Northern <strong>Growth</strong> Corridor <strong>Transport</strong> <strong>Modelling</strong><br />
2.1.2 Zone Disaggregation<br />
GAA developed a notional 2046 land use plan (see Figure 3) which was discussed<br />
and agreed with stakeholders. GAA then developed a zone system based on the<br />
land use plan which separately identified areas of different land use. SKM<br />
developed an equivalence table to equate original VITM zones to the new zone<br />
system. This became the key tool for transforming the many inputs in VITM to the<br />
new zone system. In total an additional 261 zones were added to VITM through<br />
this disaggregation process. These zones are numbered 2924 -3184.<br />
Figure 3: Northern <strong>Growth</strong> Corridor Land Use - 2046<br />
2.1.3 External Car Zones<br />
The northern extent of VITM (before the Wallan extension) contained three external<br />
zones which fed a fixed number of car trips into the model from outside the model<br />
boundary. In the new model, the total volumes of external trips from these three<br />
PAGE vii