; and<br />
D. Mobile crane lifts of over 50 tons, exceeding 80% of the crane’s capacity, involving more<br />
than one crane, lifting a non-rigid object, or lifting over active work areas or public<br />
property shall be considered “critical lifts” and require approval from the Safety Manager.<br />
A critical lift plan shall be submitted to the Authority for review prior to the lift. Such plan<br />
shall include, at a minimum, the following:<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Exact size and weight of the load to be lifted and all crane and rigging<br />
components which add to the weight. The manufacturer’s maximum load<br />
limits for the entire range of the lift, as listed in the load charts, shall also be<br />
specified;<br />
2. Lift geometry and procedures, including the crane position, height of the lift,<br />
load radius, and the boom length and angle, for the entire range of the lift;<br />
3. Designation and qualifications of the crane operator, lift supervisor, and<br />
rigger;<br />
4. Rigging plan that shows the lift points and describes rigging procedures and<br />
hardware requirements;<br />
5. Ground conditions, outrigger requirements, and if necessary, design of mats<br />
necessary to achieve a level, stable foundation of sufficient bearing capacity<br />
for the lift;<br />
6. Environmental conditions under which the lift operations are to be stopped;<br />
and<br />
7. Coordination and communication requirements for the lift.<br />
8.3.5 Protection from Falls<br />
Design-Builder shall maintain the Site in an organized and clean manner, as accepted by the<br />
Authority, to reduce the potential for slips, trips, and falls.<br />
8.3.6 Excavations<br />
A. All excavation activities shall comply with Sections 8.1.1 and 8.1.2.A; and<br />
98 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
B. All excavation operations shall be under the immediate supervision of a competent<br />
Person, as defined in CCR Title 8, who is fully familiar with the requirements for safe<br />
excavation procedures and capable of enforcing strict compliance. The support system<br />
shall be designed by a civil engineer, licensed in the State of California and the support<br />
system plan shall be available for review by the Authority without prior notice.<br />
8.3.7 Lock-out/Tag-out Procedures<br />
Design-Builder shall include written lock out/tag out procedures in Design-Builder’s injury and<br />
illness prevention program (IIPP).<br />
8.3.8 Injury and Illness Prevention Program (IIPP) Plan<br />
Design-Builder shall submit a site-specific IIPP plan(s) to the Authority for review and approval.<br />
The plan(s) is a working document and shall be revised and resubmitted as conditions warrant.<br />
Design-Builder’s IIPP plan shall include the following:<br />
A. The requirements specified in CCR Title 8 Sections §3203 and §1509;<br />
B. The requirements specified in CCR Title 8 Section 5192 Hazardous Waste Operations and<br />
Emergency Response, with respect to the handling of Hazardous Substances and<br />
mandated specialty training and health screening;<br />
C. Key personnel and Safety representative responsibilities, organization chart, Safety<br />
committee descriptions, Subcontractor policies, etc;<br />
D. Training procedures for personnel who are subject to exposure of construction hazards.<br />
Design-Builder shall provide such training prior to construction and shall provide<br />
necessary yearly refresher training as required by Sections 8.1.1 and 8.1.2.A;<br />
E. An emergency action plan, including coordination with local emergency services, first<br />
aid, etc;<br />
F. A confined space program including a permitting system, training, non-entry rescue, etc;<br />
G. Personal protection mitigations including personal protective equipment (PPE), hearing<br />
conservation, respiratory protection, fall protection (scaffolds), heat illness, fire<br />
protection, etc;<br />
H. Alcohol and drug-free construction workplace policy, including drug testing protocol for<br />
pre-employment, random, post incident, and Subcontractor participation;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
99 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
I. <strong>General</strong> construction safety including crane certifications, trenching/excavation,<br />
demolition, electrical, welding/cutting, etc;<br />
J. Traffic control procedures, including flagging, road closure policies, typical warning<br />
devices, traffic circulation, etc;<br />
K. Earthquake safety awareness program and procedures. These procedures shall include<br />
instruction in case of falsework collapses, major earth distortion, Utility breaks and<br />
identify gathering locations and contacts for work crews to obtain further directions from<br />
Design-Builder’s safety officer and the Authority;<br />
L. Incident/accident reporting procedures including site control, notifications, investigating,<br />
etc;<br />
M. Appendices including forms addressing hazard reporting, safety inspections, non-<br />
compliance violations, safety action plans, etc;<br />
N. Lock-out/tag-out procedures; and<br />
O. Security loss prevention program plan, including measures of protecting property (i.e.,<br />
physical barriers, warning signage, office/facility security and illumination.<br />
8.3.9 Housekeeping<br />
The Site shall be maintained in a clean and neat manner. All scrap, trash, and other refuse shall be<br />
placed in containers prior to the end of each work shift. Trash containers shall be scheduled for<br />
regular emptying or replacement. Immediate emptying or replacement shall be ordered by Design-<br />
Builder in the event a container is filled prior to the scheduled emptying or replacement.<br />
8.4 Design-Builder Responsibility<br />
Any time a Cal-OSHA or Fed-OSHA representative seeks access to the Site, Design-Builder's<br />
Safety representative on duty shall immediately contact the designated Authority Safety<br />
representative to inform and seek direction on how to proceed. It is understood that the Site<br />
belongs to the Authority and Design-Builder has no authority to prohibit access to Cal-OSHA/Fed-<br />
OSHA representatives. If Design-Builder's Safety representative fails to meet any of the duties and<br />
obligations described above, the individual may be removed immediately by the Authority.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
END OF SECTION<br />
100 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
9.0 REVIEW, VERIFICATION AND ACCEPTANCE<br />
Throughout the duration of the Contract, Design-Builder shall demonstrate and verify that the<br />
design, procurement, fabrication, installation, construction, commissioning and overall<br />
implementation of the Project and performance of the Work comply with all of the requirements of<br />
the Contract Documents and in accordance with the approved QAQCP. Design-Builder shall<br />
determine compliance using one (or more) methods including: (1) analysis, (2) inspection, and (3)<br />
testing.<br />
A. Analysis shall include the review of design data, test data, or other data describing the<br />
design and/or functions of the Work. Such analysis shall include the review of<br />
engineering drawings, engineering reports, and test reports, including identification of<br />
compliance with national standards and/or applicable Governmental Rules. Analysis<br />
shall be the method of verification used when rigorous testing may be impossible or<br />
impractical because of the required environmental or other conditions needed to conduct<br />
a realistic test.<br />
B. Inspection shall include the examination of specific physical elements of the Project.<br />
Inspection shall include the taking of specific static measurements (such as length,<br />
width, or height) where simple measuring devices are used. In cases where physical<br />
inspection of specific assemblies or components is not possible because of constraints<br />
imposed by manufacturing or construction, inspection shall be conducted by the review<br />
of reports during fabrication, assembly, and installation, and of previously conducted<br />
inspections. Inspections may be conducted in combination with other verification<br />
methods, such as test, where visual observation as well as the taking of measurement<br />
data is necessary to verify a particular requirement.<br />
C. Testing shall include the systematic evaluation and documentation of the performance of<br />
the elevators, power distribution, lighting, HVAC, sump pump, fire suppression systems,<br />
and any other equipment. Performance parameters shall be measured using specific<br />
instrumentation and recording devices appropriate to that parameter, or the employment<br />
of testing laboratories. All tests shall be conducted using previously developed and<br />
Authority approved procedures, which shall be followed in a step-by-step fashion. Test<br />
data and results shall be formally recorded and evaluated for conformity to the<br />
requirements of the Specifications and test procedures.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
101 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Factory testing shall include the in-plant testing of assemblies and subsystems<br />
prior to shipment to the Site to check and establish proper individual operation;<br />
2. Construction testing shall include the testing of construction materials, samples<br />
of materials and sub-construction assemblies as construction proceeds at the<br />
Site to check and establish that construction plans and Specifications are met;<br />
and<br />
3. Local field acceptance testing shall be performed on the Site to check and<br />
establish operation of the equipment in accordance with the Contract<br />
Documents.<br />
Design-Builder's internal verification shall be accomplished by Design-Builder's inspections, factory<br />
testing, and local field acceptance testing. After the elevators, power distribution, lighting, HVAC,<br />
fire suppression systems, and any other equipment have been completely tested by Design-Builder,<br />
the Parking Facilities shall be made available to the Authority for follow-on contractor(s) and<br />
integration testing. Design-Builder shall provide support on an as-needed basis during the Project<br />
systems integration testing if problems are encountered with the operation of Design-Builder’s<br />
equipment due to interface anomalies.<br />
As provided in the sections that follow, the Authority shall have inspection and audit rights<br />
throughout the supply, manufacture, factory testing, construction, installation, on-site testing, and<br />
acceptance procedures.<br />
9.1 Facilities Tests and Inspection<br />
It is Design-Builder's responsibility to ensure that materials and workmanship are in accordance<br />
with the Contract Documents.<br />
Design-Builder shall develop a construction inspection procedure detailing the inspection<br />
requirements and reporting methods. The procedure shall require a daily inspection report to be<br />
completed for every day on which work is performed.<br />
Design-Builder shall develop a procedure detailing the construction monitoring requirements. The<br />
procedure shall include the following:<br />
A. Report number, period covered, and title;<br />
B. Scheduled status;<br />
C. Percentage complete;<br />
102 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
D. Weather;<br />
E. Manpower and equipment;<br />
F. Construction status;<br />
G. Visitors;<br />
H. Problems;<br />
I. Summary of inspector reports; and<br />
J. Log of test results.<br />
9.1.1 Power Distribution and Lighting Systems Equipment<br />
Design-Builder shall at a minimum perform local field acceptance testing, as follows:<br />
A. Inspect each equipment installation against installation drawings and instructions. All<br />
equipment shall be energized and be operational;<br />
B. Make continuity checks of all interconnecting wiring and check the phase of any three-<br />
phase power connections;<br />
C. Check all wire and cable terminations for integrity;<br />
D. Measure and record conductor-to-ground resistance of all power cables;<br />
E. Verify that all circuit breakers de-energize the intended circuit; and<br />
F. Perform all tests necessary to ensure the proper functioning of the uninterruptible power<br />
supply (UPS) systems provided. With incoming power turned off, the UPS systems shall<br />
be tested to ensure continuous power at the rated voltage level for the rated time period.<br />
Additionally, the interfaces for all remote status and alarm reporting shall be verified.<br />
9.1.2 Corrosion Control<br />
As a minimum, Design-Builder shall perform local field acceptance tests to verify the integrity of<br />
corrosion protection measures and installations.<br />
9.1.3 Elevators<br />
Testing of the elevators shall be as follows:<br />
A. Factory acceptance testing of the elevator equipment shall be performed as<br />
recommended by the elevator manufacturer; and<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
103 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
B. Local field acceptance testing shall demonstrate complete, proper elevator operation,<br />
controls, and indications. Additionally, the interfaces for all remote controls and remote<br />
status and alarm reporting shall be verified.<br />
9.1.4 Mechanical Equipment<br />
Local field acceptance testing shall be performed on HVAC, fire suppression, sump pump, and any<br />
other equipment to demonstrate proper operation, controls, and indications. Additionally, the<br />
interfaces for all remote status and alarm reporting shall be verified.<br />
9.2 Verification and Acceptance<br />
This Section 9.2 describes the methods and procedures by which the Work will be verified by<br />
Design-Builder as complying with the requirements of the Contract, and thereafter accepted by the<br />
Authority.<br />
Design-Builder shall thoroughly verify each aspect of the Project and equipment prior to conditional<br />
acceptance and Substantial Completion, upon which final acceptance activities shall commence;<br />
such prior verification shall be accomplished during the design review, product qualification testing,<br />
factory testing, local field acceptance testing and inspections.<br />
Design-Builder shall advise the Authority when the Work is ready for final acceptance activities.<br />
This shall not occur until Design-Builder has completed all of the inspection and testing activities,<br />
and corrected any deficiencies and failures that are not acceptable as a Punch List item. Design-<br />
Builder shall provide all resources necessary for, and carry out all of the compliance verification and<br />
conditional acceptance activities defined herein. The Authority will witness and review the results of<br />
these activities. Compliance verification and conditional acceptance will be accomplished on the<br />
basis of the Authority's review and acceptance. Conditional acceptance is also contingent upon<br />
successful completion and Authority approval of Design-Builder’s safety certification specification<br />
conformance checklists of final design and construction, as specified in the Safety and Security<br />
Certification Plan (SSCP).<br />
9.2.1 Verification and Acceptance Procedures<br />
Documentation associated with the three methods of compliance verification and conditional<br />
acceptance are indicated and defined as follows:<br />
A. Analysis - Design-Builder shall submit analysis information and data, as defined in<br />
Section 9.0 (A), in a manner which does not impede the verification and acceptance<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
104 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
process. Analyses provided by Design-Builder during the design review process may, at<br />
the sole discretion of the Authority, be used for verification and acceptance purposes. At<br />
the time of the design reviews, the Authority will examine the design review material and,<br />
in its sole discretion determine its applicability for any verification and acceptance<br />
purposes;<br />
B. Inspection - In cases where inspections as defined in Section 9.0 (B) are to serve as the<br />
basis for compliance verification, Design-Builder shall prepare detailed inspection<br />
procedures and submit these to the Authority for review not later than thirty (30) days<br />
prior to the scheduled date of the inspection. The inspection procedures shall identify all<br />
applicable requirements of Section 9.1 and each section of Volume 3, Document 2-<br />
Performance Specifications for which inspection is mandated to demonstrate<br />
compliance.<br />
Design-Builder shall conduct each inspection in accordance with the inspection<br />
procedures reviewed by the Authority; no inspection shall be performed prior to obtaining<br />
the Authority's review and approval of the applicable inspection procedures. The results<br />
shall be documented in an inspection report clearly showing that the inspection passed<br />
or failed based on the pass/fail criteria shown in the procedure. The Authority shall be<br />
notified of and shall have the right to witness any inspection conducted for compliance<br />
verification and acceptance purposes; and<br />
C. Test - Design-Builder shall prepare detailed procedures for all tests, as defined in<br />
Section 9.0 (C) and submit these to the Authority for review and acceptance not later<br />
than thirty (30) days prior to the scheduled date of the test. The test procedures shall<br />
identify all applicable requirements set forth in Section 9.1 and each section of Volume<br />
3, Document 2- Performance Specifications for which test is mandated to demonstrate<br />
compliance.<br />
Design-Builder shall conduct each test in accordance with the test procedure reviewed<br />
and approved by the Authority and no test shall be performed prior to obtaining the<br />
Authority's approval of the applicable test procedures. Design-Builder shall document<br />
the results in a suitable test report containing test data in an easily interpretable form<br />
and clearly showing that the test passed or failed based on the pass/fail criteria shown in<br />
the test procedure. The Authority shall be notified of and shall have the right to witness<br />
any test conducted for compliance verification and acceptance purposes.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
105 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
9.2.2 Acceptance<br />
At its discretion, and upon written request from Design-Builder, the Authority may elect to perform<br />
in-progress inspections on selected portions of the Work. At that time, a Punch List of any items to<br />
be completed or corrected shall be prepared by Design-Builder. This inspection shall not be<br />
construed as the pre-final inspection. Once the Work is nearing Substantial Completion, as<br />
determined by Design-Builder, Design-Builder shall request a pre-final inspection. If this inspection<br />
is satisfactory to the Authority, a Punch List of any items to be completed or corrected shall be<br />
prepared by Design-Builder. After completing the Punch List, Design-Builder shall submit the<br />
Punch List to the Authority, as described in Section 9.3. If satisfactory to the Authority, the Authority<br />
will conditionally accept the Work.<br />
Among other requirements, the Certificate of Substantial Completion, however, shall not be issued<br />
until all conditional acceptance activities are successfully completed. Until Substantial Completion,<br />
Design-Builder shall retain the responsibility of maintaining the Parking Facilities, and the<br />
equipment contained therein, in accordance with the manufacturer’s recommended preventive<br />
maintenance procedures and schedules.<br />
9.2.3 Test/Inspection Acceptance Activities<br />
The Authority has developed a standard format which shall be used by Design-Builder to prepare<br />
detailed acceptance inspection test procedures for each activity.<br />
A. Title: Title of acceptance activity including its identification code;<br />
B. Reference contract section: The section number and title of the Contract provision,<br />
which is addressed by the acceptance activity;<br />
C. Reference Design-Builder specification conformance checklist item(s): The item number<br />
and title from the applicable supplier specification conformance checklist which is<br />
addressed by the acceptance activity;<br />
D. Prerequisite acceptance activities: The acceptance activity categories which must be<br />
successfully completed prior to conducting this activity;<br />
E. Objectives: The specific intent of the acceptance activity regarding the referenced<br />
section of the Contract Documents;<br />
F. Sample size: The number of units (e.g., facilities) required to be used in the acceptance<br />
activity or the specific area involved;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
106 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
G. Environmental requirements: Any specific environmental conditions required in order for<br />
the acceptance activity to demonstrate conformance with the referenced technical<br />
requirement;<br />
H. Equipment/facility requirements: Any test equipment or special facility needs of the<br />
acceptance activity;<br />
I. Personnel/skill requirements: The number of Design-Builder personnel required to<br />
perform the acceptance activity as well as the skill levels of the individuals;<br />
J. Estimated time requirement: The period of time required to conduct each acceptance<br />
activity. If the activity is conducted on each of several units (e.g., facilities), the time<br />
required for each unit shall be given;<br />
K. Data to be recorded: The specific data which is necessary to show compliance with the<br />
referenced Contract requirement shall be listed as well as the means by which it is to be<br />
obtained. The specific method of documentation shall also be identified;<br />
L. Pass/fail criteria: The specific limits within which the data identified in Item K must fall in<br />
order for the activity to be acceptable;<br />
M. Procedures: The detailed, step by step, description of the acceptance activity. This will<br />
provide specific directions to the person(s) conducting the activity including operating<br />
instructions for test equipment and when to record data;<br />
N. Comments: Narrative description of any occurrences or events that may have an impact<br />
on personnel safety, equipment integrity or the validity of the data; and<br />
O. Conclusions: The results of the activity including a formal test report statement by<br />
Design-Builder as to whether the data satisfied the Pass/Fail criteria.<br />
Design-Builder will develop the details of format elements A through M. The detailed description of<br />
each acceptance activity per CDRL must be submitted to the Authority not less than 120 days prior<br />
to its being conducted by Design-Builder.<br />
Format elements N and O will be completed during the actual acceptance activity. Both Design-<br />
Builder's personnel conducting the activity and the Authority's observer will be permitted to enter<br />
comments in item N.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
107 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
9.2.4 Schedule<br />
Final Acceptance activities are scheduled to be conducted after completion of local field acceptance<br />
testing and prior to Final Acceptance. While the Authority has established the general sequence in<br />
which these activities are to occur, Design-Builder shall develop the specific acceptance schedule<br />
and submit it to the Authority for its review and approval.<br />
Design-Builder may propose to conduct additional categories of acceptance activities prior to the<br />
Final Acceptance, but they shall not preclude, or be considered in lieu of, the activities required by<br />
the Authority.<br />
9.2.5 Authority Involvement<br />
9.2.5.1 Procedure<br />
The following procedures shall be followed to permit Authority involvement in accepting the<br />
procedures, and in witnessing and tracking the status of all acceptance activities.<br />
A. Design-Builder shall develop the required acceptance inspection/test procedures for<br />
each of the activities in accordance with the required format of Section 9.2.3 and submit<br />
them to the Authority for approval. Simultaneously, Design-Builder shall submit the<br />
acceptance schedule for Authority approval.<br />
The Authority will review and approve the acceptance inspection/test procedures for<br />
each activity submitted by Design-Builder. Submittals will be evaluated for conformance<br />
with the Contract Documents;<br />
B. The Authority will review the acceptance schedule and give Design-Builder written<br />
notification when it approves the proposed schedule per CDRL. The Authority and<br />
Design-Builder will work to resolve any differences and concur on a final schedule;<br />
C. Design-Builder shall revise its acceptance inspection/test procedures in accordance with<br />
the Authority's review of (B) above and resubmit them at least 60 days prior to the<br />
beginning of acceptance activities;<br />
D. Each acceptance activity shall be conducted by Design-Builder and witnessed by the<br />
Authority in accordance with the agreed upon procedure and schedule. As required in<br />
Section 9.4, briefings will be held before and after these activities and activity reports<br />
shall be submitted to the Authority in accordance with the CDRL; and<br />
E. The Authority will give Design-Builder written notification whether the submitted activity<br />
report is acceptable. The Authority will give Design-Builder specific reasons for not<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
108 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
9.2.5.2 Monitoring<br />
accepting an activity report as well as providing specific requirements for making the<br />
activity acceptable.<br />
The Authority will monitor the status of the documentation and progress of each activity relative to<br />
the procedure described above. The status of the acceptance activities will be monitored and<br />
discussed at progress meetings.<br />
The active status tracking of each activity will start six months prior to the scheduled beginning of<br />
acceptance activities or with the first significant submittal of acceptance inspection/test procedures<br />
by Design-Builder, whichever occurs first. These activities will be continuously tracked through the<br />
successful completion of the acceptance activities.<br />
9.3 Punch Lists<br />
During the course of testing and Acceptance activities, formal Punch Lists shall be developed that<br />
identify “clean-up” work items which may be compiled while acceptance activities continue. The<br />
Authority reserves the right to identify items for the Punch Lists up to Substantial Completion.<br />
Punch List development constitutes milestones in the acceptance process. Punch List content shall<br />
require Authority approval to achieve the acceptance milestones. Once an item is established as a<br />
formal Punch List item, Design-Builder shall demonstrate to the Authority that the item has been<br />
satisfactorily addressed. The status of each listed item shall be tracked on the Punch List through<br />
completion and demonstration.<br />
9.4 Verification, Notifications, Briefings, and Documentation<br />
Design-Builder shall provide no less than seven days prior notice to the Authority of any compliance<br />
verification and/or acceptance activity. The Authority shall have the right to witness each test,<br />
inspection, and demonstration.<br />
A briefing shall be held prior to each activity (analysis, inspect, test, demonstration). At this<br />
meeting, Design-Builder shall distribute copies of the approved written procedures and shall discuss<br />
principle aspects of the activity. Following each activity, a briefing shall be held to discuss the<br />
results of the activity and obtain agreement upon whether it was successful or if there is a need for<br />
additional work. Where activities are sequentially scheduled on the same day, these briefings may<br />
be consolidated into one briefing at the start of the day and one debriefing at the end of the day.<br />
Reports shall be submitted to the Authority for review and acceptance for each activity in<br />
accordance with the CDRL. These reports shall include the procedures, prevailing weather,<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
109 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
unusual conditions or events, complete data, and pass/fail disposition. The reports shall note any<br />
failures that occurred during the activity, whether or not they related to the equipment under test.<br />
The equipment tested shall be clearly identified. Proof of calibration of all test equipment used and<br />
traceability to primary calibration standards shall be documented. Subcontractor reports shall be<br />
accepted by Design-Builder prior to submittal.<br />
If corrections are necessary during any activity, the procedure affected shall be repeated at no<br />
additional cost to the Authority.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
END OF SECTION<br />
110 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
10.0 CONTRACT DATA REQUIREMENTS LIST (CDRL)<br />
10.1 Definitions and Use<br />
The Contract Data <strong>Requirements</strong> List (CDRL) located in Appendix B identifies certain items that are<br />
contractually required to be submitted to and, as applicable, approved by the Authority and the<br />
required delivery due dates. The CDRL does not include financial reports, invoices, and other<br />
information required for Contract administration. All submittals, including any additional submittals<br />
identified during the Project as discussed below, must follow these requirements and shall be<br />
subject to the review and, as applicable, the approval of the Authority and applicable third parties.<br />
10.2 Master List of Submittals<br />
Design-Builder shall be responsible for updating and maintaining the CDRL which includes verifying<br />
and identifying additional submittal requirements and determining the date on which each submittal<br />
is required in conformity with schedules specified in Section 4.0. Within 30 days after issuance of<br />
Notice to Proceed, Design-Builder shall furnish a master list of submittals required by the Contract<br />
Documents, with corresponding submittal dates which match milestones listed in the Baseline<br />
Schedule or Current Project Schedule, as applicable, and allow for review and approval, as<br />
applicable, by the Authority and applicable third parties. Design-Builder shall submit monthly<br />
updates to the master list of submittals to the Authority for review and approval.<br />
10.3 Format <strong>Requirements</strong> for Submittals<br />
All submittals shall be prepared with a title block and action block on the front page or cover,<br />
substantially as follows:<br />
A. Title Block—show the following information:<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Date and revision dates;<br />
2. The Authority Project title and number;<br />
3. The names of Design-Builder, Subcontractor, supplier, manufacturer, and<br />
when applicable, the seal and signature of a registered engineer for the<br />
involved discipline; and<br />
4. Subject identification by Contract reference; and<br />
111 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
B. Action block—Include a blank space, three inches by four inches, in the lower right<br />
corner, just above the title block, in which the Authority may indicate the action taken.<br />
Additionally, all submittals shall be transmitted as enclosures to a Contract transmittal<br />
form containing the following information:<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Design-Builder’s name, address and telephone number;<br />
2. Submittal number and date;<br />
3. Project title and number;<br />
4. Supplier’s, manufacturer’s or Subcontractor’s name, address and telephone<br />
number, as applicable;<br />
5. Subject identification including Contract reference;<br />
6. Identification of any deviations from the Contract Documents; and<br />
7. Engineer of Record’s stamp and signature.<br />
Each Design-Builder transmittal form shall be limited to one transmittal and shall fully describe the<br />
transmittal as outlined below. Design-Builder shall submit hardcopies in accordance with Appendix<br />
B- Contract Data <strong>Requirements</strong> List (CDRL) and an electronic PDF copy of all correspondence and<br />
data submittals.<br />
All submittals shall use software compatible with the software used by the Authority. Drawings shall<br />
comply with the Authority and applicable third party drafting requirements.<br />
10.4 Identification <strong>Requirements</strong><br />
The following identification requirements are in addition to Design-Builder’s own identification, such<br />
as drawing or document numbers. Each submittal item of the CDRL is identified by a numeric<br />
designation according to location of the requirement in the Contract. Each item may require one or<br />
more submittals and each submittal may be subject to revision from time to time. Identification of<br />
CDRL and submittal numbers shall be provided by Design-Builder as follows:<br />
A. CDRL numbering corresponds to the volume, document, and section number pertaining<br />
to the location of the requirement in the Contract and shall adhere to the following<br />
spacing convention: X.Y.ZZ.<br />
112 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Example: <strong>General</strong> project management requirements are found in Volume 3,<br />
Document 1, Section 1. The CDRL number for all project management<br />
submittals would therefore be 3.1.01.<br />
B. Each discrete submittal under a CDRL item will be identified based on the location of its<br />
10.5 Submittals<br />
requirement designation within the Contract. Specifically, submittal numbers shall<br />
correspond to the volume, document, section, subsection, and item number under which<br />
it is specified. Subsection and item numbers may contain letters or numbers. The<br />
number is then followed by a sequential unique numerical suffix beginning with “01”,<br />
which identifies the submittal as distinct from all others under that item. Submittal<br />
numbers shall adhere to the following spacing convention X.Y.ZZ.AA.BB.CC.<br />
1. Example: The Project Management Plan submittal requirement is designated<br />
in Volume 3, Document 1, Section 1, Subsection 2. As there are no further<br />
items under Subsection 2, its item number is “00”. Further, this is the first<br />
submittal requirement under this CDRL number, thus it will be assigned<br />
unique number “01”. The submittal number corresponding to the Project<br />
Management Plan would therefore be 3.1.01.02.00.01.<br />
Design-Builder shall include the following submittals in the master list of submittals:<br />
A. Design Documents – Design drawings, reports, and Specifications as defined in Section<br />
2.0 Design Management;<br />
B. As-built drawings and current status documents – Refer to Section 7.0;<br />
C. Shop Drawings – Fabrication or layout drawings required to supplement construction<br />
drawings or individual specification sections for permanent incorporation in the Work;<br />
D. Working Drawings – Design-Builder’s plan for temporary equipment or structures such<br />
as decking, temporary bulkheads, support of excavation, support of Utilities, ground<br />
water control, and forming and falsework; and for such other Work as may be required<br />
for construction but do not become an integral part of permanent Work. Submit signed<br />
and stamped Working Drawings, and associated calculations for temporary Work which<br />
will not become a part of permanent structures included in this Contract.<br />
1. Provide cross-reference to construction drawing numbers. Use a Working<br />
Document sheet with a maximum size of 22 inches by 34 inches;<br />
113 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
2. Have Working Drawings prepared, stamped and signed by an engineer of the<br />
involved discipline, currently registered as a professional engineer in the<br />
State of California;<br />
3. Verify field measurements and coordinate with pertinent contract drawings<br />
from other contracts, where applicable;<br />
4. Do not begin the Work for which Working Drawings and associated<br />
calculations are required until drawings and calculations have been reviewed<br />
by Authority; the Authority’s exceptions, if any, have been addressed, and<br />
submittals have been returned to Authority with the required Design-Builder’s<br />
and Designer of Record’s approval stamps and signatures;<br />
5. Distribute copies of Working Drawings and calculations after the Authority's<br />
review and, if required, its approval; and<br />
6. Provide all information required by the Contract Data Requirement List<br />
(CDRL), included as Appendix B;<br />
E. Engineering calculations – Signed and stamped by the Designer of Record, an engineer<br />
registered in the State of California for the involved discipline. Have calculations,<br />
required by Specifications sections, prepared on 8½” x 11” sheets. When calculations<br />
accompany drawings in a submittal, the body of the calculations must contain cross-<br />
referencing to the individual drawing to which the page of the calculations pertain;<br />
F. Permits, third party inspection reports, third party sign-offs – Documentation that<br />
provides verification of third party permission to work and approval of the Work during<br />
performance of the Work and at Project completion;<br />
G. Certifications and documentation - Certificates or certified test results that demonstrate<br />
proof of compliance with Specifications for products, materials, equipment, systems, and<br />
qualifications of personnel, manufacturers, fabricators and installers. Documentation<br />
required by the Contract Documents including miscellaneous items such as delivery<br />
tickets, batch tickets and bills of materials;<br />
H. Inspection and test procedures/reports - Test procedures for review and, if required,<br />
approval by the Authority before commencement of testing. Provide test reports in the<br />
accepted format for review by the Authority;<br />
114 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
I. Manufacturer/product data – Standard schematics and drawings, stamped calculations<br />
and data, and product data:<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
1. Modify manufacturers' standard schematic drawings to delete information<br />
which is not applicable to the Contract. Supplement standard information<br />
with additional information applicable to this Contract;<br />
2. Modify manufacturers' standard catalog cuts, brochures, diagrams,<br />
schedules, performance charts, illustrations, calculations, and other<br />
descriptive data to delete information that is not applicable to the Contract.<br />
Failure to comply with this requirement will result in rejection of the submittal.<br />
Indicate dimensions, clearances, performance characteristics, capacities,<br />
wiring and piping diagrams, controls, and other information as required;<br />
3. Modify manufacturer's printed installation, erection, application and placing<br />
instructions to delete information that is not applicable to the Contract;<br />
4. Include appropriate information as required herein and the Contract<br />
Documents; and<br />
5. Submit certificates of compliance not later than 30 days before products are<br />
installed. Have copy of certificate accompany the product for which the<br />
certificate is prepared. Include on the certificate:<br />
a. Affirmation that the product complies with respective requirements<br />
indicated; and<br />
b. Submittal date, Design-Builder's name and address, Contract title<br />
and number, product represented and its location in the Contract,<br />
producer's name, product trade name and catalog number, place<br />
of product origin, test date, testing organization's name and<br />
address, and quantity of the product furnished;<br />
J. Permanent Materials Data, Mock-ups, and Samples:<br />
1. Submit samples of sizes and quantities to clearly illustrate full color range and<br />
functional characteristics of products and materials, including attachment<br />
devices. Indicate country of origin;<br />
115 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
2. Erect field samples and mock-ups at the Site as specified in Contract<br />
Documents, and as may be necessitated by Design-Builder, submitting<br />
substitutions, at locations acceptable to the Authority;<br />
3. Include appropriate information and have product data accompany samples;<br />
and<br />
4. Right is reserved to require submission of samples or Site mock-ups of any<br />
material whether or not such material has been previously approved for use<br />
elsewhere on the Project;<br />
K. Operation and Maintenance Manuals – Operations and maintenance manuals as<br />
specified in Section 11.3;<br />
L. Construction progress photographs – Photographs documenting construction progress<br />
as specified in Section 4.12;<br />
M. Project schedules – Refer to Section 4.0 of these <strong>General</strong> <strong>Requirements</strong> for submittal<br />
requirements;<br />
N. Design-Builder shall send submittals directly to, resolve all comments directly with, and<br />
obtain approvals directly from third parties, when required, with the exception of <strong>Metro</strong>.<br />
The Authority will distribute submittals to <strong>Metro</strong> and provide consolidated (Authority and<br />
<strong>Metro</strong>) comments to Design-Builder. Design-Builder shall provide a copy to the Authority<br />
of any submittals sent directly to third parties; and<br />
O. Design-Builder shall submit the interface management plan required in Section 2.1 that<br />
identifies all interfaces associated with the Project and document how each interface will<br />
be accommodated during the Contract.<br />
10.6 Supplemental Submittals<br />
Supplemental submittals initiated by Design-Builder for consideration of corrective procedures shall<br />
contain sufficient data for review. Supplemental submittals shall be made in the same manner as<br />
initial submittals.<br />
10.7 Design-Builder Responsibilities<br />
Design-Builder shall have the following responsibilities regarding all submittals:<br />
116 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
A. Coordinate each submittal with the requirements of the Work; place particular emphasis<br />
upon ensuring that each submittal of one trade is compatible with other submittals of that<br />
trade and submittals of other trades;<br />
B. Design-Builder’s responsibility for errors and omissions in submittals and associated<br />
calculations is not relieved by the Authority’s review, correction and/or approval of<br />
submittals;<br />
C. Design-Builder’s liability to the Authority in case of deviations in the submittals from the<br />
requirements of the Contract Documents is not relieved by the Authority’s review and<br />
approval of submittals containing deviations unless the Authority expressly approves the<br />
deviation through the issuance of a Change Order;<br />
D. Design-Builder shall maintain a file of all Approved/Approved as Noted/Approved for<br />
Construction submittal documents at the Site;<br />
E. Prior to submitting any material to the Authority for its review and/or approval, Design-<br />
Builder shall review all of its submittals including design drawings and data, and stamp<br />
and sign them as reviewed and approved by Design-Builder, to demonstrate to the<br />
Authority that Design-Builder has performed an internal review and checked the<br />
submittal as part of the design control procedures of the quality control/quality assurance<br />
plan (QCQAP);<br />
F. Make submissions sufficiently in advance of the Work so that the Authority review may<br />
be completed in accordance with the CDRL; and<br />
G. Allow a minimum review cycle pursuant to the CDRL for review of each submittal by the<br />
Authority and other agencies.<br />
The CDRL is provided in Attachment B as an aid to allow Design-Builder for planning and<br />
scheduling of the development of many required submittals. In those cases where the submittal<br />
delivery is at Design-Builder’s discretion, the delivery date column of the table for that submittal<br />
contains the acronym “DBC”, meaning determined by contractor. In all cases and for all CDRL<br />
submittals, the requirements of Section 4.6 apply, i.e., all CDRLs shall be included as separate<br />
activities in the Baseline Schedule or Current Project Schedule.<br />
10.8 Authority’s Review<br />
Review and/or Approval, Approval as Noted, or any other similar action by the Authority will not<br />
relieve Design-Builder from its responsibility for accuracy of submittals, for conformity of submittals<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
117 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
to requirements of the Contract Documents, for compatibility of described product with contiguous<br />
products and the rest of the facility, structure, Utility, etc., or for prosecution and completion of the<br />
Work in accordance with the Contract Documents. The Authority will withhold approval of<br />
submittals that depend on other submittals not yet submitted or not yet “Approved” or “Approved as<br />
Noted.”<br />
The Authority will review submittals for approval for general conformity with the Contract<br />
Documents and provide status of the submittals to Design-Builder, along with any associated<br />
comments if applicable. The Authority’s submittal status determinations shall have the following<br />
meanings:<br />
A. Approved shall mean that every illustration and description appears to conform to the<br />
respective requirements of the Contract Documents; fabrication, assembly, manufacture,<br />
installation, application, and erection of the illustrated and described product may<br />
proceed; the submittal is approved and need not be resubmitted (See also Volume 2-<br />
Design-Build Contract, Appendix 1- Abbreviations and Definitions);<br />
B. Approved as Noted shall mean that the submittal and its contents appear to conform to<br />
the respective requirements of the Contract Documents for that submittal after revisions<br />
are made to the areas noted in recognition of the reviewer’s comments. Submittals so<br />
marked need not be resubmitted unless otherwise indicated; fabrication, assembly,<br />
manufacture, installation, application, and erection of the illustrated and described<br />
product may proceed after the Authority’s comments are incorporated. Approved as<br />
Noted submittals sent back with request to resubmit for Authority approval shall be<br />
revised based upon Authority comments and submitted to the Authority as the<br />
appropriate revision number; fabrication, assembly, manufacture, installation,<br />
application, and erection of the illustrated and described product may not proceed until<br />
after the Authority has indicated no resubmission is required;<br />
C. Approved for Construction shall mean that every illustration and description appears to<br />
conform to the respective requirements of the Contract Documents; fabrication,<br />
assembly, manufacture, installation, application and erection of the illustrated and<br />
described product may proceed; the submittal is Approved for Construction and need not<br />
be resubmitted; and<br />
D. Rejected, Revise and Resubmit shall mean that the submittal is deficient to the degree<br />
the reviewer cannot correct the submittal with a reasonable degree of effort, has not<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
118 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
made a thorough review of the submittal, and/or the submittal needs revision and is to<br />
be corrected and resubmitted, within 30 days for review.<br />
Submittals requiring the Authority’s approval will receive said approval, approval as noted, approval<br />
for construction, or rejection. Submittals not requiring the Authority’s approval are For Record Only.<br />
For Record Only shall mean that the submittal was not reviewed for approval and was received for<br />
information only. The Authority may, however, use the submittal to verify or monitor Design-<br />
Builder’s Work and/or progress and may elect to provide comments. In the event that the Authority<br />
elects to provide comments to submittals not requiring approval, Design-Builder will receive the<br />
Authority’s comments within 30 days of receipt. For submittals not requiring approval, absence of<br />
the Authority’s comments shall not be the basis for Design-Builder’s lack of release or lack of any<br />
other action required to maintain the Baseline Schedule or Current Project Schedule. Review of a<br />
separate item will not constitute review of an assembly in which the item functions. Refer to the<br />
Contract Data Requirement List (CDRL) for the types of documents to be submitted For Record<br />
Only.<br />
Any comment by the Authority shall not relieve Design-Builder of the obligation to fully satisfy all of<br />
the requirements of the Contract Documents, or be interpreted as a directive to perform any work<br />
that is not already called for in the Contract Documents. By reviewing Design Documents and other<br />
submittal documents, the Authority shall not become a responsible party for any specific submittal<br />
or design; rather, the Authority’s review will be generally provided for the purpose of early<br />
identification of any submittals and designs which it believes are not in conformity with the<br />
requirements set forth in the Contract Documents.<br />
If a submittal is Rejected, no time that elapsed as part of the review of the Rejected submittal shall<br />
be credited against the time period to review the resubmitted submittal. The Authority may withhold<br />
payments for Rejected submittals.<br />
Changes to any Authority Approved or Approved as Noted submittals will not be permitted unless<br />
those changes have been approved, respectively, in writing by the Authority.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
END OF SECTION<br />
119 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
11.0 ADDITIONAL DESIGN-BUILDER REQUIREMENTS<br />
11.1 Mitigation Monitoring Program<br />
Design-Builder shall be responsible for the performance, compliance, monitoring, and reporting of<br />
environmental mitigation measures identified in Volume 4- Environmental <strong>Requirements</strong> that are<br />
applicable to the scope of work for the Project.<br />
Design-Builder shall provide to the Authority bi-annual updates of the status of all environmental<br />
mitigation measures and a final report documenting compliance with all environmental mitigation<br />
measures.<br />
11.2 Coordination and Conformity with Agreements<br />
11.2.1 Work Plans<br />
In order to assist the Authority with preparation and issuance of Work Orders to applicable third<br />
parties in accordance with their respective agreements, (as provided in Volume 5- Agreements or<br />
as may be entered into between the Authority and a third party), Design-Builder shall prepare and<br />
submit to the Authority, in accordance with the applicable schedule set forth in Volume 5-<br />
Agreements, annual work plans addressing activities that likely will require Work Orders for the<br />
applicable third party during its fiscal year. The work plans shall address all anticipated work to be<br />
performed by the third party within the terms of the third party agreement. If requested by the<br />
Authority, Design-Builder shall prepare and submit draft Work Orders to the Authority for approval,<br />
submittal to the third party, and execution.<br />
11.2.2 Information and Documentation<br />
Design-Builder shall supply all information and documentation as requested by Authority in order to<br />
assist Authority in developing reports, schedules, plans, and other documentation and materials<br />
contemplated by the third party agreements in connection with the Project.<br />
11.3 Operations and Maintenance Manuals<br />
Design-Builder shall provide operations and maintenance (O&M) manuals and data that<br />
comprehensively address elevators, UPS, HVAC, sump pump, fire suppression, and any other<br />
equipment assemblies and equipment delivered to the Project for the Parking Facilities.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
120 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
11.3.1 <strong>General</strong> Manual <strong>Requirements</strong><br />
Manuals shall be written in American English, to be understood by a high school graduate with two<br />
years of experience in a related field. The writing shall be concise and free of ambiguities.<br />
Manufacturers’ standard manuals may be acceptable, subject to Authority approval. Revisions to a<br />
manual shall be reflected in a revision index included in each manual and revised with each manual<br />
update.<br />
Content overview for manual:<br />
A. Theory of operation;<br />
B. Schematic diagrams;<br />
C. Preventive maintenance tasks and procedures, including recommended intervals;<br />
D. Test procedures;<br />
E. Safety precautions;<br />
F. Functional relationship with other equipment or systems; and<br />
G. Operational limits and restrictions.<br />
Detailed Manual Content:<br />
A. Index of volumes, in each volume of multiple volume systems;<br />
B. Index, in and for each volume. List and combine the literature, for each system, in<br />
sequence of operation;<br />
C. Names, addresses, and telephone numbers of contractor, suppliers, and installers;<br />
D. Names, addresses, and telephone numbers of manufacturers' nearest service<br />
representatives;<br />
E. Names, addresses, and telephone numbers of local parts vendor and service agency;<br />
F. Anticipated date Design-Builder releases responsibility for maintenance;<br />
G. Description of system and component parts;<br />
H. Pre-operation check or inspection list;<br />
I. Procedures for starting, operating, and stopping equipment;<br />
J. Post-operation check or shutdown list;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
121 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
K. Inspection and adjustment procedures;<br />
L. Emergency operating instructions;<br />
M. Accepted test data;<br />
N. Maintenance schedules and procedures;<br />
O. One copy of each wiring diagram;<br />
P. One copy of each piping diagram;<br />
Q. One copy of each duct diagram;<br />
R. One copy of each accepted shop drawing;<br />
S. Manufacturers' parts lists with catalog names, numbers, and illustrations;<br />
T. Exploded view of each piece of equipment with part designations;<br />
U. List of manufacturers' recommended spare parts, prices, and quantities for two years of<br />
operation;<br />
V. List of special tools and test equipment required for the operation, maintenance,<br />
adjustment, testing, and repair of the equipment, instruments and components;<br />
W. Scale and corrosion control procedures;<br />
X. Dismantling and reassembly instructions;<br />
Y. Troubleshooting and repair instructions;<br />
Z. Calibration procedures;<br />
AA. Ordering information; and<br />
BB. Transmittal memo and document table of contents to identify clearly if any<br />
warranties/guarantees and spare parts are included in the manual and the relevant page<br />
numbers on which they are noted.<br />
Hardcopy format of manuals: Design-Builder shall be responsible for submitting manuals<br />
consistent with <strong>Metro</strong>’s existing manuals. Operation and maintenance manual hardcopies shall<br />
typically be printed on 8½” x 11” paper and bound by 3-ring binders or equivalent approved by the<br />
Authority. Diagrams or illustrations can be printed on a maximum size of 11” x 17” and creased<br />
such that the title sheet is visible when folded. The manual covers (binders) shall be 30 to 50<br />
millimeters thick and shall be resistant to wear, oil, grease, and solvents.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
122 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
Electronic format of manuals: Design-Builder shall transfer all final manuals and revisions in PDF<br />
format.<br />
11.3.2 Operating Manuals<br />
In accordance with the CDRL, Design-Builder shall prepare and submit for Authority approval a<br />
complete set of operating manuals covering the detailed operating procedures for elevators, UPS,<br />
HVAC, sump pump, fire suppression, and any other components of the Project.<br />
The operating manuals shall contain all information needed to operate the equipment, and shall<br />
include, at least, the following:<br />
A. <strong>General</strong> familiarization materials;<br />
B. Location, function and operation of pertinent systems and subsystems;<br />
C. Start-up and shut-down procedures;<br />
D. Trouble symptoms, diagnostic methods and procedures for isolating faults;<br />
E. Operating data, initial calibration/setup, etc; and<br />
F. Emergency Procedures.<br />
11.3.3 Maintenance Manuals<br />
Maintenance manuals shall be provided for all elevators, UPS, HVAC, sump pump, fire<br />
suppression, and any other equipment. These manuals shall provide detailed procedures and<br />
reference data for performing all of the required maintenance tasks. The manuals shall include<br />
expanded assembly pictorials and complete instructions for assembly and disassembly as required.<br />
The maintenance manuals shall contain information that includes:<br />
A. Preventive maintenance and overhaul schedules;<br />
B. Descriptions of maintenance procedures;<br />
C. Description of Project operation including interactions between major subsystem<br />
elements;<br />
D. Detailed descriptions of individual components and assemblies including clearances;<br />
tolerances, circuit operations, test point voltages, waveforms, etc., with references to<br />
Project drawings as applicable down to the lowest replaceable unit (LRU);<br />
E. Detailed descriptions of operational procedures for all manual operations;<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
123 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
F. Detailed description of test equipment operation and procedures for its correct use in<br />
equipment maintenance;<br />
G. Description of replacement parts, including identifying description and parts numbers as<br />
necessary to order such parts from the original parts supplier or manufacturer. These<br />
shall be a complete parts list for all numbered parts, correlating the parts number with<br />
the parts name, and name of the original manufacturer down to and including the LRU.<br />
Where an LRU is not a Design-Builder-specific design or product but is purchased from<br />
a vendor or Subcontractor, the Original Equipment Manufacturer (OEM) shall be<br />
identified together with the OEM-specified part and/or model numbers and copies of the<br />
OEM maintenance instructions;<br />
H. Appropriate drawings, literature and other information which accompany LRUs<br />
purchased from other vendors. These may be provided as appendices to the manuals;<br />
I. Troubleshooting guides at the system, subsystems and component equipment level to<br />
aid diagnosis of common failure modes;<br />
J. Basic schematic and block diagrams and the requirements for setting up and use of<br />
diagnostic test equipment and special tools;<br />
K. Maintenance data, inspection logs, adjustments, repairs, etc; and<br />
L. Integrated wiring diagrams, schematic drawings and interconnection diagrams.<br />
11.3.4 Required Submittals<br />
To fulfill the operations and maintenance manual requirements under this Contract, Design-Builder<br />
shall provide the followings submittals for the review and acceptance of the Authority:<br />
A. Manual format – Not later than 90-days prior to equipment installation, submit the<br />
proposed format and table of contents for each of the Operation and Maintenance<br />
manuals;<br />
B. Draft manuals – Not later than 30-days prior to equipment installation, submit the<br />
Operation and Maintenance manuals in final form for Authority review and comment;<br />
C. Final manuals – Not later than 30-days prior to Substantial Completion, submit the final<br />
operation and maintenance manuals with Authority comments incorporated; and<br />
D. Manual revision – Through warranty period, update pages, as necessary for each<br />
Operation and Maintenance manual.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
124 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
11.4 Spare Parts and Materials<br />
Design-Builder shall provide consumable parts recommended by the manufacturer to support the<br />
operation of the Parking Facilities for a period of one year after Substantial Completion.<br />
Design-Builder shall provide spare parts for elevators, UPS, HVAC, sump pump, fire suppression,<br />
and any other equipment. The direct costs of spare parts will be paid from the Provisional Sum set<br />
forth in Contract Section 7.1.2. The definitive lists of recommended spare parts with quantities and<br />
prices shall be developed by Design-Builder and submitted to the Authority for review and approval.<br />
The Authority will finalize the list and provide them to Design-Builder for procurement of the spare<br />
parts.<br />
Design-Builder shall also provide spare materials for all architectural material on the Project in a<br />
quantity equal to 2% of the total used.<br />
11.4.1 Packaging<br />
The packaging of each spare part or consumable part shall consider the requirements for inspection<br />
and inventory. Design-Builder shall package the materials as follows:<br />
A. Package and label spare parts and replacement materials in moisture proof containers<br />
suitable for shipment and storage. Attach copies of shipping list in package and to<br />
exterior of package. Submit procedures for packaging of spare parts for review and<br />
approval by the Authority or its designee prior to any delivery of spare parts;<br />
B. Packaging shall consider the durability and reliability of the parts and the normal<br />
procedures for inspecting and inventorying (e.g., the packaging selected for highly<br />
durable parts shall be such that the parts can be identified, inspected, stored for long<br />
periods, and endure multiple inventories);<br />
C. Ship spare parts and materials as directed by the Authority or its designee;<br />
D. Coordinate delivery of spare parts and materials with <strong>Metro</strong> prior to Substantial<br />
Completion;<br />
E. Unload spare parts and materials in a manner which will prevent damage to packages<br />
and contents. Spare Parts maybe inspected for damage. Damaged parts and materials<br />
will be returned to Design-Builder to be replaced with undamaged parts and materials, at<br />
no additional cost to the Authority; and<br />
F. Apply preservative coatings to all materials subject to corrosion.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
125 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
11.4.2 Part Identification<br />
Design-Builder shall provide an inventory of the supplied spare parts. The inventory list shall have<br />
the following information:<br />
A. Item by item listing;<br />
B. Applicable system (e.g., ventilation, elevators, etc.);<br />
C. Quantity provided;<br />
D. Product name/description (starting with the appropriate key word, followed by key word<br />
modifiers);<br />
E. Manufacturer’s name, address and telephone number;<br />
F. Manufacturer’s part number;<br />
G. Manufacturer’s model number;<br />
H. Unit of measure (each, feet, etc.);<br />
I. Unit cost;<br />
J. Local distributor (name, address, Federal ID and phone number);<br />
K. Distributor's part number;<br />
L. Authorized OEM rebuild facility (name, address and phone number);<br />
M. Storage restriction, if applicable, such as shelf life;<br />
N. Confirmation of whether part is hazardous or not. Include MSDS sheet if hazardous;<br />
O. Recommended stocking quantities;<br />
P. Alternate vendor sources; and<br />
Q. Spare parts not readily available shall be labeled as such.<br />
11.4.3 Special Tools<br />
Design-Builder shall supply a complete set of special tools recommended by the manufacturer(s)<br />
for the Work, including all architectural building material, elevators, mechanical, and electrical<br />
equipment.<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
END OF SECTION<br />
126 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS
APPENDICES<br />
Appendix A Environmental Sustainability Guidelines and Checklist<br />
Appendix B Contract Data Requirement List<br />
Appendix C Tree Removal Policy<br />
METRO GOLD LINE FOOTHILL EXTENSION<br />
CONSTRUCTION AUTHORITY<br />
RFP C1150<br />
127 INTERMODAL PARKING FACILTIES AND ENHANCEMENTS<br />
DESIGN-BUILD PROJECT<br />
VOLUME 3, DOCUMENT 1 – GENERAL REQUIREMENTS